LAMPIRAN A

Tabel Efisiensi Kerja

Efisiensi Kerja (Tenriajeng, 2003)


Klasifikasi Efisiensi Kerja
Baik >85 %
Sedang 65 % - 85 %
Kurang < 65 %

Bucket Fill Factor (Komatsu, 2009)


Excavating Conditions Bucket Fill Factor
Easy excavating Clay Soil, or Soft Soil 1,1 – 1,2
Average excavating Sandy Soil, San Soil 1,0 – 1,1
Rather difficult excavating Sandy Soil with Gravel 0,8 – 0,9
Difficult excavating Loading Blasted Rock 0,7 – 0,8
Nilai Swell Factor (Tenriajeng, 2003)
Macam Mineral Densitu Insitu Swel Factor
(lb/cu yd) (%)
Bauksit 2700 - 4325 75
Tanah Liat Kering 2300 85
Tanah Liat Basah 2800 – 3000 80 – 82
Antrasit 2200 76
Batubara Bituminus 1900 74
Bijih Tembaga 3800 74
Tanah Biasa Kering 2800 85
Tanah biasa basah 3370 85
Tanah biasa tercampur pasir dan 3100 90
kerikil
Kerikil kering 3250 89
Kerikil basah 3600 88
Granit pecah-pecah 4500 56 – 67
Hematit pecah-pecah 6500 – 8700 45
Bijih besi pecah-pecah 3600 – 5500 45
Batu kapurpecah-pecah 2500 – 4200 57 – 60
Lumpur 2160 – 2970 83
Lumpur sudah ditekan 2970 – 3510 83
Pasir kering 2200 – 3250 89
Pasir basah 3300 – 3600 88
Serpih (shale) 3000 75
Batu sabak (slate) 4590 – 4860 77