2
1. Rencana Pekerjaan Struktur Beton
Arena Sepatu Roda
A. Pekerjaan Kolom Elv. + 3,950
B. Pekerjaan Balok Elv. + 8,950
C. Pekerjaan Kolom Elv. + 8,950
D. Pekerjaan Balok Elv. + 12,000
3
4
Keterangan :
= Sudah Selesai
Pengecoran
= Sudah selesai
pengecoran
= Target Pengecoran
Tgl 21 September 2020
= Target Pengecoran
Tgl 27 September 2020
= Target Pengecoran
Tgl 16 September 2020
= Target Pengecoran
Tgl 3 Oktober 2020
= Target Pengecoran
Tgl 26 September 2020
(Pek. Angkur Mulai)
= Target Pengecoran
Tgl 10 Oktober 2020
= Pengecoran Kolom
Elv. + 8,950
= Pemasangan Angkur
M 25 – Panjang 600 mm
= Pemasangan Angkur
M 25 – Panjang 600 mm
10
Pengiriman Material Baja :
11
12
Pekerjaan Pengujian Penetrant
13
Pekerjaan Pengujian Penetrant
14
A. Perhitungan Kapasitas Mobile Crane 15
Keterangan :
14
22
Keterangan :
1. Finish : 15/10/2020
2. Finish : 16/10/2020
3. Finish : 17/10/2020
4. Finish : 24/10/2020
5. Finish : 25/10/2020
6. Finish : 26/10/2020
7. Finish : 27/10/2020
8. Finish : 28/10/2020
9. Finish : 29/10/2020
9 8 7 6 5
4 3 2 1
1. Finish : 17/10/2020
2. Finish : 27/10/2020
3. Finish : 28/10/2020
4. Finish : 29/10/2020
5. Finish : 30/10/2020
6. Finish : 31/10/2020
7. Finish : 1/11/2020
5 4 3 2
7 6 1
1. Finish : 18/10/2020
2. Finish : 27/10/2020
3. Finish : 28/10/2020
4. Finish : 29/10/2020
5. Finish : 30/10/2020
6. Finish : 31/10/2020
7. Finish : 1/11/2020
8. Finish : 2/11/2020
9. Finish : 3/11/2020
10.Finish : 4/11/2020
13 11 2 1 11.Finish : 5/11/2020
3
12 10 9 8 7 6 5 4 12.Finish : 6/11/2020
13.Finish : 7/11/2020
D. Pekerjaan Gording dan Trekstang CNP 26
4. Rencana Pekerjaan Penutup Atap
Spandek Arena Sepatu Roda
A. Monitoring Material Penutup Atap dan Insulation
B. Detail gambar pelaksanaan pekerjaan
C. Rencana Kerja Pelaksanaan Pekerjaan Penutup Atap
Spandek Arena Sepatu Roda.
27
Note :
1. Finish : 28/10/2020
2. Finish : 29/10/2020
3. Finish : 30/10/2020
26
24
22
20
18
16
14
12
10
8
6
2
4. Finish : 31/10/2020
5. Finish : 1/11/2020
6. Finish : 2/11/2020
7. Finish : 3/11/2020
8. Finish : 4/11/2020
25
23
21
19
17
15
13
11
9. Finish : 5/11/2020
9
7
5
1
10.Finish : 6/11/2020
11.Finish : 7/11/2020
12.Finish : 8/11/2020
13.Finish : 9/11/2020
C. Pekerjaan Penutup Atap Spandek dan Insulation 31
Keterangan :
24
22
20
18
16
14
12
10
8
6
2
17.Finish : 13/11/2020
18.Finish : 14/11/2020
19.Finish : 15/11/2020
20.Finish : 16/11/2020
21.Finish : 17/11/2020
25
23
21
19
17
15
13
11
22.Finish : 18/11/2020
9
7
5
1
23.Finish : 19/11/2020
24.Finish : 20/11/2020
25.Finish : 21/11/2020
26.Finish : 22/11/2020
C. Pekerjaan Penutup Atap Spandek dan Insulation 32
33