BERITA ACARA PROGRESS

PROYEK HOTEL NOVOTEL


GRAND SHAYLA MAKASSAR
No : 1
Periode : 01 November 2012 - 30 Januari 2013
PROYEK HOTEL NOVOTEL GRAND SHAYLA MAKASSAR
PAKET PEKERJAAN ELEKTRONIKA

Amount Amount Amount


NO. DESCRIPTION Material Upah Material + Upah
Rp. Rp. Rp.

I. PEKERJAAN PERSIAPAN - - -

II. PEKERJAAN FIRE ALARM - - -

III, PEKERJAAN SOUND SYSTEM

IV. PEKERJAAN TELEPON

V. PEKERJAAN DATA

VI. PEKERJAAN CCTV

VII. PEKERJAAN MATV

VIII. MATERIAL ON SITE

TOTAL

PT.Plammeka Jayaasri Rekapitulasi Pekerjaan MEP


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

III. PEKERJAAN PENGINDERA API ( FIRE ALARM )


III.1 PERALATAN UTAMA
a. MCFA 2 Loop, 100 Point, MDF c/w grounding dan interface ke ext 1 Unit
b. Battery type Nicad Recharger 2 Jam c/w grounding 1 Unit
c. Power Surge Aresster c/w grounding 2 Unit
d. Annunciator 1 Unit
e. Testing and Commissioning 1 Lot

III.2 KABEL UTAMA


a Kabel (FRC 2 x 2.5 mm2 + PVC Cond. HI 20 mm) 445 M'
c Twisted Shielded 18 AWG 2 Pairs (Tahan Api) + 450 M'
Konduit Dari MDFA - TB-FA
d Twisted Shielded 18 AWG 2 Pairs (Tahan Api) + 1 Lot
Konduit Dari MCFA ke sound system
e Twisted Shielded 18 AWG 2 Pairs (Tahan Api) + 1 Lot
Konduit Dari MCFA ke telphone
f Twisted Shielded 18 AWG 2 Pairs (Tahan Api) + 1 Lot
Konduit Dari MCFA ke lift
g Twisted Shielded 18 AWG 2 Pairs (Tahan Api) + 1 Lot
Konduit Dari MCFA ke pressure fan

III.3 PEKERJAAN INSTALASI DAN FIXTURES


III.3.1 LANTAI BASEMENT
a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 53 Titik
- Instalasi Smoke Detector 3 Titik
- Instalasi Fixed Temperature Detector 2 Titik
- Instalasi Alarm Bell 4 Titik
- Instalasi Manual Break Glass Push Button 4 Titik
- Instalasi Indicating Lamp 4 Titik

PT.Plammeka Jayaasri halaman -1/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

c. Fixtures dan armatures


- Rate of Rise Detector 53 Buah
- Smoke Detector 3 Buah
- Fixed Temperature Detector 2 Buah
- Alarm Bell 4 Buah
- Manual Break Glass Push Button 4 Buah
- Indicating Lamp 4 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 4 Buah
- Box Fire Extinguisher 4 Buah
- Mobile Dry Extinguisher CO2 25 kg 1 Buah

III.3.2 LANTAI GROUND


a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 19 Titik
- Instalasi Smoke Detector 8 Titik
- Instalasi Fixed Temperature Detector 2 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 19 Buah
- Smoke Detector 8 Buah
- Fixed Temperature Detector 2 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah
- Indicating Lamp 2 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah
- Box Fire Extinguisher 2 Buah

PT.Plammeka Jayaasri halaman -2/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

III.3.3 LANTAI MEZANINE


a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 38 Titik
- Instalasi Smoke Detector 12 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 38 Buah
- Smoke Detector 12 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah
- Indicating Lamp 2 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah
- Box Fire Extinguisher 2 Buah

III.3.4 LANTAI DUA


a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 20 Titik
- Instalasi Smoke Detector 9 Titik
- Instalasi Alarm Bell 3 Titik
- Instalasi Manual Break Glass Push Button 3 Titik
- Instalasi Indicating Lamp 3 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 20 Buah
- Smoke Detector 9 Buah
- Alarm Bell 3 Buah
- Manual Break Glass Push Button 3 Buah
- Indicating Lamp 3 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 3 Buah
- Box Fire Extinguisher 3 Buah

PT.Plammeka Jayaasri halaman -3/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

III.3.5 LANTAI 3 - 4 ( 2 LANTAI TYPICAL )


a. Adressible Moudul Box ( AMB ) 2 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 30 Titik
- Instalasi Smoke Detector 74 Titik
- Instalasi Alarm Bell 6 Titik
- Instalasi Manual Break Glass Push Button 6 Titik
- Instalasi Indicating Lamp 6 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 30 Buah
- Smoke Detector 74 Buah
- Alarm Bell 6 Buah
- Manual Break Glass Push Button 6 Buah
- Indicating Lamp 6 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 6 Buah
- Box Fire Extinguisher 6 Buah

III.3.6 LANTAI 5
a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 15 Titik
- Instalasi Smoke Detector 37 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 15 Buah
- Smoke Detector 37 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah
- Indicating Lamp 2 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah

PT.Plammeka Jayaasri halaman -4/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

- Box Fire Extinguisher 2 Buah

III.3.7 LANTAI 6 -7 -8 ( 3 LANTAI TYPICAL )


a. Adressible Moudul Box ( AMB ) 3 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 45 Titik
- Instalasi Smoke Detector 111 Titik
- Instalasi Alarm Bell 6 Titik
- Instalasi Manual Break Glass Push Button 6 Titik
- Instalasi Indicating Lamp 6 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 45 Buah
- Smoke Detector 111 Buah
- Alarm Bell 6 Buah
- Manual Break Glass Push Button 6 Buah
- Indicating Lamp 6 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 6 Buah
- Box Fire Extinguisher 6 Buah

III.3.8 LANTAI 9
a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 15 Titik
- Instalasi Smoke Detector 37 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 15 Buah
- Smoke Detector 37 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah
- Indicating Lamp 2 Buah

PT.Plammeka Jayaasri halaman -5/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah


- Box Fire Extinguisher 2 Buah

III.3.9 LANTAI 10
a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 15 Titik
- Instalasi Smoke Detector 37 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 15 Buah
- Smoke Detector 37 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah
- Indicating Lamp 2 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah
- Box Fire Extinguisher 2 Buah

III.3.10 LANTAI 11
a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 15 Titik
- Instalasi Smoke Detector 37 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 15 Buah
- Smoke Detector 37 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah

PT.Plammeka Jayaasri halaman -6/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN FIRE ALARM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

- Indicating Lamp 2 Buah


- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah
- Box Fire Extinguisher 2 Buah

III.3.11 LANTAI 12
a. Adressible Moudul Box ( AMB ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Instalasi Rate of Rise Detector 15 Titik
- Instalasi Smoke Detector 37 Titik
- Instalasi Alarm Bell 2 Titik
- Instalasi Manual Break Glass Push Button 2 Titik
- Instalasi Indicating Lamp 2 Titik
c. Fixtures dan armatures
- Rate of Rise Detector 15 Buah
- Smoke Detector 37 Buah
- Alarm Bell 2 Buah
- Manual Break Glass Push Button 2 Buah
- Indicating Lamp 2 Buah
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) 2 Buah
- Box Fire Extinguisher 2 Buah

Dipindahkan ke Penjumlahan Total - - -

PT.Plammeka Jayaasri halaman -7/45 Fire Alarm


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

IV. PEKERJAAN SOUND SYSTEM


IV.1 PERALATAN UTAMA
a. PUBLIC ADDRESS/EVACUATION SYSTEM
- Emergency Microphone 1 Unit
- Ext. Power Amplifier 240 Watt 7 Unit
- Mixer Voice Alarm System 1 Unit
- CD/MMC/USB player with FM Tunner 1 Unit
- Double Cassete Deck Player 1 unit
- Remote Paging Mic. 2 unit
- Speaker Selector 16 Ch. 1 unit
- Power Supply + Surge Arrester 1 unit
- Graphic Equalizer 2 Ch. 1 unit
- Cabinet Rack w/ Accessories 1 unit
- Testing and Commissioning 1 Ls

b. CARCALL SYSTEM
- Mixer Amplifier 120 W 1 Unit
- Power Amplifier 120 W 1 Unit
- Carcall Microphone 1 Unit
- Cabinet Rack w/ Accessories 1 Unit
- Testing and Commissioning 1 Ls

c LOCAL SOUND SYSTEM (SKY LOUNGE) - LANTAI GROUND


- 8 Ch Mixer Console 1 Unit
- Graphic Equalizer 2 Ch. 1 Unit
- Amplifier 2 x 250W 1 Unit
- CD/MMC/USB player with FM Tunner 1 unit
- Hand-held Wireless Mic + Wireless Tuner 2 unit
- Cabinet Rack w/ Accessories 1 unit
- Speaker 180W 4 unit
- Testing and Commissioning 1 Ls

PT.Plammeka Jayaasri halaman - 1/45 Sound system


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.
d PROFFESIONAL SOUND SYSTEM - BALLROOM
- 16 Ch Mixer Console 1 Unit
- Graphic Equalizer 2 Ch 4 Unit
- Digital Speaker Controller 1 Unit
- Power Amplifier 2 x 450W 1 Unit
- Power Amplifier 2 x 600W 1 unit
- CD/MMC/USB player with FM Tunner 1 unit
- DVD Player 1 unit
- Hand held Wireless Mic 4 unit
- Antenna Distributor 1 unit
- Wireless Antenna 4 Unit
- Dynamic Microphone w/ floor stand 4 Unit
- Prof. Speaker 200W 4 Unit
- Sub Woofer Speaker 2 Unit
- Cabinet Rack w/ Accessories 1 Ls
- Head Phone 1 unit
- Wireless Receiver 1 unit
- 24 channel Audio Multicore cable 1 Ls
- 2 core @2.5 mm Loudspeaker cable 1 Ls
- Extention Cable for Hand Microphone 1 Ls
- Material pendukung (konektor2,jumper cable,dsb) 1 Ls
- Ceiling Speaker 1,5 - 3W (Evacuation) 7 Unit
- Volume Kontrol 3 Buah
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 7 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 3 Titik
- Testing and Commissioning 1 Ls

IV.2 INSTALASI DAN FIXTURES


Instalasi Tata Suara termasuk kabel NYMHY 3 x 1,5 mm2,
konduit, terminasi, T-does, socket, dan accessories.
IV.2.1 LANTAI BASSEMENT
a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 50 M'
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 6 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Instalasi Column Speaker 10 Watt NYMHY 2x1.5mm2 9 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 3 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 15 M'
PT.Plammeka Jayaasri halaman - 2/45 Sound system
PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.
c. Fixtures dan armatures
- Ceiling Speaker 1,5 - 3 Watt 6 Buah
- Column Speaker 10 Watt - Carcall 9 Buah
- Wall Speaker 6 Watt - at StairCase 3 Buah
- Volume Kontrol 2 Buah

PT.Plammeka Jayaasri halaman - 3/45 Sound system


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

IV.2.2 LANTAI GROUND


a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 86 M'
- Instalasi Horn Speaker 15 watt NYMHY 2x2.5mm2 3 Titik
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 11 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 3 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 3 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 82 M'
c. Fixtures dan armatures
- Horn Speaker 15 Watt - Carcall 3 Buah
- Ceiling Speaker 1,5 - 3 Watt 11 Buah
- Wall Speaker 6 Watt - at StairCase 3 Buah
- Volume Kontrol 3 Buah

IV.2.3 LANTAI MEZANINE


a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 90 M'
- Instalasi Column Speaker 10 Watt NYMHY 2x1.5mm2 7 Titik
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 21 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 12 M'
c. Fixtures dan armatures
- Column Speaker 10 W - CarCall 7 Buah
- Ceiling Speaker 1,5 - 3 Watt 21 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

IV.2.4 LANTAI 2
a. Terminal Boxes ( TB - TS. ) 2 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 94 M'
- Instalasi Column Speaker 10 Watt NYMHY 2x1.5mm2 4 Titik
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 32 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
PT.Plammeka Jayaasri halaman - 4/45 Sound system
PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 12 M'
- Kabel Distribusi dari MDF ke TB taman NYMHY 2 x 2.5 mm2 138 M'
c. Fixtures dan armatures
- Column Speaker 10 W - di Taman 4 Buah
- Ceiling Speaker 1,5 - 3 Watt 32 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

d MEETING ROOOM 1 - 5
PEKERJAAN CONFERENCE SYSTEM - AUDITORIUM
- Central Unit Amplifier 1 unit
- Chairman Unit 1 unit
- Delegate Unit 48 unit
- Mixer Amplifier 120 W 1 unit
- DVD Recorder 1 unit
- Speaker System 30W 4 unit
- Hand held Wireless Mic + Wireless Tuner 2 unit
- Wooden Rack 1 unit
- Power Supply + Surge Arrester 1 unit
- Testing and commissioning 1 ls

IV.2.5 LANTAI 3 - 4 ( 2 LANTAI TYPICAL )


a. Terminal Boxes ( TB - TS. ) 2 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 220 M'
- Instalasi Column Speaker 10 Watt NYMHY 2x1.5mm2 4 Titik
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 26 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 4 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 4 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 4 M'
- Kabel Distribusi dari MDF ke TB taman NYMHY 2 x 2.5 mm2 145 M'
c. Fixtures dan armatures
- Column Speaker 10 W - di Taman 4 Buah
- Ceiling Speaker 1,5 - 3 Watt 26 Buah
- Wall Speaker 6 Watt - at StairCase 4 Buah
- Volume Kontrol 4 Buah

PT.Plammeka Jayaasri halaman - 5/45 Sound system


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

IV.2.6 LANTAI 5

a. Terminal Boxes ( TB - TS. ) 1 Unit


b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 115 M'
- Instalasi Column Speaker 10 Watt NYMHY 2x1.5mm2 2 Titik
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 13 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 110 M'
- Kabel Distribusi dari MDF ke TB taman NYMHY 2 x 2.5 mm2 150 M'
c. Fixtures dan armatures
- Column Speaker 10 W - di Taman 2 Buah
- Ceiling Speaker 1,5 - 3 Watt 13 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

IV.2.7 LANTAI 6 -7 -8 ( 3 LANTAI TYPICAL )


a. Terminal Boxes ( TB - TS. ) 3 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 390 M'
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 39 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 6 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 6 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 130 M'
c. Fixtures dan armatures
- Ceiling Speaker 1,5 - 3 Watt 39 Buah
- Wall Speaker 6 Watt - at StairCase 6 Buah
- Volume Kontrol 6 Buah

IV.2.8 LANTAI 9
a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 135 M'
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 13 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 12 M'
PT.Plammeka Jayaasri halaman - 6/45 Sound system
PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.
c. Fixtures dan armatures
- Ceiling Speaker 1,5 - 3 Watt 13 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

IV.2.9 LANTAI 10
a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 140 M'
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 13 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 12 M'
c. Fixtures dan armatures
- Ceiling Speaker 1,5 - 3 Watt 13 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

IV.2.10LANTAI 11
a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 145 M'
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 13 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 12 M'
c. Fixtures dan armatures
- Ceiling Speaker 1,5 - 3 Watt 13 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

PT.Plammeka Jayaasri halaman - 7/45 Sound system


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN SOUND SYSTEM

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

IV.2.11LANTAI 12
a. Terminal Boxes ( TB - TS. ) 1 Unit
b. Instalasi peralatan lengkap kabel, konduit dan accessories
- Kabel Distribusi dari MDF ke TB - TS.1, NYMHY 3 x 2,5 mm2 150 M'
- Instalasi Ceiling Speaker 1,5 - 3 Watt NYMHY 2x1.5mm2 13 Titik
- Instalasi Wall Speaker 6 Watt ( FRC 2 x 1.5 mm2) 2 Titik
- Instalasi Volume control NYMHY 3x1.5mm2 2 Titik
- Kabel Distribusi dari MDF ke TB - TS.1, FRC 2x 2,5 mm2 12 M'
c. Fixtures dan armatures
- Ceiling Speaker 1,5 - 3 Watt 13 Buah
- Wall Speaker 6 Watt - at StairCase 2 Buah
- Volume Kontrol 2 Buah

Dipindahkan ke Penjumlahan Total - - -

PT.Plammeka Jayaasri halaman - 8/45 Sound system


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN TELEPON

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

V PEKERJAAN TELEPON
V.1 PERALATAN UTAMA
a. PABX kap. 25 / 350 ext (Expandable), lengkap dengan power 1 Unit
supply, rectifier, battery charger 3 jam, operator console,
Billing system, MDF 200 Pair dan peralatan bantu lainnya.
b. Instalasi dari R. Kabel Telkom ke MDF (ruang operator), 120 M'
Jelly Armoured Cable 30 x 2 x 0,6 mm
c. Kabel distribusi dan Instalasi dari MDF ke tiap TB :
TB – T.B, ITC 40 x 2 x 0,6 mm. 50 M'
TB – T.1, ITC 40 x 2 x 0,6 mm. 86 M'
TB – T.M2, ITC 40 x 2 x 0,6 mm. 90 M'
TB – T.2, ITC 40 x 2 x 0,6 mm. 94 M'
TB – T.3, ITC 40 x 2 x 0,6 mm. 98 M'
TB – T.4 s/d 12, ITC 40 x 2 x 0,6 mm. 1,200 M'
d. Testing dan Commissioning 1 Lot
e. Grounding system 1 Lot

V.2 INSTALASI DAN FIXTURES


Instalasi Telepon termasuk pengkabelan ITC 2x2x 0,6 mm
konduit, terminasi, T-Does, socket, dan accessories

V.2.1 LANTAI BASSEMENT


a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 4 Titik
c. Fixtures dan armatures
- Outlet Telepon 4 Buah
- Hand Set Telepon 4 Buah
- Cable Tray 600 x 100 17 M'
- Cable Tray 400 x 100 82 M'

PT.Plammeka Jayaasri halaman - 1/45 Telepon


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN TELEPON

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

V.2.2 LANTAI GROUND


a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 4 Titik
c. Fixtures dan armatures
- Outlet Telepon 4 Buah
- Hand Set Telepon 4 Buah
- Cable tray, 300 mm x 100 mm 15 M'
- Cable tray, 200 mm x 100 mm 45 M'

V.2.3 LANTAI MEZANINE


a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 17 Titik
c. Fixtures dan armatures
- Outlet Telepon 17 Buah
- Hand Set Telepon 17 Buah
- Cable tray, 300 mm x 100 mm 15 M'
- Cable tray, 200 mm x 100 mm 53 M'

V.2.4 LANTAI 2
a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 8 Titik
c. Fixtures dan armatures
- Outlet Telepon 8 Buah
- Hand Set Telepon 8 Buah
- Cable tray, 200 mm x 100 mm 55 M'
- Cable tray, 300 mm x 100 mm 15 M'

V.2.5 LANTAI 3 - 4 ( 2 LANTAI TYPICAL )


a. Terminal Boxes (TB) 2 Unit
b. Pekerjaan Instalasi :

PT.Plammeka Jayaasri halaman - 2/45 Telepon


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN TELEPON

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

- Instalasi Telepon langsung 68 Titik

PT.Plammeka Jayaasri halaman - 3/45 Telepon


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN TELEPON

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

c. Fixtures dan armatures


- Outlet Telepon 68 Buah
- Hand Set Telepon 68 Buah
- Cable tray, 200 mm x 100 mm 156 M'
- Cable tray, 300 mm x 100 mm 30 M'

V.2.6 LANTAI 5
a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 34 Titik
c. Fixtures dan armatures
- Outlet Telepon 34 Buah
- Hand Set Telepon 34 Buah
- Cable tray, 200 mm x 100 mm 78 M'
- Cable tray, 300 mm x 100 mm 15 M'

V.2.7 LANTAI 6 -7 -8 ( 3 LANTAI TYPICAL )


a. Terminal Boxes (TB) 3 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 102 Titik
c. Fixtures dan armatures
- Outlet Telepon 102 Buah
- Hand Set Telepon 102 Buah
- Cable tray, 200 mm x 100 mm 234 M'
- Cable tray, 300 mm x 100 mm 45 M'

V.2.8 LANTAI 9
a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 34 Titik
c. Fixtures dan armatures
- Outlet Telepon 34 Buah
- Hand Set Telepon 34 Buah
- Cable tray, 200 mm x 100 mm 78 M'
PT.Plammeka Jayaasri halaman - 4/45 Telepon
PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN TELEPON

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

- Cable tray, 300 mm x 100 mm 15 M'

PT.Plammeka Jayaasri halaman - 5/45 Telepon


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN TELEPON

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

V.2.9 LANTAI 10
a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 34 Titik
c. Fixtures dan armatures
- Outlet Telepon 34 Buah
- Hand Set Telepon 34 Buah
- Cable tray, 200 mm x 100 mm 78 M'
- Cable tray, 300 mm x 100 mm 15 M'

V.2.10 LANTAI 11
a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 34 Titik
c. Fixtures dan armatures
- Outlet Telepon 34 Buah
- Hand Set Telepon 34 Buah
- Cable tray, 200 mm x 100 mm 78 M'
- Cable tray, 300 mm x 100 mm 15 M'

V.2.11 LANTAI 12
a. Terminal Boxes (TB) 1 Unit
b. Pekerjaan Instalasi :
- Instalasi Telepon langsung 34 Titik
c. Fixtures dan armatures
- Outlet Telepon 34 Buah
- Hand Set Telepon 34 Buah
- Cable tray, 200 mm x 100 mm 78 M'
- Cable tray, 300 mm x 100 mm 15 M'

Dipindahkan ke Penjumlahan Total - - -

PT.Plammeka Jayaasri halaman - 6/45 Telepon


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN DATA

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VI. PEKERJAAN DATA


VI.2 PEKERJAAN INSTALASI DAN FIXTURES, DLL
Instalasi Data termasuk pengkabelan UTP Cat 5e
pipa konduit, terminasi, T-Dos, socket, dan accessories

VI.2.1 LANTAI BASSEMENT


a. Access Switch 24 port c/w Accessories 1 Set
b. Switch Hub 8 port c/w Accessories 1 Set
c. Instalasi titik data UTP Cat.5e 2 Titik
d. Fixtures :
- Outlet Data RJ 45 2 Buah

VI.2.2 LANTAI GROUND


a. Switch Hub 16 port c/w Accessories 1 Set
b. Instalasi titik data UTP Cat.5e 10 Titik
c. Instalasi titik data UTP Cat.5e untuk Access Point 6 Titik
d. Instalasi feeder data UTP Cat.6 dr Switch 24port Lt. Bsment 86 M;
e. Fixtures :
- Outlet Data RJ 45 16 Buah
- Access Point / WiFi 6 Buah

VI.2.3 LANTAI MEZANINE


a. Switch Hub 16 port c/w Accessories 1 Set
b. Instalasi titik data UTP Cat.5e 10 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 16 port Lt.Ground 15 M;
d. Fixtures :
- Outlet Data RJ 45 10 Buah

PT.Plammeka Jayaasri halaman - 1/45 Data


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN DATA

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VI.2.4 LANTAI 2
a. Switch Hub 8 port c/w Accessories 1 Set
b. Instalasi titik data UTP Cat.5e 7 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 16 port Lt.Mezanine 15 M;
d. Fixtures :
- Outlet Data RJ 45 7 Buah

VI.2.5 LANTAI 3 -4 ( 2 LANTAI TYPICAL )


a. Switch Hub 8 port c/w Accessories 2 Set
b. Instalasi titik data UTP Cat.5e untuk Access Point 12 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 8 port Lt.2 30 M;
d. Fixtures :
- Outlet Data RJ 45 12 Buah
- Access Point / WiFi 12 Buah

VI.2.6 LANTAI 6 -7-8 ( 3 LANTAI TYPICAL )


a. Switch Hub 8 port c/w Accessories 3 Set
b. Instalasi titik data UTP Cat.5e untuk Access Point 9 Titik
c. Instalasi feeder data UTP Cat.6 152 M;
d. Fixtures :
- Outlet Data RJ 45 9 Buah
- Access Point / WiFi 9 Buah

VI.2.7 LANTAI 9
a. Switch Hub 8 port 1 Set
b. Instalasi titik data UTP Cat.5e untuk Access Point 3 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 24 port Lt.Bsment 134 M;
d. Fixtures :
- Outlet Data RJ 45 3 Buah
- Access Point / WiFi 3 Buah

PT.Plammeka Jayaasri halaman - 2/45 Data


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN DATA

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

PT.Plammeka Jayaasri halaman - 3/45 Data


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN DATA

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VI.2.8 LANTAI 10
a. Switch Hub 8 port 1 Set
b. Instalasi titik data UTP Cat.5e untuk Access Point 3 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 8 port Lt.9 15 M;
d. Fixtures :
- Outlet Data RJ 45 3 Buah
- Access Point / WiFi 3 Buah

VI.2.9 LANTAI 11
a. Switch Hub 8 port 1 Set
b. Instalasi titik data UTP Cat.5e untuk Access Point 3 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 8 port Lt.10 15 M;
d. Fixtures :
- Outlet Data RJ 45 3 Buah
- Access Point / WiFi 3 Buah

VI.2.10 LANTAI 12
a. Switch Hub 8 port 1 Set
b. Instalasi titik data UTP Cat.5e untuk Access Point 3 Titik
c. Instalasi feeder data UTP Cat.6 dr Switch 8 port Lt.11 15 M;
d. Fixtures :
- Outlet Data RJ 45 3 Buah
- Access Point / WiFi 3 Buah

Dipindahkan ke Penjumlahan Total - - -

PT.Plammeka Jayaasri halaman - 4/45 Data


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN CCTV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VII PEKERJAAN CCTV


VII.1 PERALATAN UTAMA
a. 16 Channel Digital Video Recording (DVR) 3 Unit
b. 21" LED Colour Monitor for Multiscreen 3 Unit
c. 21" LED Colour Monitor for Spot 3 Unit
d. Keyboard Joystick 3 Unit
e. 19" Rack for main unit c/w Accessories 1 Unit
f. Material bantu 1 Ls
g. Testing and Commissioning 1 Ls

VII.2 PEKERJAAN INSTALASI DAN FIXTURES, DLL


a. Indoor Fixed Dome Color Camera 35 Unit
b. Indoor Speeddome Color Dome Camera 22x Optical Zoom 12 Unit
c. Instalasi titik Camera RG-6 in pipa conduit 20mm2 47 Titik
Instalasi titik Control Speeddome Camera STP AWG18 in pipa
d. conduit 20mm2 12 Titik
Instalasi titik Power Camera NYM 3x1.5mm in pipa conduit
e. 20mm2 47 Titik

Dipindahkan ke Penjumlahan Total - - -

PT.Plammeka Jayaasri 1 CCTV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VIII. PEKERJAAN MATV


Pekerjaan termasuk pengadaan dan pemasangan material di-site,
lengkap peralatan bantu dan berfungsi dengan baik.

VIII.1 PERALATAN UTAMA


a. Kabel Vision Provider 1 Lot
b. Parabola 12 Ft 2 Unit
c. Antena UHF 2 Unit
d. Antena VHF 1 Unit
e. Line Antenna Amplifier 5 Unit
f. Power Divider 3 Unit
g. Satellite Receiver 10 Unit
h. RF Modulator for Satellite Receiver 10 Unit
i. RF Modulator for In-House Movie 3 Unit
j. Single Channel Receiver for Local Channel 15 Unit
k. Active Combiner 1 Unit
l. 19" Rack c/w Accessories 2 Unit
m. Base Frame for Modulator+Single Channel Receiver 4 Unit
n. Power Supply Unit for All Modules 4 Unit
o. Splitter 4W 1 Unit
p. Splitter 6W 1 Unit

q. Kabel Coaxial RG 11 / 75 Ohm + PVC HI 20 mm untuk antenna 850 M'


UHF/VHF/Parabola

r. 455 M'
Kabel Coaxial RG 11 / 75 Ohm + PVC HI 20 mm untuk Feeder/Riser
s. Grounding System 1 Lot
t. Material bantu 1 Lot
u. Testing and Commissioning 1 Lot

VIII.2 PEKERJAAN INSTALASI & FIXTUIRES


VIII.2.1 Lantai BASSEMENT
a. Tap Off 4W 1 Unit
b. Outlet TV 2 Buah
c. Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 2 Titik

PT.Plammeka Jayaasri halaman - 1/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

1 Titik
d. Instalasi Kabel Power untuk booster, NYM 3x1.5 mm + PVC Cond. HI 20 mm

PT.Plammeka Jayaasri halaman - 2/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VIII.2.2 Lantai GROUND


a. Tap Off 4W 1 Unit
b. Booster Amplifier 1 Unit
c. Outlet TV 6 Buah
d. Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 6 Titik

e. Instalasi Kabel Power untuk booster, NYM 3x1.5 mm + PVC Cond. HI 20 mm 1 Titik

VIII.2.4 Lantai 2
a. Tap Off 4W 3 Unit
b. Booster Amplifier 1 Unit
c. Outlet TV 12 Buah
d. Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 12 Titik
e. Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 1 Titik

VIII.2.5 Lantai 3 - 4 ( 2 lantai typical )


a Tap Off 4W 18 Unit
b Booster Amplifier 2 Unit
c Splitter 3W 2 Unit
e Outlet TV 72 Buah
f Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 72 Titik
g Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 2 Titik

VIII.2.6 Lantai 5
a Tap Off 4W 9 Unit
b Booster Amplifier 1 Unit
c Splitter 3W 1 Buah
d Outlet TV 36 Buah
e Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 36 Titik
f Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 3 Titik

PT.Plammeka Jayaasri halaman - 3/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VIII.2.7 Lantai 6 -7-8 ( 3 LANTAI TYPICAL )


a Tap Off 4W 27 Unit
b Booster Amplifier 3 Unit
c Splitter 3W 3 Buah
d Outlet TV 108 Buah
e Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 108 Titik
f Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 3 Titik

VIII.2.8 LANTAI 9
a Tap Off 4W 9 Unit
b Booster Amplifier 1 Unit
c Splitter 3W 1 Buah
e Outlet TV 36 Buah
f Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 36 Titik
g Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 1 Titik

VIII.2.9 LANTAI 10
a Tap Off 4W 9 Unit
b Booster Amplifier 1 Unit
c Splitter 3W 1 Buah
e Outlet TV 36 Buah
f Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 36 Titik
g Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 1 Titik

VIII.2.10LANTAI 11
a Tap Off 4W 9 Unit
b Booster Amplifier 1 Unit
c Splitter 3W 1 Buah
e Outlet TV 36 Buah
f Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 36 Titik
g Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 1 Titik

PT.Plammeka Jayaasri halaman - 4/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

VIII.2.11LANTAI 12
a Tap Off 4W 9 Unit
b Booster Amplifier 1 Unit
c Splitter 3W 1 Buah
e Outlet TV 36 Buah
f Instalasi Coax. 5C-2V, 75 Ohm + PVC. Cond. HI 20 mm 36 Titik
g Instalasi Kabel Power untuk booster, NYM 3x2.5 mm + PVC Cond. HI 20 mm 1 Titik

Dipindahkan ke Penjumlahan Total - - -

PT.Plammeka Jayaasri halaman - 5/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

PT.Plammeka Jayaasri halaman - 6/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

PT.Plammeka Jayaasri halaman - 7/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

PT.Plammeka Jayaasri halaman - 8/45 MATV


PAKET PEKERJAAN ELEKTRONIK
PEKERJAAN MATV

Unit Price Unit Price Amount Amount Total


NO. DESCRIPTION Quantity Unit Material Upah Material Upah Amount
Rp Rp Rp. Rp. Rp.

PT.Plammeka Jayaasri halaman - 9/45 MATV


LIST OF MATERIAL SPECIFICATION

HOTEL NOVOTEL GRAND SHAYLA


JL. CHAIRIL ANWAR - MAKASAR
NO DESCRIPTION OF MATERIAL MANUFACTURE

I PEKERJAAN PUBLIC ADDRESS


A. Main Unit
1 MP3 Player,AM/FM Tuner Bosch
2 Paging Microphone Bosch
3 Mixer Pre Amplifier Bosch
4 Power Amplifier 240W Bosch
5 Speaker Selector 16 Zone Inter-M
6 Ceiling Speaker Bosch
7 Volume Control Bosch
8 Rack 19" dan Accessories Local
B. Material Instalasi
1 Kabel instalasi titik NYMHY Supreme
2 Kabel instalasi feeder/riser NYMHY Supreme
3 Terminal Box dan Accessories Local
4 Material bantu Local

II PEKERJAAN FIRE ALARM


A. Main Unit
1 MCFA Full Addressible 2 Loop Edward
2 Remote Annunciator Edward
3 Addressible Module Edward
4 All Detectors Edward/FST/setara
5 Alarm Bell Edward/FST/setara
6 Indicator Lamp Edward/FST/setara
7 Manual Call Point Edward/FST/setara
B. Material Instalasi
1 Kabel instalasi titik NYA Supreme
2 Kabel instalasi control STP AWG-18 Belden
3 Terminal Box dan Accessories Local
4 Material bantu Local

III PEKERJAAN TELEPON


A. Main Unit
1 Hybrid PABX Panasonic
B. Material Instalasi
1 Outlet Telepon Schneider/Hager/setara
2 Kabel instalasi titik ITC 2p Supreme
3 Kabel Feeder ITC Multipair Supreme
4 Terminal Box dan Accessories Local
5 Material bantu Local
IV PEKERJAAN MATV
A. Main Unit
1 Antenna UHF/VHF Ikusi/setara
2 Antenna Parabola Local
3 Channel Amplifier Ikusi/setara
4 Satellite Receiver Local
5 Modulator Ikusi/setara
6 RF Booster Ikusi/setara
7 Active Combiner Ikusi/Fagor/setara
8 Splitter Ikusi/setara
9 Tap Off Ikusi/setara
10 Rack 19" dan Accessories Local
B. Material Instalasi
1 Outlet TV Schneider/Hager/setara
2 Kabel instalasi titik Coaxial RG-6 Belden/setara
3 Kabel instalasi feeder/riser Coaxial RG-11 Belden/setara
4 Material bantu Local

V PEKERJAAN CCTV
A. Main Unit
1 16 Ch. DVR Bosch
2 Indoor Fixed Dome Color Camera Bosch
3 Indoor Speeddome Color Camera Bosch
4 Material bantu Local
B. Material Instalasi
1 Kabel instalasi titik Coaxial RG-6 Belden/setara
2 Material bantu Local

VI PEKERJAAN DATA
A. Main Unit
1 Switch Hub/Access Point/WiFi Dlink/LinkSys/setara
2 Outlet data Schneider/Hager/setara
B. Material Instalasi
1 Instalasi kabel UTP Cat.5e dan Cat.6 Schneider/setara
2 Material bantu Local

VII PEKERJAAN TRAY


TRAY
1 Straight Tray Interack
2 Fitting-fitting Local
3 Material bantu Local
FICATION

D SHAYLA
KASAR
REMARK
PAKET PEKERJAAN ELEKTRIKAL
PEKERJAAN PERSIAPAN
Unit Price Unit Price Amount
No Uraian Pekerjaan Unit Qty Material Upah Material
Rp Rp Rp.

1
Biaya - biaya untuk mengadakan staf dilapangan yang akan mengelola pelaksanaan pekerjaan,
semua biaya administrasi dan biaya mengurus segala hal yang berhubungan dengan tanggung
jawabnya terhadap kontrak ini.
Jumlah 1 - - -
2
Biaya mobilisasi dan demobilisasi termasuk biaya ijin pemasukan peralatan dan perlengkapan
kerja kedalam lokasi proyek dan pemindahan dari satu tempat ke tempat lainnya didalam
lokasi pekerjaan serta mengeluarkannya setelah penyelesaian pekerjaan
Jumlah 1 - - -
3
Pengadaan peralatan dan perlengkapan kerja yang lengkap untuk kelancaran pelaksanaan
pekerjaan sebagaimana yang dimaksud dalam Dokumen Kontrak berikut pemeliharaannya
selama digunakan di proyek
Jumlah 1 - - -
4
Pembuatan dan pencetakan Dokumen Kontrak lengkap dengan gambar kontrak sebanyak 4 (empat) set yang
terdiri atas 2 (dua) set asli dan 2 (dua) set copy.
Jumlah 1 - - -
5
Pengadaan gambar pelaksanaan (construction drawing) sebanyak yang diperlukan untuk
keperluan kerja dilapangan termasuk 2 (dua) set keperluan pengawasan.
Jumlah 1 - - -
6
Pembuatan gambar kerja (shop drawing) berikut perhitungan atau kalkulasi yang terinci
sebanyak 3 (tiga) set, hingga disetujui Manajemen Konstruksi dan atau Pemberi Tugas.
Jumlah 1 - - -
7 Pembuatan gambar-gambar terlaksana (as built drawing) sebanyak 1 (satu) set kalkir dan 4
(empat) set blue print. Jumlah 1 - - -
8
Kontraktor harus menjaga lokasi kerja tetap bersih dan mengangkut ke luar lokasi proyek semua sampah secara
teratur setiap hari dan pada waktu penyelesaian pekerjaan harus tetap bersih dan rapih.
(catatan : Dalam pengangkutan keluar proyek tidak boleh mengotori jalan dan prasarana umum )
Jumlah 1 - - -
9
Kontraktor bertanggung jawab atas penjagaan, penerangan dan perlindungan terhadap semua
material dan pekerjaan dilokasi proyek selama masa pelaksanaan kontrak siang dan malam
hari. Pemberi Tugas tidak bertanggung jawab terhadap Kontraktor dan sub Kontraktor atas
kehilangan, kerusakan bahan - bahan bangunan, peralatan atau pekerjaan yang sedang dalam
pelaksanaan.
Jumlah 1 - - -
10
Setiap pembangkit tenaga listrik sementara atau penerangan sementara termasuk pemasangan
kabel-kabel dan meteran yang dipergunakan untuk pekerjaan atau pengambilan daya dari
sumber atau PLN yang sudah ada, maka semua biaya pengadaan dan pemakaian daya selama
pelaksanan proyek termasuk izin yang diperlukan serta perapihan setelah pekerjaan selesai
sudah harus diperhitungkan oleh Kontraktor.
Jumlah 1 - - -
11 Pengadaan sumber air bersih sementara untuk air kerja dan keperluan lainnya dari sumber
yang ada ( sumur pantek / jet pump, sumur dalam / deep well), termasuk membuat
sambungan-sambungan sementara untuk mengalirkan air dan mencabutnya kembali setelah
pekerjaan selesai. Jumlah 1 - - -

PT.Plammeka Jayaasri halaman - 14/45 Prelim


PAKET PEKERJAAN ELEKTRIKAL
PEKERJAAN PERSIAPAN
Unit Price Unit Price Amount
No Uraian Pekerjaan Unit Qty Material Upah Material
Rp Rp Rp.
12
Pengadaan telephone dan perlengkapannya sesuai kebutuhan termasuk pengurusan
permohonan kepada Perumtel dan pembayaran semua tagihan selama masa pelaksanaan
pekerjaan dan menyerahkannya kepada Pemberi Tugas setelah penyerahan pertama termasuk
biaya balik nama kepada Pemberi Tugas.
Jumlah 1 - - -
13 Asuransi Tenaga Kerja (ASTEK) untuk pekerja dan staff Jumlah 1 - - -
14 Biaya Testing dan Commissioning

Termasuk operasi lengkap dengan Instalasi dan pengabelan dari Panel (sumber daya) sampai
ke alat (mesin) yang mau ditest termasuk pengadaan air dan penunjang lainnya, serta melatih
personel dan menyediakan buku petunjuk yang merupakan tanggung jawab kontraktor dan
sesuai kondisi didalam Dokumen Tender untuk lingkup pekerjaan, sebagai berikut :

(1) Elektrikal Jumlah 1 Termasuk


(2) Fire Alarm Jumlah 1 - Termasuk
(3) Tata Suara Jumlah 1 - Termasuk
(4) MATV Jumlah 1 - Termasuk
(5) Telepon Jumlah 1 - Termasuk
(6) Penangkal Petir Jumlah 1 Termasuk
15 Biaya resmi untuk penyambungan dan perijinan IMB ( Tidak termasuk ), Daya Listrik 2 x500
kva (Existing 865 KVA), Telepon dan Air Bersih dari Instansi Pemerintah ditanggung oleh
Pemberi Tugas. Jumlah 1 - - -
16
Kontraktor diwajibkan membantu Pemberi Tugas dalam pengurusan perolehan perijinan dan
penyediaan dokumen yang diperlukan oleh Instansi-instansi Pemerintah tersebut :

(1) Biaya pengurusan ijin penyambungan daya listrik ......... KVA


(PT.PLN) termasuk biaya administrasi dan terduga lainnya. Jumlah 1 - - -
(2) Biaya pengurusan ijin penyambungan telepon ..... Saluran
(lines) dari PT. TELKOM termasuk biaya administrasi dan
tak terduga lainnya. Jumlah 1 - - -

Dipindahkan ke Penjumlahan Total -

PT.Plammeka Jayaasri halaman - 15/45 Prelim


Amount
Upah
Rp.

PT.Plammeka Jayaasri halaman - 16/45 Prelim


Amount
Upah
Rp.

-
-

-
-
-
-

PT.Plammeka Jayaasri halaman - 17/45 Prelim