RAFT FOUNDATION
008/NKET4.T5/MS/STR/XII/2015
WORKING AREA
SEQUENCE OF WORKS
GALIAN
TANAH AREA
MASS
CONCRETE
BOBOK DAN
POTONG
BORE PILE
WATER
MANAGEMENT
FORMWORKS
awal
pembahas
an
STOP COR
THERMOCOUP
LE
REBARS
LEAN
CONCRETE
FACILITIES
FINAL CHECK
LIST
POURING
WORKS
CURING
WAT E R M A N A G E M E N T
WAT E R M A N A G E M E N T
WAT E R M A N A G E M E N T T O W E R 4
WAT E R M A N A G E M E N T T O W E R 5
FORMWORK
FORMWORK UNTUK PEKERJAAN RAFT FOUNDATION AKAN
MENGGUNAKAN PRECAST PANEL DENGAN UKURAN MODUL
2200 X 1000 X 80 MM
MODUL PANEL TERSEBUT AKAN DIPASANG BERJAJAR SESUAI
PERIMETER RAFT FOUNDATION, DENGAN SISTEM SLOT
DIBAWAHNYA DAN WELDED JOIN DIATASNYA
FORMWORK
FORMWORK
SISI BAWAH U 50
2D32-200
LAYER 1
LAYER 2
2D32200
LAYER 3
2D32
-200
D16-200
D19-200
LAYER 4
2D32200
D19-200
LAYER 5
D32200
D25-200
D16-200
LAYER 6
2D32200
D32-200
D25-200
LAYER 7
2D32
-200
LAYER 8
D32200
D19-200
2D32-200
LAYER 9
D32200
D13-200
LAYER 10 D25-200
2D32-200
LAYER 11 2D32-200
D25-200
REBARS
STARTER BAR U 40
SISI SAMPING U 50
LAYER
D32-200
PEMINGGANG
D13-350
D25-200
SISI ATAS U 50
LAYER
LAYER
LAYER
LAYER
1
2
3
4
D19-200
D32-200
D25-200
D16-200
D19-200
D32-200
KOLOM
D13
D16
D25
FACING WALL D10
CONCRETE WALL
D13
D16
D19
TANGGA
D10
D16
PIT LIFT
D10
D13
REBARS PENUNJANG U
40 & 50
KAKI AYAM
D32
REBARS
THERMOCOUPLE
RADIUS PENGUKURAN SETIAP TIANG THERMOCOPLE
ADALAH 8 M, DIMANA COVERAGE AREA ADALAH 200 M2.
TOTAL KEBUTUHAN TIANG PENGUKURAN PADA SETIAP RAFT
ADALAH 8 TITIK
THERMOCOUPLE
SELISIH SUHU ANTARA PROBE BAWAH 20 C TENGAH 20 C
ATAS
MONITORING SUHU AKAN DILAKUKAN SETIAP 2 JAM
SELAMA 7 HARI KEDEPAN SETELAH PENGECORAN BERAKHIR
STOP COR
POSISI STOP COR AKAN DILAKUKAN OVERLAP + 50 CM DARI ARAH
RAFT FOUNDATION KE ARAH PELAT PODIUM
MATERIAL STOP COR YANG AKAN DIGUNAKAN ADALAH KAWAT AYAM &
PAPAN, SERUPA DENGAN PEMBAGI RUANG/SEKAT PENGECORAN
PADA POSISI INI JUGA MERUPAKAN POSISI WATER STOP DENGAN TYPE
SWELLABLE. PEMASANGAN WATER STOP MEMILIKI JARAK 20 CM DARI
POSISI BOTTOM PELAT (ELV. -1.750)
FA C I L I T I E S & E Q U I P M E N T
UNIT,
TRAFO
LAS
UNIT,
BLOWER
UNIT,
POMPA
PERMUKAAN
&
0,8
M3,
TROWEL
FINISHER
MACHINE
UNIT
YANG
AKAN
LABORATORIUM BETON
AREA INI AKAN DILENGKAPI ALAT-ALAT SEPERTI MEASUREMENT TAPE, THERMOMETER,
OFFICE DESK, BAK CURING BENDA UJI BETON, TROLLEY DAN MOBIL OPEN BACK. KHUSUS
UNTUK BAK CURING, AKAN DIBANTU OLEH PIHAK PLAN UNTUK PENAMBAHANNYA
AKSES VERTIKAL
KAMI AKAN MEMBUAT AKSES VERTIKAL BERUPA SCHAFFOLDING SYSTEM, DARI POSISI
ELEVASI EXISTING DI LUAR BASEMENT, MENUJU ELEVASI AREA MASS CONCRETE.
EQUIPMENT
SITE MANAGEMENT
SITE MANAGEMENT
M A N P O W E R PA D A S A AT K E G I ATA N
KEBUTUHAN WORKERS
TOTAL
118 ORG
1.
TUKANG BESI
2.
3.
TUKANG COR
4.
TENAGA PEMBERSIHAN
5.
8 ORG (2 SHIFT)
6.
10 ORG (2 SHIFT)
7.
TENAGA UMUM
. KEBUTUHAN STAFF
6 ORG
10 ORG
64 ORG (2 SHIFT)
12 ORG (2 SHIFT)
8 ORG (2 SHIFT)
TOTAL
100
ORG
1.
PELAKSANA BESI
4 ORG (2 SHIFT)
2.
PELAKSANA COR
10 ORG (2 SHIFT)
3.
QUALITY CONTROL
4.
GUDANG
5.
LOGISTIK
6.
SURVEYOR
7.
MEKANIK/ME
8.
9.
SAFETY/HSE
10. SECURITY
11. UMUM
12. SITE MANAGER
4 ORG (2 SHIFT)
10 ORG (2 SHIFT)
4 ORG (2 SHIFT)
4 TEAM (@TEAM 3 ORG)
8 ORG (2 SHIFT)
24 ORG
4 ORG
16 ORG
2 ORG
2 ORG
POURING WORKS
MUTU BETON YANG DIGUNAKAN PADA MASS CONCRETE ADALAH FC 35, SLUMP
12 + 2, FLY ASH 15% DAN SUHU ON SITE < 35C.
TYPE BETON PERTAMA : NORMAL (SESUAI POINT DI ATAS)
TYPE BETON KEDUA : PENAMBAHAN WATER PROOFING CONTENT
KHUSUS UNTUK AREA PELAT DENGAN KETEBALAN 500 MM, BETON YANG
DIGUNAKAN ADALAH BETON INTEGRAL KRISTALIN/GEL (MASIH DALAM PROSES
APPROVAL)
DENGAN ADANYA PERBEDAAN JENIS BETON PADA SATU MASS CONCRETE INI,
MAKA, PENGECORAN DENGAN TYPE BETON PERTAMA AKAN BERHENTI DI
ELEVASI -1.950
SELANJUTNYA AKAN DITERUSKAN DENGAN TYPE BETON KEDUA HINGGA
ELEVASI 1.450
POURING WORKS
POURING WORKS
ARAH PENGECORAN
MULAI DARI POSISI
TERJAUH
BETON TYPE 1
BETON TYPE 2
POURINGS AREA
PELAT B3
STOP COR
BARIER
DILUAR
COR
POURINGS TIMELINE
LUAS AREA KESELURUHAN
= 1.600 M2
VOLUME KESELURUHAN
= 4.050 M2
= 90 M2
90 M2 X 2,5 = 225 M3/RUANG
= 3 JAM
90 M2 X 2
= 180
90 M2 X 0,5 = 45
POURINGS TIMELINE
ESTIMASI
CYCLE
TRUK
MIXER
KEBUTUH
AN TRUK
MIXER
. CONCRETE PUMP :
1. TYPE STATION 4 UNIT, @ KAPASITAS 22,5 M3/JAM (KONDISI STANDAR)
2. TYPE MOBILE 1 UNIT SUPER LONG BOOM, KAPASITAS 22,5 M3/JAM
(KONDISI STANDAR)
3. TOTAL KEBUTUHAN PIPA : 624 M1 : 2 M = 312 BATANG
. INITIAL SETTING TIME BETON UNTUK FC 35, FLY ASH 15% :
1. ADHIMIX : 3 JAM
2. SCG/JAYAMIX : 3,5 JAM
DELIVERY to SITE
DELIVER
30 menit
MANUVER
POSITIONING
UNLOADING
TURN BACK
RETURN
RETURN
35 menit
LOADING
ON SITE
40 menit
CONCRETE CURING
SETELAH PENGECORAN SELESAI LAPISAN ATAS CONCRETE YANG SUDAH DI FINISH SEGERA
DITUTUP DENGAN PLASTIC SHEET DIMANA DI SETIAP SAMBUNGAN DITUTUP PLASTER/SEAL TAPE
DIATAS PLASTIC SHEET DITUTUP DENGAN 1 LAPIS STYROFOAM (TEBAL = 5 CM)
SELAMA 7 HARI PERBEDAAN TEMPERATURE ATAS MASS CONCRETE DENGAN SUHU LUAR SEKITAR
+/- 20 DERAJAT CELCIUS AKAN DIMONITOR
SETELAH KURANG LEBIH 2 HARI, PLASTIC SHEET DAN STYROFOAM DILEPAS (ATAU SESUAI
DENGAN HASIL YANG DIDAPAT DARI MONITORING SUHU BETON)