452.340,00
III. PEKERJAAN DINDING
3.1. Dinding
3
2.2.1. Pasangan Dinding Batubata (1:4) 413,6000 M 50.000,00 20.680.000,00
3
2.2.2. Pasangan Dinding Batubata (1:2) 51,1000 M 56.200,00 2.871.820,00
23.551.820,00
3.2. Kusen
3
2.3.1. Kusen Pintu dan Jendela 1,2600 M 2.786.375,00 3.510.832,50
3.510.832,50
IV. PEKERJAAN KAP DAN ATAP
4.1. Kap dan Rangka Atap
3
4.1.1.. Balok Dinding 8/12 0,3000 M 16.037,50 4.811,25
3
4.1.2. Pekerjaan Kuda-Kuda 1,3700 M 2.419.981,29 3.315.374,37
3
4.1.3. Pekerjaan Rangka Atap 138,0646 M 34.345,00 4.741.828,69
3
4.1.4. Pekerjaan Listplank 3/25 53,9000 M 28.935,00 1.559.596,50
3
4.1.5. Gording 8/12 5,6300 M 689.120,96 3.879.751,00
4.1.6. Talang 17,0000 M' 519.704,83 8.834.982,17
22.336.343,98
4.2. Atap
4.2.1. Pemasangan Atap 158,0646 M2 43.785,80 6.920.984,96
4.2.2. Pemasangan Perabung 34,1700 M3 130.387,47 4.455.339,71
11.376.324,68
V. PEKERJAAN PLAFOND
5.1. Balok Plafond
5.1.1. Rangka Plafon 207,0075 M2 36.913,93 7.641.460,07
7.641.460,07
5.2. Memasang Plafond
5.2.1. Memasang Plafond Gypsum 165,6500 M2 64.214,67 10.637.159,53
5.2.2. Memasang Lis Plafond 179,9500 12.394,20 2.230.336,29
12.867.495,82
VI. PEKERJAAN PLASTERAN
6.1. Plasteran
6.1.1. Plasteran Dinding (1:2) 134,5000 M2 26.166,30 3.519.366,81
6.1.2. Plasteran Dinding (1:4) 780,2350 M2 22.553,96 17.597.388,98
6.1.3. Aian 914,7350 M2 4.837,48 4.425.013,64
Universitas Muhammadiyah
Manajemen Biaya Proyek Tangerang
25.541.769,43
6.2. Turap Porslen
6.2.1. Pasangan Turap Porslent 47,2160 M2 114.875,64 5.423.968,22
5.423.968,22
VII. PEKERJAAN LANTAI
7.1. Urugan Bawah Lantai
7.1.1. Urugan Pasir 11,2648 107.150,00 1.207.023,32
1.207.023,32
7.2. Pasangan Lantai
7.2.1. Pasangan Lantai Kramik 33 x 33 182,3750 M2 127.032,22 23.167.501,85
7.2.2. Pasangan Lantai Kramik 20 x 20 24,6325 M2 148.382,22 3.655.025,13
26.822.526,98
VIII. PEKERJAAN PINTU DAN JENDELA
8.1. Pintu dan Jendela
8.1.1. Pasangan Pintu 28,9350 Bh 521.600,00 15.092.496,00
8.1.2. Pasangan Jendela kaca 17,0000 M2 219.829,17 3.737.095,83
18.829.591,83
8.2. Kaca
8.2.1. Pasangan Kaca Tebal 15 mm 71,5420 M2 112.829,75 8.072.065,97
8.072.065,97
8.3. Penggantung/Kunci
8.3.1. Pasangan Engsel Pintu 68,0000 Bh 25.592,50 1.740.290,00
8.3.3. Pasangan Kunci Taman Antik 12,0000 Bh 144.595,00 1.735.140,00
3.475.430,00
IX. PEKERJAAN PENGECATAN
9.1. Mendempul dan Mrnggosok Kayu 90,9809 M2 7.414,50 674.577,88
9.2. Mengecat Kayu Baru 610,5400 M2 20.915,50 12.769.749,37
9.3. Mengecat Tembok Baru 464,7500 M2 14.340,80 6.664.886,80
20.109.214,05
X. PEK. INSTALASI DAN SANITASI
10,1 Listrik
10.1.1 Pemasangan Listrik Baru 1,0000 Ls 9.380.200,00 9.380.200,00
9.380.200,00
10.2. Sanitair dan Instalasi Air
10.2.1. Pemasangna Kloset Jongkok 2,0000 Bh 604.640,00 1.209.280,00
Universitas Muhammadiyah
Manajemen Biaya Proyek Tangerang
REKAPITULASI HARGA