KONSEP DAN PERTIMBANGAN DESAIN
PENGANTAR
Latar Belakang
Definisi Galian Dalam
Resiko
CATATAN :
Materi ini bersifat umum dan menyeluruh (tidak detail)
www.liputan6.com
Peserta diharapkan memiliki pengetahuan dasar mengenai mekanika tanah dan
https://www.newcivilengineer.com/latest/no-11-nicoll-highway-collapse-02-05-2012/
geoteknik secara umum
Keterangan :
H = Tinggi tanah (m)
σv = Tekanan vertikal tanah (kPa)
γ = Berat isi tanah (kN/m3)
σh = Tekanan lateral tanah (kPa)
K = Koefisien tekanan lateral tanah (-)
Jenis koefisien K :
Ka = K dalam kondisi aktif
Kp = K dalam kondisi pasif
Ko = K dalam kondisi “at-rest” atau diam
TANAH
Konsep Tekanan Lateral Tanah
TANAH TANAH
Stabilitas Galian
Sistem Penahan Tanah
Retaining structure
Secant Pile
Kelemahan
Diaphragm Wall
Panjang terbatas, mobilisasi dapat menjadi kendala
Penetrasi ke tanah keras terbatas
Kapasitas lentur relatif rendah
Sulit untuk pemasangan ground anchor
Bersifat temporary
SISI GALIAN
SISI GALIAN
SISI TANAH
SISI GALIAN
SISI GALIAN
Secondary Piles
Hard : beton bertulang
Kelemahan
Perlu peralatan khusus
Ada waste material primary piles
Penulangan kurang efisien
Bentuk permukaan secant pile kadang menyulitkan
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
Secant Pile
Kelemahan
Diaphragm Wall
Perlu peralatan khusus
Beresiko longsor pada tanah sangat lunak atau lepas
Resiko gangguan ke tetangga relatif tinggi
Volume beton setiap pengecoran panel relatif tinggi
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Guide Wall
Sheetpile
Soldier Pile
D-Wall Panel D-Wall Panel D-Wall Panel
Contiguous Pile
Secant Pile
Diaphragm Wall
Guide Wall
B
JENIS RETAINING
STRUCTURE
Guide Wall
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
Guide Wall
D-Wall Panel #1
D-Wall Panel #2
D-Wall Panel #3
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Guide Wall
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
Guide Wall
D-Wall Panel #1
D-Wall Panel #2
D-Wall Panel #3
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS RETAINING
STRUCTURE
Sheetpile
Soldier Pile
Contiguous Pile
Secant Pile
Diaphragm Wall
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
Retaining structure
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
Retaining structure
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
Kelemahan
Galian dan konstruksi basement menjadi terhalang
Umumnya memiliki kekakuan aksial yang relatif tidak terlalu besar
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
Retaining structure
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting King post
Pelat Lantai Basement (Top-Down)
Retaining structure
Bored piles
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
JENIS SISTEM
PENAHAN LATERAL
Berm Tanah (Island Method)
Ground Anchor
Strutting
Pelat Lantai Basement (Top-Down)
Penetrasi ke Lahan Sekitar Penurunan muka air tanah di sekitar galian yang signifikan dapat diakibatkan
oleh :
Dewatering yang berlebihan
Penetrasi ke Lahan Sekitar Penurunan muka air tanah di sekitar galian yang signifikan dapat diakibatkan
oleh :
Dewatering yang berlebihan
Ei Eur
Persamaan Hooke :
σ=E×ε
E = Ei = Eur
Dimana :
σ = tegangan (kPa)
E = Modulus elastisitas (kPa)
ε = regangan (-)
Plaxis CE v20.04 Material Models Manual (Bentley, 2020)
Kondisi uji adalah kondisi aktual (tegangan, drainase, jenis tanah, dll.)
Umumnya bersifat undrained, dan kondisi uji umumnya tidak dapat diatur
Uji laboratorium
Umumnya bersifat sporadis
Kondisi uji dapat diatur, dan sifat uji dapat berupa undrained atau drained
Pressure Cell
Berfungsi mengukur gaya atau tekanan yang bekerja
Sangat jarang digunakan