Basic Engineering Design

Air Curah Tirta Benteng


Pegadungan – Golden Palm
– Pergudangan 198
– Tapping Citra 8 ke Pipa Primer Pegadungan
Daftar Isi

TIRTA BENTENG - PEGADUNGAN ................................................................................................... I


A. Calon pelanggan Tirta Benteng – Pegadungan........................................................................... 1
B. Tambahan Design Pegadungan .................................................................................................. 1
B.1 Tapping Golden Palem Residence ke Pipa Primer Pegadungan ........................................... 1
i. Gambar Lokasi Golden Palm....................................................................................... 1
ii. Detail 1 : titik tapping pipa 300 mm Pipa Primer Pegadungan ke pipa 160 mm
Golden Palem ................................................................................................................ 2
B.2 Pergudangan 198 ................................................................................................................. 3
i. Rencana Perpipaan Pergudangan 198 ........................................................................ 3
ii. Layout Bangunan Pergudangan 198 .......................................................................... 4
B.3 Tapping Citra 8 ke Pipa Primer Pegadungan......................................................................... 5
i. Rencana Tapping Citra 8 ke Pipa Primer Pegadungan ................................................ 5
ii. Detail 1 & 2 : Lokasi Pemasangan Valve .................................................................... 6
TIRTA BENTENG - PEGADUNGAN

I
A. Calon pelanggan Tirta Benteng – Pegadungan

B. Tambahan Design Pegadungan


B.1 Tapping Golden Palem Residence ke Pipa Primer Pegadungan
i. Gambar Lokasi Golden Palm

1
ii. Detail 1 : titik tapping pipa 300 mm Pipa Primer Pegadungan ke pipa 160 mm Golden
Palem

Valve Eksisting
akan ditutup

2
B.2 Pergudangan 198
i. Rencana Perpipaan Pergudangan 198

Pipa 90 mm
Panjang + 576 m
Pipa Primer 300 mm
Pegadungan

Pipa 110 mm
Panjang +740 m

1. Pipa Distribusi Connect


dengan KA RS Ciputra
2. Install Valve 110 mm

3
ii. Layout Bangunan Pergudangan 198

4
B.3 Tapping Citra 8 ke Pipa Primer Pegadungan
i. Rencana Tapping Citra 8 ke Pipa Primer Pegadungan

5
ii. Detail 1 & 2 : Lokasi Pemasangan Valve

Panjang Pipa
300mm + 140 m

6
II