i
LEMBAR PENGESAHAN
PENGEMBANGAN LAPANGAN MIGAS
LAPANGAN BLOK RAYU
SEMESTER GASAL 2021/2022
Menyetujui,
ii
DAFTAR ISI
HALAMAN JUDUL................................................................................................ i
LEMBAR PENGESAHAN .................................................................................... ii
DAFTAR ISI .......................................................................................................... iii
DAFTAR TABEL .................................................................................................. vi
DAFTAR GAMBAR ............................................................................................ vii
BAB I EXECUTIVE SUMMARY .....................................................................8
BAB II GEOLOGICAL FINDINGS AND REVIEWS .....................................10
II.1 Geologi Regional .........................................................................10
II.1.1 Kerangka Tektonik.........................................................10
II.1.2 Stratigrafi Regional ........................................................11
II.1.3 Stratigrafi Lapangan.......................................................12
II.1.3 Petroleum System ..........................................................15
II.2 Karakteristik Reservoir Lapangan Rayu ......................................18
II.2.1 Stratigrafi Lapangan RU-1 dan RU-2 ............................19
II.2.2 Interpretasi Geofisika dan Pemetaan Lapisan
Produktif.........................................................................20
II.2.2.1. Perhitungan OGIP (Original Gas in Place) ......24
II.2.3 Analisis Petrofisik ..........................................................24
II.2.3.1. Penyiapan Data ................................................24
II.2.3.2. Volume Clay ...................................................25
II.2.3.3. Porositas ..........................................................25
II.2.3.4. Saturasi Air (Sw) .............................................26
II.2.3.5. Estimasi Permeabilitas ....................................26
II.2.3.6. Hasil Analisis Log ...........................................27
II.2.3.7. Cut Off dan Reservoir Summary .....................27
BAB III DESKRIPSI RESERVOIR LAPANGAN .............................................30
III.1 Karakteristik Fluida Reservoir .....................................................30
III.2 Karakteristik Batuan reservoir .....................................................32
II.2.1 Routine Core Analysis. ..................................................33
II.2.2 Special Core Analysis ....................................................33
III.3 Hasil dan Analisis ........................................................................34
III.3.1 Faktor Kompresibilitas Gas ...........................................34
III.3.2 Faktor Volume Formasi Gas ..........................................35
III.3.3 Evaluasi Performance Reservoir Lapangan ...................35
III.3.4 Perkiraan Perolehan Gas dengan Material Balance
Analysis..........................................................................35
III.3.5 Recovery Factor .............................................................37
BAB IV RESERVES AND PRODUCTION FORECAST .................................38
IV.1. Performance Produksi Lapangan .................................................38
IV.1.1 Hydrocarbon in-place.....................................................38
IV.1.2 Cadangan Hidrokarbon yang Terambil ..........................38
IV.2. Prediksi Future Production Performance .....................................40
IV.2.1. Skenario produksi ..........................................................40
IV.2.2. Material balance analysis ...............................................42
IV.2.3. Decline curve analysis ...................................................42
iii
IV.2.4. Profil Laju Produksi Gas Skenario I dan II ....................43
IV.2.5. Profil Kumulatif Produksi Gas.......................................43
IV.2.6. Summary Hasil Skenario Pengembangan ......................44
BAB V DRILLING AND COMPLETION ........................................................45
V.1. Jumlah Sumur, Target, dan Jadwal Pemboran .............................45
V.2. Geological Prognose....................................................................47
V.3. Rencana Pengeboran ....................................................................47
V.3.1. Persiapan Spud In ..........................................................48
V.3.2. Trayek Lubang 26” ........................................................49
V.3.3. Trayek Lubang 17 1/2" ..................................................50
V.3.4. Trayek Lubang 12 1/4" ..................................................52
V.3.5. Trayek Lubang 8 1/2" ....................................................54
V.4. Komplesi Sumur ..........................................................................57
V.5. Perkiraan Jumlah Hari dan Biaya Pemboran dan Komplesi ........59
V.6. Rencana pembuangan limbah pengeboran ...................................62
BAB VI PRODUCTION FACILITIES ...............................................................64
VI.1 Fasilitas Produksi Eksisting .........................................................64
VI.2 Perbandingan Forecast dan Kapasitas Existing. ..........................66
VI.3 Penambahan Fasilitas Produksi ....................................................68
BAB VII SKENARIO PENGEMBANGAN LAPANGAN .................................69
VII.1 Skenario Pengembangan Lapangan .............................................69
VII.1.1 Penambahan Sumur-Sumur Infill ..................................69
VII.1.4 Penambahan Fasilitas Produksi......................................70
VII.2 Future Profil Produksi .................................................................71
BAB VIII HEALTH SAFETY & ENVIRONMENT (HSE) AND
CORPORATE SOCIAL RESPONSIBILITY (CSR) ............................73
VIII.1.Sistem Manajemen HSE (SMHSE) ............................................74
VIII.2.Aspek Keselamatan Kerja...........................................................75
VIII.2.1. Contractor Safety Management System (CSMS) ..........76
VIII.2.2. Surat Izin Kerja Aman (SIKA) ......................................78
VIII.2.3. JSA (Job Safety Analysis) .............................................79
VIII.2.4. Induksi aspek HSE .........................................................82
VIII.2.5. Pengamatan Keselamatan Kerja (PEKA) ......................83
VIII.3. Aspek Pengelolaan Lingkungan Hidup .....................................83
VIII.4. Implementasi HSE di PT Bahari Sukses Mandiri......................84
VIII.5. Aplikasi HSE pada Lingkungan ................................................87
VIII.6. Aplikasi HSE pada Pemboran ...................................................88
VIII.7. Aplikasi HSE dalam Produksi ...................................................92
VIII.8. Corporate Social Responsibility.................................................93
VIII.8.1. Pemberdayaan Masyarakat ............................................93
VIII.8.2. Tahapan Pemberdayaan Masyarakat..............................93
VIII.8.3. Pembangunan Pedesaan .................................................94
VIII.8.4. Pembangunan Ekonomi .................................................94
VIII.8.5. Program Corporate Social Responsibility (CSR) ..........95
VIII.8.6. Manfaat CSR bagi Masyarakat ......................................95
VIII.8.7. Manfaat CSR bagi Perusahaan.......................................95
VIII.8.8. Pemetaan Sosio Ekonomi ..............................................96
BAB IX ABANDONMENT AND SITE RESTORATION ................................97
iv
IX.1. Plug dan Abandon Sumur ............................................................97
IX.2. Pembersihan Peralatan Fasilitas Produksi....................................98
IX.3. Perkiraan Biaya Abandon ............................................................98
BAB X ORGANISASI DAN JADWAL PROYEK ...........................................99
X.1. Organisasi.....................................................................................99
X.2. Project Schedule ...........................................................................99
BAB XI TINGKAT KOMPONEN DALAM NEGERI ....................................102
BAB XII COMMERCIAL ..................................................................................105
XII.1 Biaya Pengembangan Lapangan ................................................105
XII.2 Keekonomian Proyek .................................................................107
XII.3 Analisis Sensitivitas ...................................................................112
BAB XIII KESIMPULAN ...................................................................................114
DAFTAR PUSTAKA ..........................................................................................115
v
DAFTAR TABEL
vi
DAFTAR GAMBAR
vii
BAB I EXECUTIVE SUMMARY
1
Tabel I.1 Summary Skenario Pengembangan Lapangan Rayu
Gp Gp Gp ∆Gp INC. RF RF RF
OGIP ∆RF
Field Time Case Initial End EL Dari BC Init. End EL
2
BAB II GEOLOGICAL FINDINGS AND REVIEWS
Prospek ini terdiri dari struktur penemuan minyak dan gas berturut-turut
dari utara ke selatan. Lapangan minyak dan gas terdekat adalah Lapangan Musi
yang terletak lebih kurang 4 km ke arah timur Lapangan Jene dan Pian, lebih kurang
10 km ke barat. Sub Cekungan Sumatera Selatan merupakan cekungan belakang
busur magmatik pada sistem aktif margin antara Lempeng Benua Eurasia dan
Lempeng Samudra India (Gambar II.1).
3
Pembentukan Sub Cekungan Sumatera Selatan tidak terlepas dari evolusi
tektonik yang terjadi Asia Tenggara. Pergerakan Lempeng Benua India yang terus
bergerak menuju utara hingga bertumbukan (collision) dengan Lempeng Benua
Eurasia dan subduksi Lempeng Samudra Australia-India ke bawah Lempeng
Eurasia seluruhnya mempengaruhi pembentukan cekungan-cekungan di Asia
Tenggara, khususnya Cekungan Sumatera Selatan. Konfigurasi batuan dasar
(Kraton Sunda) yang terdiri atas beberapa lempeng mikro juga mempengaruhi
konfigurasi struktur geologi khususnya di wilayah Pulau Sumatera. Konfigurasi
batuan dasar umumnya ber arah Barat laut-Tenggara yang tn beramalgamaerbentuk
dasi dari satu lempeng mikro dan lempeng lainnya.
4
Blok patahan ini membentuk konfigurasi basement dan mengontrol
sedimentasi Formasi Lahat dan Talang Akar di dalam struktur graben, dan
kemungkinan juga mengontrol perkembangan penumpukan karbonat dari Formasi
Baturaja pada struktur basement tinggi. Fase tektonik kedua terjadi pada Miosen
Tengah setelah pengendapan Formasi Gumai, dan selama itu terjadi penurunan
aktivitas tektonik ekstensional, dan digantikan oleh kompresi yang menyebabkan
pengangkatan dan erosi di beberapa daerah. Fase tektonik terakhir terjadi pada Plio-
Pleistosen, yang mengakibatkan adanya konfigurasi cekungan dan mengontrol
distribusi terjadinya hidrokarbon di daerah Musi-Klingi.
5
1. Batuan Basement (Pra-Tersier)
Batuan basement Pra-Tersier mengandung batuan beku granit yang teramati
pada sumur DOS-1 dan batuan metamorf kuarsit yang teramati pada sumur RU-1,
Formasi ini merupakan batuan dasar (basement rock) dari Cekungan Sumatera
Selatan. Tersusun atas batuan beku Mesozoikum, batuan metamorf Paleozoikum
Mesozoikum, dan batuan karbonat yang bermetamorfosa. Pra-Tersier hanya
tersingkap di Bukit Pendopo, arah barat kota Prabumulih dan Bukit Batu arah timur
kota Palembang. Singkapan batuan Pra-Tersier dijumpai sepanjang bagian muka
dari Pegunungan Bukit Barisan (Gumai-Garba) yang membentuk batas pada arah
batuan.
2. Formasi Talang akar (Oligosen Akhir - Miosen Awal)
Formasi Talang Akar diendapkan secara tidak selaras di atas kompleks
basement pra-Tersier. Di Blok Rayu, formasi ini terbentuk sebagai lapisan tipis
batupasir konglomerat yang tidak terkonsolidasi dan terfragmentasi, diendapkan
pada lingkungan laut dangkal Formasi Talang Akar berakhir pada masa transgresi
maksimum dengan munculnya endapan laut pada cekungan selama Miosen Awal.
Formasi ini memiliki ketebalan ± 460-610 m, ditindih selaras oleh Formasi
Baturaja, dan diendapkan di lingkungan darat hingga laut dangkal, yaitu di laguna.
Secara umum formasi Talang Akar terdiri dari 2 bagian yaitu bagian atas dan
bawah. Pada bagian bawah secara umum terdiri dari batupasir kasar – sangat kasar,
berselang – seling dengan lapisan tipis shale dan batubara. Pada bagian atas terdiri
dari selang – seling batupasir dan shale, dengan beberapa sisipan tipis batubara,
yang secara berangsur menjadi lebih bersifat marine. Meskipun terdapat batubara,
shale marine dan batupasir semakin ke atas bersifat gampingan.
6
Penumpukan karbonat terutama berkembang di basement high. Unit
karbonat ini mengidentifikasikan kondisi lingkungan laut di Sub Cekungan
Palembang Selatan. Unit ini berkembang sebagai reef coral yang tebal pada struktur
bagian dari cekungan, lebih bersifat lempungan dan terdapat fasies marly. Formasi
ini berketebalan mencapai 85 m dan ditindih selaras oleh Formasi Gumai.
Lingkungan pengendapan batuan berhubungan dengan laut yang sesuai bagi
pertumbuhan dan perkembangan terumbu, yaitu laut dangkal dengan kondisi air
yang jernih dan hangat.
7
5. Formasi Air Benakat (Miosen Awal - Miosen Tengah)
Formasi yang selaras ini berada di atas Formasi Gumai dan terendapkan
secara luas di Blok Rayu. Formasi Air Benakat terdiri dari interbedded sandstone
dan carbonaceous deposit, dengan interkalasi batubara berumur Miosen Tengah,
yang diendapkan pada lingkungan marine-littoral dangkal. terdiri dari batu lempung
dengan sisipan batupasir, yang semakin ke atas semakin dominan batulempung.
Secara umum kehadiran batulempung dan batu lanau lebih dominan di bagian
bawah dan atas, sedangkan kehadiran batupasir lebih dominan di bagian tengah.
Formasi ini berketebalan mencapai 330 m, diendapkan di lingkungan laut dangkal
yang dicirikan oleh kehadiran moluska yang melimpah.
8
Pada reservoir rock terdapat di formasi baturaja dan formasi talang akar
dimana formasi batu raja memiliki kandungan batuan karbonat dan batu gamping,
untuk formasi talang akar memiliki kandungan batu pasir dan sisipan batu bara yang
diendapkan. Lalu untuk seal rock terdapat pada formasi gumai dimana bagian
bawah terusan memiliki kandungan serpih calcareous shale dengan sisipan
batugamping, napal, batu lanau untuk bagian atas memiliki perselingan batupasir
dan shale. Kemudian untuk trap yaitu kombinasi struktural dan stratigrafi
mengandung sedimen clastic dan karbonat build up maupun reservoir klastik untuk
formasi talang akar. Terakhir untuk migrasi cekungan Sumatera selatan merupakan
migrasi sekunder terbagi menjadi dua migrasi vertikal bermigrasi melalui updip
musi platform dan lateral melalui lapisan pembawa formasi talang akar atau melalui
rekahan batu gamping. Di bawah ini akan dijelaskan lagi mengenai petroleum
system element:
9
Migrasi sekunder merupakan perpindahan hidrokarbon lebih lanjut menuju
batuan reservoir yang memiliki perangkap hidrokarbon atau tempat lain dimana
hidrokarbon terakumulasi. Jalur untuk perpindahan hidrokarbon mungkin terjadi
dari jalur keluar yang lateral atau vertical dari cekungan awal. Migrasi lateral
mengambil tempat didalam unit – unit lapisan dengan permeabilitas horizontal yang
baik, sedangkan migrasi vertikal terjadi 13 ketika migrasi yang utama dan langsung
yang tegak menuju lateral. Jalur migrasi lateral berciri tetap dari unit – unit
permeable. Sesar menjadi saluran utama untuk migrasi vertikal dengan transportasi
yang cepat dari cairan yang bersamaan dengan waktu periode tektonik aktif dan
pergerakan sesar.
3. Batuan Reservoir
Batuan reservoir merupakan batuan berpori dan permeable yang
mengandung minyak bumi. Batuan reservoir umumnya terdiri dari batuan sedimen,
yang berupa batu pasir, batuan karbonat dan shale atau kadang-kadang vulkanik.
Batuan reservoir merupakan batuan berpori yang dapat diisi oleh fluida seperti air,
lumpur, minyak dan gas. Untuk mengidentifikasi keberadaan batuan reservoir yang
mengandung minyak dan gas, perlu dilakukan kegiatan eksplorasi hidrokarbon
(Koesoemadinata, 1980). Pada Cekungan Sumatera Selatan yang berkembang
sebagai batuan reservoir adalah batugamping Formasi Baturaja dan batupasir
Formasi Air Benakat. Batu gamping Formasi Baturaja diperkirakan merupakan
fasies platform yang secara litologi pejal, namun sesar – sesar yang cukup intensif
menghasilkan porositas sekunder pada reservoir. Batuan Reservoir utama pada
lapangan ini adalah batu gamping terumbu formasi baturaja, formasi batu raja pada
umumnya di Cekungan Sumatra Selatan, pelamparannya cukup luas. Batu gamping
disini berkembang di bagian bawah sebagai batugamping klastik berupa paparan
karbonat sedangkan bagian atas berkembang pada tempat-tempat tertentu.
10
Pada Cekungan Sumatera Selatan terdapat bentuk utama struktur geologi adalah
dome anticlinal yang lebar dan cebakan dari blok sesar yang miring.
5. Seal Rock
Batuan penutup atau Seal merupakan lapisan impermeable yang dapat
menghambat atau menutup jalannya hidrokarbon. merupakan batuan yang memiliki
porositas dan permeabilitas kecil, yang biasanya terdapat di atas batuan reservoir.
Lapisan ini juga biasa disetarakan dengan lapisan overburden. Litologi yang sangat
baik adalah batulempung dan batuan evaporit. Seal rock pada lapangan ini adalah
batuan serpih gampingan dengan sisipan batu pasir, batuan napal dan batu gamping
dibawahnya dari Formasi Gumai lalu serpih bagian bawah formasi gumai yang
menutupi tonjolan - tonjolan karbonat formasi baturaja dianggap sebagai batuan
penutup atau cap rock.
11
Gambar II.4 Porositas Reservoir lapangan RU-1
12
Gambar II.5 Stratigrafi Umum sub Cekungan Sumatera Selatan
13
Dari overlay yang telah kami lakukan terdapat 4 zona produktif yang
menurut kami sangat berpotensi menjadi sumur infill atau sumur baru dimana
permeabilitas maupun porositas dan saturasinya sudah sesuai dengan kriteria untuk
dijadikan sumur baru, kedalaman dari sumur infill yang telah kami pilih yaitu infil
yang pertama 990 mss dengan saturasi 0.22, dengan porositas 0.2 %. Berdasarkan
letak maupun keekonomian yaitu zona yang terletak pada koordinat X = 9638550,
dan Y = 209900.
1. Metode Volumetris
Metode volumetris digunakan untuk memperkirakan besarnya cadangan
reservoir pada suatu lapangan minyak atau gas yang baru, dimana data-data yang
tersedia belum lengkap. Data-data yang diperlukan untuk perhitungan perkiraan
cadangan secara volumetrik, yaitu bulk volume reservoir (V ), porositas batuan (f),
b
14
Nilai tersebut akan berperan penting dalam keputusan dasar pengembangan dan
operasional suatu reservoir. Dalam perhitungan Volume Bulk menggunakan
Planimeter. Dalam hal ini ketika peta isopach telah dibuat maka luas daerah setiap
garis isopach dapat dihitung dengan planimeter dan dilakukan plot terhadap luas
lapisan produktif versus kedalaman lapisan. Maka dalam hal ini metode
perhitungan volume bulk adalah:
a. Metode Pyramidal
Metode ini dapat digunakan apabila perbandingan luas antara peta isopach
sebesar (An+1) An<0.5, maka didapat perhitungan volume bulk:
Vb = ⅓ h (An + An + 1 + ((√An x An + 1)
b. Metode Trapezoid
Metode ini dapat digunakan apabila perbandingan luas antara peta isopach
sebesar (An+1) An>.5, maka didapat perhitungan volume bulk:
Vb= ½ x h x (An +An +1)
Dalam perhitungan volume bulk terdapat data yang dapat digunakan sebagai
patokan yang dikenal dengan GWC (Gas Water Contact) yang merupakan batas
antara zona gas. Pada sumur RU-1 dan RU-2 didapat GWC sebesar 1010 mss
yang merupakan batasan antara zona prospek dengan zona non prospek.
Parameter yang lain pada plot peta depth structure menggunakan skala 1:
333.33 m. Dalam penentuan GWC dilakukan plot terhadap tiap kedalaman
sumur sehingga didapat nilai luas yang berbeda. Pada kedalaman 1010 m
memiliki luas sebesar 7447485.45 m2 , pada kedalaman 1005 didapat luas
sebesar 6344566.59 m2, pada kedalaman 1000 mdidapat luas sebesar
5131965.51 m2, untuk RU-1 pada kedalaman 995 m didapat luas sebesar
2248511.57 m2 dan untuk RU-2 di kedalaman yang sama sebesar 931474.58
m2, pada sumur RU-1 di kedalaman 990 m didapat luas sebesar 1315022.89 m2
dan sumur RU-2 pada kedalaman yang sama diperoleh luas 104001.39 m2, pada
sumur RU-1 di kedalaman 985 m diperoleh luas sebesar 813619.15 m2 dan pada
sumur RU-1 di kedalaman 980 m diperoleh luas sebesar 312628.94 m2. Pada
penentuan nilai volume bulk peta Depth Structure dibantu dengan peta RMS
sehingga untuk sumur Rayu didapat nilai Volume Bulk sebesar 92483.06955
acre-ft.
15
Tabel II.1 Perhitungan Volume Bulk RU-1
Total VB 79516.31781
Nama Luas (m2) Luas (Acre) Kedalaman Interval Interval a/(a+1) Metode Vb
(Ft) (m) (ft) (acre Ft)
Total VB 12966.75174
16
II.2.2.1. Perhitungan OGIP (Original Gas in Place)
OGIP merupakan geologi model yang menggunakan akumulasi data yang
menggunakan parameter Volume bulk, konstanta, porositas, saturasi air dan Bgi.
Nilai OGIP untuk keseluruhan sumur sebesar 65.322 bscf.
17
Interpretasi ini dilakukan dengan menggunakan data logging yang tersedia
seperti yang ditunjukkan pada Tabel II.2 yang menjelaskan log pada masing-masing
sumur, yaitu sumur RU-1 dan RU-2 sebagai berikut.
RU-2 � ➖ ➖ � � � � � �
II.2.3.3. Porositas
Porositas adalah merupakan fraksi dari volume ruang kosong terhadap total
volume yang bernilai antara 0 - 1, atau sebagai presentasi antara 0 - 100%. Porositas
bergantung pada jenis bahan, ukuran bahan, distribusi pori, sementasi, riwayat
diagenetik, dan komposisinya. Porositas batuan umumnya berkurang dengan
bertambahnya usia dan kedalaman. Porositas efektif mampu mengalirkan fluida
yang ada di dalamnya yang dapat diperoleh dari perhitungan berdasarkan data
densitas (RHOB) dan data neutron (NPHI). Tabel II.4 merupakan hasil perhitungan
porositas untuk setiap zona potensi pada kedua sumur di reservoir tersebut adalah
sebagai berikut.
18
Tabel II.5 Hasil Perhitungan Volume Shale
Sumur Zona Porositas
RU-1 1 0.269
RU-1 2 0.208
RU-2 1 0.302
19
II.2.3.6. Hasil Analisis Log
Dari data yang telah disediakan dan telah dihitung dengan dilakukan
pembacaan-pembacaan log secara manual di mana pembacaan tersebut dilakukan
dengan membaca nilai log dan skala log. Setelah dilakukan pembacaan dan analisa
log maka perhitungan parameter - parameter reservoir dilakukan. Hasil dari analisis
log dapat dijelaskan dalam Tabel II.8 sebagai berikut.
20
Vshale, SW, porositas dan lainnya. Setelah melakukan cut off maka zona net sand
dan net pay dapat ditemukan di mana net pay merupakan ketebalan zona
hidrokarbon dan net sand merupakan ketebalan zona permeabel. Pada penentuan
nilai cut off porositas dan volume shale dilakukan dengan melakukan plot antara
nilai porositas efektif terhadap volume shale. Begitu juga dengan cut off saturasi air
dengan porositas efektif. Lalu, setelah di plot dibuat parameter batas Vshale,
porositas, dan Sw untuk dapat dilakukan nya cut off, pada sumu RU-1 digunakan
parameter sebagai berikut.
21
rata, dan permeabilitas rata-rata. Tabel II.10 menunjukkan reservoir summary
sebagai berikut.
Tabel II.11 Reservoir Summary
Z
O
WELL RESERVOIR SUMMARY PAY SUMMARY
N
E
NET NET
BOTTOM GROSS Avg Avg Avg NTG
TOP (ft) SAND NTG PAY
(ft) (ft) Por Vsh Sw (%)
(ft) (ft)
16.51 66.66
RU-1 1 3301.342 3326.11 24.772 22.019 66.666 0.269 0.318 0.866
43 6
59.64
55.55
RU-1 2 3403.316 3510.67 107.35 22.019 55.555 0.207 0.210 0.225 12888
5
9
22.89
44.44
RU-2 1 3520.2 3557.69 51.5117 40.064 44.444 0.301 0.244 0.180 40888
4
9
22
BAB III DESKRIPSI RESERVOIR LAPANGAN
Reservoir didefinisikan sebagai tempat terakumulasi atau terkumpulnya
fluida hidrokarbon berupa gas, minyak, atau air. Dalam eksplorasi minyak dan gas
bumi, reservoir merupakan salah satu faktor penting untuk lanjut atau tidaknya
sebuah proyek eksplorasi. Parameter-parameter yang menjadi acuan untuk
mendeskripsikan reservoir dimulai dari data tekanan reservoir, kedalaman lapisan,
penentuan porositas dan saturasi air yang terkandung di dalam reservoir tersebut
untuk menghitung Original Gas in Place (OGIP) atau cadangan awal gas yang
terdapat didalam reservoir tersebut. Selain itu, penentuan drive mechanism pun juga
berpengaruh terhadap perhitungan GPmax.
Sumur RU-1 dan RU-2 memiliki data cadangan awal gas di tempat dengan
menggunakan metode volumetrik sebesar 65.322 BSCF. Disebabkan oleh adanya
perkembangan data-data, maka dapat dilakukan evaluasi produksi kumulatif gas
dengan menggunakan metode material balance, setelah dilakukan evaluasi maka
dilakukan peramalan produksi pada sumur RU-1 dan RU-2 dengan menggunakan
kurva gas plateau rate. Data PVT yang perlu dihitung pada studi pengembangan
lapangan ini adalah faktor kompresibilitas gas. Dalam penentuan jenis tenaga
dorong dilakukan plot P/z vs kumulatif produksi gas (Gp), dari analisa tenaga
dorongnya berupa depletion drive, sehingga tidak perlu dilakukan pengukuran
water influx dikarenakan jumlah air yang sedikit. Kemudian dari perhitungan
didapatkan nilai recovery factor pada sumur RU-1 dan RU-2 sebesar 84% dengan
menggunakan hasil cadangan awal gas di tempat metode straight line material
balance.
23
Fluida reservoir yang terdapat dalam ruang pori-pori batuan reservoir
tertentu, secara alamiah merupakan campuran yang sangat kompleks dalam
susunan atau komposisi kimianya. Sifat-sifat fluida hidrokarbon perlu dipelajari
untuk memperkirakan cadangan akumulasi hidrokarbon, menentukan laju aliran
minyak atau gas dari reservoir menuju dasar sumur, dan lainnya. Fluida reservoir
dapat berupa hidrokarbon dan air formasi. Hidrokarbon yang terbentuk di alam
dapat berupa zat cair, gas, ataupun zat padat.
Parameter-parameter yang termasuk ke dalam karakteristik fluida adalah
viskositas, faktor volume formasi, densitas, dan kompresibilitas. Terdapat dua
lapisan, yaitu Baturaja. Karakteristik fluida pada satu lapisan memiliki nilai ᵒAPI
densitas gas masing-masing sebesar 57.3ᵒ API dan 0.67 dengan data tambahan
komposisi gas pada tabel dibawah ini sehingga dapat disimpulkan bahwa gas yang
terkandung di dalam reservoir merupakan wet gas.
Berdasarkan Tabel III.2, terdapat data mengenai tekanan inisial, kumulatif produksi
masing-masing sumur, Bgi, dan saturasi air.
24
Berdasarkan data komposisi gas diketahui pada Tabel III.3, gas pada
reservoir ini memiliki senyawa pengotor yang sedikit, yaitu kurang dari 2%
sehingga untuk menghitung faktor kompresibilitas gas tidak perlu dilakukan
koreksi terhadap senyawa pengotor. Oleh karena itu, dari data tersebut dapat
dilakukan untuk menentukan faktor kompresibilitas gas (z) dan faktor volume
formasi gas (Bgi).
Tabel III.3 Data Komposisi Gas di Separator
COMPONENT Mole Percent GPM
Hydrogen Sulfides H2S 0
Carbondioxide CO2 0.9649
Nitrogen N2 2.6885
Methane C1 86.0019
Ethane C2 5.0139 1.337
Propane C3 2.9469 0.8089
iso-Butane i-C4 0.587 0.1915
n-Butane n-C4 0.6602 0.2075
iso-Pentane i-C5 0.338 0.1234
n-Pentane n-C5 0.2509 0.0907
Hexane C6 0.3157 0.1295
Heptane C7 0.1421 0.0654
Octane C8 0.0717 0.0366
Nonane C9 0.0137 0.0077
Decane C10 0.0035 0.0021
Undecane C11 0.0009 0.0006
Dodocane Plus C12+ 0.0002 0.0001
Total 100.00 3.001
25
Selanjutnya, data dari permeabilitas horizontal digunakan untuk mendapatkan rock
types dari batuan reservoirnya. Dari data yang ada, dilakukan normalisasi dan
denormalisasi terhadap tekanan kapiler menggunakan J-function.
26
Gambar III.2 Teknanan Kapiler Vs Saturasi Air
27
III.3.2. Faktor Volume Formasi Gas
Faktor volume formasi gas dapat didefinisikan sebagai perbandingan
volume gas pada kondisi reservoir dengan volume gas pada kondisi standar (60 °F,
14.7 psia). Nilai faktor volume formasi gas pada sumur RU-1 dan RU-2 sebesar
0,0092 cuft/SCF.
28
Pwf, psia P/z Gp, MMSCF
900 1071.429 28919.478
800 952.381 32964.160
700 833.333 37008.842
600 714.286 41053.524
500 595.238 45098.206
400 476.190 49142.889
300 357.143 53187.571
200 238.095 57232.253
100 119.048 61276.935
0 0 65321.617
29
III.3.5. Recovery Factor
Recovery factor (RF) adalah faktor perolehan gas yang didefinisikan
sebagai perbandingan jumlah gas yang diproduksikan ke permukaan (EUR atau
Gpmax) dengan cadangan awal gas di tempat (OGIP atau G). Nilai recovery factor
yang akan ditentukan dengan Gp pada saat tekanan abandon sebesar 300 psia
sebelum dilakukan perhitungan nilai Gpmax. Setelah dilakukan perhitungan
didapatkan Gpmax pada sumur Rayu sebesar 54705.304 MMSCF dengan nilai OGIP
sebesar 65321.617 sehingga dapat diperoleh nilai recovery factor sebesar 84%.
Untuk menentukan estimated ultimate recovery secara komersial, dapat dilakukan
dengan melakukan perkalian antara nilai Gpmax pada sumur Rayu, yakni sebesar
84% dari nilai 65321.617 MMSCF sehingga diperoleh nilai EUR sebesar
54704.324 MMSCF.
30
BAB IV RESERVES AND PRODUCTION FORECAST
31
Gambar IV.1 Wellbore Property and Production Nodal Analysis Sumur RU-1
Nilai n pada kedua sumur tersebut dapat diasumsikan, dalam hal ini nilai n
yang digunakan sebesar 0.7. Namun, nilai C yang dihasilkan pada masing-masing
sumur berbeda. Untuk nilai C pada sumur RU-1 sebesar 0.0022 dan nilai C pada
sumur RU-2 sebesar 0.0019. Nilai AOFP, Qmax, n dan C ini akan berguna dalam
perhitungan pada Skenario I dan II.
Gambar IV.2 Wellbore Property and Production Nodal Analysis Sumur RU-2
32
Dengan nilai OGIP sebesar 65321.617 MMSCF dan nilai tekanan reservoir
sebesar 1615 psia serta nilai faktor kompresibilitas gas (z) sebesar 0.84, maka dapat
diplot grafik P/z Vs Gp di mana nilai P/z adalah 1922.619 dan Gpmax adalah OGIP.
Grafik ini akan memberikan formula atau rumus P/z = -0.0294(Gp)+1922.6 yang
dapat berguna dalam memperoleh nilai tekanan (P) perhitungan Skenario I dan II.
Tabel IV.2 Kumulatif Produksi Per Lapisan Per Blok pada Lapangan Rayu-1 dan
Rayu-2
Liq. Oil Wat.
OGIP Gas Cum WC RF
No. Lapisan Cum Cum Cum
MMSCF MSTB MSTB MMSCF MSTB % %
1. Baturaja 65321.617 - - 52156.843 - - 84
33
Gambar IV.3 Overlay Lokasi Sumur Infill dengan Gas Per Unit Area Kondisi
Initial
34
IV.2.2. Material Balance Analysis
Metode material balance analysis merupakan hasil plot antara P/z Vs Gp
yang berguna untuk menentukan nilai tekanan yang akan digunakan pada skenario
I dan II di mana ditentukan oleh rumus P/z = -0.0294(Gp)+1922.6 dari grafik yang
diplot. Metode ini menggunakan data well flowing pressure (Pwf) dan kumulatif
produksi gas yang sama dengan data yang digunakan untuk menentukan kurva Q
Vs Pwf atau Inflow Performance Relationship (IPR).
35
IV.2.4. Profil Laju Produksi Gas Skenario I dan II
Kurva plateau rate pada skenario I dan skenario II yang terdapat sumur infill
menunjukkan laju produksi gas sebesar 6.8 MMSCFD dari tahun 2020 hingga 2040.
36
IV.2.6. Summary Hasil Skenario Pengembangan
Berdasarkan skenario hasil produksi, pada skema end contract, kumulatif
produksi yang diperoleh sebesar 29803.910 MMSCF pada akhir tahun 2031.
Kemudian, dikembangkan satu sumur infill untuk memenuhi laju produksi
konsumen (Qconsumer) dan usia sumur sehingga diperoleh kumulatif produksi sebesar
52156.843 MMSCF pada akhir kontrak tahun 2040. Skema economic limit untuk
skenario I base case pada akhir tahun 2031 diperoleh kumulatif produksi sebesar
29803.910 MMSCF. Selanjutnya, pada skenario II base case+infill, kumulatif
produksi pada akhir tahun 2041 diperoleh sebesar 54640.502 MMSCF.
37
BAB V DRILLING AND COMPLETION
38
01 November 05 Desember
Rig Permit 4 10 0 0
2031 2031
05 Desember 06 Desember
Rig Up 1 11 0 0
2031 2031
Drilling Time
Drill 26" Hole 06 Desember 07 Desember
1 12 116 380.00
(Conductor Casing) 2031 2031
Run & Cement 20",
07 Desember 09 Desember
Run CBL +VDL & 2 14 116 380.00
2031 2031
Casing
Drill 17 1/2" Hole 09 Desember 11 Desember
2 16 335 1100.00
(Surface Casing) 2031 2031
Run & Cement 13
3/8", Run CBL 11 Desember 13 Desember
2 18 335 1100
+VDL & Casing 2031 2031
Test BOP
Drill 12 1/4" Hole
13 Desember 16 Desember
(Intermediate 3 21 605 1986
2031 2031
Casing)
Run & Cement 9
5/8", Run 16 Desember 18 Desember
2 23 605 1986
CBL+VDL & 2031 2031
Casing Test BOP
Drill 8 1/2" Hole 18 Desember 24 Desember
6 29 1116 3660
(Production Casing) 2031 2031
Running Production
24 Desember 26 Desember
7", Cement & Run 2 31 1116 3660
2031 2031
CBL, VDL
Sirkulasi ganti isi 26 Desember 26 Desember
0.5 31.5 1116 3660
lubang dengan CF 2031 2031
Run Production
26 Desember 27 Desember
String (Tubing), Set 0.5 32 1116 3660
2031 2031
X-mastree
Perforation job & 27 Desember 30 Desember
3 35 1116 3660
Drill Steam Test 2031 2031
Preparation Rig 30 Desember
2 37 1116 3660 1 Januari 2032
Down 2031
39
V.2. Geological Prognose
Secara umum, formasi yang ditembus selama operasi pengeboran di
lapangan Rayu di Cekungan Sumatera Selatan berturut-turut adalah Formasi Muara
Enim, Formasi Air Benakat, Formasi Gumai, Formasi Baturaja, dan Formasi
Talangakar. Target utama pemboran adalah reservoir produktif yang terdapat pada
Formasi Baturaja. Karakteristik litologi dari reservoir Formasi Baturaja yaitu
Formasi ini terdiri atas batu lempung, beberapa jenis batu gamping yakni
wackestone, packstone, boundstone dengan sisipan batuserpih karbonat.
Reservoir ini cukup baik dan memiliki ketebalan 23,20 m. Permeabilitas
rata-ratanya berkisar 88,33 mD, porositas efektif rata-rata 20,79 %. Hasil tersebut
merupakan hasil setelah cut off.
upnormal
Gumai pressure
Intermediate Casing Interbedded Claystone,
9-5/8" @1986 ft Limestone, sandstone
permeable = lost
134 °F circulation
Baturaja
Predominant reefal
carbonate limestone with
shale intercalation
Production Casing
7" @3660 ft
1714 °F Talang Akar
Basement
40
langkah-langkah dan trayek-trayek yang akan dilakukan sebagai berikut.
41
V.3.2. Trayek Lubang 26”
Pada trayek ini dimaksudkan untuk dipasang casing conductor yang
berfungsi untuk menahan agar permukaan tidak runtuh.
Kedalaman akhir trayek : ± 380 ft
Interval bor : 380 ft (0 – 328 ft)
Drilling Hazard : -
Action Plan : -
BOP : 5000 psia
Bit : Tricone Bit 26”
BHA : Rock Bit 26”
DC OD 6.25 ID 2.75
HWDP OD 5” ID 3”
DP OD 5” ID 4.408”
Survey : 3 days
Parameter : WOB 10 Ton
Casing : CONDUCTOR PIPE OD 20" H-40 94 ppf ID 19,12"
(Collapse 167.96 psi, Burst 349.80 psi, tension
35.720 Klbs)
Program Lumpur : Spud Mud
42
Casing Weight 94
ID (inch) 19.12
API Fluid Loss (ml) < 10
Mud Volume (bbl) 249.54
Excess (30 %) (bbl) 74.86
43
berfungsi untuk melindungi zona air tanah.
Kedalaman akhir trayek : ± 1100 ft
Interval bor : 1100 ft ( 0 – 1100 ft)
Drilling Hazard : Shale
Action Plan : Penggunaan KCL Polimer
BOP : 5000 psia
Bit : Tricone Bit 17 ½ ”
BHA : Tricone Bit 17 ½ ”
DC OD 6.25 ID 2.75
HWDP OD 5” ID 3”
DP OD 5” ID 4.408”
MWD, Stabilizer, JAR
Survey : 3 days
Parameter : WOB 12.5 Ton
Casing : 13 3/8’’ H-40, 48 ppf (Collapse 514.80 psi, Burst
631.55 psi, tension 59.950 Klbs)
Program Lumpur : KCl Polimer
44
Excess (30 %) (bbl) 102.64
45
Bit : PDC 12 ¼ ”
BHA : PDC 12 ¼ ”
DC OD 6.25 ID 2.75
HWDP OD 5” ID 3”
DP OD 5” ID 4.408”
Stabillizer, MWD, JAR
Survey : 3 days
Parameter : WOB 15 Ton
Casing : 9 5/8’’ H-40, 32.3 ppf (Collapse 1903.20 psi, Burst
1281.00 psi, tension 84.180 Klbs)
Program Lumpur : KCl Polimer
46
V.3.4.1. Operasi Pemboran
Tahap pemboran yang berlangsung pada trayek 12 ¼” adalah sbb:
1. Running drill bit, drill collar dan juga drill pipe.
2. Putar drill string dengan menggunakan top drive.
3. Sirkulasikan Mud hingga mencapai kedalaman yang diinginkan.
4. Cabut rangkaian pengeboran.
47
DP OD 5” ID 4.408”
Stabilizer, MWD, JAR
Survey : 3 days
Parameter : WOB 20 Ton
Casing : 7’’ LS-65, 23 ppf (Collapse 1903.20 psi, Burst
1281.00 psi, tension 84.180 Klbs)
Program Lumpur : KCl Polimer
48
3. Sirkulasikan Mud hingga mencapai kedalaman yang diinginkan.
4. Cabut rangkaian pengeboran.
49
Kecepatan Kritis
Di dalam DP Di dalam DC Annulus DC Annulus DP
(m/menit) (m/menit) (m/menit) (m/menit)
297.48 318.96 240.74 239.81
288.30 308.52 239.34 236.50
245.91 265.33 217.47 206.55
176.51 195.81 428.81 162.88
V
Di dalam DP Di dalam DC Annulus DC Annulus DP
(m/menit) (m/menit) (m/menit) (m/menit)
1071.965179 3136 80.91 69.69
937.9695317 2744 70.79 60.98
669.9782369 1960 142.34 97.95
187.5939063 548.8 415.76 72.59
Jenis Aliran
Di dalam DP Di dalam DC Annulus DC Annulus DP
Turbulen Turbulen Laminer Laminer
Turbulen Turbulen Laminer Laminer
Turbulen Turbulen Laminer Laminer
Turbulen Turbulen Laminer Laminer
50
4. Running casing gun dengan CCL menggunakan wireline.
5. Setelah mencapi titik yang diinginkan ledakkan casing gun menggunakan
detonator.
6. Running out rangkaian perforasi.
51
V.5. Perkiraan Jumlah Hari dan Biaya Pemboran dan Komplesi
Kegiatan pengeboran diperkirakan berlangsung dalam waktu 37 hari operasi
tanpa adanya technical issue yang dapat menghambat jalannya kegiatan
pengeboran. Sehingga diharapkan akan menambah produksi hidrokarbon dar
lapangan ini. Jumlah hari tersebut terlihat pada Tabel V.7 dan Gambar V.4, yang
mencakup:
1. 11 hari rig move, rig up dan Rig permit.
2. 21 hari drilling days.
3. 3 hari komplesi sumur.
4. 2 hari rig down.
Tabel V.8 Perkiraan Hari Pemboran dan Komplesi Sumur Infill
Drilling Time RU-3
Kumulati
Durasi Depth
Aktivitas f
(hari) (hari) (m) (ft)
Preparation
Surveying, Planning, Programs 3 3 0 0
Rig Contract
Rig Move 3 6 0 0
Rig Permit 4 10 0 0
Rig Up 1 11 0 0
Drilling Time
Drill 26" Hole (Conductor Casing) 1 12 116 380
Run & Cement 20", Run CBL +VDL & Casing 2 14 116 380
Drill 17 1/2" Hole (Surface Casing) 2 16 335 1100
Run & Cement 13 3/8", Run CBL +VDL &
2 18 335 1100
Casing Test BOP
Drill 12 1/4" Hole (Intermediate Casing) 3 21 605 1986
Run & Cement 9 5/8", Run CBL+VDL &
2 23 605 1986
Casing Test BOP
Drill 8 1/2" Hole (Production Casing) 6 29 1116 3660
52
Running Production 7", Cement & Run CBL,
2 31 1116 3660
VDL
Sirkulasi ganti isi lubang dengan CF 0.5 31.5 1116 3660
Run Production String (Tubing), Set X-mastree 0.5 32 1116 3660
Perforation job & Drill Steam Test 3 35 1116 3660
Preparation Rig Down 2 37 1116 3660
53
Tabel V.9 Rincian Biaya Pemboran dan Komplesi
BUDGET
UNIT
NEW PURCHASE GRAND TOTAL
No DESCRIPTION OF
UNIT
ISSUE QTY AMOUNT
PRICE
TANGIBLE COST
1 CASING + DRILL PIPE
Conductor Pipe OD 20" H-40 94 ppf
$ 13
ID 19,124" 1950.04 $ 24,700.51
Surface Casing OD 13 3/8" H-40 48
$ 37
ppf ID 12,715" 1845.35 $ 67,662.83
Intermediate Casing OD 9 5/8" H-40
$ 66
32,3 ppf ID 9,001" 1029.14 $ 68,129.07
Production OD 7" LS-65 23 ppf ID
$ 122
6,366" 463.88 $ 56,593.36
Tubing 5" $ 114 158.38 $ 18,132.13
Drill Pipe ft 3660 40 146,400
Permanent Packer 38,000
2 Well Equipment - Surface 100,000
3 Well Equipment - Sub Surface 76,000
TOTAL $ 595,617.90
INTANGIBLE COST
4 PREPARATION AND EXECUTION
Surveys Days 3 4000 12,000
Well site and access road preparation 100,000
Planning and Programs 180
Lease Acquisition and License Fees 3,100
5 DRILLING OPERATION
Well Insurance ft 4800 7.00 33600
Rig Move days 3 3600 10800
Rig Permit days 4 0 0
Rig Contract (1000 HP) days 27 35000 945,000
Rig Mob Demob 210,000
PDC Bit 12-1/4" 30,000 30,000
PDC Bit 8.5" 30,000 30,000
Tricone Bit 26" 10,000
54
Tricone Bit 17-1/2" 10,000
Mud Tank 350
Mud Program 89,495
Mud Engineer days 30 300 9,000
Cementing Program 51,068
Basic Cementing Service days 30 3000 90,000
Mixing Truck days 30 300 9,000
Drilling Engineer (Standby) person 2 1000 60,000
6 Formation Evaluation
CBL VDL 120,000
DST 50,000
Well Testing 1 75000 75,000
7 Completion
Perforation and Wireline Service 1 95000 95,000
Cased Hole Electrical Logging Service 50,000
8 General
HSE 500,000
Crew Payment person 14 1200 16,800
Crew Camp days 31 2000 62,000
Fuel and Lubricants days 31 3000 93,000
Crew Transportation 31 350 10,850
Abandonment and Site Restoration
(ASR) 150,000
TOTAL $ 2,926,243.23
GRAND TOAL $ 3,521,861.13
55
dilakukan untuk mencegah kerusakan lingkungan. Langkah ini diperlukan karena
pengeboran menjadi tulang punggung kegiatan usaha hulu migas.
Apabila pengelolaan limbah tidak dilakukan dengan benar, kegiatan
pengeboran bisa dihentikan karena dianggap membahayakan lingkungan. Oleh
karenanya dalam kegiatan pengeboran sumur infill ini untuk urusan pembuangan
limbah menggunakan jasa kontraktor dari PT Prasadha Pamunah Limbah Industri
(PPLI). Sehinggal segala permasalahan yang berkaitan dengan limbah menjadi
wewenang dari kontraktor tersebut.
56
BAB VI PRODUCTION FACILITIES
57
Gambar VI.1 Skematik Arus Fluida Dari Lapangan Hingga Fasilitas Pengumpul
58
b. Tambahan Surface Facilities
Penambahan fasilitas di permukaan sesuai dengan skenario pengembangan
yang direncanakan seiring dengan meningkatnya jumlah produksi gas.
Tabel VI.2 Tambahan Suface Facilities
No Fasilitas produksi tambahan Quantity Harga Total
1 Sewa 3 Phase Separator Test (1 bulan) 1 $10,000 $ 10,000.00
2 FWKO 1 $15,000 $ 15,000.00
3 flow line 6,625" 750 Meter $12 $ 8,835
4 Three Phase Separator 9.2 MMSCFD 1 $450,000 $ 450,000.00
$ 483,835.00
59
Gambar VI.3 Proyeksi Cumulative Gas Rate
VI.3. Power Plant
Gas yang terproduksi digunakan sebagai power plant pada Lapangan rayu.
Lapangan rayu ini memakai 2 jenis power plant, yaitu gas engine dan diesel engine.
1. Diesel Engine
Motor bakar diesel biasa disebut juga dengan Mesin diesel (atau mesin pemicu
kompresi) adalah motor bakar pembakaran dalam yang menggunakan panas
kompresi untuk menciptakan penyalaan dan membakar bahan bakar yang telah
diinjeksikan ke dalam ruang bakar.
2. Gas Engine
Pada umumnya gas engine digunakan sebagai penggerak untuk alat-alat
seperti generator, pompa, kompressor, dsb di industry Oil and Gas. Cara kerja gas
engine sama dengan diesel engine, hanya saja proses penyalaan bahan bakar-nya
berbeda. Gas engine menggunakan percikan api dari busi (spark ignition)
sedangkan diesel engine mengunakan kompresi untuk menyalakan bahan bakar
(compression ignition).
60
VI.4. Penambahan Fasilitas Produksi
Setelah semua penjelasan dari grafik-grafik sebelumnya, maka sudah dapat
disimpulkan ada atau tidak adanya penambahan fasilitas produksi untuk lapangan
rayu di tiap skenarionya.
61
BAB VII SKENARIO PENGEMBANGAN LAPANGAN
Setelah sumur RU-1 dan RU-2 melalui skenario I base case, selanjutnya
akan dilakukan Plan of Development (POD) mengenai skenario lain yang akan
dilakukan, yaitu skenario II base case + infill dengan satu sumur.
1. RU-3 Infill
62
Tabel VII.1 menunjukkan jadwal pemboran sumur infill selama satu bulan.
63
3. Biaya yang dikeluarkan untuk perawatan diperlukan sehingga tidak perlu
membeli peralatan dengan harga mahal.
Tidak perlu dilakukan penambahan satu sumur lagi, karena hasilnya cukup
baik dan dapat memenuhi permintaan produksi hingga masa akhir kontrak.
64
Pada skema end contract, kumulatif produksi pada akhir tahun 2031
diperoleh sebesar 29803.910 MMSCF. Lalu, dikembangkan satu sumur infill untuk
memenuhi laju produksi konsumen (Qconsumer) dan usia sumur pada skenario II base
case+infill hingga akhir tahun 2040 sehingga diperoleh kumulatif produksi sebesar
52156.843 MMSCF. Skema economic limit untuk skenario I base case diperoleh
kumulatif produksi sebesar 29803.910 MMSCF pada akhir tahun 2031. Kemudian,
pada skenario II base case+infill, kumulatif produksi diperoleh sebesar 54640.502
MMSCF pada akhir tahun 2041.
65
BAB VIII HEALTH, SAFETY & ENVIRONMENT (HSE) AND
CORPORATE SOCIAL RESPONSIBILITY (CSR)
66
VIII.1. Sistem Manajemen HSE
Sistem Manajemen K3 adalah bagian dari sistem manajemen secara
keseluruhan yang meliputi struktur organisasi, perencanaan dan tanggung jawab,
pelaksanaan, prosedur, proses dan sumberdaya yang dibutuhkan bagi
pengembangan, penerapan, pencapaian, pengkajian dan pemeliharaan kebijakan
keselamatan dan kesehatan kerja dalam rangka pengendalian resiko yang berkaitan
dengan kegiatan kerja guna terciptanya tempat kerja yang aman, efisien dan
produktif (Permenaker No. 5, 1996). Penerapan K3 di Wilayah Kerja memiliki
tujuan sebagai berikut.
1. Melindungi dan menjamin keselamatan setiap tenaga kerja dan orang lain di
tempat kerja.
2. Menjamin setiap sumber produksi dapat digunakan secara aman dan efisien.
3. Meningkatkan kesejahteraan dan produktivitas nasional.
Aspek penerapan K3 di Wilayah Kerja (WK) adalah perencanaan yang
meliputi pemasangan, pemakaian, dan perawatan serta pengendalian yang meliputi
administrasi, legalitas, standarisasi, dan sertifikasi. Fokus pelaksanaan K3 terdiri
dari dua hal utama, yaitu mencegah kecelakaan kerja dan mencegah penyakit akibat
kerja. Sistem manajemen K3 terdiri dari beberapa elemen, yaitu Peraturan,
Standarisasi, Pengawasan, Penelitian Teknik, Penelitian Medis, Penelitian
Psikologis, Penelitian Statistik, Pendidikan, Pelatihan, Persuasi, dan Asuransi serta
Penerangan poin-poin tersebut.
Pencegahan kecelakaan tertuang dalam Undang-Undang No. 22 Tahun
2001 tentang Minyak dan Gas Bumi yang berisikan poin-poin sebagai berikut.
1. Menjamin standar dan mutu.
2. Menerapkan kaidah keteknikan yang baik, keselamatan dan kesehatan kerja
serta pengolahan lingkungan hidup.
3. Mengutamakan pemanfaatan tenaga kerja setempat dan produk dalam negeri.
Keselamatan kerja merupakan perlindungan bagi keamanan dan kesehatan pekerja
agar terhindar dari kecelakaan kerja yang terdiri dari beberapa syarat, yaitu
terdapatnya standarisasi kompetensi, tempat kerja dan lingkungan kerja yang baik,
dan prosedur kerja menggunakan alat pelindung diri (APD) bagi yang bekerja di
tempat berbahaya.
67
Keselamatan umum merupakan perlindungan bagi keamanan masyarakat
umum sehingga dapat terhindar dari kecelakaan yang disebabkan oleh kegiatan
usaha migas yang meliputi penyuluhan terhadap bahaya migas, tanda peringatan
atau larangan, sertifikat kelaikan terhadap instalasi dan peralatan, dan tanda
keselamatan peralatan dan sebagainya. Keselamatan instalasi atau peralatan
merupakan suatu perlindungan bagi instalasi dan peralatan yang digunakan
sehingga dapat terhindar dari kerusakan yang dapat membahayakan bagi para
pekerja, lingukangan, masyarakat umum serta kerugian investasi. Untuk dapat
menghindari hal tersebut, terdapat beberapa persyaratan, antara lain prosedur
operasi dan perawatan, sertifikat kelaikan instalasi dan peralatan, penggunaan
standar/SNI, tanda kesesuaian SNI, sertifikat kompetensi bagi pekerja, kesiapan
alat pemadam, dan prosedur dan latihan tanggap darurat.
68
Perusahaan perlu menjalankan K3 dengan konsisten dan berkesinambungan
(practices).
69
Berdasarkan penerapan Contractor Safety Management System (CSMS),
KSO PT Pertamina EP – PT Bahari Sukses Mandiri mendapatkan beberapa
manfaat, di antaranya sebagai berikut:
1. Seimbangnya tanggung jawab penerapan K3 PT Pertamina EP - PT Bahari
Sukses Mandiri.
2. Meminimalisasi terjadinya kecelakaan kerja sebagai bentuk peningkatan
kepedulian kontraktor terhadap penerapan K3.
3. Konsistensi kontraktor dalam menerapkan K3 dapat diawasi dan dikontrol oleh
PT Pertamina EP.
Risiko pekerjaan di WK migas dapat dievaluasi yang disebut dengan
Penilaian Risiko. Penilaian Risiko dalam pekerjaan di area kerja dapat dilakukan
dengan berpedoman pada CSMS yang dilalui oleh beberapa tahap sebagai berikut.
1. Penilaian Risiko
Pada tahap penilaian risiko, kemungkinan risiko atau dampak negatif yang
diakibatkan oleh pekerjaan dapat dikaji terhadap penerapan K3. Kemungkinan
risiko yang terjadi yang menyebabkan kerugian materi dan immateri seperti
kerugian pada pekerja, peralatan kerja, lingkungan, dan perusahaan.
2. Pra-Kualifikasi
Pada tahap ini, kualifikasi dan kemampuan kontraktor dikaji untuk menentukan
apakah kontraktor memiliki potensi dan mampu dalam mengelola pekerjaan
yang akan dilaksanakan yang sesuai dengan kontrak.
3. Seleksi
Tahap ini merupakan langkah untuk menentukan kontraktor terbaik yang paling
baik yang dapat diseleksi berdasarkan rencana-rencana HSE yang akan
diterapkan oleh kontraktor tersebut.
4. Pra-Pekerjaan
Pra Pekerjaan merupakan tahap yang terkait dengan keselamatan pekerjaan
ketika pekerjaan dimulai. Pada tahap ini perlu dilengkapi beberapa persyaratan,
yaitu melengkapi dokumen persyaratan kerja (terdiri dari company profile
kontraktor dan sertifikat kompetensi pekerja), melengkapi Job Safety Analysis
yang berisi langkah pekerjaan disertai dengan risiko dan pengendalian risiko.
70
JSA ini perlu ditandatangani oleh kontraktor dan tim HSE yang kemudian
melengkapi surat izin kerja, dan melakukan safety induction.
5. Pelaksanaan Pekerjaan
Pada tahap ini, pekerjaan yang akan dilakukan oleh kontraktor perlu diverifikasi
agar sesuai dengan rencana HSE yang disepakati. Rencana HSE yang akan
dilakukan dapat berubah apabila terdapat perubahan potensi bahaya ketika
pekerjaan sedang berlangsung. Untuk memenuhi aspek keselamatan kerja,
maka dilakukan langkah-langkah yang meliputi inspeksi oleh safety officer
kontraktor, inspeksi oleh contract giver, dan inspeksi oleh safety team.
6. Pasca Pekerjaan
Pasca pekerjaan merupakan tahapan untuk mengevaluasi kinerja kontraktor
dalam mengelola HSE selama kontrak berlaku. Hasil evaluasi akan menentukan
apakah akan ada pemberian penghargaan atau sanksi.
71
2. Izin kerja pekerjaan dingin (cold work permit). Diperlukan apabila akan
melaksanakan pekerjaan perbaikan, pemeliharaan, atau konstruksi seperti
pengecatan, pekerjaan bangunan, dan pekerjaan sipil.
3. Izin kerja memasuki ruang terbatas (confined space entry permit). Diperlukan
apabila akan memasuki dan melakukan pekerjaan di ruang terbatas, seperti silo,
tangki, atau saluran tertutup.
4. Izin kerja pekerjaan listrik (electrical work permit). Diperlukan apabila akan
melakukan perbaikan, pemeliharaan, atau pemeriksaan kelistrikan.
5. Izin kerja khusus (special permit). Diperlukan apabila akan melaksanakan
pekerjaan berbahaya, seperti bekerja dengan paparan radioaktif.
Peran penting dari SIKA adalah sebagai berikut.
1. Identifikasi wewenang pekerjaan tertentu dan siapa yang bertanggung jawab
untuk menentukan tindakan pencegahan yang diperlukan dan diperhatikan.
2. Instruksi dalam penggunaan dan penutupan izin.
3. Memonitoring dan mengaudit K3 yang berlaku agar sistem dan prosedur
bekerja sesuai harapan.
4. Identifikasi jenis pekerjaan yang dianggap berbahaya.
5. Identifikasi penilaian risiko dan SOP serta aktivitas yang akan dilakukan agar
sesuai dengan harapan.
72
3. Memikirkan cara untuk mencegah terjadinya cidera, atau kecelakaan.
4. Membantu pembuatan prosedur kerja yang aman (SOP).
Tiga Metode Dasar Untuk Melakukan JSA (Friend and Kohn, 2017):
1. Metode observasi langsung. Metode ini menggunakan wawancara observasi
untuk menentukan langkah-langkah kerja dan bahaya yang dihadapi.
2. Metode diskusi. Metode ini biasanya digunakan untuk pekerjaan atau aktivitas
yang jarang dilakukan. Metode ini melibatkan pekerja-pekerja yang telah
selesai bekerja dan membiarkan mereka bertukar pikiran terkait langkah-
langkah pekerjaan dan potensi bahaya yang ada.
3. Metode recall dan recheck. Metode ini biasanya digunakan ketika proses
sedang berlangsung dan pekerja tidak bisa bersama-sama. Semua orang yang
berpartisipasi dalam proses ini menuliskan ide-ide tentang langkah-langkah dan
potensi bahaya yang ada di pekerjaan.
Tahapan Pelaksanaan Analisis Keselamatan Kerja (Job Safety Analysis):
1. Pemilihan pekerjaan yang akan dianalisis.
2. Pembagian kerja berdasarkan proses yang berurutan.
3. Menentukan tindakan perbaikan.
4. Mengkomunikasikan informasi pada yang lain.
5. Follow-up dan Review Job Safety Analysis.
73
Urutan Kerja Potensi Bahaya atau Rekomendasi Prosedur
Kecelakaan Keamanan
Perjalanan dari dan Mengendarai kendaraan Berhati-hati saat
menuju lokasi. melintasi jalan dan
parkir. Petakan rute ke
lapangan, memiliki peta
area yang tersedia, dan
mengikuti praktik
mengemudi defensif.
Kedatangan awal di Kondisi cuaca Memakai tabir surya
lapangan. ketika cuaca panas dan
kenakan topi bertepi
lebar. Ketika cuaca
dingin menggunakan
pakaian berlapis dan
sarung tangan.
Inspeksi visual tata letak Pemilik area yang kesal Bersikap sopan dan
lapangan. dengan lingkungan diplomatis.
berbahaya.
Menjaga keamanan Terluka akibat serangan Identifikasi area
lapangan. hewan buas. biohazard dan buat rute
evakuasi.
Area pembuangan bahan Kenakan APD dan
kimia. hindari area yang
terkontaminasi.
Uap Evakuasi dengan belari
berlawanan dengan arah
angin.
Pengawasan selama Pengoperasian rig. kenakan APD dan
pengeboran berlangsung. memahami cara
mengoperasikan dasar
rig pengeboran.
74
Potensi Bahaya atau Rekomendasi Prosedur
Urutan Kerja
Kecelakaan Keamanan
Pengawasan selama Pengoperasian alat berat. Jaga jarak aman dari
pemeliharaan peralatan. peralatan. Kenakan APD
dan jangan membantu
kontraktor selama
operasi di lokasi
Pengawasan cairan Kenakan APD, sarung
pengambilan sampel. tangan, dan kacamata.
Keluar dari lapangan. Terkontaminasi bahan Lepas APD, cuci tangan,
kimia. dan lakukan
dekontaminasi dengan
segera serta perbarui log
eksposur.
Penjemputan pekerja Mengendarai kendaraan. Petakan rute ke
lapangan, memiliki peta
area yang tersedia, dan
mengikuti praktik
mengemudi defensif.
Pulang ke tempat Bahaya lalu lintas. Ikuti dan patuhi
tinggal. peraturan lalu lintas.
75
6. Prosedur pelaporan kecelakaan.
7. Bahaya spesifik pada area tempat bekerja dan cara mengendalikannya.
8. Prosedur pembuatan izin kerja (khusus kontraktor).
76
VIII.4. Implementasi HSE di PT Bahari Sukses Mandiri
Pada subbab ini akan dibahas bagaimana pelaksanaan program keselamatan
dan kesehatan kerja serta menganalisa kesesuaian implementasi Program K3 sesuai
dengan yang diinginkan dalam upaya mencapai predikat zero accident.
77
Gambar VIII.3 Safety Glasses
4. Ear Plug, berfungsi sebagai pelindung telinga pada saat bekerja di tempat
bising.
78
Gambar VIII.6 Safety Gloves
7. Safety Shoes, berfungsi mencegah kaki tertusuk benda tajam atau tertimpa
peralatan berat. Safety shoes juga dapat memberikan kenyamanan dalam
bekerja yang dapat mencegah pekerja terjatuh akibat permukaan yang licin dan
membahayakan pergerakan pekerja.
79
VIII.5. Aplikasi HSE pada Lingkungan
Pada aplikasi Health, Safety & Environment (HSE) pada aspek lingkungan
Musi antara lain pembuangan lumpur pemboran, pembuangan air produksi,
kebisingan, dan gas beracun.
VIII.5.3. Kebisingan
Aktivitas pengembangan oil and gas menghasilkan marine noise, termasuk
operasi seismik, aktivitas pemboran dan produksi. Polusi suara dapat terjadi akibat
peralatan-peralatan berat yang bekerja pada proses pengembangan lapangan.
Tingkat kebisingan tersebut akan diukur dan diawasi karena dapat mengganggu
warga, bahkan pada level yang terlampau tinggi dapat membahayakan pendengaran
tenaga kerja yang lewat daerah kegiatan pemboran. Tingkat kebisingan tempat kerja
untuk 8 jam per hari (24 jam) tidak boleh melebihi 85 db.
80
VIII.5.4. Emisi Udara
Sumber utama dari emisi udara adalah pembakaran yang dilakukan oleh
mesin yang menghasilkan energi dan panas untuk memastikan gas dan hidrokarbon
lainnya.
81
VIII.6.2. Pelaksanaan Pemboran
Pelaksanaan pemboran yang mengaplikasikan aspek HSE perlu
diperhatikan hal-hal sebagai berikut:
1. Tersedia fasilitas camp yang memenuhi minimal gizi yang diperlukan bagi
pekerja shift.
2. Menyediakan kotak P3K.
3. Memasang rambu-rambu peringatan di sekitar lokasi.
4. Memberikan safety induction kepada setiap pengunjung yang masuk
kedalam lokasi pengeboran.
5. Melakukan safety meeting setiap kali akan melakukan pekerjaan yang
berbahaya.
6. Melakukan kick drill, pit drill secara berkala.
7. Menyediakan satu orang tenaga medis di lokasi.
8. Melaksanakan safety talk, setiap pergantian shift.
9. Pekerjaan di lapangan harus menggunakan pakaian kerja yang standar
10. Pekerja harus menggunakan alat – alat pelindung diri untuk mengurangi
cedera akibat kecelakaan (safety shoes, safety gloves, safety goggle, ear plug,
safety helmet, safety mask, safety belt).
11. Mempunyai standard operating procedure (SOP) sebagai acuan dalam
melakukan pekerjaan dan mengoperasikan alat.
12. Melakukan pengelolaan limbah pemboran yang keluar dari sumur dan akibat
chemical lumpur.
13. Menyediakan vacuum truck untuk mengangkut limbah yang berlebihan,
untuk diolah di tempat lain.
14. Menyediakan alat detektor untuk gas beracun dan exsplosive gas.
15. Menyediakan fire pump dan sprayer di sekitar cellar.
82
2. Jika sumur tidak langsung diproduksikan, maka sumur harus dilengkapi
dengan back pressure safety down valve.
3. Sumur dinyatakan tidak ekonomis (dry hole), maka sumur harus ditutup
mengikuti prosedur yang baku sesuai SOP (plug and abandon).
83
• Terhadap sumur eksplorasi di darat perlu dilakukan uji TCLP pada saat
mencapai kedalaman akhir (total depth) untuk setiap jenis lumpur. Hal
ini diperlukan untuk memastikan keberadaan logam berat pada suatu
struktur yang di bor.
• Terhadap uji sumur pengembangan tidak perlu dilakukan uji LC50-96
jam dan uji TCLP selama menggunakan jenis lumpur yang sama dengan
pada waktu pengeboran pada tahap eksplorasi.
• Apabila bahan dasar dan bahan aditif yang digunakan berbeda maka uji
ulang perlu dilaksanakan.
2. Perlakuan Serbuk Bor
Terhadap pengeboran di darat uji TCLP tidak perlu dilakukan, tetapi apabila
ditemukan kandungan logam berat pada lumpur, maka serbuk bor harus
dikelola secara aman. Apabila menggunakan lumpur minyak dan sintetis
maka perlu dilakukan paling sedikit 1 (satu) kali pengujian kandungan
minyak pada serbuk bor selama lumpur minyak digunakan.
84
• Proses pengolahan lumpur bor dan serbuk bor berbahan dasar minyak
diawali dengan pemisahan minyak dari padatan (deoiling). Lumpur bor
berbahan dasar minyak dapat dipergunakan kembali (reuse atau recycle).
Padatannya dilakukan pengelolaan lebih lanjut sampai memenuhi baku
mutu sesuai dengan ketentuan yang berlaku.
85
1. Melakukan preventive maintenance.
2. Melakukan sertifikasi seluruh peralatan sesuai aturan migas.
3. Penanggulangan kemungkinan terjadinya pencemaran lingkungan.
4. Antisipasi kejadian kebakaran, sehingga harus disiapkan fasilitas seperti alat
deteksi kebakaran dan penanggulangan kebakaran.
86
3. Tahap Evaluasi Program
Dalam pelaksanaan CSR tersebut, Perusahaan akan selalu memantau hasil
capaian program dan melakukan perbaikan pada beberapa sektor kerja yang
belum termaksimalkan. Tujuan dari dilakukannya evaluasi tersebut guna
mendapatkan data dan informasi terkait hambatan dan permasalahan yang ada
di lapangan, serta solusi mengatasinya agar program dapat berjalan maksimal.
87
6. Renovasi tempat-tempat ibadah.
7. Perbaikan fasilitas-fasilitas umum.
8. Bantuan paket sembako untuk hari raya.
9. Peningkatan kualitas jalan melalui pengaspalan dan pembuatan parit.
10. Bantuan sponsorship yang diberikan terhadap kegiatan-kegiatan yang
dilakukan oleh para stakeholder.
11. Bantuan sarana air bersih.
88
Memilih kegiatan CSR yang sesuai dengan kegiatan utama perusahaan
memerlukan kreativitas. Merencanakan CSR secara konsisten dan berkala dapat
memicu inovasi dalam perusahaan yang pada akhirnya dapat meningkatkan
peran dan posisi perusahaan dalam bisnis global.
5. Membedakan perusahan tersebut dengan para pesaingnya.
89
BAB IX ABANDONMENT AND SITE RESTORATION
2. Plug II
Plug ini diset sepanjang 60 meter di tengah-tengah kedalaman sumur,
umumnya di set sekitar intermediate casing shoe.
90
3. Plug III
Plug ini di set minimum 60 meter dengan top of plug di kedalaman 50 meter
di bawah tanah.
91
BAB X ORGANISASI DAN JADWAL PROYEK
X.1. Organisasi
Organisasi PT Bahari Sukses Mandiri Lapangan Rayu dapat ditampilkan
pada Gambar X.1 sebagai berikut ini.
92
Tabel X.1 Project Schedule POFD Lapangan Rayu
2019 2020
No. Uraian 2031 2040
7 1 2
2 Persetujuan POFD
93
Run & Cement 13
3/8", Run CBL 11 Desember 13 Desember
2 18 335 1100
+VDL & Casing 2031 2031
Test BOP
Drill 12 1/4" Hole
13 Desember 16 Desember
(Intermediate 3 21 605 1986
2031 2031
Casing)
Run & Cement 9
5/8", Run 16 Desember 18 Desember
2 23 605 1986
CBL+VDL & 2031 2031
Casing Test BOP
Drill 8 1/2" Hole 18 Desember 24 Desember
6 29 1116 3660
(Production Casing) 2031 2031
Running Production
24 Desember 26 Desember
7", Cement & Run 2 31 1116 3660
2031 2031
CBL, VDL
Sirkulasi ganti isi 26 Desember 26 Desember
0.5 31.5 1116 3660
lubang dengan CF 2031 2031
Run Production
26 Desember 27 Desember
String (Tubing), Set 0.5 32 1116 3660
2031 2031
X-mastree
Perforation job & 27 Desember 30 Desember
3 35 1116 3660
Drill Steam Test 2031 2031
Preparation Rig 30 Desember
2 37 1116 3660 1 Januari 2032
Down 2031
94
BAB XI TINGKAT KOMPONEN DALAM NEGERI
95
b. Pelaksanaan kegiatan pengadaan barang/jasa khususnya dalam rangka
mengutamakan penggunaan barang Produksi Dalam Negeri dan mengutamakan
pemanfaatan jasa dalam negeri, menggunakan Buku Apresiasi Produksi Dalam
Negeri (buku APDN), yang diterbitkan oleh instansi pemerintah yang
membidangi industri minyak dan gas bumi. Kontraktor KKS wajib
menggunakan buku APDN tersebut sebagai acuan untuk menetapkan strategi
pengadaan serta menetapkan persyaratan dan ketentuan pengadaan.Daftar
tersebut berisikan informasi tentang:
1. Barang Wajib Dipergunakan, berisi jenis barang kebutuhan utama kegiatan
eksplorasi dan produksi yang telah diproduksi di dalam negeri dan salah
satu pabrikan telah mencapai penjumlahan TKDN 199 ditambah bobot
manfaat perusahaan (BMP) minimal 40%
2. Barang Dimaksimalkan, berisi jenis:
a) Barang kebutuhan utama yang telah diproduksi di dalam negeri dan
salah satu pabrikan telah mencapai TKDN minimal 25% (dua puluh
lima persen), namun belum ada pabrikan yang mencapai penjumlahan
TKDN ditambah bobot manfaat perusahaan (BMP) minimal 40%
(empat puluh persen).
b) Barang kebutuhan pendukung yang telah diproduksi didalam negeri dan
salah satu pabrikan telah mencapai TKDN minimal 25% (dua puluh
lima persen).
c) Barang Diberdayakan, berisi daftar barang kebutuhan
kegiatanoperasional Kontraktor KKS yang telah diproduksi di dalam
negeri dan TKDN salah satu pabrikan telah mencapai minimal 5% (lima
persen), namun belum ada pabrikan denganpencapaian TKDN 25%
(dua puluh lima persen).
d) Jasa Dalam Negeri, berisi daftar jasa yang telah pernah diselesaikan oleh
Perusahaan Dalam Negeri dan Perusahaan Nasional di wilayah negara
Republik Indonesia dalam kurun waktu 7 (tujuh) tahun terakhir, dengan
pencapaian TKDN minimal 30% (tiga puluh persen).
96
Tabel XI.1 TKDN Peralatan Pengembangan Lapangan Rayu
%
No Deskripsi Material
TKDN
1 Penyediaan Rig 60
2 Bit 100
3 Tubing 100
4 Lumpur Pemboran 80
5 Semen Pemboran 90
6 Cementing tools 15
7 Well head 70
8 Perforasi 35
9 Completion Fluid 35
10 Transportasi 100
11 Drilling engineer 100
12 Production facilities unit 20
13 Casing 20
14 Drill pipe 20
Persen TKDN 36,21
97
BAB XII COMMERCIAL
98
Tabel XII.1 Fiscal Terms
General Parameter Amount Remark
1 Oil Price (USD/BBL) 50
2 Gas Price (USD/MMBTU) 8
3 Gas Price Escalation 2.5% /yr
4 Variabel Cost (USD/BOE) 11.25
5 Variabel Cost Escalation 2.5% /yr
Fixed Cost Lapangan Minyak
6 105000 /yr
(USD)
7 Fixed Cost Escalation 2.5% /yr
8 ASR Cost (USD) 900000 /well
/investasi Production
9 ASR Production Facilities (USD) 5%
Facilities
10 Intangible cost 93%
Tangible Cost
11 7%
99
XII.2. Keekonomian Proyek
Mempertimbangkan berbagai aspek untuk menentukan skenario yang akan
digunakan, seperti kondisi reservoir, kemampuan pengoperasian, kondisi lapangan
dan juga keekonomian pada masing – masing skenario yang digunakan. Seperti
yang diketahui harga gas yang digunakan dan ketentuan kontrak untuk standar
adalah : Pada PT. Bahari Sukses Mandiri menjual Produksi gas dan seperti yang
digunakan dan ketentuan kontrak untuk standar PT Bahari Sukses Mandiri adalah:
1. Harga gas 8 USD/MMBTU eskalasi 2.5% dari tahun 2015.
2. Operating Cost 11.25 USD/boe, eskalasi 2.5%/tahun.
3. FTP 20%.
4. Tax 44%.
5. Contractor Share after tax 15%, Government Share after tax 85%.
6. DMO Price 100%, DMO Volume 25%.
7. Depresiasi capital terjadi selama 5 tahun, declining balance.
Bagi kontraktor bila mungkin seluruh biaya diganti atau minimal sebagian
dapat diganti dan lebih dari itu wilayah kerja dapat dipertahankan sampai 20 tahun.
Ada beberapa macam indikator yang dipakai untuk menilai kelayakan suatu proyek;
yang penting adalah POT (Pay Out Time), NPV (Net Present Value), dan IRR
(Internat Rate of Return). POT merupakan indikator keekonomian yang
menunjukkan berapa lama modal investasi dapat kembali. Proyek yang mempunyai
harga POT berarti layak, tetapi POT juga menunjukkan resiko proyek. Makin
panjang POT maka makin besar resiko yang dihadapi proyek. Untuk situasi dimana
ketidakpastiannya tinggi, seperti misalnya negara yang pemerintahannya tidak
stabil, investor akan memilih proyek-proyek yang memiliki POT pendek (quick
yielding). NPV menunjukkan nilai absolut earning power dari modal yang
diinvestasikan di proyek, yaitu total pendapatan (discounted) selama proyek. NPV
positif menunjukkan proyek layak. Mudah dipahami bahwa makin besar discount
rate yang dipakai, maka makin kecil NPV yang bisa diperoleh. IRR menunjukkan
nilai relatif earning power dari modal yang diinvestasikan di proyek, yaitu discount
rate yang menyebabkan NPV sama dengan nol. Suatu proyek dianggap layak
apabila IRR memiliki nilai yang lebih besar dibandingkan dengan cost of capital.
100
Gross Revenue
320,608,440.45
Cost Recovery
207,232,329.95
101
Tabel XII.2. Ringkasan Perhitungan Keekonomian (Sampai Akhir Kontrak PSC)
Gas
1 MMBTU 43,296,854 23,231,520 54,206,880
Production
2 Gas Price $/MMBTU 12.61 13.80 12.01
3 Gross Revenue $/yr 496,268,241 320,608,440 650,983,617
4 Project Period years 21 9 21
5 FTP $ 99,253,648 64,121,688 130,196,723
Contractor
6 $ 53,171,597 34,350,904 69,748,245
FTP
7 Investment:
Tangible $ 92,000 2,311,652 2,311,652
Intangible $ 1,023,000 24,731,279 24,731,279
Total
8
Operating Cost
OPEX $ 271,753,402 176,542,015 355,135,017
ASR $ 1,890,000 3,647,384 5,471,075
Cost
9 $ 274,758,402 207,232,330 387,649,023
Recovery
%Gross
% 55.36 64.64 59.55
Revenue
Unrecovered
10 $ 0 28,780,562 28,780,562
Cost
Equity to be
11 $ 122,256,191 49,254,422 133,137,871
split
Government
12
Take:
Undiscounted $ 155,056,888 79,363,277 184,334,216
% Gross
% 31.24 24.75 28.32
Revenue
Contractor
13
Take:
Cash Flow $ 68,342,952 37,660,217 84,471,454
% Gross
% 13.77 11.75 12.98
Revenue
NPV @10% $ 33,276,917 21,658,664.60 35,382,407.05
IRR % #NUM! 48% #NUM!
POT years 0.00 0.00 0.00
102
Tabel XII.3 Ringkasan Perhitungan Keekonomian (Economic Limit)
103
Gambar XII.2. Distribusi Incremental Revenue dari Skenario Pengembangan
Lapangan Rayu Utara
XII.2.1 Skenario I
Tabel XII.4 Skenario I Calculation
Skenario I End Contract
Parameter Unit Nilai
Gross Revenue $ 496,268,241 100%
Cost Recovery $ 274,758,402 55%
Government Take $ 155,056,888 31%
Contractor Cash Flow $ 68,342,952 14%
POT years 0
IRR % #NUM!
NPV 10% $ 33,276,917
104
XII.2.3 Skenario II
Tabel XII.5. Skenario II Calculation
Skenario II Strike Forward
Parameter Unit Nilai
Gross Revenue $ 320,608,440 100%
Cost Recovery $ 207,232,330 65%
Government Take $ 79,363,277 25%
Contractor Cash Flow $ 37,660,217 12%
POT years 0.00
IRR % 48%
NPV 10% $ 21,658,664.60
105
Gambar XII.3. Spider Diagram untuk IRR Project
106
BAB XIII KESIMPULAN
107
DAFTAR PUSTAKA
Audey, Patricia. 2014. "Cost Recovery Dalam Kontrak Kerjasama Minyak dan Gas
Bumi di Indonesia Ditinjau Dari Hukum Kontrak Internasional". Malang.
Universitas Brawijaya.
Bourgoyne Jr, A., Millheim, K., Chenevert, M., and Young Jr, F. . (1986): Applied
Drilling Engineering, Society of Petroleum Engineers, Texas.
Brill, J.P. (1999): Multiphase Flow in Wells. First Printing. University of Tulsa:
Richardson, Texas.
Cendekiawan, Seminar Nasional et al. 2015. “Minyak Awal Dengan Menggunakan
data Logging Pada Lapangan Apr.” : 151–57.
Cole, F. W. (1960): Reservoir Engineering Manual (Second Edition), Gulf
Publishing Company, Houston, Texas
108
Decline Curve Analysis di Lapangan “R”. Seminar Nasional Cendekiawan.
Madewa, N.P, Kasmungin, Ir. S. dkk. (2017): Perhitungan Isi Awal Minyak Dengan
Metode Material Balance dan Peramalan Produksi pada Lapangan ‘A’.
Prosper, Y.-M. S., Djoko, I., & Mt, S. (n.d.). Studi Evaluasi Dan Optimasi
Penggunaan ESP Pada Sumur Muhammad Dzulfiqar Anindhito.
109