Waktu selesai terdahulu (EFT) dari suatu kegiatan adalah jumlah dari
waktu mulai terdahulu (EST) dan waktu kegiatannya
EFTi = EST i + t i
Perhitungan Forward Pass
EST (Earliest Start Time) EFT (Earliest Finish Time)
ESTA = 0 EFTA = ESTA + tA = 0 + 4 = 4
ESTB = EFTA = 4 EFTB = ESTB + tB = 4 + 3 = 7
ESTC = EFTB = 7 EFTC = ESTC + tC = 7 + 4 = 11
ESTD = EFTB = 7 EFTD = ESTD + tD = 7 + 2 = 9
ESTE= EFTD = 9 EFTE = ESTE + tE = 9 + 6 = 15
ESTF = EFTD = 9 EFTF = ESTF + tF = 9 + 14 = 23
ESTG = EFTC = 11 EFTG = ESTG + tG = 11 + 6 = 17
ESTH = EFTG = 17 EFTH = ESTH + tH = 17 + 4 = 21
ESTI = EFTE = 15 EFTI = ESTI + tI = 15 + 12 = 27
ESTJ = EFTE = 15 EFTJ = ESTJ + tJ = 15 + 4 = 19
ESTK = EFTE = 15 EFTK = ESTK + tK = 15 + 12 = 27
ESTL = EFTF = 23 EFTL = ESTL + tL = 23 + 4 = 27
ESTM = Max (EFTH, EFTI, EFTJ, EFTK, EFTL) = 27 EFTM = ESTM + tM = 27 + 33 = 31
Result of Forward Pass
of Earliest Start and
7 11 11 17 17 21
Finish Time
C 4 G 6 H 4
15 27
I 12
0 4 4 7 9 15 15 19 27 31
A 4 B 3 E 6 J 4 M 4
15 27
K 12
7 9 9 23 23 27
D 2 F 14 L 4
Backward Pass
➢ Aturan Waktu Selesai Terakhr (LFT)
Sebelum suatu kegiatan dapat dimulai, seluruh pendahulu langsungnya harus
diselesaikan.
Jika suatu kegiatan memiliki pendahulu langsung hanya satu kegiatan, LFT-nya
sama dengan LST dari kegiatan yang secara langsung mengikutinya.
Apabila suatu kegiatan terpecah menjadi 2 kegiatan atau lebih, maka waktu
paling akhir (LFT) kegiatan tersebut sama dengan waktu mulai paling akhir
(LST) kegiatan berikutnya yang terkecil.
➢ Aturan Waktu Mulai Terakhir (LST)
Waktu mulai terakhir (LST) dari suatu kegiatan adalah perbedaan/selisih
antara waktu selesai terakhir (LFT) dan waktu kegiatannya.
LSTi = LFTi - ti
Perhitungan Backward Pass
LFT (Latest Finish Time) LST ( Latest Start Time)
LFTM = EFTM = 31 LSTM = LFTM – tM = 31-4 = 27
LFTL = LSTM = 27 LSTL = LFTL – tL = 27-4 = 23
LFTK = LSTM = 27 LSTK = LFTK – tK = 27-12 = 15
LFTJ = LSTM = 27 LSTJ = LFTJ – tJ = 27-4 = 23
LFTI = LSTM = 27 LSTI = LFTI – tI = 27-12 = 15
LFTH = LSTM = 27 LSTH = LFTH – tH = 27-4 = 23
LFTG = LSTH = 23 LSTG = LFTG – tG = 23-6 =17
LFTF = LSTL = 23 LSTF = LFTF – tF = 23-14 = 9
LFTE = Min (LSTI, LSTJ, LSTK) = 15 LSTE = LFTE – tE = 15-6 = 9
LFTD = LSTF = 9 LSTD = LFTD – tD = 9-2 = 7
LFTC = LSTG = 17 LSTC = LFTC – tC = 17-4 =13
LFTB = Min (LSTC, LSTD) = 7 LSTB = LFTB – tB = 7-3 = 4
LFTA = LSTB = 4 LSTA = LFTA – tA = 4-4 = 0
Result of Backward
Pass of Latest Start and
7 11 11 17 17 21
Finish Time
C 4 G 6 H 4
13 17 17 23 23 27
15 27
I 12
15 27
0 4 4 7 9 15 15 19 27 31
A 4 B 3 E 6 J 4 M 4
0 4 4 7 9 15 23 27 27 31
15 27
K 12
15 27
7 9 9 23 23 27
D 2 F 14 L 4
7 9 9 23 23 27
Slack dan Jalur Kritis
➢Slack adalah waktu yang dimiliki oleh setiap kegiatan untuk bisa
diundur tanpa menyebabkan keterlambatan proyek keseluruhan.
Slack for activity i = LSTi – ESTi
Slack for activity i = LFTi – EFTi
➢ Jalur Kritis adalah jalur waktu terpanjang yang melalui jaringan yang
terdiri dari kegiatan yang memiliki slack 0. Sehingga jika kegiatan
dalam jalur tersebut mengalami penundaan, maka penyelesaian
proyek tersebut juga akan mengalami penundaan.
Perhitungan Slack
The critical path
The critical path and
slack conditions 7 11 11 17 17 21
C 4 G 6 H 4
13 17 17 23 23 27
Slack = 6 Slack = 6 15 27 Slack = 6
I 12
15 27
0 4 4 7 9 15 Slack = 0 15 19 27 31
A 4 B 3 E 6 J 4 M 4
0 4 4 7 9 15 23 27 27 31
Slack = 0 Slack = 0 Slack = 0 15 27 Slack = 8 Slack = 0
K 12
15 27
7 9 9 23 Slack = 0 23 27
D 2 F 14 L 4
7 9 9 23 23 27
Slack = 0 Slack = 0 Slack = 0
Jalur Kritis
➢ Waktu yang diperlukan untuk menyelesaikan seluruh kegiataan pada
masing-masing jalur yang timbul sebagai berikut:
a. Jalur 1 (A-B-C-G-H-M) = 4+3+4+6+4+4 = 25 minggu
➢ Dalam proyek ini ada tiga jalur kritis dengan waktu penyelesaian selama
31 minggu. Ketiga jalur kritis tersebut adalah jalur 2, jalur 4, dan jalur 5.
SOAL LATIHAN
Carilah Critical Path dari soal di bawah ini: