IK-K3L-01 Standard Operating Procedure
IK-K3L-01 Standard Operating Procedure
Dok : IK-K3L-01
INSTRUKSI KERJA
STANDARD OPERATING PROCEDURES Page 1 of 6
26-10-23 Rev. 00
1. TUJUAN
2. RUANG LINGKUP
SOP ini berlaku untuk pekerjaan-pekerjaan teknis di lokasi project atau di proyek.
3. REFERENSI
- K3L Manual Perusahaan
- Klausul 4.4.6, ISO 14001 dan ISO 45001
(Fabrication Welding)
Strictly Remind
No welding work shall be done on the used oil / fuel drum …!!!
Dilarang mengelas diarea penyimpanan bahan bakar / oli …!!!
No. Dok : IK-K3L-01
INSTRUKSI KERJA
STANDARD OPERATING PROCEDURES Page 3 of 6
26-10-23 Rev. 00
Strictly Remind
No welding work shall be done on the used oil / fuel drum …!!!
DILARANG MELAKUKAN PENGELASAN DI AREA DRUM PENYIMPANAN BAHAN BAKAR / OLI …!!!
No. Dok : IK-K3L-01
INSTRUKSI KERJA
STANDARD OPERATING PROCEDURES Page 4 of 6
26-10-23 Rev. 00
Purpose
All pipe storage, handling & transportation procedure shall be designed to protect pipe
and its coating and ensure the K3L of pipe handlers and the general public.
1 Handling
All pipe shall be handled in such manner that impact loads
sufficient to cause out of roundness denting of pipes
1.1 Transport
Semua pipa harus diperlakukan secara benar untuk
menghindari kerusakan pipa
Pipe shall be unload from truck by lifting, rolling is not
permitted to avoid accident.
1.2 Transport
Pembongkaran pipa dari truk harus dengan cara diangkat,
dilarang menggelincirkan pipa untuk mencegah kecelakaan
Crane operator to unload pipe should have Migas certificate.
1.3 Operator crane pembongkaran pipa harus bersertifikat dari K3L
Migas
Rigger to work on this activities should be experienced and
certified
1.4 K3L
Rigger yang bekerja pada kegiatan ini harus berpengalaman
dan bersertifikat
Crane condition shall be maintained in good conditioned and
Migas certified
1.5 K3L
Crane harus dirawat dalam kondisi baik dan bersertifikat dari
Migas
Sling which is used shall be in a good condition and certified.
1.6 Sling yang digunakan harus dalam kondisi baik dan K3L
disertifikasi
Shackle to be used shall be in a good condition and certified.
1.7 Shackle yang digunakan harus dalam kondisi baik dan K3L
disertifikasi
2 Transport
Pipe transported by truck shall be loaded on padded or wood
bolster and tied down with chain at each bolster
Pipa yang akan diangkut dengan truk harus diletakkan pada
2.1 Transport
landasan atau wood bolster dan diikat dengan rantai pada
setiap alasnya
3
Storage
Pipe shall be stacked properly and secured with wedges to
avoid rolling down
3.1 Transport
Pipa harus disimpan semestinya dan aman dan dikunci untuk
mencegah tumpukan pipa runtuh/ambrol
Pipe shall be stacked on sleepers or sand bag to avoid
3.2 Transport
contact with storage.
2. Objective
In all handling operations, PT. Ciriajasa CM. shall make sure that the agreements made are not
likely to cause permanent deformation of elements by bending, bucking or warping, taking into
account its weight and any wind induced forces
No. DESCRIPTION ACTION REMARKS
3. Operation / Equipment
Crane or other lifting equipment shall be in a good condition
3.1
and has been certified.
Skilled manpower (rigger & operator) assigned shall be
3.2
qualified and certified
3.3 Operation
3.3.1 Operator shall check crane foundation, K3Laves,
brakes, boom guard, load hook and load chart.
3.3.2 The operator shall follow the instruction / signal from
a qualified rigger/foreman, single command and
monitor boom angle
3.3.3 All wire line has been checked prior to operation for
good condition, if its found corrosion, shall be
replaced.
3.3.4 Each time a load is lifted, the crane hook must use
K3L or latches
4. Lifting
Lifting operation shall be discontinued as soon as the wind
4.1
velocity exceeds 20 m/s
Purpose
The purpose of this procedure is to define good K3L operation in handling excavation work at job
site for field operation.