MENGHITUNG LEAD TIME PROSES

MANUFAKTUR
• LEAD TIME ADALAH WAKTU YANG DIPERLUKAN UNTUK
MENYELESAIKAN SUATU PROSES PENGERJAAN SUATU
BARANG/PRODUK MANUFAKTUR.
• LEAD TIME DIGUNAKAN UNTUK MENGETAHUI BIAYA PROSES
UNTUK SETIAP WORK CENTER (KELOMPOK MESIN
TERTENTU) MAUPUN SELURUH WORK CENTER PADA
PEMBUATAN SUATU PRODUK MANUFAKTUR
KOMPONEN LEAD TIME
KOMPONEN

No. Order : Ukuran :


No. Bag. : Jenis Material :
Nama Bag. : Roda gigi Jumlah :
Keterangan :

Waktu Waktu
Tgl. Tgl. Tgl.
Metode Proses Tgl. Mulai operasi Catatan
Mulai Selesai Selesai
(TP) (TO)
Rencana Aktual
GER BB BR DB

1-1-16 1 jam 2-1-16 2-1-16 2 jam 3-1-16


KOMPONEN LEAD TIME
• KOMPONENLEAD TIME WORK CENTER BUBUT
• KOMPONENLEAD TIME BUBUT
TO dan TOP
• PERUBAHAN WAKTU DARI JAM KE HARI

1 HARI KERJA = 8 JAM ATAU DISEBUT CAPACTY DAY (CDY)


𝑻𝑶
Sehingga TOP 𝑪
(𝑯𝑨𝑹𝑰)
= 𝑫
𝒀
WAKTU TUNGGU (TW)
• PENGGAMBARAN WAKTU TUNGGU (TW)
WAKTU TUNGGU (TW) = TWA +TWB
PENGGAMBARAN KOMPONEN LEAD TIME
STANDARD
• GBR KOMPONEN DIAGRAM TROUGHPUT
MENGHITUNG TP
 MENGUKUR WAKTU OPERASI (TP)
1. Berdasarkan pengalaman (EMPIRIK), yaitu
dengan mengamati waktu proses yang dilakukan
operator dengan kualifikasi tertentu. Pengukuran
waktu mulai pertama kali setting alat atau
benda kerja dilakukan hingga terakhir benda
kerja dilepas.
 Menghitung waktu secara analitis
WAKTU TRANSIT DAN INSPEKSI (TT)
MENETUKAN TT
• TT DAPAT DITENTUKAN DENGAN ASUMSI. UNTUK ORDER YANG
PADAT (MELEBIHI KAPASITAS INDUSTRI) TT DIASUMSIKAN 0,5 HARI,
SEDANGKAN UNTUK PEMBELAJARAN CUKUP 1 JAM (0,125 HARI)
MENGHITUNG WAKTU SETTING DAN
TUNGGU

 Waktu setting (TS) = TO –TP atau operasai (TO) = TS + TP,


TP dapat diobservasi pada saat proses.
 Untuk menentukan Waktu Tunggu (TW) dapat
digunakan dua cara, yaitu:
(1) mengukur waktu TWA dan TWB selama proses,
(2) TW = TO (jam), atau TW = TOP (hari).
CONTOH SOAL
• ADA 4 ORDER PEMBUATAN KOMPONEN YANG SEMUA MELIBATKAN
MESIN BUBUT. WAKTU OPERASI (TO) DIRENCANAKAN LIHAT DI KARTU
PROSES BERIKUT:
KARTU PROSES 1
• Kartu proses 1

No. Order : 1 Ukuran :


No. Bag. : Jenis Material :
Nama Bag. : Jumlah :
Keterangan :

Waktu Waktu
Metode Tgl. Mulai Order Tgl. Selesai Tgl. Mulai Operasi Tgl. Selesai Catatan
(T0) (TO)
Rencana Aktual
GER BB SL HT

1-1-21
3 jam 2-1-21 2-1-21 3-1-21
KARTU PROSES 2
• Kartu proses 2

No. Order : 2 Ukuran :


No. Bag. : Jenis Material :
Nama Bag. : Jumlah :
Keterangan :

Waktu
Tgl. Tgl. Waktu Tgl.
Metode Operasi Tgl. Mulai Catatan
Mulai Selesai Operasi Selesai
(TO)
Rencana Aktual
GER BOR BB HT

2-1-21 1 jam 4-1-21 2-1-21 2 jam 3-1-21


KARTU PROSES 3
• Kattu prosess 3

No. Order : 3 Ukuran :


No. Bag. : Jenis Material :
Nama Bag. : Jumlah :
Keterangan :

Waktu
Tgl. Tgl. Waktu Tgl.
Metode Operasi Tgl. Mulai Catatan
Mulai Selesai Operasi Selesai
(TO)
Rencana Aktual
GER BB PON HT

4-1-21 4 jam 6-1-21 2-1-21 3-1-21


KARTU PROSES 4
• Kartu proses 4;

No. Order : 4 Ukuran :


No. Bag. : Jenis Material :
Nama Bag. Jumlah :
Keterangan :

Waktu Waktu
Tgl. Tgl. Tgl.
Metode Operasi Tgl. Mulai Operasi Catatan
Mulai Selesai Selesai
(TO) (TO)
Rencana Aktual
GER FR BB HT

6-1-16 3 jam 9-1-16 2-1-16 3-1-16


Tabel pertolongan diagram troughput
• TABEL PERTOLONGAN
TOP
No. TO (Hari)
Komponen/ORD (TS + TP) 𝑻𝑶
( )
Tgl. Mulai Tgl. Selesai
ER (Jam) 𝑪𝑫𝒀

1 1-1-21 2-1-21 3 0,375


2 2-1-21 4-1-21 1 0,125
3 4-1-21 6-1-21 4 0,500
4 6-1-16 9-1-16 3 0.375
Jumlah 4 hari kerja 11 1,375
SILAKAN DIPELAJARI DENGAN SEKSAMA

• TO rata-rata= 11 jam/4 = 2,75 jam


• TOP rata-rata = 2,75 jam /8 jam/hari = 0,34375 hari
• TW rata-rata = TO = 0,34375 hari
• TT (untuk semua order) diasumsikan 1 jam = 1 jam/8
jam/hari = 0,125 hari (untuk semua order)
• TIO rata rata = TT + TW = 0,125 hari + 0,34375 hari = 0.46875
hari
• TO dan TOP sesuai dengan setiap order.
PENGGAMBARAN ELEMEN LEAD TIME
UNTUK
SETIAP ORDER
• Komponen lead time
TO=3 JAM

TO=4 JAM
TIO = 0.46875 hari TOP=0,500 HARI
TOP=0,375 HARI
TIO = 0.46875 hari

TO=3 JAM
ORDER 1
ORDER 3
TO=1 JAM

TOP=
TIO = 0.46875 hari 0,125 TOP=0,375 HARI
HARI TIO = 0.46875 hari

ORDER 4

ORDER 2
DIAGRAM
DIAG RAM TROUGHPUT RENCANA

TIO = 0.46875
hari
TO = 11 JAM

TOP=
0,375 HARI

TIO = 0.46875
TOP=0,500 HARI
hari
TIO = 0.46875 TOP=
hari 0,125
HARI

TIO = 0.46875 TOP=


hari 0,375 HARI

1 2 3 4 5 6 7 8 9
TANGGAL
TOTAL HARI UNTUK SEMUA ORDER
TOTAL WAKTU SEMUA ORDER (HARI)

• WAKTU TOTAL PROSES = 4 X 0.46875 hari + 1,375 HARI = 3,25 HARI


• RENTANG DUE DATE PENGERJAAN TANGGAL MULAI 1-1-21 hingga 9-
1-16 = 9 HARI
BIAYA PROSES BUBUT
• BIAYA PROSES UNTUK SEMUA KOMPONEN /ORDER ADALAH WAKTU
PROSES (DALAM HARI DIJADIKAN JAM) DIKALIKAN ONGKOS BUBUT
PERJAM.

• MISAL ONGKOS SEWA MESIN BUBUT Rp. 20.000,- PER JAM, MAKA
BIAYA PROSES ADALAH = (3,25 HARI X 8 JAM/HARI) X Rp. 20.000,- /JAM

= Rp. 520.000,-
BIAYA LEAD TIME = (9 X 8 JAM/HR) X Rp. 20.000/JAM)
= Rp. 1.440.000,-