KOLEJ VOKASIONAL

KEMENTERIAN PENDIDIKAN MALAYSIA


DIPLOMA TEKNOLOGI ELEKTRIK

DEA1323
AC&DCMOTOR LABSHEET1

STAR-DELTA AC MOTOR CONNECTION

8Jam

TAJUK / TITLE: STAR-DELTA AC MOTOR CONNECTION

MASA YANG DIBENARKAN : 8 JAM

OBJEKTIF / OBJECTIVE:
1. Student will be able to differentiate DC & AC Motor With Operating Procedure and apply the
basic knowledge from motor control and understanding of the PLC and UPS for real
application with hands-on workshop.

TUJUAN PENILAIAN / ASSESSMENT AIMS:


1. Demonstrate connection of AC motor and protection feature
2. Demonstrate AC motor maintenance
3. Detect damage and repair SENARAI PERALATAN DAN BAHAN:
Bil. Bahan/ Komponen/ Peralatan Kuantiti
1 Motor aruhan AU 3 fasa sangkar tupai 1
2 Bekalan kuasa AU 3 fasa 1
3 Meter pelbagai 1
4 Meter penguji penebatan 1
5 Meter Tong (Clamp meter) 1
6 Meter Volt 1
7 Tachometer 1
8 Kabel penyambung secukupnya
PANDUAN KESELAMATAN:
Anda dikehendaki mengamalkan amalan keselamatan diri, peralatan dan tempat kerja.
ARAHAN KERJA:
Anda dikehendaki melakukan tugasan berikut:
1. Anda dikehendaki menyambung litar motor arus ulang alik (AU) 3 fasa sambungan
bintang dan delta seperti yang ditujukkan pada Rajah 2 dan 3.
2. Semua hasil dapatan hendaklah diisi di dalam lampiran 1 dan 2.
3. Markah akan diberi berdasarkan proses kerja, hasil kerja, aspek keselamatan dan nilai
etika.

LANGKAH KERJA:
LANGKAH KERJA BUTIRAN KERJA
(1) Menyediakan (a) Sediakan komponen seperti yang di senaraikan. (b)
komponen Pastikan komponen yang digunakan selamat.

(a) Catat data yang terdapat pada motor di Lampiran 2.


(2) Mencatat data pada plat
nama. (a) Uji gelung motor dan catat pada jadual 2 di Lampiran 2.
(b) Uji pembumian motor dan catat pada jadual 2 di Lampiran 2.
(3) Menguji motor (c) Uji penebatan motor dan catat pada jadual 2 di Lampiran 2.

(a) Sambung motor AU 3 fasa secara sambungan star seperti Rajah 2.


(b) Ambil dan catatkan bacaan kelajuan motor aruhan 3 fasa pada jadual
(4) Penyambungan litar 4di Lampiran 2.
(c) Ambil dan catatkan bacaan arusdan bacaan voltan pada jadual 5 di
Lampiran 2.
(d) Ulang langkah a – c untuk motor AU 3 fasa bagi sambungan secara
delta seperti Rajah 3.

(a) Membuka semula semua litar pendawaian.


(b) Memastikan tempat kerja bersih dan kemas berdasarkan piawaian
(5) Persekitaran tempat
kerja
5S.
GAMBARAJAH SAMBUNGAN LITAR:
Rajah 1.1: Tamatan motor dan ujian keterusan Rajah 1.2: Tamatan motor dan ujian rintangan penebatan

Rajah 2: Sambungan litar motor sambungan bintang Rajah 3: Sambungan litar motor sambungan delta
Lampiran 1
LUKISAN PENDAWAIAN
Punca Bekalan Motor Sangkar Tupai

L1 W2 U2 V2

L2
U1 V1 W1
L3

N
ϑ>

Rajah 4: Penyambungan motor AU 3 fasa sambungan bintang

Lampiran 2
BORANG PENGUJIAN
( Untuk Di isi Oleh Calon )

1.0 SPESIFIKASI MOTOR

1.1 Kadar Voltan : ………………415………………… Volt


1.2 Kadar Arus : ………………10………………… Amp
1.3 Kelajuan Motor : ………………450………………… RPM
1.4 Frekuensi : ………………50………………… Hz
1.5 Model : …………………28817002………………
1.6 Kelas Penebatan Motor : …………………………………
1.7 Kuasa Motor : ………………………………… kW

2.0 UJIAN PADA MOTOR

Jenis & Jenama Meter: ……………Multimeter…………………….


Sambungan Bacaan Rintangan (ohm) Keputusan

(U1 – U2) 0 Ohm Baik

(V1 – V2) 0 Ohm Baik

(W1 –W2) 0 Ohm Baik


Jadual 1: Ujian Keterusan Motor AU 3 Fasa

Jenis & Jenama Meter: ………………Earth Resistance Tester………………….

Sambungan Bacaan Rintangan (ohm) Keputusan

BUMI – KERANGKA BADAN 0.5 M Ohm Baik


MOTOR
Jadual 2: Ujian Pembumian Motor AU 3 Fasa

Jenis & Jenama Meter: ……………Insulation Tester…………………….

Sambungan Bacaan Rintangan (ohm) Keputusan

(U1 – U2) dan (V1 – V2) 1 M Ohm Baik

(U1 – U2) dan (W1 – W2) 1 M Ohm Baik

(V1 – V2) dan (W1 – W2) 1 M Ohm Baik

(U1 – U2) dan BUMI 1 M Ohm Baik

(V1 – V2) dan BUMI 1 M Ohm Baik

(W1 –W2) dan BUMI 1 M Ohm Baik


Jadual 3: Ujian Penebatan Motor AU 3 Fasa

PERATURAN PEMARKAHAN AMALI


Markah Diberi
Wajaran Jumlah Peratus
Bil Perkara Yang Dinilai
0 1 2 3 (1-3) Markah Markah
Proses dan Prosedur Kerja – 40 %
1.1 Melakar rajah litar motor AU 3
fasa sambungan bintang dengan 3
betul
1.2 Melakar rajah litar motor AU 3 / 27 X
1 fasa sambungan delta dengan 3 40%
betul
1.3 Menyediakan peralatan, bahan
3
dan kelengkapan
JUMLAH
2 Penilaian Hasil Kerja – 50%
2.1 Membuat penyambungan motor 3 / 63 x
AU 3 fasa sambungan bintang 50%
pada tamatan yang betul
2.2 Membuat penyambungan motor
3 fasa sambungan delta pada 3
tamatan yang betul
2.3 Mengendali motor AU 3 fasa
3
dengan betul
2.4 Mengambil nilai ukuran ujian
3
keterusan dan mencatat bacaan
2.5 Mengambil nilai ukuran ujian
3
pembumian dan mencatat bacaan
2.6 Mengambil nilai ukuran ujian
3
penebatan dan mencatat bacaan
2.7 Membuat ulasan dapatan ujian
3
dengan tepat
JUMLAH

Sikap dan Keselamatan– 10%


3.1 Persediaan diri 1
3.2 Pengurusan peralatan 1
3.3 Kekemasan kawasan kerja 1 / 15 X
3
10%
3.4 Keselamatan diri dan peralatan 1
3.5 Ketepatan masa 1
JUMLAH
JUMLAH KESELURUHAN (1 + 2 + 3 = 100%) %

a. Skala Markah:
0 – tidak menjalankan tugasan
1 – menjalankan tugasan dan tidak mengikut kriteria yang ditetapkan
(1% – 49%)
2 – menjalankan tugasan dan mengikut sebahagian kriteria yang
ditetapkan (50% - 74%) 3 – menjalankan tugasan dan mengikut kriteria yang ditetapkan
(75% - 100%) b. Wajaran:
1 – perkara yang penting / tidak memerlukan kemahiran tinggi
2 – perkara penting / perlu kemahiran tinggi
3 – perkara sangat penting / mempengaruhi kefungsian

KEPUTUSAN KOMPETEN / BELUM KOMPETEN

TANDATANGAN PEMERIKSA

NAMA PEMERIKSA MAGENDRAN PERUMAL

TARIKH

CATATAN / ULASAN