DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
FLOWCHART PERENCANAAN PEKERJAAN APRON
MULAI
DETAIL DESAIN
• DESAIN STRUKTUR
• DESAIN PONDASI
• DESAIN MEKANIKAL &
ELEKTRIKAL
• GAMBAR DESAIN
• BoQ & RAB
• SPESIFIKASI TEKNIS
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
KURVA S PERENCANAAN PEKERJAAN APRON
Pekerjaan Design & Build Pengembangan Bandar Udara Sultan Hasanuddin
Makassar Sulawesi Selatan Tahap 1 - Stage 1 - Paket 2
(Pembangunan Apron Selatan Dan Timur Beserta Infrastruktur Penunjangnya)
JADWAL PELAKSANAAN DESAIN
DUR. BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5
No. URAIAN PEKERJAAN
(Minggu) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
I MEETING KOORDINASI & PERIZINAN 1 x
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
FLOW CHART PELAKSANAAN PEKERJAAN
APRON A MULAI
APPRON A
ZONA 1
ZONA 3 ZONA 2
TIMBUNAN PILIHAN
TIMBUNAN PILIHAN TIMBUNAN PILIHAN
DRAINASE
DRAINASE DRAINASE
PEK. MEEP
PEK. MEEP PEK. MEEP
PEMBERSIHAN
PEMBERSIHAN PEMBERSIHAN
PEK. MARKA
PEK. MARKA PEK. MARKA
PENGUJIAN HWD & KEKESATAN
PENGUJIAN HWD & KEKESATAN PENGUJIAN HWD & KEKESATAN
Tidak Tidak
Setuju
Ya
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
FLOW CHART PELAKSANAAN PEKERJAAN
APRON B MULAI
APPRON B
ZONA 1
ZONA 3 ZONA 2
TIMBUNAN PILIHAN
TIMBUNAN PILIHAN TIMBUNAN PILIHAN
DRAINASE
DRAINASE DRAINASE
PEK. MEEP
PEK. MEEP PEK. MEEP
PEMBERSIHAN
PEMBERSIHAN PEMBERSIHAN
PEK. MARKA
PEK. MARKA PEK. MARKA
PENGUJIAN HWD & KEKESATAN
PENGUJIAN HWD & KEKESATAN PENGUJIAN HWD & KEKESATAN
Tidak Tidak
Setuju
Ya
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
FLOW CHART PELAKSANAAN PEKERJAAN MULAI
APRON C
PERKERASAN APPRON C
TIMBUNAN PILIHAN
GEBALAN RUMPUT
PEK. MARKA
Tidak
Setuju Setuju Tidak
Ya
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN TAHAP AWAL SAMPAI PENUNTASAN DED
DAN PENGENDALIAN DESAINSELAMA MASA PELAKSANAAN
MULAI
DETAIL DESAIN
•Desain Struktur
•Desain Pondasi
•Desain Mekanikal & Elektrikal
•Gambar Desain
•BoQ & RAB
•Spesifikasi Teknis
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN TAHAP AWAL SAMPAI PENUNTASAN DED
DAN PENGENDALIAN DESAINSELAMA MASA PELAKSANAAN
PERSIAPAN DATA
•Jadwal Waktu Pelaksanaan
•Organisasi Lapangan
•Tenaga Kerja
•Peralatan dan Material
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN DARI TAHAP AWAL SAMPAI PENUNTASAN DED, DAN PENGENDALIAN
DESAIN SELAMA MASA PELAKSANAAN
DESAIN STRUKTUR PERKERASAN BETON
I. Kegiatan desain struktur perkerasan suatu fasilitas bandar udara biasanya mencakup dua hal, yaitu:
‒ Evaluasi terhadap kecukupan kapasitas daya dukung perkerasan dari desain yang diusulkan terhadap
beban yang bekerja
‒ Menyatakan kecukupan kapasitas daya dukung perkerasan dari desain yang diusulkan tersebut dalam
bentuk Pavement Classification Number (PCN)
II. Untuk kegiatan desain struktur perkerasan fasilitas bandar udara, terdapat dua standar Federal Aviation
Administration (FAA) yang digunakan, yaitu:
‒ FAA AC 150/5320-6F tentang Airport Pavement Design and Evaluation
‒ FAA AC 150/5335-5C tentang Standardized Method of Reporting Airport Pavement Strength – PCN
VI. Evaluasi terhadap desain yang diusulkan menggunakan program FAA Rigid and Flexible Iterative Elastic
Layer Design (FAARFIELD). Untuk perkerasan kaku, perhitungan dalam FAARFIELD berdasarkan 3D
finite element model.
VII. Tahap pertama penggunaan FAARFIELD adalah penentuan input data, yang terdiri dari data airplane
dan pavement structure.
VIII. Untuk desain struktur perkerasan apron, data lalu lintas yang digunakan adalah data annual departure
pada tahun 2017 dari 11 jenis pesawat. Tingkat pertumbuhan lalu lintas bervariasi antara 0,5% s/d 2%.
IX. Desain apron adalah pada titik yang dianggap menahan beban tertinggi, yaitu pada apron taxiway yang
berada di dekat salah satu taxiway dari tiga taxiway yang ada yaitu taxiway India, sehingga lalu lintas
yang diambil sebagai beban adalah sepertiga dari total lalu lintas di Bandar Udara Hasanuddin.
X. Diasumsikan tidak ada lalu lintas pesawat wide body pada titik tersebut dikarenakan posisi parking stand
pesawat tersebut tidak berada di dekat taxiway India.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN DARI TAHAP AWAL SAMPAI PENUNTASAN DED, DAN PENGENDALIAN
DESAIN SELAMA MASA PELAKSANAAN
DESAIN STRUKTUR PERKERASAN BETON
XI. Struktur perkerasan apron yang diusulkan XII. Tebal slab beton untuk menahan beban selama 20
adalah sebagai berikut. tahun pada kondisi optimum hanya diperlukan
Slab beton, K-400, tebal 45 cm tebal 15,96 in. (dari 18 in. yang direncanakan).
Sehingga struktur perkerasan dianggap mampu
Lean concrete, K-125, tebal 10 cm menahan beban selama umur rencana.
XIII. Penentuan nilai Pavement Classification Number (PCN) dilakukan dengan menggunakan:
‒ COMFAA support spreadsheet, yaitu spreadsheet yang disediakan oleh FAA untuk menentukan
evaluation thickness dan k value sebagai input untuk program COMFAA
‒ COMFAA, merupakan aplikasi untuk menghitung nilai PCN pesawat berdasarkan input data yang
berupa data lalu lintas pesawat dan data struktural perkerasan
XIV. Ada sedikit perbedaan dalam input data yang dibutuhkan oleh program COMFAA dan COMFAA support
spreadsheet dengan program FAARFIELD, yaitu:
‒ Tebal lapisan di dalam program COMFAA, terutama perkerasan kaku, hanyalah tebal slab beton
‒ Tebal lapisan yang lain, bersama-sama dengan nilai subgrade k-value, akan digunakan untuk
menentukan composite k value
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN DARI TAHAP AWAL SAMPAI PENUNTASAN DED, DAN PENGENDALIAN
DESAIN SELAMA MASA PELAKSANAAN
DESAIN STRUKTUR PERKERASAN BETON
COMFAA
support
spreadsheet
DATA HASIL PROGRAM COMFAA
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN DARI TAHAP AWAL SAMPAI PENUNTASAN DED, DAN PENGENDALIAN
DESAIN SELAMA MASA PELAKSANAAN
DESAIN STRUKTUR PERKERASAN BETON
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
TATA KELOLA PERENCANAAN DARI TAHAP AWAL SAMPAI PENUNTASAN DED, DAN PENGENDALIAN
DESAIN SELAMA MASA PELAKSANAAN
DESAIN STRUKTUR PERKERASAN BETON
PCN =
82/R/B/W/T
APPRON A
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
DENAH
SPLIT GULLY
DATA APRON A
Luasan = 48.913 m2
Volume Beton = 22.010,8 m3
Panjang Split Gully = 997,17 m1
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
AREA 1
AREA 2
Alat pengecoran dengan menggunakan 2 alat concrete paver masing-masing 1 unit Area 1 dan Area 2
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
DETAIL
URUTAN
Arah COR
cor Beton
Arah
cor Beton
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
1 1 1 1 1 1 1 1 1 1 AREA 1
2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9 0
1
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
APRON B
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
APPRON B
SPLIT GULLY
DATA APRON B
Luasan = 59.327 m2
Volume Beton = 26.697,15 m3
Panjang Split Gully = 1.175,89 m1
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
RENCANA PENGECORAN APRON B
AREA 1
AREA 2
Alat pengecoran dengan menggunakan 2 alat concrete paver masing-masing 1 unit Area 1 dan Area 2
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
DETAIL
URUTAN
Arah COR
cor Beton
Arah
cor Beton
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
DETAIL URUTAN COR
1 1 1 1 1 1 1 1 1 1 AREA 1
2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9 0
1
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
APRON C
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
APPRON C
DATA APPRON C
Luasan = 47.120 m2
Volume Beton = 21.204 m3 SPLIT GULLY
Panjang Split Gully = 354,42 m1
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
APRON C
AREA 3
AREA 2
AREA 1
DATA APRON C
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
Arah
Pekerjaan Rigid
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
LEAN CONCRETE K-125 TEBAL 10 cm 4. Pekerjaan penghamparan lean concrete
1. Pekerjaan penentuan elevasi lean concrete oleh tim 5. Pekerjaan finishing permukaan lean concrete
surveyor
2. Pembersihan lokasi lean concrete menggunakan compresor
3. Pekerjaan pemasangan bekisting lean concrete
Plat Metal mm
45 cm
Lean Concrete t= 10 cm
75 cm 75 cm 75 cm 75 cm
41 cm
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
PENGECORAN SLAB BETON K-400
1. Pekerjaan persiapan (pengukuran, marking, dsb)
2. Pekerjaan pembersihan, pekerjaan lean concrete;
dan proses pembuatan trial mix di lakukan sebelum
pekerjaan Pengecoran
3. Pekerjaan formwork slab beton, pembesian dowel, tie bar & wiremesh.
4. Pekerjaan pengecoran beton
dengan menggunakan Concrete
Pever Machine dan trowelling finish
5. Grooving
6. Perawatan Beton (Curing)
7. Pembongkaran bekisting, cutting,
dan joint sealant Concrete Paver Machine
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
JUMLAH PERALATAN :
- CONCRETE PAVER = 2.00 unit
- TRUCK MIXER = 13.00 unit PERKERASAN
- CRONCRETE VIBRATOR = 6.00 unit
RIGID PAVEMENT
APRON B
- TOWER LAMP = 10.00 unit
VOLUME = 26,697.15 m3
AREA = 59,327.00 m2
WAKTU PELAKSANAAN : PERKERASAN
- Jumlah Hari = 63.00 hari
RIGID PAVEMENT
APRON C PEKERJAAN RIGID PAVEMENT (T = 45 CM)
VOLUME = 21,204.00 m3 KAPASITAS PRODUKSI PER HARI / PAVER
AREA = 47,120.00 m2 BETON K -400 = 175.00 m3
WAKTU PELAKSANAAN :
- Jumlah Hari = 85.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
PENGUJIAN BESI TULANGAN
Pemeriksaan tulangan dimaksudkan untuk mengetahui mutu tulangan yang dipakai. Tulangan diambil sampel pada tiap jenis diameter tulangan sepanjang 1
meter. Setiap 1 meter besi mewakili 1000 ton material besi yang datang. Sampel tersebut kemudian dibawa ke laboratorium untuk dilakukan pengujian kuat tarik
dan lengkung statis baja. Pemeriksaan tulangan yang dilakukan antara lain adalah :
1. Pemeriksaan Visual Tulangan
2. Pengujian Tarik Tulangan
3. Pengujian Lengkung Statis Tulangan
Contoh Tabel Hasil Pengujian Kuat Tarik Statis Tulangan Pengujian Kuat Tarik Tulangan
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
PENGUJIAN BESI TULANGAN
3. Pengujian Lengkung Statis Tulangan
Pengujian lengkung statis dilakukan terhadap sampel tulangan dengan berbagai diameter dengan menggunakan mesin uji lengkung statis sehingga
didapatkan data gaya maksimum yang dapat ditahan oleh tulangan sampai tulangan mengalami sudut lengkung 180º. Pengujian ini dilakukan oleh
Laboratorium Uji Independent yang sudah berser.tifikasi atau badan uji / dinas-dinas uji yang ditunjuk oleh owner.
Pengujian Lengkung Statis Tulangan Hasil Pengujian Kuat Tarik Statis dan Tulangan Lengkung Statis Tulangan
Pemilihan mutu baja tulangan seperti dalam spesifikasi yang ada yaitu disesuaikan dengan pembebanan yang ada sehingga konstruksi kuat karena memenuhi
spesifikasi pembebanan yang ada dan diameter yang sesuai sehingga tidak terjadi pemborosan biaya. Mutu baja tulangan disesuaikan dengan yang diinginkan
oleh pemilik proyek serta tercantum dalam Rencana Kerja dan Syarat-syarat teknis.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE PEMERIKSAAN SLUMP BETON
I. TUJUAN PERCOBAAN
Percobaan ini bertujuan untuk menentukan konsistensi suatu campuran beton berdasarkan satuan SLUMP. Suatu campuran beton memiliki konsistensi yang
berbeda – beda sesuai kebutuhan suatu bangunan yang akan di beton. Konsistensi itu dapat sangat kering, kering, plastis, plastis cair, cair, dan sebagainya.
II. PERALATAN
1. Peralatan bagi pemeriksaan SLUMP yang terdiri dari :
Cetakan
Timbangan
Alat ukur
2. Tongkat pemadat dengan diameter 10mm, panjang Ø)cm.
Ujung dibulatkan dan sebaiknya dari bahan baja anti karat.
3. Pelat logam dengan permukaan rata dan kedap air.
4. Sendok cekung Kerucut Abrahm
Stik Besi
III. BAHAN – BAHAN Tinggi Slump
Contoh beton segar sesuai dengan isi cetakan. Peralatan Slump Test
V. PERHITUNGAN
Nilai SLUMP = Tinggi cetakan – Tinggi rata rata benda uji.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE PEMERIKSAAN SLUMP BETON
ILUSTRASI PEMERIKSAAN SLUMP BETON
Slump test dilakukan dengan menggunakan kerucut Abrams dengan dimensi kerucut : 10 cm diameter atas dan diameter bawah 20 cm, tinggi 30 cm dan
tongkat baja bulat dengan diameter 16 mm panjang 60 cm . Pengujian dilakukan di atas area rata dan tidak menyerap air.
1. Isi cetakan dengan beton segar sampai penuh 3. Setelah selesai pemadatan, ratakan 5. Angkat perlahan – lahan tegak
dalam tiga lapis. permukaan benda uji, tunggu selama ½ lurus keatas.
menit
2. Setiap lapis dipadatkan dengan tongkat pemadat 4. lapisan kelebihan beton segar disekitar 6. Balikkan cetakan dan letakkan
sebanyak 25 kali tusukan secara merata cetakan harus dibersihkan disamping benda uji. Ukur nilai
Slumpnya
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE PENGUJIAN KUAT TEKAN
START PENGUJIAN KARAKTERISTIK/KUAT TEKAN BETON
Tes kuat tekan beton dilakukan untuk mengetahui mutu beton apakah sesuai dengan kualitas yang
CAMPURAN BETON SESUAI DENGAN JOB MIX dibutuhkan. Test dilakukan di laboratorium sipil. Sampel uji berupa silinder (diameter 150 mm,
DESIGN
tinggi 300 mm) atau kubus (15x15x15 cm). Dibuat 9 sample dimana 3 digunakan untuk test pada
BETON TERSEDIA DILOKASI saat umur beton 7hari (kekuatan beton 70 % dari fc'), 3 pada saat umur beton 14 hari (kekuatan
beton 85-90 % dari fc') dan sisanya untuk 28 hari (kekuatan beton 100 % dari fc').
TEST KUAT
TEKAN NO
BETON UMUR
7, 14, 28 HARI
Silinder Beton
BUAT BENDA UJI
YES
PENGARSIPAN HASIL TEST PERBAIKAN PERENCANAAN DILOKASI BENDA UJI BETON TEST UJI KUAT TEKAN
ATAU MENGGUNAKAN HAMMER TEST BETON
FINISH
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
IDENTIFIKASI BAGIAN KRITIS TAHAP PERENCANAAN DAN PELAKSANAAN PEKERJAAN
SESUAI PAKET
Pekerjaan Apron
Pada pekerjaan Apron tedapat bagian yang kritis
disebabkan oleh :
• Supply beton
• Cuaca Hujan
Solusi :
• Menambah armada Truck mixer untuk meningkatkan supply beton
• Menyiapkan Terpal untuk kondisi cuaca hujan
• Monitor Batching Plant (keberadaan material, alat dan SDM)
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
KOORDINASI DENGAN BIDANG PEK. YANG TERKAIT DALAM PELAKSANAAN
1. Direksi Pekerjaan adalah Project Management Airport Development di Jakarta dan Pimpinan Satuan
Kerja (Satker) PT Angkasa Pura 1 (Persero) Bandar Udara Sultan Hasanuddin, Makassar.
Koordinasi yang terkait dengan pihak-pihak lain (pihak ke-3) semua akan melalui Direksi Pekerjaan.
2. Pengawas Lapangan yaitu Airport Facilities Readiness Dept. Head Satker PT Angkasa Pura 1 (Persero),
Konsultan QS Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin,
Makassar.
2. Pengawas Harian yaitu Staff Project PT Angkasa Pura 1 (Persero) yang dibantu oleh Konsultan QS
Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin, Makassar.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN APRON
RENCANA ANTISIPASI TERTUNDANYA TARGET PENYELESAIAN
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
FLOWCHART SEKUEN/ TAHAPAN PELAKSANAAN PEKERJAAN GALIAN
Tahap Pelaksanaan :
Mulai 1. Merelokasi Utilitas MEEP Bandara (yang kena dampak pekerjaan) ketempat yang aman
2. Pekerjaan penyelidikan tanah.
3. Apabila kondisi tanah asli sudah mencapai CBR > 8% maka pekerjaan galian hanya
Relokasi sampai pada di kedalaman pada level dasar Sub Base.
4. Apabila kondisi tanah asli CBR < 8% maka digali mencapai kedalaman 1.75 m dari elevasi
Pengukuran /survey top rencana
lapangan 5. Membuat drainase sementara ke arah drainase exsisting untuk menghindari genangan
pada saat kondisi hujan
Penyelidikan Tanah 6. Material tanah yang tidak memenuhi spesifikasi teknis dibuang ke disposal area, dan
diganti dengan tanah pilihan yang memenuhi spesifikasi
7. Galian dilakukan secara bertahap, kedalaman galian maksimal disesuaikan dengan
Galian
rencana (Slope kemiringan lereng & kedalaman yang diisyaratkan)
8. Penyiraman dengan air untuk menjaga kondisi tanah kering (menghidari debu) dan
Unloading Material ke Dumptruk di tutup menggunakan terpal
disposal area 9. Hasil galian dibuang ke Disposal Area
10. Pembersihan Jalan Akses
Pembersihan Peralatan yang diperlukan
- Excavator
- Dump Truck (Penutup Bak/Terpal)
Selesai - Water Tank
- Peralatan Pengukuran
- Peralatan Komunikasi (HT)
- Peralatan lain yang diperlukan
- Penerangan Lokasi Kerja (Tower Lamp)
PENGENDALIAN MUTU ANALISA PEMAKAIAN PERSONIL & K3
Personil yang dikerahkan :
Mutu yang diharapkan
• Pelaksana • Petugas K3
• Elevasi timbunan sesuai dengan gambar
• Surveyor • Operator Alat Berat
• Permukaan timbunan yang rata
• Staf Proyek • Pekerja Harian
• Kepadatan timbunan sesuai dengan spesifikasi
• Driver Truck ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
FLOWCHART SEKUEN/ TAHAPAN PELAKSANAAN PEKERJAAN TIMBUNAN
MULAI
Lingkup Pekerjaan
Pekerjaan timbunan didahului oleh pengkondisian
Pengukuran area (stake out)
lokasi yang akan ditimbun lahan sesuai dengan spesifikasi yang ditentukan.
Perbaikan
test kepadatan.
Tes Kepadatan 1
Dengan melakukan
pemadatan kembali Tidak
sampel Tiap 500 m2 Derajat kepadatan yang disyaratkan minimal 98%.
Kepadatan min. 98%
dengan alat
Ya
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
APRON A APRON B
Taxiway
Akses Keluar/
Taxiway
TAXIWAY 1
Masuk Apron A Taxiway
APRON
EXIXSTING TAXIWAY 2
Akses Keluar/
APRON C Masuk Apron B
TERMINAL
Akses Keluar/
Masuk Apron C
Keterangan :
= Arah Masuk
= Arah Keluar
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
ZONA 1 APRON A
ZONA 3 APRON A
Jalan Kerja
ZONA 2 APRON A
Keterangan :
= Arah Masuk
= Arah Keluar
= Alur Galian
= Arah Galian
ENGINEERING
PT. PELABUHAN INDONESIA IV (Persero) PEKERJAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN MAKASSARSELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
METODE PELAKSANAAN STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR PENUNJANGNYA)
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
PEMADATAN TANAH (SUB GRADE) CBR 8
Peralatan yang digunakan: Tenaga yang digunakan:
- Bulldozer - Pelaksana
- Vibro Roller - Surveyor
- Stamper - Staf Proyek
- Water Tank - Petugas K3
- Peralatan Pengukuran - Operator Alat Berat
- Peralatan Komunikasi (HT) - Pekerja
- Peralatan Lab
- Penerangan Lokasi Kerja (Tower Lamp)
VIBRO ROLLER
VIBRO ROLLER
BULLDOZER WATER TANK TRUCK
BULLDOZER
PATOK ELEVASI
1 2
Pemadatan Sub grade harus menggunakan Vibrator Roller/Static Roller dan tempat tertentu menggunakan Stamper sampai
mencapai kepadatan sesuai dengan spesifikasi. Sedangkan untuk leveling digunakan Bulldozer, atau sesuai petunjuk
Pengawas. Kontraktor harus memberi air secukupnya untuk mendapatkan kadar air optimum. Pemadatan dianggap cukup
baik apabila kepadatan Sub grade sudah mencapai minimal 98% dry max dari kepadatan kering maksimum Proctor Modified.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
SUB BASE TEBAL 20 CM, CBR 30%
JUMLAH ARMADA :
- Excavator = 4.00 unit
- DT Kap. 10 m3 = 20.00 unit
- Water Tank = 1.00 unit
WAKTU PELAKSANAAN :
- Jumlah Hari = 45.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
ESTIMASI KAPASITAS PRODUKSI DAN JANGKA WAKTU PER SUB KELOMPOK PEKERJAAN
PEKERJAAN TIMBUNAN APRON A
VOLUME = 36,684.75 m3
AREA = 48,913.00 m2
PEKERJAAN TIMBUNAN
KAPASITAS PRODUKSI PER HARI
Pek. Timbunan = 825.00 m3
JUMLAH ARMADA :
- BULLDOZER D 65 = 1.00 unit
- DUMP TRUCK = 9.00 unit
- VIBRO ROLLER 10 Ton = 1.00 unit
- WATER TANK = 1.00 unit
WAKTU PELAKSANAAN :
- Jumlah Hari = 44.00 hari
PEKERJAAN TIMBUNAN APRON B
VOLUME = 44,495.25 m3
AREA = 59,327.00 m2
PEKERJAAN TIMBUNAN APRON C PEKERJAAN TIMBUNAN
KAPASITAS PRODUKSI PER HARI
VOLUME = 150,784.00 m3 Pek. Timbunan = 825.00 m3
AREA = 47,120.00 m2 JUMLAH ARMADA :
PEKERJAAN TIMBUNAN - BULLDOZER D 65 = 2.00 unit
KAPASITAS PRODUKSI PER HARI - DUMP TRUCK = 20.00 unit
Pek. Timbunan = 3,300.00 m3 - VIBRO ROLLER 10 Ton = 1.00 unit
JUMLAH ARMADA : - WATER TANK = 1.00 unit
- BULLDOZER D 65 = 6.00 unit
- DUMP TRUCK = 24.00 unit WAKTU PELAKSANAAN :
- VIBRO ROLLER 10 Ton = 4.00 unit - Jumlah Hari = 54.00 hari
- WATER TANK = 1.00 unit
WAKTU PELAKSANAAN :
- Jumlah Hari = 46.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
ESTIMASI KAPASITAS PRODUKSI DAN JANGKA WAKTU PER SUB KELOMPOK PEKERJAAN
PERKERASAN
SUB BASE
APRON A
VOLUME = 9,782.60 m3
AREA = 48,913.00 m2
PEKERJAAN SUB BASE (T = 20 CM)
KAPASITAS PRODUKSI PER HARI
Pek. Sub Base = 640.00 m3
JUMLAH ARMADA :
- MOTOR GRADER = 1.00 unit
- VIBRO ROLLER 10 Ton = 1.00 unit
- Dump Truck 10 M3 = 15.00 unit
- WATER TANK = 1.00 unit
PERKERASAN
WAKTU PELAKSANAAN : SUB BASE
APRON B
- Jumlah Hari = 16.00 hari
VOLUME = 11,865.40 m3
AREA = 59,327.00 m2
PEKERJAAN SUB BASE (T = 20 CM)
PERKERASAN KAPASITAS PRODUKSI PER HARI
SUB BASE
APRON C Pek. Sub Base = 640.00 m3
VOLUME = 9,424.00 m3 JUMLAH ARMADA :
AREA = 47,120.00 m2 - MOTOR GRADER = 1.00 unit
PEKERJAAN SUB BASE (T = 20 CM) - VIBRO ROLLER 10 Ton = 1.00 unit
KAPASITAS PRODUKSI PER HARI - Dump Truck 10 M3 = 14.00 unit
Pek. Sub Base = 640.00 m3 - WATER TANK = 1.00 unit
JUMLAH ARMADA : -
- MOTOR GRADER = 1.00 unit WAKTU PELAKSANAAN :
- VIBRO ROLLER 10 Ton = 1.00 unit - Jumlah Hari = 19.00 hari
- Dump Truck 10 M3 = 13.00 unit
- WATER TANK = 1.00 unit
WAKTU PELAKSANAAN :
- Jumlah Hari = 15.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
IDENTIFIKASI BAGIAN KRTITIS DARI KELOMPOK PEK. PERBAIKAN TANAH &
PEKERJAAN CUT AND FILL
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE TES SANDCONE
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE TES CBR
Cara melakukan percobaan :
1. Percobaan C.B.R menggunakan contoh tanah dalam kadar air optimum.
2. Metode yang digunakan dalam metoda 2 atau standar ASTM D – 70 atau D – 1557 – 70. diameter tabung = 6 inci = 15 cm dan tinggi = 5 sampai 7 inci = 12,50 cm
sampai 17,50 cm.
3. Dengan menggunakan dongkrak mekanis sebuah piston penetrasi ditekan supaya masuk ke dalam tanah dengan kecepatan tetap = 1,25 mm/menit dengan beban awal
= 0,05 kN.
4. Pembebanan pada pluyer diamati pada penetrasi berturut-turut : 0.625 ; 1,250 ; 1,875 ; 2,500 ; 3,750 ; 5,000 ; 6,250 dan 7,500 mm hasil perhitungan ini di plot dalam
kertas kurva.
A. percobaan di Lapangan
Tujuan untuk melakukan nilali C.B.R asli di Lapangan sesuai dengan kondisi tanah . digunakan untuk perencanaan tebal lapisan perkerasan yang perkerasan lapisan
tanah dasarnya tidak akan dipadatkan lagi.pemeriksaan dilakukan dengan kondisi kadar air tanah tinggi.
2) Di Laboratorium
a. Beban statis diletakkan pada bagian atas tabung untuk mencegah pengembangan tanah dalam tabung
b. Arloji penunjuk beban dan arloji penetrasi dipasang dan angka dinolkan
c. Pembebanan dimulai dengan beraturan sesuai dengan urutan waktu maupun kedalaman yang ada pada forulir data.
d. Catat angka yang dibaca pada arloji pengukur pada formulir.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
1. Direksi Pekerjaan adalah Project Management Airport Development di Jakarta dan Pimpinan Satuan
Kerja (Satker) PT Angkasa Pura 1 (Persero) Bandar Udara Sultan Hasanuddin, Makassar.
Koordinasi yang terkait dengan pihak-pihak lain (pihak ke-3) semua akan melalui Direksi Pekerjaan.
2. Pengawas Lapangan yaitu Airport Facilities Readiness Dept. Head Satker PT Angkasa Pura 1 (Persero),
Konsultan QS Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin,
Makassar.
2. Pengawas Harian yaitu Staff Project PT Angkasa Pura 1 (Persero) yang dibantu oleh Konsultan QS
Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin, Makassar.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEK. PERBAIKAN TANAH DAN PEK. CUT & FILLSECARA KHUSUS
1. Mempercepat proses approval for construction drawing yang terkait dengan pekerjaan
tanah.
2. Mempercepat proses pengurusan izin masuk area proyek untuk alat dan tenaga kerja.
3. Jumlah excavator sebanyak 23 unit dan dump truck sebanyak 204 unit telah melebihi
dari jumlah excavator yang disarankan yaitu 5 unit dan dump truck sebanyak 50 unit
sebagai rencana percepatan.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN PENERANGAN JALAN UMUM
FLOWCHART SEKUEN /TAHAPAN PELAKSANAAN PEKERJAAN
PEKERJAAN LAMPU JALAN
Pekerjaan ini meliputi pekerjaan pondasi tiang lampu, pemasangan lampu dan kelistrikan.
Tahapan Pelaksanaan :
START 1. Penetapan lokasi pondasi PJU ditetapkan, kemudian dilakukan penggalian untuk
pondasi di lanjutkan dengan pembesian dan pengecoran secara insitu untuk
pondasi.
Persiapan 2. Ditempat lain tiang2 lampu dibuat dan difabrikasi sesuai dengan spesifikasi yang
telah ditetapkan dalam gambar.
3. Pada lokasi2 tertentu dibuat galian kabel untuk pemasangan kabel bawah tanah.
Marking Lokasi PJU Galian kabel tersebut ada yang dibuat langsung dipermukaan tanah, tetapi ada
pula yang di buatkan pipa sparing pada concrete barrier median sebagai penarik
kabel.
4. Setelah semua tiang dan jaringan kabelnya terpasang maka dilakukan
Fabrikasi Tiang PJU pemasangan lampu PJU kemudian di lakukan pengujian.
FINISH
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR DAN ZONA KERJA
LAYOUT PEKERJAAN AIRFIELD LIGHTING
APRON
TL - CODE C
D
S JI
MA
DCS 1
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ESTIMASI KAPASITAS PRODUKSI DAN JANGKA WAKTU PER SUB KELOMPOK PEKERJAAN
Jumlah PJU adalah 17 titik, dengan kapasitas produksi 1 titik PJU lengkap dengan lampu
adalah 2 hari. Sehingga pekerjaan pemasangan PJU akan selesai dalam 34 hari.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
Kendali Mutu :
Quality Control adalah proses pengawasan dan pengontrolan kualitas/mutu dari pekerjaan – pekerjaan mulai dari saat proses
pengerjaan instalasi sampai dengan selesainya pekerjaan / tahap testing & commissioning. Hal ini bertujuan untuk menjaga
kualitas dari hasil pekerjaan agar dapat mencapai standar bakunya dan mencapai tingkat kualitas sesuai dengan yang
direncanakan.
Quality Qontrol ini dilakukan disetiap tahap pengerjaan pekerjaan – pekerjaan mulai dari awal/tahap pengadaan barang sampai
tahap akhir/finishing harus terus dipantau prosesnya. Upaya – upaya quality control ini dapat diujudkan dengan cara : dalam
proses pengerjaan pekerjaan juga harus selalu mengacu pada aturan/standar baku dari pekerjaan tersebut, selalu
mengindahkan RKS, dan disetiap akhir proses pengerjaan harus selalu diperlakukan adanya Testing & Commissioning.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
Kendali Mutu :
Pada tiap tahap pengerjaan harus selalu berpedoman pada aturan/standar baku dari pekerjaan tersebut.
Selalu mengindahkan Rancangan Kerja Sistem/RKS yang telah dirancang oleh konsultan dalam setiap tahap
pengerjaan pekerjaan.
Diakhir tahap proses pengerjaan harus selalu dilakukan perlakuan Testing & Commissioning untuk menguji unjuk
kerja dari sistem tersebut.
Testing & commissioning dilakukan untuk mengetahui apakah instalasi pekerjaan sudah sesuai dengan standart
dan RKS yang sudah ditetapkan, pengetesan dilakukan pada semua pekerjaan dan proses ini harus dengan
sepengetahuan dari pihak-pihak terkait.
Prosedur pengetesan harus sesuai dengan prosedur dan ketentuan yang berlaku.
As Built Drawing :
Penyerahan as built drawing dilakukan setelah pengetesan selesai dan hasilnya sesuai dengan ketentuan yang
berlaku
Solusi :
• Monitor pengadaan dan ekspedisi
• Monitor pabrikasi
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
KOORDINASI DENGAN BIDANG PEK. YANG TERKAIT DALAM PELAKSANAAN
1. Direksi Pekerjaan adalah Project Management Airport Development di Jakarta dan Pimpinan Satuan
Kerja (Satker) PT Angkasa Pura 1 (Persero) Bandar Udara Sultan Hasanuddin, Makassar.
Koordinasi yang terkait dengan pihak-pihak lain (pihak ke-3) semua akan melalui Direksi Pekerjaan.
2. Pengawas Lapangan yaitu Airport Facilities Readiness Dept. Head Satker PT Angkasa Pura 1 (Persero),
Konsultan QS Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin,
Makassar.
2. Pengawas Harian yaitu Staff Project PT Angkasa Pura 1 (Persero) yang dibantu oleh Konsultan QS
Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin, Makassar.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN AIRFIELD LIGHTING
RENCANA ANTISIPASI TERTUNDANYA TARGET PENYELESAIAN
1. Mempercepat proses approval for construction drawing yang terkait dengan pekerjaan
MEP.
2. Mempercepat proses pengurusan izin masuk area proyek untuk alat dan tenaga kerja.
3. Mempercepat proses pengadaan besi beton untuk segera dikirimkan ke lokasi proyek
sehingga proses fabrikasi dapat segera dilakukan.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR ZONA KERJA
LAYOUT DRAINASE
START
SESUAI SPEK
Tidak
Ya
SELESAI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
FLOWCHART SEKUEN /TAHAPAN PELAKSANAAN PEKERJAAN
FLOW CHART PEKERJAAN SALURAN PASANGAN BATU
START
Persiapan :
- Alat, Bahan & Tenaga
- Pengukuran & Bouwplank galian
Dimensi
YA
Finishing (Plesteran)
FINISH
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
FLOWCHART SEKUEN /TAHAPAN PELAKSANAAN PEKERJAAN
FLOW CHART PEKERJAAN SALURAN BOX CULVERT
MULAI
N Pengadaan Material
CEK
Box Culvert
Y
Pembuangan Material N
Galian Tanah CEK
Ex-Galian
Y
Finishing Penampang Y N
CEK
Galian
N Y
CEK
Pemasangan
Box Culvert
N Y
CEK Timbunan Kembali
Finishing dan Y N
CEK
Pembersihan Akhir
** :
Y (ya, ke Tahap Selanjutnya)
N (tidak, pekerjaan diulang, reject, SELESAI
remove)
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR ZONA KERJA
PEKERJAAN SALURAN SPLIT GULLY
Pekerjaan galian menggunakan excavator sesuai dengan ILUSTRASI
trace dan kondisi yang telah diukur sebelumnya dan dalam ex dt
sr
pelaksanaannya harus hati – hati dan berkoordinasi dengan
instansi terkait dalam hal identifikasi utilitas dan property au as
disekitar lokasi penggalian.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR ZONA KERJA
PEKERJAAN DRAINASE V-DITCH PASANGAN BATU
Tahapan Pelaksanaan :
1. Survey dan pemasangan profil galian tanah.
2. Galian tanah saluran.
DETAIL SALURAN PASANGAN BATU
Profil Galian dari
kayu 5/7
Pas. Batu
4. Pemasangan podasi batu kosong
5. Pemasangan pasangan batu kali dengan dimensi
Pas. Batu kosong sesuai gambar dan campuran spesi sesuai spek
6. Pemasangan drain pipa PVC
7. Pekerjaan Plesteran
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR ZONA KERJA
PEKERJAAN SALURAN BOX CULVERT
TAHAPAN PEKERJAAN :
Tahapan dalam pekerjaan Box Culvert (direncanakan dikerjakan
insitu) adalah sebagai berikut:
Wate
rstop
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
CARA PELAKSANAAN, TERMASUK PEMETAAN ALUR ZONA KERJA
PEKERJAAN SALURAN BOX CULVERT
3. Pekerjaan Pengecoran Dinding Box Culvert (Termasuk pembesian dan Begisting)
Begisting
4. Pekerjaan Pengecoran Slab Atas (Penutup) Box Culvert (Termasuk pembesian dan Begisting)
Begistin
g
DRAINASE
DRAINASE
APRON C SPLIT GULLY
APRON B
SPLIT GULLY
PANJANG = 1,175.89 m'
PANJANG = 354.42 m'
VOLUME BETON = 3,104.03 M3
VOLUME BETON = 935.57 M3
KOEFISIEN
KOEFISIEN
- Beton K-250 = 2.640 m3/m'
- Beton K-250 = 2.640 m3/m'
PEKERJAAN Saluran PEKERJAAN Saluran
KAPASITAS PRODUKSI PER HARI KAPASITAS PRODUKSI PER HARI
Pek. Drainase = 68.63 m3 Pek. Drainase = 68.63 m3
JUMLAH PERALATAN : JUMLAH PERALATAN :
Keterangan : - CONCRETE PAVER = - unit - CONCRETE PAVER = - unit
- TRUCK MIXER = 2.00 unit - TRUCK MIXER = 2.00 unit
= Saluran Existing - VIBRO = 2.00 unit - VIBRO = 2.00 unit
= Arah Aliran - TOWER LAMP = 10.00 unit - TOWER LAMP = 10.00 unit
WAKTU PELAKSANAAN : WAKTU PELAKSANAAN :
- Jumlah Hari = 14.00 hari
- Jumlah Hari = 45.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
ESTIMASI KAPASITAS PRODUKSI DAN JANGKA WAKTU PER SUB KELOMPOK PEKERJAAN
DRAINASE
V - DITH
APRON A
PANJANG = 473.25 m'
VOLUME V - DITH = 831.71 M3
KOEFISIEN
- Pek. Pas. Batu = 1.757 m3/m'
PEKERJAAN Saluran
KAPASITAS PRODUKSI PER HARI DRAINASE
Pek. Drainase = 43.94 m3
V - DITH
APRON B
JUMLAH PERALATAN :
PANJANG = 560.32 m'
- CONCRETE PAVER = - unit
VOLUME V - DITH = 984.73 M3
- TRUCK MIXER = - unit
KOEFISIEN
- MOLEN = 5.00 unit
- Pek. Pas. Batu = 1.757 m3/m'
- TOWER LAMP = 4.00 unit
PEKERJAAN Saluran
WAKTU PELAKSANAAN :
KAPASITAS PRODUKSI PER HARI
- Jumlah Hari = 19.00 hari
Pek. Drainase = 43.94 m3
JUMLAH PERALATAN :
- CONCRETE PAVER = - unit
Keterangan : - TRUCK MIXER = - unit
- MOLEN = 5.00 unit
= Saluran Existing
- TOWER LAMP = 4.00 unit
= Arah Aliran WAKTU PELAKSANAAN :
- Jumlah Hari = 22.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
ESTIMASI KAPASITAS PRODUKSI DAN JANGKA WAKTU PER SUB KELOMPOK PEKERJAAN
DRAINASE
BOX CULVERT
APRON A
PANJANG = 96.23 m'
VOLUME BETON = 200.91 M3
KOEFISIEN
- Beton K-250 = 2.088 m3/m'
PEKERJAAN Saluran
KAPASITAS PRODUKSI PER HARI
Pek. Drainase = 41.75 m3
JUMLAH PERALATAN :
- CONCRETE PAVER = - unit
- TRUCK MIXER = 1.00 unit
- VIBRO = 2.00 unit
- TOWER LAMP = 2.00 unit
WAKTU PELAKSANAAN :
- Jumlah Hari = 5.00 hari DRAINASE
BOX CULVERT
APRON B
PANJANG = 80.47 m'
VOLUME BETON = 168.00 M3
KOEFISIEN
- Beton K-250 = 2.088 m3/m'
PEKERJAAN Saluran
KAPASITAS PRODUKSI PER HARI
Pek. Drainase = 41.75 m3
JUMLAH PERALATAN :
- CONCRETE PAVER = - unit
Keterangan : - TRUCK MIXER = 1.00 unit
= Saluran Existing - VIBRO = 1.00 unit
- TOWER LAMP = 10.00 unit
WAKTU PELAKSANAAN :
- Jumlah Hari = 4.00 hari
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
PENGUJIAN BESI TULANGAN
Pemeriksaan tulangan dimaksudkan untuk mengetahui mutu tulangan yang dipakai. Tulangan diambil sampel pada tiap jenis diameter tulangan sepanjang 1
meter. Setiap 1 meter besi mewakili 1000 ton material besi yang datang. Sampel tersebut kemudian dibawa ke laboratorium untuk dilakukan pengujian kuat tarik
dan lengkung statis baja. Pemeriksaan tulangan yang dilakukan antara lain adalah :
1. Pemeriksaan Visual Tulangan
2. Pengujian Tarik Tulangan
3. Pengujian Lengkung Statis Tulangan
Contoh Tabel Hasil Pengujian Kuat Tarik Statis Tulangan Pengujian Kuat Tarik Tulangan
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
PENGUJIAN BESI TULANGAN
3. Pengujian Lengkung Statis Tulangan
Pengujian lengkung statis dilakukan terhadap sampel tulangan dengan berbagai diameter dengan menggunakan mesin uji lengkung statis sehingga
didapatkan data gaya maksimum yang dapat ditahan oleh tulangan sampai tulangan mengalami sudut lengkung 180º. Pengujian ini dilakukan oleh
Laboratorium Uji Independent yang sudah berser.tifikasi atau badan uji / dinas-dinas uji yang ditunjuk oleh owner.
Pengujian Lengkung Statis Tulangan Hasil Pengujian Kuat Tarik Statis dan Tulangan Lengkung Statis Tulangan
Pemilihan mutu baja tulangan seperti dalam spesifikasi yang ada yaitu disesuaikan dengan pembebanan yang ada sehingga konstruksi kuat karena memenuhi
spesifikasi pembebanan yang ada dan diameter yang sesuai sehingga tidak terjadi pemborosan biaya. Mutu baja tulangan disesuaikan dengan yang diinginkan
oleh pemilik proyek serta tercantum dalam Rencana Kerja dan Syarat-syarat teknis.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE PEMERIKSAAN SLUMP BETON
I. TUJUAN PERCOBAAN
Percobaan ini bertujuan untuk menentukan konsistensi suatu campuran beton berdasarkan satuan SLUMP. Suatu campuran beton memiliki konsistensi yang
berbeda – beda sesuai kebutuhan suatu bangunan yang akan di beton. Konsistensi itu dapat sangat kering, kering, plastis, plastis cair, cair, dan sebagainya.
II. PERALATAN
1. Peralatan bagi pemeriksaan SLUMP yang terdiri dari :
Cetakan
Timbangan
Alat ukur
2. Tongkat pemadat dengan diameter 10mm, panjang Ø)cm.
Ujung dibulatkan dan sebaiknya dari bahan baja anti karat.
3. Pelat logam dengan permukaan rata dan kedap air.
4. Sendok cekung Kerucut Abrahm
Stik Besi
III. BAHAN – BAHAN Tinggi Slump
Contoh beton segar sesuai dengan isi cetakan. Peralatan Slump Test
V. PERHITUNGAN
Nilai SLUMP = Tinggi cetakan – Tinggi rata rata benda uji.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
SISTEM MONITORING KUALITAS PELAKSANAAN PEKERJAAN
METODE PEMERIKSAAN SLUMP BETON
ILUSTRASI PEMERIKSAAN SLUMP BETON
Slump test dilakukan dengan menggunakan kerucut Abrams dengan dimensi kerucut : 10 cm diameter atas dan diameter bawah 20 cm, tinggi 30 cm dan
tongkat baja bulat dengan diameter 16 mm panjang 60 cm . Pengujian dilakukan di atas area rata dan tidak menyerap air.
1. Isi cetakan dengan beton segar sampai penuh 3. Setelah selesai pemadatan, ratakan 5. Angkat perlahan – lahan tegak
dalam tiga lapis. permukaan benda uji, tunggu selama ½ lurus keatas.
menit
2. Setiap lapis dipadatkan dengan tongkat pemadat 4. lapisan kelebihan beton segar disekitar 6. Balikkan cetakan dan letakkan
sebanyak 25 kali tusukan secara merata cetakan harus dibersihkan disamping benda uji. Ukur nilai
Slumpnya
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
IDENTIFIKASI BAGIAN KRITIS DARI KELOMPOK PEK. SALURAN DRAINASE
Solusi :
• Meyiapkan managemen taffict selama pelaksanaan
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
KOORDINASI DENGAN BIDANG PEK. YANG TERKAIT DALAM PELAKSANAAN
1. Direksi Pekerjaan adalah Project Management Airport Development di Jakarta dan Pimpinan Satuan
Kerja (Satker) PT Angkasa Pura 1 (Persero) Bandar Udara Sultan Hasanuddin, Makassar.
Koordinasi yang terkait dengan pihak-pihak lain (pihak ke-3) semua akan melalui Direksi Pekerjaan.
2. Pengawas Lapangan yaitu Airport Facilities Readiness Dept. Head Satker PT Angkasa Pura 1 (Persero),
Konsultan QS Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin,
Makassar.
2. Pengawas Harian yaitu Staff Project PT Angkasa Pura 1 (Persero) yang dibantu oleh Konsultan QS
Pengawas dan Management Project (PMSC) Bandar Udara Sultan Hasanuddin, Makassar.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN SALURAN DRAINASE
RENCANA ANTISIPASI TERTUNDANYA TARGET PENYELESAIAN
1. Mempercepat proses approval for construction drawing yang terkait dengan pekerjaan saluran drainase.
2. Mempercepat proses pengurusan izin masuk area proyek untuk alat dan tenaga kerja.
3. Mempercepat proses pengadaan besi beton untuk segera dikirimkan ke lokasi proyek sehingga proses
fabrikasi dapat segera dilakukan.
4. Memastikan kesiapan material beton di batching plant dengan beberapa alternatif batching plant lain
diluar rencana batching plan yang telah disebutkan pada bagian “Akses Logistik Material”.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN PEMELIHARAAN
PEKERJAAN PEMELIHARAAN
FLOWCHART PEKERJAAN PEMELIHARAAN
START
Apabila, setelah dilakukan proses Serah Terima Pertama Pekerjaan
ditemukan adanya penurunan performance atau kerusakan selama
Ditemukan cacat / ketidaksesuaian masa pemeliharaan maka akan dilakukan beberapa tahapan
tindakan sebagaimana flowchart di samping.
TIDAK
YA
FINISH
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN PEMELIHARAAN
PEKERJAAN PEMELIHARAAN
JADWAL MONITORING IDENTIFIKASI DAN EVALUASI
Selama masa pemeliharaan, monitoring identifikasi dan evaluasi dilakukan oleh posisi sesuai
dengan tabel di bawah ini.
Jumlah Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke Bulan ke
No. Posisi
Orang 1 2 3 4 5 6 7 8 9 10 11 12
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN PEMELIHARAAN
PEKERJAAN PEMELIHARAAN
KOORDINASI DENGAN BIDANG PEKERJAAN YANGTERKAIT DALAM PROSES
PEMELIHARAAN
Terkait dengan koordinasi selama masa pemeliharaan, kami PT.Adhi Karya (Persero),Tbk siap
berkoordinasi dan melakukan monitoring dengan dukungan manajemen melalui kantor PT.Adhi
Karya (Persero),Tbk Divisi Konstruksi VI Jl. Letjend Hertasning B II/No. 2 Makassar, sesuai
flowchart pekerjaan pemeliharaan.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN PEMELIHARAAN
PEKERJAAN PEMELIHARAAN
METODE PEMELIHARAAN FASILITAS (REACTIVE DAN PREVENTIVE)
SITE MANAGER
Site Project
Office
AHLI TRANSPORTASI
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C
PT. ADHI KARYA (Persero) Tbk.
DEPARTEMEN INFRASTRUKTUR I I PEKERJAAN PEMELIHARAAN
PEKERJAAN PEMELIHARAAN
METODE PEMELIHARAAN FASILITAS (REACTIVE DAN PREVENTIVE)
• Metode preventive dilakukan mengacu pada manual book dari manufaktur untuk pekerjaan
Mekanikal dan Elektrikal sedangkan untuk pekerjaan struktur apron dilakukan pengamatan
saat terjadi curah hujan dengan intensitas tinggi untuk mengetahui kondisi permukaan apron.
ENGINEERING
PT. PELABUHAN
METODE INDONESIA IV (Persero) PEKERJAAN
PELAKSANAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI
PEMBANGUNAN
STAGE 1 - PAKET 2 (PEMBANGUNAN APRON SELATAN DAN TIMUR BESERTA INFRASTRUKTUR MAKASSAR
PENUNJANGNYA)
SELATAN TAHAPTAHAP
NEWPORT 1- 1B DAN 1C