SEJARAH RU II
PROFIL RU II
DISTRIBUSI PRODUK
PROSES PRODUKSI
PENUTUP
1. SEJARAH REFINERY UNIT II
Kilang Dumai
CDU — 120 MBSD
PL-I/II — 15 MBSD
HVU — 106 MBSD
DCU — 35.2 MBSD
HCU — 63 MBSD
Kilang SPK 1971 Pembangunan CDU 100 MBSD
Title 1972 1st development : Penambahan Naphtha
Measure Rerun Unit, Hydrobon-Platforming, and
CDU SPK — 50 MBSD Mogas blending facilities
1981 2nd development : Penambahan
1969 Pembangunan CDU oleh Refican (25 MBSD) Hydrocracking Complex (HCC) and Heavy
1974 Penyerahan ke Pertamina Oil Complex (peresmian tahun 1984)
1977 Menaikkan kapasitas 35 MBSD (revamp Heater) 1992 Pemasangan APH in CDU’s & menaikkan
1979 Menaikkan kapasitas 50 MBSD (revamp Kolom) kapasitas dari 100 to 120 MBSD
2007 Start-up unit LBO Plant, HCU Revamp (naik
113%) & HVU Revamp (naik 114%).
3
Content
SEJARAH RU II
PROFIL RU II
DISTRIBUSI PRODUK
PROSES PRODUKSI
PENUTUP
2. PROFIL RU II
RU III 11,18 %
RU V 23,17 %
• Tidak merefleksikan marjin / profitabilitias, hal-hal lain seperti tantangan logistik juga mempengaruhi profil ekonomi kilang
dan tidak direfleksikan oleh indeks Nelson.
Sumber: FACTS; US Ebassy Jakarta Petroleum Report 2005; analisa McKinsey
Content
SEJARAH RU II
PROFIL RU II
DISTRIBUSI PRODUK
PROSES PRODUKSI
PENUTUP
3. DISTRIBUSI PRODUK
Lokasi Produk
NAD BBM
BBM
Sumut Avtur
LPG
BBM
Riau Avtur
LPG
BBM
Sumbar Avtur
LPG
DKI Avtur
LSWR
Ekspor
Green Coke
DISTRIBUSI BBM DARI KILANG DUMAI & S.PAKNING
LPG : 3.42*
AVTUR : 3.61 PEKANBARU P. BENGKALIS &
S.PAKNING, DUMAI (RIAU),
PADANG
SEJARAH RU II
PROFIL RU II
DISTRIBUSI PRODUK
PROSES PRODUKSI
PENUTUP
4. PROSES PRODUKSI
RENCANA
DISTRIBUSI
KANTOR
PUSAT
RAPAT ALOKASI
MM & INTERMEDIA
ANTAR RU &
KANTOR PUSAT
PENYALURAN PRODUK
• PIPA / MOBIL
PERENCANAAN PROGRAM PELAYANAN
• KAPAL ALOKASI UPMS I
PRODUKSI TRANFER / PEMUATAN KILANG
BULANAN RU II DMI / S.PK • KAPAL ALOKASI KANTOR
PUSAT
PROSES
PRODUKSI
RENCANA
DISTRIBUSI
UPMS I
KAPASITAS REFINERY UNIT – II DUMAI
MBSD
UNIT PRODUKSI
KAP. DESIGN KAP. EFEKTIF
CDU DUMAI 120,0 127,0
CDU S. PAKNING 50,0 49,0
NAPTHA RERUN UNIT 9,0 9,0
HYDROBON & PLATFORMER 6,2 6,9
HIGH VACUUM UNIT 106,0 106,0
HYDROCRACKER 211 31,5 31,5
HYDROCRACKER 212 31,5 31,5
NAPTHA HYDROTREATER 10,1 10,1
CCR PLATFORMER 8,8 8,8
DISTILLATE HYDROTREATER 12,7 13,3
DELAYED COOKER 35,2 35,2
CALCINER @ 1.063,0 *) 1.063,0
LPG RECOVERY 174,0 *) 174,0
HYDROGEN PLANT 701 39,2**) 39,2
HYDROGEN PLANT 702 39,2**) 39,2
*) TON / DAY **) MMSCF /DAY
@ Saat ini unit tidak beroperasi (Idle)
6,66
MBCD
16,67
MBSD
13.12
MBCD
60.13
MBCD
11.95
MBCD
7.10
MBCD
8.98
MBCD
4.08
MBCD
SEJARAH RU II
PROFIL RU II
DISTRIBUSI PRODUK
PROSES PRODUKSI
PENUTUP
5. UTILITIES & OFFSITE FACILITIES
• Steam Generator
– HP Steam : 350 Ton/jam
– MP Steam : 200 Ton/jam
– LP Steam : 170 Ton/jam
POWER UTILITIES • Power Plant
– Power generate : 45 MW
• Cooling Water System
• Fuel System
• Instrument - Plant Air System
UTILITIES
• Air Baku
Sumber air baku dari Sei Rokan jarak dari
Dumai + 43 km.
OTHER • WTP Bukit Datuk
Kapasitas produksi 1100 - 1200 m3/jam.
• Udara Kempa.
Kompresor udara kempa + 10700 NM3/Jam
5. UTILITIES & OFFSITE FACILITIES
SEJARAH RU II
PROFIL RU II
DISTRIBUSI PRODUK
PROSES PRODUKSI
PENUTUP
PT PERTAMINA (PERSERO)
REFINERY UNIT II DUMAI
SISTEM MANAJEMEN
PT PERTAMINA (PERSERO) RU - II
1. Penerapan Quality Management system (QMS) dalam
wadah Sistem Manajemen Mutu Pertamina
Sertifikasi ISO-14001, ISO-17025 dan ISO-9000
Manajemen Keselamatan Proses (MKP)
Implementasi Enterprise Resource Planning (ERP) SAP R/3
Kebijakan PROPER Biru
Pengukuran Kinerja dengan menggunakan kriteria MBNQA
(early improvement)
2. Penerapan Good Corporate Governance (GCG)
Implementasi e-Auction untuk proses pelelangan
Penandatanganan Pakta Integritas oleh Tim Manajemen
3. Program transformasi
OPI (Operational Performance Improvement)