Perencanaan Tambang Mine Planning
Perencanaan Tambang Mine Planning
(MINE PLANNING)
CONTOH SOAL
SUATU TAMBANG TERBUKA LOGAM DASAR
DENGAN
KAP.TAMBANG 35.000 MT/BULAN, SR 1/7,8
1 TON BHN GALIAN = 0,27 M3
KAP.DOZER 250 M3/JAM (SATU UNIT) DAN
320
M3/JAM (2 UNIT), JAM KERJA PADA SHIFT II
225 JAM
JIKA AKAN DITAMBANG SEBANYAK 65 %
DARI
KAP.TOTAL/BULAN PADA SHIFT II ,
HITUNGLAH
PENAMBAHAN UNIT PADA SHIFT II DGN
KAP.320
M3/JAM/UNIT.
JAWAB :
KAP.DOZER (II)
= (250)(225)(1) + (320)(225)
(2)=56.250+144.000=200.250 BCM
KAP.PENAMBANGAN DLM SHIFT II =
(0,65)((35.000)(0,27)+(35.000)(7,8))
=(0,65) (9.450+273.000) BCM = 183.592,5
BCM
TDK PERLU ADA PENAMBAHAN DOZER LAGI
SUATU PIT TAMKA DENGAN BAGIAN PIT A, B
DAN C
DATANYA SBB
PIT A KAP.22.000 MT, SR 1/8,6
PIT B, KAP 31.000 MT, SR 1/8,4
PIT C, KAP 25.000 MT, SR 1/9,2
KAP.DOZER/UNIT = 290 M3, FAKTOR
EFISIENSI 0,84
JAM KERJA PADA SHIFT III 290 JAM
65 % OB DIANGKUT KE DISPOSAL AREA,
SISANYA BACK
FILLING (HANYA PERLU DOZER)
KAP. DT 63 M3/JAM,
1 TON BHN GALIAN = 0,79 M3
HITUNG:
UNIT DOZER PADA PIT A, B DAN C
UNIT DT UNTUK MENGANGKUT OB DAN
BATUBARA
PADA SEMUA PIT
CONTOH SOAL
SUATU BLOK TAMBANG (MINING BLOCK)
BATUBARA
DENGAN DIMENSI PANJANG SEARAH JURUS
160
METER, LEBAR SEARAH KEMIRINGAN 75 M,
DAN
KETEBALAN RATA-RATA 4,5 METER, BJ NYA
1,29 TON/M3. JIKA KAP.DOZER 325 M3/JAM
DAN 275 M3/JAM, DENGAN FAKTOR
EFISIENSI 0,81 DAN 0,75. JAM KERJA 270
JAM/BLN, HITUNGLAH BERAPA LAMA
PENGGALIAN OB DAN BATUBARA AKAN
DILAKSANAKAN. SR = 1/5,7.
JAWAB :
TOTAL VOL.PENAMBANGAN
TOTAL VOL.BATUBARA + TOTAL VOL OB
= (160)(75)(4,5) + (5,7)(160)(75)(4,5)(1,29)
M3
= (54.000) + (5,7) (54.000)(1,29) M3 =
54.000 +397.062 M3. = 451.062 M3.
TOTAL KAP.2 DOZER/BLN
= (325)(270)(0,81) + (275)(270)(0,75) M3
= 71.077,5 M3 + 55.687,5 M3 = 126.765 M3
LAMA PENGGALIAN BERLANGSUNG
TOTAL VOL YG AKAN DITAMBANG/TOTAL
KAP./BLN
= 451.062 /126.765 BLN = 3,56 BULAN
ATAU = 3,56 x 270 JAM = 961,2 JAM.