SUMEDANG, Oktober 2013

PAPARAN
PEMBANGUNAN JBH CISUMDAWU

SATUAN KERJA PELAKSANAAN JALAN BEBAS HAMBATAN CISUMDAWU


Kampus ITB, Jl.Winaya Mukti No.01 Jatinangor – Kab.Sumedang
Telp / Fax : (022) 7795590 E-mail: jbh_cisumdawu@yahoo.com
I. DATA UMUM
II. PROGRAM
III. DATA PROGRES
A. Progres Lahan
B. Progres Kegiatan
1. Kegiatan 2011
2. Kegiatan 2013
United Nations Economic and Social
Commission for Asia and the Pacific
http://www.unescap.org/
EXISTING TOLL ROAD
1. Jakarta Cikampek = 72,0 km
2. Jakarta – Bogor – Ciawi = 50,0 km LOKASI TOLL CISUMDAWU
3. Palimanan – Kanci = 26,3 km
4. Padalarang – Cileunyi = 35,6 km
5. Cikampek – Padalarang = 58,6 km

ON GOING INVESTOR
6. Ciranjang – Sukabumi = 33 Km
7. Bekasi – Cawang – Kp.Melayu = 21 Km

REVIEW TENDER 1997


8. Ciawi- Sukabumi = 54 Km
9. Cikampek – Palimanan = 114 Km
10. Kanci – Pejagan = 34 Km

DIRECT APPOINMENT TO JASA MARGA


11. Bogor Ring Road = 11 Km

TENDER BATCH 1-2005


12. Depok – Antasari = 21,7 Km
13. Cinere – Jagorawi = 14,7 Km
14. Cikarang – Tanjung Priok = 34,0 Km

TENDER BATCH – II
15. Cileunyi – Sumedang – Dawuan = 60,28 Km
16. Pasir Koja – Soreang = 15 Km

PLANNING & PROGRAMMING


17. Sukabumi –Ciranjang = 31,0 Km
18. Ciawi – Sukabumi = 54,0 Km
19. Pastuer – Ujungberung- Gedebage = 20,9 Km
20. Jagorawi – Tol Cikampek = 27,1 Km
21. Ujung berung – Gedebage – Majalaya = 19,2 Km
1. Meningkatan RENCANA TOL CIKAMPEK-
Bandara
PALIMANAN ( 116 Km )
Internasional
perekonomian Provinsi PKN
JAKARTA
Jawa Barat

Jawa Barat khususnya


Kota Bandung Cileunyi, PKN
CIREBON
Sumedang dan Cirebon.
2. Meningkatkan Kapasitas
Jalan yang
PKN
menghubungkan Kota BANDUNG

Bandung dan Cirebon.


EXISTING TOLL ROAD
3. Melengkapi jaringan PLANNED TOLL ROAD
jalan tol Jakarta- Tender / Planning Process

PLANNED TOLL ROAD


Bandung-Cirebon :
Jakarta-Cikampek-
Purwakarta-Padalarang-
Cileunyi-Sumedang-
Dawuan.
4. Terkoneksi dengan
rencana pembangunan
Bandara Internasional
Jawa barat.
SEKSI I : 12,025 Km SEKSI II : 17,350 Km SEKSI III : 3,750 Km SEKSI IV : 7,200 Km SEKSI V : 15,900 Km SEKSI VI : 4,048 Km

STA 27+100 STA 30+850 STA 38+050 STA 53+950 STA 57+998

Jatinangor Rancakalong Sumedang Ujung Jaya


Cimalaka Legok Dawuan
Cileunyi
SEKSI I SEKSI II SEKSI III SEKSI IV SEKSI V SEKSI VI
NO INFORMASI Cileunyi- Rancakalong- Sumedang- Cimalaka- Legok- Ujung Jaya- TOTAL
Rancakalong Sumedang Cimalaka Legok Ujung Jaya Dawuan
1. Panjang (Km) 12,025 17,350 3,750 7,200 15,900 4,048 60,273

2. Estimasi Kebutuhan Lahan (Ha) 134,8 291,5 100,2 83,6 216,1 22,00 848

3. Masa Konstruksi 2 TAHUN 3 TAHUN 1 TAHUN 2 TAHUN 2 TAHUN 1 TAHUN -

* : Engineer Estimate 2011 Barrier Gate Interchange Junction


NO. SEGMEN PANJ. JADWAL KESIAPAN KESIAPAN LAHAN PROGRES TINDAK LANJUT YANG DIPERLUKAN
KONSTRUK DOK. DESAIN
(km) SI LINK.
I Seksi I
Sta -2+275-8+425 10,70 2014 - 2016 Sudah Detail Desain Belum Proses • Diperlukan Percepatan proses pembebasan tanah oleh PPK Lahan dan
(Main Road Amdal 2004 2010 bebas pembebasan P2T Sumedang.
termasuk dan lahan • Diperlukan kepastian sumber/skema pendanaan.
Interchange Revisi
Cileunyi) Amdal
2011
Sta 9+000-9+350 0,35 2014 Detail Desain Sudah Usulan • Diperlukan penyiapan dokumen tender.
(Jembatan 2010 dan bebas Pendanaan 2014 • Diperlukan kepastian sumber/skema pendanaan.
Cipeles) Pemutahiran
Data 2012
2 Seksi II
Sta 9+750-12+000 6,35 2012 - 2014 Sudah Detail Desain 99,58 % Dalam proses • Percepatan pembebasan tambahan lahan yang diperlukan.
& Amdal 2005 2010 bebas konstruksi
Sta 13+100- dan ( 6,062 % )
17+200 Revisi
Amdal
Sta 12+000- 11 2014 - 2016 Detail Desain Sebagian Proses • Diperlukan Percepatan proses pembebasan tanah oleh PPK Lahan dan
2011
12+600 2010 sudah pembebasan P2T Sumedang, serta perlu revisi SP2LP.
& & bebas lahan • Proses pendanaan loan China.
Sta 12+600- Detail Desain &
13+100 (TUN) 2012 (Tun) penyusunan DED
& Tunnel
Sta 17+200-
27+100
Lanjutan Akses IC 1,10 2014 Detail Desain Sebagian Proses • Diperlukan Percepatan proses pembebasan tanah oleh PPK Lahan dan
Rancakalong 2010 sudah pembebasan P2T Sumedang, serta perlu revisi SP2LP.
Sta 0+000-1+100 Pemutahiran bebas lahan • Diperlukan kepastian sumber/skema pendanaan.
data 2012
NO. SEGMEN PANJ. JADWAL KESIAPAN KESIAPAN LAHAN PROGRES TINDAK LANJUT YANG DIPERLUKAN
KONSTRUK DOK. DESAIN
(km) SI LINK.
3 Seksi III
Sta 27 + 100 – Sta. 3,75 2015 - 2017 Sudah Detail Desain Belum Proses • Diperlukan Percepatan proses pembebasan tanah oleh TPT dan P2T
30 + 850 Amdal 2005 2010 bebas pembebasan Sumedang.
lahan • Diperlukan kepastian skema pendanaan.

4 Seksi IV
Sta. 30 + 850 – 7,20 2015 - 2017 Sudah Detail Desain Belum Proses • Diperlukan Percepatan proses pembebasan tanah oleh TPT dan P2T
Sta. 38 + 050 Amdal 2005 2010 bebas pembebasan Sumedang.
lahan • Diperlukan kepastian skema pendanaan.

5 Seksi V
Sta.38 + 050 – Sta. 15,90 2015 - 2017 Sudah Detail Desain Belum Proses • Diperlukan Percepatan proses pembebasan tanah oleh TPT dan P2T
53 + 950 Amdal 2005 2010 bebas pembebasan Sumedang.
lahan • Diperlukan kepastian skema pendanaan.

6. Seksi VI
Sta. 53 + 950 – 4,048 2015 - 2017 Sudah Detail Desain Belum Proses • Diperlukan Percepatan proses pembebasan tanah oleh TPT dan P2T
Sta. 57 + 998 Amdal 2005 2010 bebas pembebasan Sumedang.
lahan • Diperlukan kepastian skema pendanaan.
SEKSI I : 14,55 Km SEKSI II : 21,55 Km SEKSI III : 6,40 Km SEKSI IV : 6,47 Km SEKSI IV : 14,40 Km SEKSI VI : 3,35 Km

STA -1+750 STA


STA
10+450
10+450 STA 29+550 STA 35+250 STA 40+650 STA 55+000 STA 58+350

KEBUTUHAN
(LUAS TOTAL)
190,36 Ha 346,60 Ha 156,62 Ha 112,85 Ha 306,05 Ha 16,57 Ha

BEBAS 26,31 % 49,01 % 7,68 % 0% 0% 0%


50,91Ha 169,88 Ha 12,03 Ha 0 Ha 0 Ha 0 Ha

BELUM 73,26 % 50,99 % 92,32 % 100 % 100 % 100%


139,45 Ha 176,72 Ha 144,59 Ha 112,85 Ha 306,05 Ha 16,57 Ha

CATATAN : - DATA DARI PPK LAHAN PROGRES KEGIATAN PENGADAAN TANAH JALAN TOL CISUMDAWU
- PEMBAGIAN SEKSI BERBEDA ANTARA PPK LAHAN DENGAN SATKER PJBH CISUMDAWU.
Lanjutan ...

SEKSI I : 11,500 Km SEKSI II : 17,350 Km SEKSI III : 3,750 Km SEKSI IV : 7,200 Km SEKSI IV : 15,900 Km SEKSI VI : 4,048 Km

STA -1+750 STA 27+100 STA 30+850 STA 38+050 STA 53+950 STA 57+998

KEBUTUHAN
(LUAS TOTAL)
152,83 Ha 338,06 Ha 64,76 Ha 209,75 Ha 381,88 Ha 32,06 Ha

BEBAS 25,77 % 53,66 % 18,58 % 0% 0% 0%


39,39 Ha 181,39 Ha 12,03 Ha 0 Ha 0 Ha 0 Ha

BELUM 74,23 % 46,34 % 81,42 % 100 % 100 % 100 %


113,44 Ha 156,66 Ha 52,73 Ha 209,75 Ha 381,88 Ha 32,06 Ha

CATATAN : DATA LUAS KEBUTUHAN DARI USULAN REVISI ROW 2012 SATKER PJBH CISUMDAWU,
DATA PROGRES LAHAN BEBAS DI-EXERCISE DARI DATA PPK LAHAN
NO SEKSI LUAS LAHAN SUMBER PENDANAAN
1 Seksi I 190,36 Ha APBN
2 Seksi II 346,60 Ha APBN & APBD
3 Seksi III 156,62 Ha INVESTOR/ JASA SARANA
4 Seksi IV 112,85 Ha INVESTOR/ JASA SARANA
5 Seksi V 306,05 Ha INVESTOR/ JASA SARANA
6 Seksi VI 16,57 Ha INVESTOR/ JASA SARANA
TOTAL 1.129,05 Ha

Sumber : PPK LAHAN


-1+750 6+600
9+750 21+850
27+100 30+850

IC CILEUNYI IC RANCAKALONG ICSUMEDANG IC CIMALAKA

8+350 10+600 14+600 20+150 29+550


13+250 16+900

4+535 8+950
BARIER GATE

> 80 % LAHAN BEBAS LAHAN DALAM PROSES LAHAN BELUM BEBAS


PEMBEBASAN

1. Desa Pasigaran 1. Desa Sukarapih 9. Desa Sukasirnarasa 1. Desa Cileunyi Wetan 11. Desa Margamukti
2. Desa Gudang 2. Desa Margaluyu 10. Desa Pasirbiru 2. DesaCibeusi 12. Desa Mekarjaya
3. Desa Pamulihan 3. Desa Pasigaran 11. Desa Pamekaran 3. Desa Sindangsari 13. Desa Situ
4. Desa Cigendel 4. Desa Gudang 12. Desa Ciherang 4. Desa Cileles 14. Desa Jatimulya
5. Desa Pasirbiru 5. Desa Citali 13. Desa Girimukti 5. Desa Cilayung 15. Desa Jatihurip
6. Desa Pamekaran 6. Desa Ciptasari 14. Desa Sirnamulya 6. Desa Mekarsari 16. Desa Kebonjati
7. Desa Sirnamulya 7. Desa Pamulihan 15. Desa Cikole 7. Desa Gunung manik 17. Desa Cikole
8. Desa Cigendel 16. Desa Galudra 8. Desa Mulyasari 18. Desa Galudra
9. Desa Sukamaju
23,00 Ha
Main Road (PJBHC Phase 1)
9+750 - 12+000
13+100 - 17+200
On going contract 94,60 Ha
(LOAN)

Bebas

Belum

0,21 Ha
Jalan Pendekat OP Sukamulya
0+563 - 0+950
1+040 - 1+647
3,60 Ha
(APBN)
Kegiatan Fisik TA. 2011 :
A. Pembangunan JBH Cisumdawu (Main Road)
B. Pembangunan Akses Interchange Rancakalong
Kegiatan Fisik TA. 2013 :
Pembangunan JBH Cisumdawu Phase 1 (Main Road)
Pembangunan
Main Road
(8+525 – 9+000)
&
(9+365 – 9+755)
APBN 2011

Pembangunan
IC. Akses
Rancakalong
(1+100 - 1+750)
APBN 2011

STA 9+750

STA 8+525 STA 1+750

STA 1+100
1.Pembangunan (Main Road) Jalan Bebas Hambatan Cisumdawu
– Ruas Jalan : Jalan Bebas Hambatan Cisumdawu
– Panjang Fungsional : 870 m
• Overpass : 2 Lokasi (Sta. 8+995; P: 70,9 m; L: 3 m / 6 m)
(Sta. 9+610; P: 88,4 m; L: 3 m / 6 m)
• Aquaduct : 1 Lokasi (Sta. 8+850; P: 81,6 m; L: 2,5 m / 3,5 m / Ø.0,9 m)
– Konsultan Pelaksana : PT. Waskita Karya (Persero)
– Nomor Kontrak : KU.08.08/PJBHC/98
– Nilai Kontrak : Rp. 52.285.547.686,-
– Tgl Kontrak : 28 Juni 2011
– Nomor SPMK : KU.08.09/PJBHC/106
– Tgl. SPMK : 01 Juli 2011
– Masa Kontrak : 184 Hari Kalender
– Tgl. Akhir Kontrak : 31 Desember 2011
– Progress Pekerjaan : 100,00 %
2.Pembangunan Jalan Akses Interchange Rancakalong
– Ruas Jalan : Akses Interchange Rancakalong
– Panjang Fungsional : 650 m
• JPO : 1 bh (Sta. 1+387; P: 40,8 m; L: 2,5 m / 3,5 m)
• OP : 1 bh (Sta. 1+680; P: 42,3 m; L: 3,0 m / 6,0 m)
– Konsultan Pelaksana : PT. Waskita Karya (Persero)
– Nomor Kontrak : KU.08.08/PJBHC/97
– Nilai Kontrak : Rp. 37.872.452.730,-
– Tgl Kontrak : 28 Juni 2011
– Nomor SPMK : KU.08.09/PJBHC/105
– Tgl. SPMK : 01 Juli 2011
– Masa Kontrak : 184 Hari Kalender
– Tgl. Akhir Kontrak : 31 Desember 2011
– Progress Pekerjaan : 100 %
Pemeliharaan
Main Road (APBN)
(8+425 - 9+755)
(*)

Pembangunan
Pemeliharaan Main Road (LOAN)
IC. Akses Rancakalong (9+750 - 12+000)
(APBN) &
(1+100 - 1+750) (13+100 - 17+200)
(*) (**)

STA 9+750 STA 12+000

STA 8+425 STA 1+750 STA 13+100 STA 17+200

STA 1+100

Catatan :
(* ) OP Rutin
(**) Pembangunan
STATUS : 18 Okt. 2013

1. Pembangunan Jalan Bebas Hambatan Cisumdawu Phase 1 (LOAN)


– Ruas Jalan : Jalan Bebas Hambatan Cisumdawu
– Panjang Efektif : 6,350 Km
(Sta. 9+750 – Sta. 12+000 & Sta. 13+100 – Sta. 17+200)
– Panjang Fungsional : 6,350 Km
– Kontraktor : Shanghai Construction (Group) General Company –
Consortium of WIKA – WASKITA JO
– Nomor Kontrak : KU.08.08/PJBHC/228 ;
– Nilai Kontrak : Rp. 1.022.998.753.214,90 (Multi years)
– Tgl Kontrak : 8 Nopember 2011
– Nomor SPMK : KU.08.09/PJBHC/69
– Tgl. SPMK : 7 Desember 2012
– Adendum : * Adendum I ( 14 November 2011)
* Adendum II ( 5 April 2012 )
* Adendum III ( 20 Mei 2013 )
– Masa Kontrak : 720 Hari Kalender
– Tgl. Akhir Kontrak : 26 Nopember 2014

*) Revisi Dipa Juli 2013


Foto Pelaksanaan Paket
Pembangunan Jalan Bebas Hambatan Cisumdawu Phase 1 (LOAN)

Pekerjaan Detour Sta. 9+850

Pasca Penggalian Sta. 10+100

View dari P1 s.d. A2


Jembatan Cisarongge

P1 Jembatan Cisarongge
Lanjutan … 01

Foto Pelaksanaan Paket


Pembangunan Jalan Bebas Hambatan Cisumdawu Phase 1 (LOAN)

Pemasangan besi tulangan Pile Pemancangan Pondasi Pilar P7


Cap P6 Jembatan Cisarongge Jembatan Cisarongge

Pemancangan Pondasi P6 Pekerjaan Galian di sta. 14+000


Jembatan Sukasirnarasa
Lanjutan … 02

Foto Pelaksanaan Paket


Pembangunan Jalan Bebas Hambatan Cisumdawu Phase 1 (LOAN)

Pekerjaan Galian di Sta. 15+000 Penanganan sementara aliran


Sungai Ciherang Sta. 15+600

Clearing Sta. 16+900

Pekerjaan Galian di area


Sungai Ciherang
No. Paket Desain Lahan Keterangan

1 Lanjutan Jalan Akses Rancakalong siap belum Lahan dalam Proses revisi SP2LP

Desain selesai Desember 2012 oleh Bintek


siap sebagian (Belum dikonfirmasi)
2 Terowongan (Tunnel) belum
besar Lahan proses revisi SP2LP

3 Jembatan Cipeles siap siap Desain selesai Desember 2012

4 Jalan Pendekat Overpass Sukamulya


siap belum Adendum paket Loan terkontrak
Terima Kasih