A. KEGIATAN SURVEY
3. JOINT SURVEY SISI SEBELAH BARAT AREA KOLAM (AREA SAWIT DAN HUTAN)
B. KEGIATAN PRODUKSI
C. PENGAMBILAN SAMPLE MATERIAL TANAH (TESPIT) DAN STRECHING (AREA KOLAM DAN AREA PKS)
C. DOKUMENTASI
2
A. KEGIATAN SURVEY
A. AREA RESERVOIR
c. AREA PERUMAHAN
LUAS AREA PERUMAHAN SELUAS : 6,1 Ha
3
A. KEGIATAN SURVEY
3
A. KEGIATAN SURVEY
Y= 9764134.000
Z= 33.000
PENGUKURAN JOINT SURVEY MELIPUTI AREA SAWIT DAN HUTAN YANG BERADA DI
AREA RESERVOIR
3
GAMBAR SISI SEBELAH BARAT (AREA SAWIT DAN HUTAN)
4
A. KEGIATAN SURVEY
3
GAMBAR PEMASANGAN MATTINGAN
4
A. KEGIATAN SURVEY
3
GAMBAR AREA BATAS RAWA DAN RESERVOIR
6
A. KEGIATAN SURVEY
3
GAMBAR PROGRESS GALIAN (AREA PKS ZONA ELEVASI +32)
7
A. KEGIATAN SURVEY
DENGAN ADANYA PATOK AKSES JALAN AKAN LEBIH MEMUDAHKAN ALAT BERAT
DALAM MEMBAWA MATERIAL MENUJU AREA DISPOSAL
3
B. KEGIATAN PRODUKSI
a. AREA RESERVOIR
PEMBERSIHAN SUDAH MENCAPAI 100% DENGAN TOTAL LUASAN YANG DIBERSIHKAN SELUAS 11,3
Ha
b. AREA PKS
PEMBERSIHAN SUDAH MENCAPAI 100% DENGAN TOTAL LUASAN YANG DIBERSIHKAN SELUAS 8,1Ha
b. AREA PERUMAHAN
PEMBERSIHAN SUDAH MENCAPAI 100% DENGAN TOTAL LUASAN YANG DIBERSIHKAN 6,1 Ha
RENCANA DI MINGGU PERTAMA BULAN MEI PARIT YANG BERADA DI AREA PERUMAHAN AKAN DI
LAKUKAN SCRAFT OLEH ALAT DOZER UNTUK MENIMBUN PARIT YANG BERADA DI AREA
PERUMAHAN
3
B. KEGIATAN PRODUKSI
EXCAVATOR
3
B. KEGIATAN PRODUKSI
3
B. KEGIATAN PRODUKSI
3
DOKUMENTASI PEMASANGAN BATAS AREA PEMBERSIHAN
Area perumahan
8
DOKUMENTASI PEMASANGAN BATAS AREA PEMBERSIHAN
Area PKS
8
DOKUMENTASI MONITORING PEMBERSIHAN AREA
8
DOKUMENTASI PENGUKURAN BATAS RAWA DAN
TEST PIT
8
DOKUMENTASI PENGUKURAN BATAS RAWA DAN
TEST PIT
8
DOKUMENTASI PENGUKURAN PROGRESS GALIAN
8
DOKUMENTASI PENGUKURAN PROGRESS GALIAN
8
TERIMAKASIH