REKAPITULASI

Program :PENYEDIAAN DAN PENGELOLAAN AIR BAKU


Kegiatan :PEMBANGUNAN PRASARANA PENGAMBILAN DAN SALURAN PEMBAWA
Pekerjaan : PENUNJUKAN KONSULTAN PERENCANAAN D A K TA. 2020
Lokasi : KABUPATEN NAGEKEO
Tahun Anggaran : 2020

NO. URAIAN JUMLAH HARGA

I. BIAYA LANGSUNG PERSONIL

A. TENAGA PROFESIONAL Rp 13,800,000.00

B. TENAGA SUB PROFESIONAL DAN TENAGA PENDUKUNG Rp 35,100,000.00

II. BIAYA LANGSUNG NON PERSONIL

A. BIAYA SURVEY DAN PENGUKURAN Rp 21,150,000.00

B. PERALATAN KANTOR DAN KOMUNIKASI Rp 4,250,000.00

C. BIAYA PELAPORAN Rp 2,750,000.00

TOTAL Rp 77,050,000.00

PPN 10% Rp 7,705,000.00

TOTAL BIAYA Rp 84,755,000.00

TOTAL PEMBULATAN Rp 84,755,000.00

terbilang :

Delapan puluh empat juta tujuh ratus lima puluh lima ribu rupiah

Mbay, ……Juni 2019

Pejabat Pembuat Komitmen


-

Fransiskus Petrus Goa Dajo, ST, MT

NIP.19780325 201001 1 015


HARGA PERKIRAAN SENDIRI (HPS)
Program :PENYEDIAAN DAN PENGELOLAAN AIR BAKU
Kegiatan :PEMBANGUNAN PRASARANA PENGAMBILAN DAN SALURAN PEMBAWA
Pekerjaan : PENUNJUKAN KONSULTAN PERENCANAAN D A K TA. 2020
Lokasi : KABUPATEN NAGEKEO
Tahun Anggaran : 2020

I. BIAYA LANGSUNG PERSONIL


A. TENAGA PROFESIONAL
JUMLAH Jumlah
No. URAIAN PERSONIL SATUAN VOLUME BIAYA BIAYA
(Orang) Rp. Rp.
1 2 3 4 5 6 7
1 Team Leader 1 org/bln 3.00 2,400,000.00 7,200,000.00
2 Chief Inspector (CI) 1 org/bln 3.00
5.00 2,200,000.00 6,600,000.00
Jumlah A 13,800,000.00

B. TENAGA SUB PROFESIONAL DAN TENAGA PENDUKUNG


JUMLAH Jumlah
No. URAIAN PERSONIL SATUAN VOLUME BIAYA BIAYA
(Orang) Rp. Rp.
1 2 3 4 5 6 7
1 Inspector (I) / Site Sopervisor (SS) 2 org/bln 3.00 1,500,000.00 9,000,000.00
2 Surveyor 3 org/bln 3.00 1,300,000.00 11,700,000.00
3 Drafter/Draftman/Juru Gambar 3 org/bln 3.00 1,200,000.00 10,800,000.00
4 Project Administration (Pad) 1 org/bln 3.00 1,200,000.00 3,600,000.00

Jumlah B 35,100,000.00
Jumlah A+B 48,900,000.00

II. BIAYA LANGSUNG NON PERSONIL


A. BIAYA SURVEY DAN PENGUKURAN
JUMLAH HARGA Jumlah
No. URAIAN ALAT SATUAN VOLUME SATUAN HARGA
Rp. Rp.
1 2 3 4 5 6 7
A. SEWA KENDARAAN DAN PERALATAN KANTOR DAN LAPANGAN
1 Sewa Kendaraan Roda 2 3 Bulan 3.00 650,000.00 5,850,000.00
2 Sewa GPS Map 3 Buah 3.00 500,000.00 4,500,000.00
3 Sewa Komputer dan Printer 3 Bulan 3.00 450,000.00 4,050,000.00
4 Sewa Camera Digital 3 Bulan 3.00 750,000.00 6,750,000.00
Jumlah A 21,150,000.00

B. PERALATAN KANTOR DAN KOMUNIKASI


JUMLAH HARGA Jumlah
No. URAIAN BAHAN SATUAN VOLUME SATUAN HARGA
Rp. Rp.
1 2 3 4 5 6 7
1 Komunikasi/Telepon 1 Ls 1.00 2,500,000.00 2,500,000.00
2 Alat Pakai habis/ATK 1 Ls 1.00 1,750,000.00 1,750,000.00

Jumlah B 4,250,000.00
C. BIAYA PELAPORAN
JUMLAH HARGA Jumlah
No. URAIAN SATUAN VOLUME SATUAN HARGA
Rp. Rp.
1 2 3 4 5 6 7
1 Penggandaan Laporan;
a. Laporan Pendahuluan Buku 1.00 400,000.00 400,000.00
b. Laporan Antara Buku 1.00 400,000.00 400,000.00
c. Laporan Akhir Buku 1.00 400,000.00 400,000.00
d. Dokumen Gambar Rencana (DED) Buku 1.00 750,000.00 750,000.00
e. Dokumen Engineering Estimate (EE) Buku 1.00 300,000.00 300,000.00
f. Dokumen Spesifikasi Buku 1.00 500,000.00 500,000.00
Jumlah C 2,750,000.00
RINCIAN BEBAN BIAYA PERSONIL
GAJI BEBAN BIAYA BEBAN BIAYA IMBALAN JASA/ BIAYA PENUGASAN TUNJANGAN BIAYA LANGSUNG
No. POSISI DASAR SOSIAL UMUM SUB KEUNTUNGAN KANTOR PUSAT PENUGASAN PERSONIL DIBULATKAN
(GD) (BBS) (BBU) JUMLAH (K) PER BULAN (BLP)
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9
0,4 x GD 0,7 x GD 4=1+2+3 0,1 x (GD+BBS+BBU) 6=4+5 0,1 x GD 8=6+7

I TENAGA AHLI
1 Site Engginering (SE) 1,000,000.00 400,000.00 700,000.00 2,100,000.00 210,000.00 2,310,000.00 100,000.00 2,410,000.00 2,400,000.00
Chief Inspector (CI) 950,000.00 380,000.00 665,000.00 1,995,000.00 199,500.00 2,194,500.00 95,000.00 2,289,500.00 2,200,000.00
III TENAGA PENUNJANG
1 Inspector (I)/Site Supervisor(SS) 750,000.00 300,000.00 525,000.00 1,575,000.00 157,500.00 1,732,500.00 75,000.00 1,807,500.00 1,800,000.00
2 Drafter (D) / Surveyor (S) 750,000.00 300,000.00 525,000.00 1,575,000.00 157,500.00 1,732,500.00 75,000.00 1,807,500.00 1,800,000.00
3 Material Engginering (ME) 500,000.00 200,000.00 350,000.00 1,050,000.00 105,000.00 1,155,000.00 50,000.00 1,205,000.00 1,200,000.00
3 #REF! 450,000.00 180,000.00 315,000.00 945,000.00 94,500.00 1,039,500.00 45,000.00 1,084,500.00 1,000,000.00
4 Project Administration (Pad) 700,000.00 280,000.00 490,000.00 1,470,000.00 147,000.00 1,617,000.00 70,000.00 1,687,000.00 1,600,000.00
Item jumlah Personil Sat Vol
Team Leader 1 org/bln 3.00
Chief Inspector (CI) 1 org/bln 3.00
Surveyor 3 org/bln 3.00
Drafter/Draftman/Juru Gambar 3 org/bln 3.00
Project Administration (Pad) 1 org/bln 3.00
Sewa Kendaraan Roda 2 3 Bulan 3.00
Sewa GPS Map 3 Bulan 3.00
Sewa Komputer dan Printer 3 Bulan 3.00
Sewa Camera Digital 3 Bulan 3.00
Komunikasi/Telepon 1.00 Ls 1.00
Alat Pakai habis/ATK 1.00 Ls 1.00
a. Laporan Pendahuluan 7 Buku 7
b. Laporan Antara 7 Buku 7
c. Laporan Akhir 7 Buku 7
d. Dokumen Gambar Rencana (DED) 7 Buku 7
e. Dokumen Engineering Estimate (EE) 7 Buku 7
f. Dokumen Spesifikasi 1 Buku 1
HS PPN 10 % HS + PPN Total
2,400,000.0000 240,000.0000 2,640,000.0000 7,920,000.0000 3.0000
2,200,000.0000 220,000.0000 2,420,000.0000 7,260,000.0000 3.0000
1,300,000.0000 130,000.0000 1,430,000.0000 12,870,000.0000 9.0000
1,200,000.0000 120,000.0000 1,320,000.0000 11,880,000.0000 9.0000
1,200,000.0000 120,000.0000 1,320,000.0000 3,960,000.0000 3.0000
650,000.0000 65,000.0000 715,000.0000 6,435,000.0000 9.0000
500,000.0000 50,000.0000 550,000.0000 4,950,000.0000 9.0000
450,000.0000 45,000.0000 495,000.0000 4,455,000.0000 9.0000
750,000.0000 75,000.0000 825,000.0000 7,425,000.0000 9.0000
2,500,000.00 250,000.00 2,750,000.00 2,750,000.00 1.0000
1,750,000.00 175,000.00 1,925,000.00 1,925,000.00 1.0000
400000 40,000.00 440,000.00 3,080,000.00 7.0000
400000 40,000.00 440,000.00 3,080,000.00 7.0000
400000 40,000.00 440,000.00 3,080,000.00 7.0000
750000 75,000.00 825,000.00 5,775,000.00 7.0000
300000 30,000.00 330,000.00 2,310,000.00 7.0000
500000 50,000.00 550,000.00 550,000.00 1.0000
89,705,000.0000
7,920,000.0000
7,260,000.0000
12,870,000.0000
11,880,000.0000
3,960,000.0000
6,435,000.0000
4,950,000.0000
4,455,000.0000
7,425,000.0000
2,750,000.0000
1,925,000.0000
3,080,000.0000
3,080,000.0000
3,080,000.0000
5,775,000.0000
2,310,000.0000
550,000.0000
89,705,000.0000