Anda di halaman 1dari 13

PT LAMI PACKAGING INDONESIA

DOCUMENT SUBJECT:
PROSEDUR ISOLASI – LOTO (Lock out Tag out)
PT LAMI PACKAGING INDONESIA
Contents

1 Tujuan...........................................................................................................................3
2 Ruang Lingkup............................................................................................................3
3 Definisi..........................................................................................................................3
4 Acuan............................................................................................................................4
5 Penanggung Jawab.....................................................................................................4
5.1 Manajer Proyek..................................................................................................................... 4
5.2 Superintendent Departemen................................................................................................ 4
5.3 Foreman/Supervisor............................................................................................................. 5
5.4 Karyawan............................................................................................................................... 5
5.5 SHE Representative.............................................................................................................. 5
6 Sistem Isolasi..............................................................................................................5
6.1 Pengenalan............................................................................................................................ 5
6.2 Pengajuan Permit Isolasi...................................................................................................... 6
7 Penguncian dan Penandaan......................................................................................7
7.1 Label Peralatan Rusak (Label Out of service)..................................................................... 7
7.2 Gembok dan Master Scissor................................................................................................ 7
7.3 Pelepasan label-label............................................................................................................ 7
7.4 Tanda-Tanda dan Penghalang (Barikade)........................................................................... 8
7.5 Pelaksanaan Pekerjaan........................................................................................................ 8
7.6 Penerapan Pada Kondisi Khusus........................................................................................ 8
7.7 Penyelesaian Pekerjaan....................................................................................................... 9
7.8 Pemutusan/Pengalihan listrik tegangan tinggi................................................................... 9
8 Tinjauan Ulang Prosedur..........................................................................................10
8.1 Tinjau Ulang Manajemen.................................................................................................... 10
8.2 Pelatihan.............................................................................................................................. 10
8.3 Pelanggaran Prosedur........................................................................................................ 10
9 Dokumentasi..............................................................................................................10
10 Lampiran.................................................................................................................... 10

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 1 of 12
PT LAMI PACKAGING INDONESIA
LEMBAR REVISI
REVISION SHEET

Revisi Tanggal Deskripsi perubahan


REVISION DATE DESCRIPTION OF CHANGE

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 2 of 12
PT LAMI PACKAGING INDONESIA
1 Purpose
1 Tujuan To describe the safe work procedures with apply the
Untuk membuat prosedur kerja yang aman dengan Energy isolation system and placement also removal of
menerapkan system isolasi energy dan pemasangan serta Personal padlock, Danger Tags, Scissor and Out of
pelepasan padlock, Danger tag Pribadi, Scissor dan Label Service tags during construction, repairing, servicing,
Out of service selama konstruksi, perbaikan, perawatan, testing and pre-commissioning.
pengujian dan pra-commissioning.
2 Scope
2 Ruang Lingkup The procedure is applicable for all employees of
Prosedur ini berlaku bagi seluruh karyawan Lamipak Lamipak Indonesia and Sub-contractors that they are
Indonesia dan karyawan kontraktor yang bekerja di setiap working in all business line work area.
lingkungan kerja dari seluruh lini Proyek Lamipak Indonesia.
3 Definitions
3 Definisi
Energy Disconnection or inhibition of all energy
Isolasi energi Pemutusan atau penghambatan dari semua Isolation supplies to equipment. (Electrical,
sumber penyuplai energi ke peralatan. (Listrik, mechanical, hydraulic, compressed air,
mekanik, hidrolik, udara bertekanan, kimia, chemical, thermal, include gravity or other
termal, termasuk gaya berat atau sumber energy adapted to injury to humans)
energy lainnya yang berpotensi cidera pada Isolation Permit A standard form signed by the
manusia) Superintendent/His Deputy (Or Above) and
Permit Isolasi Formulir standar yang ditandatangani oleh the Supervisor in charge to ensure the high
Superintendent/Deputy (Atau ke atas) dan voltage job is carried out safely.
pengawas yang bertanggung jawab untuk Permit Holder The person at the job site responsible for
memastikan pekerjaan bertegangan tinggi completing the high voltage task.
dilakukan secara aman.
Isolation The Isolation Requestor is the person who
Pemegang Orang yang bertanggung jawab menyelesaikan Requestor wishes to have work carried out on a piece
Permit pekerjaan bertegangan tinggi di tempat kerja of equipment or a total system of high
voltage which is to be isolated or de-
Pemohon Orang yang yang hendak melakukan pekerjaan energised for safety reasons.
Isolasi pada sebuah peralatan atau keseluruhan Energy Isolation Mechanical devices that physically prevent
sistem bertegangan tinggi yang harus diisolasi device transmission or release of energy.
untuk alasan keselamatan Preventive methods may be by
Perangkat Alat mekanis yang secara fisik mencegah disconnecting energy sources or by
isolasi energi transmisi atau pelepasan energi. Metode blocking energy flows
pencegahan mungkin dengan memutus sumber Isolation Point Controlling mechanism which when
energi atau dengan memblokir arus energi switched off or disengaged renders the
Titik Isolasi Mekanisme pengontrolan yang ketika dimatikan work area as isolated from energised
atau dilepaskan menjadikan area kerja terisolasi source.
dari sumber energi atau energy sisa. Lock Out The placement of a lockout tool on an
Penguncian Penempatan alat pengunci pada perangkat energy isolating device, in accordance with
pengiisolasi energi, sesuai dengan prosedur an established procedure, ensuring that the
yang ditetapkan, yang memastikan bahwa energy isolating device and the equipment
perangkat pengisolasi energi dan peralatan being controlled cannot be operated until
yang dikontrol tidak dapat dioperasikan sampai the lockout device is removed.
perangkat pengunci dilepas. Lock out Device A mechanical means of locking that uses an
Peralatan Alat pengunci mekanis yang menggunakan individually keyed lock to secure an energy
penguncian pengunci secara individual untuk isolating device in a position that prevents
mengamankan perangkat pengisolasi energi energization of a machine, equipment, or a
dalam posisi mencegah pemberian energi pada process
mesin, peralatan, atau proses.
Penandaan Penempatan alat penanda pada perangkat Tag Out The placement of a tag out tool on an
pengisolasi energi, sesuai dengan prosedur energy isolating device, in accordance with
yang ditetapkan, untuk menunjukkan perangkat an established procedure, to indicate the
pengisolasi energi dan peralatan yang dikontrol energy isolating device and the equipment
tidak dapat dioperasikan sampai perangkat being controlled may not be operated until
penanda dilepas the tag out device is removed
Danger tag Label yang diterapkan oleh orang yang bekerja Personal A tag applied by a person working on, or in,
Pribadi pada, atau di mesin/ peralatan untuk Danger Tag plant or equipment to indicate that operation
(Merah dan menunjukkan bahwa mesin/peralatan tersebut (Red and Black or energising of the plant or equipment is
Hitam pada tidak boleh dioperasikan. Disebut juga Label in Hazard prohibited. Also called a Personal Danger
penanda bahaya pribadi yang tujuan utamanya adalah Marking) Tag as its primary purpose is to protect
people.
bahaya) untuk melindungi orang.
Out of Service A tag applied by an employee to indicate
Tag the operational defects of a piece of
Label Peralatan Label yang dipasang oleh seseorang untuk
Rusak menunjukkan bahwa peralatan/mesin (Yellow and equipment, plant or machinery. The
(Kuning dan mengalami kerusakan. Peralatan/mesin Black) equipment, plant or machinery is not to be
used or operated if an Out of Service tag
Hitam) tersebut tidak boleh digunakanatau has been placed.

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 3 of 12
dioperasikan apabila telah dipasang label ‘Out
of service’. Voltage Level A Extra low voltage: Voltage with higher value
(Maximum voltage) 50 Volt. Extra low
Tegangan level Tegangan Ekstra Rendah: Tegangan dengan voltage is the safe voltage system for
A nilai setinggi-tingginya 50Volt. Tengangan people.
ekstra rendah ialah sistem tegangan yang Voltage Level B Low Voltage: Voltage with the maximum
aman bagi manusia 1000Volt.
Tegangan Level Tegangan Rendah (TR): Tergangan dengan
B nilai setinggi-tingginya 1000Volt (High Voltage)
Tegangan Level 1. Tegangan Menengah (TM): Tegangan lebih Voltage Level C 1. Middle Voltage: Voltage is more than
C (Tegangan dari 1000Volt (>1kV) sampai dengan 1000Volt (>1kV) until 35000Volt (35kV)
Tinggi) 35000Volt (35kV) 2. High Voltage: Voltage is more than
2. Tegangan Tinggi (TT) Tegangan lebih dari 35000Volt (>35kV)
35000Volt (>35kV)

4 Acuan
PUIL 2011 Persyaratan Umum Instalasi Listrik 4 Reference
LMIND-00-HS-PRC-
013 Procedure for Confined Space PUIL 2011 General Requirement for Electrical
LMIND-00-HS-PRC- Installation
016 Procedure for Confined Space LMIND-00-HS-PRC-
013 Procedure for Confined Space
LMIND-00-HS-
PRC-016 Procedure for Permit to Work

5 Penanggung Jawab
5.1 Manajer Proyek 5 Responsibilities
Memberi kewenangan terhadap Superintendent Departemen 5.1 Project Manager
untuk menilai dan menandatangani pengajuan permit isolasi,
dan, mendelegasikan seluruh Kepala Departemen untuk To give an authority for Superintendent Department or
memastikan pelaksanaan Prosedur Isolasi-LOTO dengan Department Head to be able to approved and
maksimal. assessed isolation permit requisition and delegate all
department head to ensure the good implementation of
5.2 Superintendent Departemen Isolation Procedure-LOTO.
Memastikan prosedur ini diterapkan oleh seluruh pekerja 5.2 Department Superintendent
termasuk sub-kontraktor saat bekerja untuk Lamipak
Indonesia. Juga, memastikan semua karyawan dan sub- Ensure this procedure is implemented for all
kontraktor mendapatkan pelatihan prosedur/instruksi kerja employees including sub-contractor when working for
isolasi energi sebelum melakukan pekerjaan di area kerja Lamipak Indonesia. And also, ensure all employees
Lamipak Indonesia. Juga menandatangani permit isolasi jika and sub-
ada pengajuan. contractors adequately trained in isolation
procedure/work instruction before commencing work in
Superintendet memberikan surat peringatan pada Karyawan Lamipak Indonesia. Also, to approve isolation permit if
(termasuk sub-kontraktor) yang melakukan pelanggaran any permit requisition.
terhadap prosedur ini dan menyerahkan surat peringatan
yang telah dilengkapi ke Departemen HR. Superintendent to give the warning letter to employees
(include sub-contractor) who failure to follow the
requirement in this procedure and submit that

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 4 of 12
5.3 Foreman/Supervisor complete warning letter to HR Department.
Memastikan prosedur dan sistem isolasi - LOTO ditaati 5.3 Foreman/Supervisor
dengan baik oleh seluruh bawahan dan sub kontraktor setiap Ensure that the correct isolation procedures and
saat. Dan memastikan semua bawahan dan sub kontraktor systems are adhered by subordinate and sub-
memiliki gembok dan label pribadi masing-masing. Juga contractors at all times. And ensure each subordinate
memastikan persyaratan Sistem Isolasi sudah dipatuhi and subcontractor has a pad lock and personal danger
sebelum menandatangani permit isolasi (Jika ada tag. Also, ensure all required by Isolation permit are
pengajuan). comply before signing off in Isolation permit (If any
Pengawas memberitahu Superintendent setiap terjadi requisition).
pelanggaran prosedur oleh pekerja (termasuk kontraktor) Supervision to report to Superintendent if any breach
sebagai proses pemberian surat peringatan. the rules by employees (include subcontractor) as part
5.4 Karyawan of punishment process.
Mengidentifikasi sumber energi dan melakukan 5.4 Employees
pengisolasian yang benar sebelum memulai pekerjaan. To identify energy sources and follow correct isolation
Melakukan pengetesan terlebih dahulu pada sistem isolasi prior to commence of work.
energy untuk memastikan efektif atau tidak. (Dead Test). Conduct prior testing of isolation systems to ensure
Merawat label (bahaya) pribadi dan gembok Pribadi (Yang they are effective or not (Dead Test).
dikeluarkan Lamipak Indonesia). Segera laporkan ke Maintain and care for their Personal Danger Tag and
Foreman/Supervisor jika terjadi kerusakan atau kehilangan Pad Lock (as issued by Lamipak Indonesia). Reporting
gembok dan label pribadi. to Foreman/Supervisor directly if broken or missing.
5.5 SHE Representative 5.5 SHE Representative
Memberikan Induksi dan Memastikan peserta induksi Conduct SHE Induction and ensuring that induction
mengerti tentang Prosedur/Instruksi Kerja Penggembokan participant understand about LOTO Procedure/Work
dan Pelabelan (Sistem Isoalsi). Instruction.
Memberikan Label Bahaya Pribadi dan Gembok standard Issued Personal Danger Tags and Pad Locks to the
kepada personil yang telah mendapatkan pelatihan LOTO. person who getting done for training LOTO.
Melaksanakan random inspeksi LOTO (Sistem Isolasi)
minimal sekali dalam sebulan Conduct random inspections LOTO (Isolation System)
at least once a month.
6 Sistem Isolasi
6 Isolation System
6.1 Pengenalan
 Semua sumber energy harus diidentifikasi dan dilakukan
6.1 Introduction
isolasi pada semua sumber energi (semua bagian/titik All energy sources shall be identified and isolated at all
energi), kemudian pengisolasian diuji untuk memastikan energy sources (all parts / energy point), then isolation
pekerjaan tersebut dapat dilakukan dengan aman. Titik-titik is tested to make sure the work can be done safely.
ini kemudian harus terkunci, dipasang label, ditutup atau Those point shall be locked, labeled, closed or secured
diamankan dan Permit Isolasi diimplementasikan untuk and Isolation Permit is implemented for high voltage
energi listrik tegangan tinggi.
Isolated all energy sources prior to servicing,
 Isolasi sumber energi sebelum melakukan perawatan, maintenance or repairing is an essential element of
pemeliharaan atau perbaikan merupakan elemen penting protecting employees from the unexpected
untuk melindungi karyawan dari potensi terlepasnya energi energization or motion, start up of the machine or
atau gerakan tak terduga, penyalaan mesin atau peralatan, equipment, or release of stored energy
atau terlepasnya energi yang tersimpan.
 Perangkat Isolasi Energi, termasuk namun tidak terbatas
 Energy Isolation Device including, but not limited to,
the following:
pada, hal-hal berikut:
- A manually operated electrical circuit breaker;
- Pemutus sirkuit listrik yang dioperasikan secara manual; - A disconnect switch;
- Sakelar pemutus;
- Manually operated switches by which the conductors
- Sakelar yang dioperasikan secara manual dimana of a circuit can be disconnected from all ungrounded
konduktor suatu rangkaian dapat diputuskan dari semua supply conductors and, in addition, no pole can be
konduktor suplai yang tidak tersalur pembumian dan, operated independently;
sebagai tambahan, tidak ada kutub (electroda) yang dapat - A line valve;
dioperasikan secara independen;
- A block (e.g. blind flange, block valve) and any
- Katup saluran; similar device used to block or isolate energy.
- Penutup (misalnya Flange, block valve) dan perangkat (Push buttons, selector switches and other control
serupa yang digunakan untuk memblokir atau mengisolasi circuit type devices are not considered energy isolating
energi devices).
(Tombol tekan, sakelar pemilih, dan perangkat jenis
rangkaian kontrol lainnya tidak dianggap sebagai The Isolation Permit System constitutes a formal and
perangkat pengisolasi energi) detailed method of ensuring safe systems of work for
task with high voltage electric. LMIND-00-HS-FOR-
 Sistem Izin Isolasi merupakan metode formal dan terperinci 0018; ISOLATION PERMIT is used where the
untuk memastikan sistem kerja yang aman untuk tugas personell involved and the tasks are exposed by
high voltage
Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 5 of 12
dengan listrik tegangan tinggi. LMIND-00-HS-FOR-0018; electrical hazard (1000 Volt or Above).
IZIN ISOLASI digunakan di mana personel yang terlibat
dan pekerjaan – pekerjaan terpapar oleh bahaya listrik Prior to the Isolation Permits becoming effective, the
tegangan tinggi (1000 Volt atau lebih). Superintendent/His Deputy (Or Above) and Supervisor
Shall be ensuring that persons involve has been
 Sebelum mengeluarkan Permit Isolasi, trained and have a personal danger tags and pad
Superintendent/Deputy (Atau lebih tinggi) dan pengawas locks.
harus memastikan bahwa semua orang yang terlibat sudah
mendapatkan pelatihan LOTO serta memiliki Danger tag  This will generally involve the fixing of a Personal
Pribadi dan Pad lock. Danger tag, Pad lock, and Scissor to every point of
isolation. Isolations must be de-isolated and every tag,
 Dalam hal ini harus memasang Danger tag Pribadi, Pad lock, pad lock, and scissor removed before the permit is
dan Scissor di setiap titik isolasi. Sistem Isolasi harus dilepas closed out.
sebelum permit isolasi ditutup atau dibatalkan.
 Pada pekerjaan mekanik dan auto elektrik (low voltage) yang  For mechanic job and auto electrician job (low voltage)
tidak memerlukan permit, semua pekerja yang terlibat which is don’t need the isolation permit, involves
tetap harus mengidentifikasi semua sumber energi yang ada person are still have to identify all energy sources at
the machine/equipment and isolated to ensure that all
pada mesin/peralatan dan diisolasi untuk menjamin bahwa
stored energy are relieve and not exposure to people in
energi apapun yang tersimpan tidak terlepas dan tidak
place. The work can be conducted safely.
terpapar dengan pekerja. Sehingga pekerjaan dapat
dilakukan dengan aman.  Locking devices shall be installed on Energy isolation
 Perangkat penguncian harus dipasang pada perangkat devices during work performed, locking devices must
isolasi energi selama proses pekerjaan dilakukan, perangkat be equipped with personal tagging personal tagging
penguncian harus dilengkapi dengan penandaan baik and equipment status
penandaan personal maupun status dari peralatan  Besides involve person to place their pad locks, tags,
 Selain pemasangan gembok, label-label, dan Scissor, juga and scissor lock, they are shall install another
harus memasang pengunci/pengaman lain seperti Pin/Safety locks/securing like a dump pin/safety line for trucks,
line untuk dump body truck, merilis tekanan angin yang relieve stored air pressure, Wheel chocked to prevent
tersimpan, mengganjal ban untuk mencegah pergerakan that machine/equipment move, protected hot are, etc.
mesin/peralatan, menutup bagian-bagian yang panas, dan
lain-lain. General Methods of hazardous Energy isolation can be
 Secara umum metode pengisolasian Energi berbahaya seen on appendix 10.2
dapat dilihat pada lampiran 10.2.

6.2 Requesting Isolation Permit


6.2 Pengajuan Permit Isolasi
Setiap pekerja yang akan bekerja pada peralatan  Any employee, who is required to work on high voltage
bertegangan tinggi, harus mendapatkan izin dari equipment, must obtain permission from an
Superintendent/His Deputy (Or Above) and complete
Superintendent/Deputy (Atau lebih tinggi) dan melengkapi
an Isolation Permit (LMIND-00-HS-FOR-0018). The
Permit Isolasi (LMIND-00-HS-FOR-0018). Permit Isolasi
Isolation Permit will describe all point to be isolated
akan menjelaskan semua bagian yang harus diisolasi dan and define the exact boundaries of the isolation,
menentukan batas-batas yang tepat dari isolasi, termasuk including switches, circuit breakers, valves etc.
switch, pemutus sirkuit, katup dll
Superintendent/Deputy (Atau lebih tinggi) akan mencatat  The Superintendent/His Deputy (Or Above) will record
rincian pekerjaan pada Permit Isolasi dan harus the details of the work on the Isolation Permit and sign
menandatangani Permit Isolasi tersebut. Salinan permit the Isolation Permit. A copy of permit isolation is given
to the permit holder and available at each isolation
isolasi diberikan kepada pemegang permit dan salinannya
point.
tersedia di setiap titik isolasi.
Semua keterangan yang diperlukan harus diisi secara rinci  All required information shall be filled in detail on the
pada label yang dipasang. label installed.

 Berapapun jumlah pekerja yang bekerja pada pekerjaan  Regardless of the number of workers who dedicated
tegangan tinggi, mereka harus menandatangani Permit on high-voltage jobs, they shall sign the Isolation
Isolasi dan memasang Danger tag Pribadi, Pad lock dan Permit and install the Personal Danger tag, Pad lock
Scissor and Scissor

 Permit Isolasi ini hanya berlaku selama 12 jam. Apabila  Isolation Permit is only valid for 12 hours. If the
pekerjaan masih akan dilanjutkan pada shift berikutnya, work is still to be continued in the next shift, the permit
pemegang permit harus mengakhiri dan menyelesaikan holder shall terminate and complete the Isolation
permit Isolasi pada akhir pergantian shift dan Permit Isolasi permit at the end of the shift change and the Isolation
diperbaharui oleh crew pada shift berikutnya dan Permit is updated by the crew on the next shift and re-
ditandangani kembali oleh pengawas dan appointed by the Supervisor and Superintendent /
Superintendent/Deputy Deputy

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 6 of 12
7 Penguncian dan Penandaan
7.1 Label Peralatan Rusak (Label Out of service) 7 Lock Out And Tag Out
 Apabila ada plant, peralatan atau mesin, yang ditemukan 7.1 Out of Service Tags
rusak atau bermasalah, maka harus segera ditarik dari  Any plant, equipment or machinery, is found to be
pengoperasian dan memasang label Out of service, untuk damaged or defective, it shall immediately be
menunjukkan bahwa plant, mesin atau peralatan tersebut withdrawn from service and an Out of Service tag
tidak layak untuk digunakan atau dioperasikan. Service tag placed on it, to indicate it is unsafe to use. The tag
tersebut harus diisi dan dipasang ke titik isolasi utama shall be filled in and fixed to the main isolation point of
peralatan. the equipment. The Supervisor or authorised repairer
 Pengawas atau Superintendent/Deputy (Atau lebih tinggi) shall be notified as soon as practicable.
Mekanik atau Elektrik harus diberitahu sesegara mungkin  Mechanic or Electric Supervisor or
untuk melakukan perbaikan superintendent/Deputy (or Above) must informed
 Mesin atau peralatan yang terdapat label Out of service immediately to conduct repair.
tidak dapat digunakan, dipindahkan atau dioperasikan  Machinery or equipment displaying an Out of Service
kecuali untuk keperluan perbaikan dan pengetesan. Tag is not to be used, moved or operated except to
 Aturan tentang label Out of service maintenance or testing purposes.
Out of service Tag ditempatkan pada:  Out of Service Tags Rules
- pekerjaan yang belum selesai Out of Service Tags are placed on:
- Perlengkapan yang salah, rusak, tidak standard atau - Incomplete jobs
berbahaya - Faulty, damage, substandard or dangerous
- Peralatan berstatus “Out of service” karena alasan equipment
operasional - Equipment to be kept out of service for
 Service tag TIDAK untuk digunakan sebagai pengganti operational reasons
Personal Danger tag. Peralatan yang telah dipasang label  Out of service NOT to be used as a substitute for
Out of service tidak akan dijalankan atau dioperasikan. Personal Danger Tags. Equipment that has been
Label Out of service harus selalu mencamtumkan status tagged Out of Service shall not be started or operated.
terkini akan mesin atau peralatan. Out of Service Tags shall always show the current
status of the equipment.
7.2 Gembok dan Master Scissor
 Gembok / Pad lock yang digunakan harus terpasang 7.2 Padlock and Master Scissor
bersamaan dengan Danger tag Pribadi.  The used padlock shall be installed with the Personal
 Master scissor dapat juga digunakan jika jumlah pekerja Danger tag.
yang terlibat lebih dari 1 atau titik pemasangan gembok /  Master scissors can also be used if the number of
padlock tidak mencukupi untuk jumlah pekerja yang terlibat. workers involved more than 1 or padlock mounting
 Gembok / Pad lock hanya dapat dilepas oleh orang yang points is insufficient for the number of workers
memasang atau pemiliknya. Aturan pelepasan gembok involved.
sama halnya dengan pelepasan Danger tag Pribadi.  Padlock can only be removed by the person who
 Apabila ada pekerja yang lupa/tidak melepas Gembok, installed it or the owner. The lock release rule is the
maka harus kembali ke tempat kerja untuk melepas same as Danger's Personal tag release.
Gembok tersebut. Apabila pemiliknya tidak dapat kembali  If there is a worker who forgot / did not remove the
ke tempat kerja, maka harus dilakukan penyelidikan dan Padlock, then the worker must return to the workplace
Gembok hanya boleh dilepas atas seijin Superintendent to remove the Padlock. If the worker is unable to
area atau lebih tinggi. return to the workplace, investigations must be
perform and Padlock may only be removed upon the
7.3 Pelepasan label-label
permission of the Superintendent area or higher
 Danger Tag Pribadi 7.3 Removal of Tags and Locks
Tidak diijinkan seseorang untuk melepas personal Danger
 Personal Danger Tags
tag milik orang lain. Personal Danger tag hanya boleh
dilepas oleh orang yang memasang dan pemilik label No person is permitted to remove personal Danger
tersebut. tags belonging to others. Personal Danger tags may
only be removed by the person who installed and the
Apabila pemilik label tidak ada, label tersebut hanya dapat
owner of the label
dilepas atas persetujuan dari Manajer/Superintendent
departemen terkait setelah penyelidikan menyeluruh If the label owner is not present, the label may only be
dilakukan. removed upon approval from the Manager /
Superintendent of the relevant department after a
Kegagalan dalam mematuhi persyaratan ini akan dianggap
thorough investigation has been conducted.
sebagai pelanggaran serius.
A Failure to comply with these terms will be
considered a serious violation.
 Label Peralatan Rusak
Hanya pengawas atau orang yang ditunjuk atau orang yang  Out of Service Tags
memiliki kewenangan selama perbaikan peralatan yang Only the authorised repairer or supervisor or
dapat melepas label Out of service.

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 7 of 12
Pelepasan label Out of service hanya dapat dilakukan delegated person of the plant or equipment shall
setelah perbaikan benar-benar selesai dan siap untuk remove an Out of Service tag.
dikembalikan untuk dioperasikan secara normal dan aman. Removal of the tag shall occur only after the
Personil yang melakukan perbaikan harus memastikan appropriate repair has been made and the repairer is
bahwa service tag telah dilepas sebelum peralatan satisfied the equipment can safely be returned to
direlokasi atau dikembalikan untuk dioperasikan. normal use.
Repairers shall ensure that the tag has been removing
 Pengunci / Gembok dan master Scissor prior to relocating or return to operate.
Pad lock yang digunakan harus terpasang bersamaan
 Locks and Master Scissor
dengan Danger tag Pribadi dan Scissor lock.
The pad lock that used must be installed along with
Gembok hanya dapat dilepas oleh orang yang memasang
Personal Danger tag and Scissor lock.
atau pemiliknya. Aturan pelepasan gembok sama halnya
dengan pelepasan Danger tag Pribadi The padlock can only be removed by the person who
installed it or the owner. The lock release rule is the
same as Personal Danger tag release
7.4 Tanda-Tanda dan Penghalang (Barikade)
7.4 Signs and Barriers
 Pengisolasian yang efektif memerlukan tindakan lebih lanjut
dalam bentuk tanda-tanda (rambu) dan  Effective isolation may require further precautions in
penghalang/barikade. Orang-orang yang terlibat dapat the form of signs and barriers. Person Involves may
menempatkan tanda-tanda/rambu yang sesuai pada place appropriate signage on equipment.
peralatan.  The Supervisor or the person Involves may install
barriers or signage as a visual warning to delineate
 Pengawas atau orang yang terlibat dapat memasang areas or systems or machine/equipment that are being
penghalang/barikade sebagai peringatan yang terlihat untuk
isolated or tested
menandakan bahwa area atau sistem atau mesin dan
peralatan tersebut sedang diisolasi atau dilakukan
pengetesan. 7.5 Performing the Work
7.5 Pelaksanaan Pekerjaan  Prior starting the job, the employee shall install Label
Out of service on equipment, or machine
 Sebelum memulai pekerjaan, karyawan harus memasang
Label Out of service pada peralatan, atau mesin  The worker who involved can install their own Pad
lock, Personal Danger tag, and Scissor lock after the
 Pekerja yang terlibat dapat memasang Pad lock masing- Out of service label has been installed.
masing, Danger tag Pribadi, dan Scissor lock setelah label
Out of service telah terpasang.  All required information shall be filled in detail on the
label installed.
 Semua keterangan yang diperlukan harus diisi secara rinci  Any stored energy shall be isolated and released.
pada label yang dipasang. Isolation not only limited to locking and labelling.
 Energi apapun yang tersimpan harus diisolasi dan dilepas.  If more than one person is working on a piece of
Pengisolasian tidak hanya terbatas pada penggembokan equipment at the same time, each person must apply
dan pelabelan. his/her personal lock to the lockout device. If more
 Jika lebih dari satu pekerja melakukan pekerjaan pada than one person is applying a lock to a lockout device,
suatu peralatan pada saat yang sama, maka setiap pekerja a hasp or lock box may be used. Specific lockout
yang terlibat harus menerapkan kunci pribadinya ke procedures should include the proper use of lockout
perangkat lockout. Jika lebih dari satu orang menerapkan devices such as lock boxes
kunci ke perangkat lockout, pengait atau kotak kunci atau  After isolation is done, prior starting the work, the
Master Scissor Lock dapat digunakan. worker shall perform testing on the installed isolation
 Setelah pengisolasian dilakukan, sebelum memulai system (dead test) to ensure that the machine or
pekerjaan, pekerja harus melakukan pengetesan pada equipment is well isolated. And ensure that all stored
sistem isolasi yang ada (tes mati) untuk memastikan bahwa energy is released so that work can be done safely.
mesin atau peralatan sudah terisolasi dengan baik. Dan Testing can be done through inspection or observing a
memastikan semua energi yang tersimpan sudah terlepas measuring instrument or indicator, manual testing,
supaya pekerjaan dapat dilakukan dengan aman. circuit testing, motion or flow monitoring, and
Pengetesan dapat dilakukan melalui inspeksi atau measurement.
mengamati alat ukur atau indikator, mencoba secara
manual, menguji sirkuit, memantau gerakan atau aliran, dan
pengukuran.

7.6 Application Under Specific Condition


7.6 Penerapan Pada Kondisi Khusus
 There may be situations where repairing, cleaning,
 Dimungkinkan ada situasi ketika perbaikan, pembersihan, lubrication or equipment adjustment must be
pelumasan atau penyetelan peralatan harus diselesaikan
saat beroperasi, dalam gerakan, atau teraliri suatu energi.
Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 8 of 12
Dan atau ketika pekerjaan harus dilakukan pada peralatan completed when on operating, in motion, or in an
di mana penguncian fisik tidak dimungkinkan untuk energy level. And or when work should be done on
diterapkan equipment where physical locking is not possible
 Dalam situasi ini, penilaian risiko dan rencana applied
pengendalaian energy berbahaya harus dikembangkan  In this situation, risk assessments and hazardous
untuk memastikan aktivitas kerja dilakukan dengan cara energy control plans shall be developed to ensure
yang aman work activities are conducted in a safe manner
 Rencana pengembangan pengendalian energi yang  The development plans for hazardous energy control
berbahaya harus mencakup unsur-unsur berikut shall include the following elements :
a. Mendokumentasikan penilaian risiko; a. Documenting risk assessments;
b. Implementasi langkah-langkah pengurangan risiko b. Implementation of risk reduction measures as
sebagaimana ditentukan dari penilaian risiko yang determined from possible risk assessments including;
mungkin termasuk; - Designing changes, substitution of less harmful
materials or application of ergonomic principles;
- Merancang perubahan, substitusi bahan yang
kurang berbahaya atau penerapan prinsip - Implementation of safeguarding and
ergonomi; complementary safeguards;
- Penerapan safeguarding dan pelengkap tindakan - Documented safe practices; and / or additional
perlindungan; Training ..
- Praktik kerja aman yang didokumentasikan; dan /  If locking procedures are unusable and adequate risk
atau Pelatihan tambahan.. reduction can not be achieved by using other control
methods, activity or work must not be performed
 Jika prosedur penguncian tidak dapat digunakan dan
pengurangan risiko yang memadai tidak dapat dicapai
dengan menggunakan metode kontrol lainnya, aktivitas
atau pekerjaan tidak boleh dilakukan.
7.7 Penyelesaian Pekerjaan
7.7 Completion of Works
 Apabila pekerjaan selesai pada shift itu juga, semua  If work is completed within the shift, the Permit Holder
personil yang terlibat melepas semua gembok, Danger tag removes the Personal Danger Tag, and takes off the
Pribadi, dan Scissor lock. Kemudian melaporkan kepada padlock and scissors and notifies the Supervisor that
pengawas bahwa pekerjaan tersebut telah selesai the work already completed.
 Untuk Pekerjaan dengan permit isolasi maka pekerja  The work with isolation permit, the dedicated worker
melapor kepada pengawas dan superintendent/ deputy shall reporting to supervisor and superintendent /
yang mengeluarkan permit untuk melakukan deputy (or above) that signed the permit to conduct
pengetesan/pemeriksaan mesin/peralatan yang telah testing/inspection to machine/equipment that has been
dikerjakan. Penandatanganan Permit Isolasi (PTP-SHE-FO- done. Signing the isolation permit (PTP-SHE-FO-G-
G-0019 ) menunjukkan bahwa permit isolasi telah selesai 0019) indicate that the isolation permit has been
masa berlakunya dan dibatalkan. completed its validity and cancelled
 Ketika pekerjaan telah selesai dilakukan, Kru mekanik atau  Once the work has been completed, an authorized
elektrik atau yang memiliki otoritas harus melakukan mechanical or electrical crew shall test that the
pengetesan bahwa mesin atau peralatan sudah terlepas machine or equipment is completely detached from
dari isolasi dengan sempurna. the insolation.
 Pengawas dan atau orang yang ditunjuk melepas label Out  The supervisor and /or designated person release the
of service yang terpasang serta mengembalikan label of the installed Out of service and return the
mesin/peralatan untuk dioperasikan sebagaiamana machine / equipment to be operated as appropriate.
mestinya.
 If the work to go over more than one shift, all involved
 Apabila pekerjaan harus dilanjutkan pada shift berikutnya, worker removed padlock, personnel danger tag, and
semua personil yang terlibat melepas semua gembok, scissor lock. Then ensure the Out of Service tag still
Danger tag Pribadi, dan Scissor lock. Kemudian attached and its information still relevant and or up-
memastikan label Out of service masih terpasang dan dated
informasi yang tertulis masih relevan dan atau diperbaharui.  Personals who will performing work on the next shift
 Personil yang melakukan pekerjaan pada shift berikutnya shall read and understand the information written on
harus membaca dan memahami informasi yang tertulis the Out of service label that is still installed. Then
pada label Out of service yang masih terpasang. Kemudian install a padlock, Personal Danger tag, and Scissor
memasang gembok, Danger tag Pribadi, dan Scissor lock lock as well as testing on the insolation system to
serta dilakukan pengujian pada sistem isolasi untuk ensure work can proceed safely
memastikan pekerjaan dapat dilanjutkan dengan aman.

7.8 Pemutusan/Pengalihan listrik tegangan tinggi 7.8 High Voltage Switching


Hanya orang yang memiliki kewenangan (misalnya Petugas Only authorised personnel (e.g. the high voltage
listrik bertengan tinggi yang berkompeten) yang diizinkan electrician) shall be permitted to carry out high
untuk melaksanakan pekerjaan atau pengalihan listrik
voltage switching.
bertegangan tinggi.

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 9 of 12
8 Tinjauan Ulang Prosedur
8 Review Of Procedure
8.1 Tinjau Ulang Manajemen
8.1 Management Review
Tinjau ulang kesesuaian prosedur ini, dan pelaksanaannya,
Review of the suitability of this procedure, and it’s
harus dilakukan apabila ada kecelakaan serius yang terkait,
implementation, shall be undertaken as a result of
kekurangan yang diamati dari hasil audit, inspeksi, dan
serious incidents, observed deficiencies, audits,
umpan balik karyawan, atau ada perubahan perundang-
inspections, employee feedback, changing legislation
undangan/regulasi, dan atau ada jadwal tinjau ulang
and/or regular documentation review. Approval of
berkala terhadap dokumentasi.
changes is the responsibility of the related Managers
Persetujuan perubahan adalah tanggung jawab Manajer-
Manajer terkait. 8.2 Training
Initial training will be provided to all employees during
8.2 Pelatihan
the site induction. This covers the use and the
Pelatihan awal akan diberikan kepada seluruh karyawan recognition of Personal Danger Tags, Out of Service
pada saat induksi site. Ini mencakup penggunaan dan Tags, Pad Locks and Scissor lock.
pemasangan Danger tag Pribadi, label Out of service, Specific LOTO training shall be provided to personnel
Gembok dan Scissor.
who have working in plant, machine and equipment
Pelatihan khusus harus diberikan kepada personil yang that required to isolated and records shall be
bekerja pada mesin atau peralatan yang mensyaratkan maintained. In addition, personnel that their jobs are
untuk diisolasi dan catatan harus dipelihara. Selain itu, not directly involved in this procedure will be advised
pekerja yang pekerjaannya tidak terlibat langsung dalam at Toolbox meetings/safety meeting/general
prosedur ini akan disampaikan pada tool box socialization
meeting/safety meeting/sosialisasi umum
8.3 Procedure Violation
8.3 Pelanggaran Prosedur Employees who do not release LOTO at the end of the
Karyawan yang tidak melepas LOTO pada akhir shift kerja, work shift, and / or violate or fail to comply with the
dan atau melanggar atau gagal mengikuti persyaratan di requirements of this procedure are categorized as
prosedur ini dikategorikan sebagai Pelanggaran Berat yang Serious Violations which may be subject to disciplinary
dapat diberikan tindakan disiplin level III atau PHK ; sesuai action level III or determination; in accordance with the
dengan Matriks Pelanggaran Golden Rules dan Peraturan Golden Rules Violation Matrix and Company
Perusahaan Regulations

9 Dokumentasi
Berikut adalah dokumentasi referensi yang 9. Documentation
digunakan dalam prosedur ini: The following company documentation is referenced in
LMIND-00-HS-FOR-0018 Permit to Work Form this procedure:
LMIND-00-HS-FOR-0018 Permit to Work Form

10 Lampiran
Flow chart penerapan sistem isolasi
10. Attachment
Flow chart of Isolation System Implementation

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 10 of 12
Awal

Jalankan mesin/
Pasang label out of NO Perlu inspeksi dan YES Mesin/ Perlu inspeksi dan peralatan secara
Peralatan
service perawatan? NO perawatan? NO
rusak? normal

YES YES
Lakukan Isolasi mesin/peralatan Lakukan Isolasi mesin/peralatan

Orang yang telah mendapatkan training LOTO, memasang


Karyawan memasang label out of service di Apakah perlu permit label out of service, danger tag pribadi, pad lock, dan scissor
peralatan atau panel isolasi? di titik isolasi utama

Pada shift berikutnya,


Karyawan mengajukan permit isolasi kepada karyawan yang telah
Superintendent ke atas atau deputi-nya Aktivitas yang berhubungan dengan tegangan tinggi (Di atas mendapatkan training
Melakukan pengetesan Isolasi (Tes Mati) dan Memastikan LOTO memastikan label
1000Volt) harus menggunakan permit isolasi semua energi yang tersimpan sudah terisolasi out of service terpasang
dan mengerti informasi
Superintendent/Deputi dan atau pengawas
yang tertulis dan
memastikan semua karyawan yang terlibat telah
ikut training dan memiliki pad lock dan label memasang danger tag pribadi, pad lock,
Lakukan pekerjaan dengan aman dan scissor di titik isolasi utama
bahaya pribadi masing-masing

Superintendent/Deputi melengkapi dan


menandatangani Permit Isolasi Karyawan melepas danger
tag pribadi, pad lock, dan
TIDAK
Pekerjaan scissor dan memastikan label out of
Semua orang yang terdaftar di isolation permit Selesai? service masih terpasang dan informasi
memasang danger tag pribadi, pad lock, scissor, yang tertulis masih relevan
dan sign on di permit
Pada awal shift berikutnya,
karyawan mengajukan permit YA
kepada Superintendent/Deputi
Pengawas menandatangani permit Catatan:
Karyawan melepas danger tag
pribadi, pad lock, dan scissor Apabila ada pekerja yang lupa/tidak melepas LOTO,
maka harus kembali ke tempat kerja untuk melepas
Melakukan pengetesan Isolasi (Tes Mati) dan LOTO tersebut. Apabila pemiliknya sudah tidak ada
Superintendent/Deputi dan pengawas Memastikan semua energi yang tersimpan atau jauh dari lokasi kerja, maka harus dilakukan
menandatangani pembatalan permit sudah terisolasi Pengawas atau orang yang ditunjuk penyelidikan dan LOTO hanya boleh dilepas atas seijin
melepas label out of service dan Superintendent ke atas. Karyawan yang tidak melepas
mengembalikan mesin/ alat untuk
dioperasikan LOTO pada akhir shift kerja, akan mendapatkan surat
Lakukan pekerjaan dengan aman teguran tertulis level 1.

TIDAK
Lepas danger tag pribadi, Pekerjaan Akhir
pad lock, dan scissor selesai?

YA

Semua karyawan sign Superintendet/Deputi dan atau


Pengawas atau
off di permit dan pengawas memastikan peralatan
melepas danger tag sudah tidak terisolasi dan orang yang ditunjuk melepas Akhir
label out of service
pribadi, pad lock, dan menandatangani pencabutan
scissor permit

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 11 of 12
Start

Out of Service Tag Inspection or Machine/ Inspection or Run Machine/


NO YES
Implementation Maintenance Equipment Maintenance Equipment
NO NO
Normally
Process Required? Defect? Required?

YES YES
Isolate the machine/equipment Isolate the machine/equipment

Employees place an out of service tag on Is the Isolation Trained (LOTO) persons place Out Service tag,
equipment or electrical panel Permit required? personal danger tags, pad locks, and
Scissors at the main isolation point

Employees request Isolation Permit from At the start of next shift, Trained
Superintendent Above/His Deputy (LOTO) persons make sure that Out of
High voltage (1000Volt above) activities is required
Test Isolation (Dead Test) and Ensure Service tag in place and understand
to complete the Isolation permit
that all stored energies relieve for the information, and place the
personal danger tags, pad locks, and
Superintendent Above/His Deputy and or supervisor to ensure that
Scissors at the main isolation point
the employees has been training and have a pad lock and personal
danger tag
Conduct job safely

Superintendent Above/His Deputy


to complete and approval the isolation permit
Is the job Employees Remove Personal Danger
NO
repaired or Tags, Pad Locks, Scissors and Ensure
All employee working under isolation permit to place their personal tested Out of Service tag in place and
At the start of next shift, danger tags, pad locks, scissors then sign on to the permit complete? Updated
employees request Isolation permit
from Superintendent
Above/His DeputyAuthorized YES
person
Supervisor to sign Isolation Permit
Employees Remove Personal
Danger Tags, Pad Locks, Scissors Notes:
If any employees who was not removed their
LOTO’s, they must back to workplace to remove
Test Isolation (Dead Test) and Ensure that all
Superintendent Above/His Deputy And Supervisor or Delegated person to these LOTO’s. If those person was not available and
stored energies relieve
Supervisor to complete and cancel remove out service tag and put or out of site, investigation must be conduct and
isolation permit back the machine/equipment into those LOTO can remove only by Superintendent
service above approval/ permission.
Conduct job safely

Employees who were not removed their LOTO’s at


NO End the end of shift will lead to warning letter level 1.
Remove personal danger Is the job repaired or
tags, pad locks, and scissors tested complete?

YES

All Employees sign off Superintendent Above/His


Supervisor or
the isolation permit and Deputy And or supervisor to End
delegated
remove personal ensure the equipment or panel is
employees remove
danger tags, pad locks, de-isolate and cancel the out of service tag
Scissor isolation permit (sign)

Once printed this document becomes uncontrolled. Refer to Lamipak Indonesia DocCon for controlled copy.
Document No.: LMIND-00-HS-PRC-015 Rev No. 2 12 of 12