2. Pokok Pembahasan
2.5.1 Requisition
To test design and implementation of Control Engagement Team perform:
Inquiry to the person who perform control about the requisition process.
compare operation standard versus step of control that perform by the controller
Inspect the Purchase Requisition Form and New Vendor Form if there is approval
based on understanding.
2.5.2 Purchase
To test design and implementation of Control Engagement Team perform:
Inquiry to the person who perform control about the purchase process.
compare operation standard versus step of control that perform by the controller
Inspect the purchase order if there is approval based on understanding.
2.5.3 Receiving
To test design and implementation of Control Engagement Team perform:
Inquiry to the person who perform control about the receiving process.
compare operation standard versus step of control that perform by the controller and
check if there is CCTV in receiving area.
Inspect the purchase order and Delivery Order if there is approval based on
understanding.
Inspect the goods receive (condition) and compare to purchase order (quantity and
item receive shall be match and write down in to Delivery Order and if there is
approval on DO based on understanding.
2.5.4 Payment
To test design and implementation of Control Engagement Team perform:
Inquiry to the person who perform control about the payment process.
compare operation standard versus step of control that perform by the controller
Inspect the purchase order, delivery order, Invoice and Payment Voucher if there is
approval based on understanding.
Inspect the item and quantity in purchase order, delivery order and Invoice shall be
match and Payment Voucher if there is approval based on understanding.