Master Plan Pembangunan Ketenagalistrikan 2010 S.D. 2014
Master Plan Pembangunan Ketenagalistrikan 2010 S.D. 2014
REPUBLIK INDONESIA
MASTER PLAN
PEMBANGUNAN KETENAGALISTRIKAN
2010 s.d. 2014
SAMBUTAN
ttd
PENGERTIAN
1.
2.
ii
SINGKATAN
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
PLTU
PLTG
PLTGU
PLTP
PLTA
PLTM
PLTS
PLTMH
PLTD
PLTMG
GI
GIS
GWh
IBT
LB
MVA
MW
kms
HSD
MFO
COD
P3B
iii
DAFTAR ISI
Halaman
Sambutan .................................................................................................................. i
Pengertian ................................................................................................................. ii
Singkatan .................................................................................................................. iii
Daftar Isi .................................................................................................................... iv
BAB I
PENDAHULUAN ......................................................................................... 1
1.1
1.2
2.2
2.3
2.4
2.5
2.6
3.2
3.3
3.4
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
4.21
4.22
4.23
4.24
4.25
4.26
4.27
4.28
4.29
4.30
4.31
4.32
4.33
BAB I
PENDAHULUAN
ketenagalistrikan
dan
kelestarian
fungsi
BAB II
KEBIJAKAN SEKTOR KETENAGALISTRIKAN NASIONAL
ada badan usaha milik daerah, badan usaha swasta, atau koperasi yang dapat
menyediakan tenaga listrik di wilayah tersebut, Pemerintah wajib menugasi
badan usaha milik negara untuk menyediakan tenaga listrik.
2.1.2 Tarif
Kebijakan Pemerintah tentang tarif dasar listrik adalah bahwa tarif listrik
secara bertahap dan terencana diarahkan untuk mencapai nilai
keekonomiannya sehingga tarif listrik rata-rata dapat menutup biaya yang
dikeluarkan. Kebijakan ini diharapkan akan dapat memberikan signal positif
bagi investor dalam berinvestasi di sektor ketenagalistrikan.
Penetapan kebijakan tarif dilakukan sesuai nilai keekonomian. Namun
demikian tarif tenaga listrik untuk konsumen ditetapkan dengan
memperhatikan keseimbangan kepentingan nasional, daerah konsumen, dan
pelaku usaha penyediaan tenaga listrik. Khusus untuk pelanggan kurang
mampu juga mempertimbangkan kemampuan bayar pelanggan. Kebijakan
subsidi untuk tarif listrik masih diberlakukan, namun mengingat kemampuan
Pemerintah yang terbatas, maka subsidi akan lebih diarahkan langsung
kepada kelompok pelanggan kurang mampu dan atau untuk pembangunan
daerah perdesaan dan pembangunan daerah-daerah terpencil dengan
mempertimbangkan
atau
memprioritaskan
perdesaan/daerah
dan
masyarakat yang sudah layak untuk mendapatkan listrik dalam rangka
menggerakkan ekonomi masyarakat.
Kebijakan tarif listrik yang tidak seragam (non-uniform tariff) dimungkinkan
untuk diberlakukan di masa mendatang, hal ini berkaitan dengan perbedaan
perkembangan pembangunan ketenagalistrikan dari satu wilayah dengan
wilayah lainnya.
lingkungan serta harus memenuhi baku mutu yang dikeluarkan oleh instansi yang
berwenang.
Untuk itu semua kegiatan ketenagalistrikan yang berpotensi menimbulkan dampak
besar dan penting wajib melakukan AMDAL (ANDAL, RKL dan RPL) sedangkan
yang tidak mempunyai dampak penting diwajibkan membuat Upaya Pengelolaan
Lingkungan (UKL) dan Upaya Pemantauan Lingkungan (UPL) sesuai dengan
ketentuan peraturan perundang-undangan.
BAB III
TINJAUAN KONDISI TENAGA LISTRIK NASIONAL
29,562
30,527
2007
2008
28,422
25,047
26,091
MW
20,000
15,000
10,000
5,000
0
2004
2005
2006
PPU
523
523
526
493
916
IPP
3,222
3,222
3,222
3,984
4,159
PLN
21,302
22,346
24,675
25,084
25,451
Pulau
Kapasitas
Terpasang (MW)
1.
Sumatera
2.
Jawa-Madura-Bali
3.
Kalimantan
1.178
4.
Sulawesi
1.195
5.
Nusa Tenggara
265
6.
Maluku
182
7.
Papua
168
Indonesia
4.941
22.599
30.527
Pulau
1.
Sumatera
2.
Jawa-Madura-Bali
3.
SUTET
SUTT
Total
(kms)
(kms)
(kms)
782
8.906
9.689
5.092
15.501
20.593
Kalimantan
1.429
1.429
4.
Sulawesi
2.474
2.462
5.
Nusa Tenggara
6.
Maluku
7.
Papua
5.874
28.310
34.184
Indonesia
Panjang (kms)
500,000
400,000
300,000
200,000
100,000
0
2004
2005
2006
2007
2008
Transmisi
30,534
30,686
32,905
33,151
34,184
Distribusi
607,755
563,838
573,049
598,498
614,925
Pulau
1.
Sumatera
2.
Jawa-Madura-Bali
3.
JTM
JTR
Total
(kms)
(kms)
(kms)
72.131
77.431
149.562
128.364
217.912
346.276
Kalimantan
23.695
21.441
45.136
4.
Sulawesi
23.017
23.795
46.812
5.
Nusa Tenggara
7.473
7.315
14.788
6.
Maluku
4.484
2.337
6.821
7.
Papua
1.999
3.531
5.530
261.163
353.762
614.925
Indonesia
11
LAOS
Manila
Bangkok
CAMBODIA
Philipines
Ban
Mabtapud
Phnom
Penh
: Pembangkit Listrik
Laut
VIETNAM
TOTAL
KAPASITAS PEMBANGKIT : 30.527
30.527 MW
PANJANG JARINGAN:
- 500 KV :
5.092 kms
- 275 KV :
782 kms
- 150 KV : 23.
23.679 kms
- 70 KV :
4.619 kms
- JTM
: 261
261..163 kms
- JTR
: 353
353..762 kms
China
Ho Chi
Minh City
Selatan
Erawan
Khanon
Songkhla
Bangkot
Lawit
Jerneh
Guntong
Banda Aceh
Penang
Lhokseumawe
Medan
West
Natuna
Alph
Natuna
a
Kuala
Port Klang
Lumpur
Port
Duri
Kota
Kinibalu
BRUNEI
Bandara Seri
Begawan
Bintulu
MALAYSIA
TIMUR
Dickson
Dumai
Manado
SINGAPORE
Kuching
Batam Bintan
Maluku :
Pembangkit: 182 MW
JTM : 4.484 kms
Ternate
JTR : 2.337
kms
HALMAHERA
Samudra Pasifik
Bontang
Sorong
Sumatera :Padang
Kalimantan :
Pembangkit: 4.941 MW
Jambi
Pembangkit: 1.178 MW
275 kV: 782 kms
150 kV: 1.305 kms
Grissi
Palembang
150 kV: 8.572 kms
k
70 kV: 123 kms
70 kV: 334 kms
JTM : 23.695 kms
JTM : 72.131 kms
JTR : 21.441 kms
JTR : 77.431 kms
Samarinda
Jayapura
Balikpapan
Sulawesi :
Ambon
Pembangkit: 1.195 MW
SERAM
150 kV: 1.957 kmsBURU
70 kV: 505 kms
JTM : 23.017 kms
I N D O N E S I A Ujung
Pandang
Jamali :
JTR : 23.795 kms
MADURA
Semarang
Jakarta
Pembangkit: 22.599 MW
Bangkalan Nusa Tenggara:
Surabaya
500 kV: 5.092 kms
BALI
Pembangkit:
MW
SUMBAW 265FLORES
MataramA
150 kV: 11.844 kms
Denpasar JTM
: Bima
7.473 kms
LOMBOK
TIMOR
70 kV: 3.657 kms
Samudra JTR : 7.315 kms
LESTE
SUMBA
JTM : 128.364 kms
Hindia
JTR : 217.912 kms
Banjarmasin
Papua :
Pembangkit: 168 MW
JTM : 1.999 kms
JTR : 3.531 kms
Merauke
AUSTRALIA
12
Tabel 3.4.
Rasio Elektrifikasi
No.
Pulau
Persen (%)
1.
Sumatera
60,6
2.
Jawa-Madura-Bali
72,0
3.
Kalimantan
57,6
4.
Sulawesi
55,3
5.
Nusa Tenggara
28,6
6.
Maluku
52,4
7.
Papua
32,3
Indonesia
65,1
13
15
16
BAB IV
RENCANA PEMBANGUNAN KETENAGALISTRIKAN
SISTEM INTERKONEKSI
SUMBAGUT
Kapasitas terpasang : 1.724,60 MW
Daya mampu
: 1.169,40 MW
Beban puncak
: 1.270,70 MW
Defisit
:
-101,30 MW
SISTEM SABANG
Kapasitas terpasang : 5,40 MW
Daya mampu
: 3,10 MW
Beban puncak
: 3,60 MW
Defisit
: -0,50 MW
SISTEM TAKENGON
Kapasitas terpasang : 10,30 MW
Daya mampu
: 9,80 MW
Beban puncak
: 17,40 MW
Defisit
: -7,60 MW
SISTEM MEOULABOH
Kapasitas terpasang : 28,20 MW
Daya mampu
: 13,95 MW
Beban puncak
: 22,16 MW
Defisit
: -8,21 MW
SISTEM BLANGKEJEREN
Kapasitas terpasang : 4,95 MW
Daya mampu
: 3,50 MW
Beban puncak
: 3,70 MW
Defisit
: -0,20 MW
SISTEM BLANGPIDIE
Kapasitas terpasang : 13,71 MW
Daya mampu
: 9,42 MW
Beban puncak
: 7,50 MW
Surplus
: 1,92 MW
SISTEM TAPAKTUAN
Kapasitas terpasang : 7,07 MW
Daya mampu
: 5,40 MW
Beban puncak
: 5,00 MW
Surplus
: 0,40 MW
SISTEM KUTACANE
Kapasitas terpasang : 8,30 MW
Daya mampu
: 7,90 MW
Beban puncak
: 9,90 MW
Defisit
: -2,00 MW
SISTEM SINABANG
Kapasitas terpasang : 6,06 MW
Daya mampu
: 2,40 MW
Beban puncak
: 3,00 MW
Defisit
: -0,60 MW
SISTEM SUBULUSSALAM
Kapasitas terpasang : 7,10 MW
Daya mampu
: 6,70 MW
Beban puncak
: 11,98 MW
Defisit
: -5,28 MW
4
17
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
o
o
o
o
Tabel 4.2
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Nanggroe Aceh Darussalam
Rencana
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTU
PLTM
PLTU
PLTA
PLTM
PLTP
PLTP
PLTU
Pendek
4
2
2
2
2
2
2
15
Jangka
Menengah/Panjang
Progress
MW
MW
MW
MW
MW
MW
MW
MW
2 x
1 x
1 x
2 x
31,0 MW
409
1
110
86
1
7
55
4
MW
MW
MW
MW
MW
MW
MW
18%
COD
Keterangan
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2013
2013
2013
2014
2014
PLN
PLN
PLN
PLN
PLN
PLN
PLN
IPP
PLN
Perpres 71
PLN
PLN
IPP
IPP
IPP
378 MW
MW
Tabel 4.3
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Nanggroe Aceh Darussalam
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
DARI
Panton Labu
Takengon
PLTA Peusangan 1
PLTA Peusangan 2
Sidikalang
Meulaboh
PLTU Meulaboh
Meulaboh
Brastagi
Jantho
Blang Pidie
Cot Trueng
Takengon
PLTP Seulawah Agam
Banda Aceh
KE
Incomer (Idi -Lhok Seumawe)
PLTA Peusangan 1
PLTA Peusangan 2
Bireun
Subulussalam
Sigli
Meulaboh
Blang Pidie
Kuta Cane
Incomer (Sigli -Banda Aceh)
Tapak Tuan
Incomer ( Bireun - Lhokseumawe)
PLTA Peusangan 1
Incomer (Sigli - Banda Aceh)
Krueng Raya
JUMLAH
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
1
22
14
114
130
333
60
190
200
1
130
6
22
16
90
1.329
PROGRESS
(%)
5
6
10
25,05
COD
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2012
2012
2014
2014
19
Tabel 4.4
Rencana Pengembangan Gardu Induk Provinsi Nanggroe Aceh Darussalam
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
LOKASI
Banda Aceh
Takengon
Subulussalam
Panton Labu
Bireun Ext LB
Peusangan 1
Peusangan 2
Meulaboh
PLTU Meulaboh
Sigli Ext LB
Kuta Cane
Brastagi Ext LB
Jantho
Blang Pidie
Meulaboh Ext LB
Tapak Tuan
Cot Trueng
PLTP Seulawah
Krueng Raya
Banda Aceh Ext LB
Takengon
Meulaboh
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah
NEW/EXTENSION
Extension
New
New
New
Extension
Extension
Extension
New
New
Extension
New
Extension
New
New
Extension
New
New
Extension
New
Extension
Extension
Extension
KAPASITAS
(MVA)
60
30
30
30
2 LB
4 LB
4 LB
PROGRESS
(%)
COD
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2010
2012
2012
2014
2014
2014
2014
30
2 LB
2 LB
30
2 LB
30
30
2 LB
30
30
4 LB
30
1 LB
30
30
420
Tabel 4.5
Program Listrik Perdesaan Provinsi Nanggroe Aceh Darussalam
KEGIATAN
2010
2011
2012
2013
2014
1.700
7.000
7.100
7.125
7.175
PLTMH (kW)
140
140
200
230
80
80
80
80
PLTS 50 Wp Tersebar
PLTS Terpusat 15 kW
220/10.750
220/11.250
220/11.250
230/11.750
255/13.000
600
600
610
690
750
550
550
600
670
700
1/ 250
4/1.000
3/750
1/250
PLTD (Unit/kW)
20
Tabel 4.6
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Nanggroe Aceh Darussalam
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
409
1.329
420
655,1
218,4
62,8
30.100
4
710
320
1.125
58.000
3.120
3.200
9
2.250
16,1
1,6
3,9
1,9
9,9
56,7
27,8
1,3
1.055,5
21
Gambar 4.2
Kondisi Kelistrikan Provinsi Sumatera Utara
SISTEM INTERKONEKSI
SUMBAGUT
Kapasitas terpasang : 1.724,60 MW
Daya mampu
: 1.169,40 MW
Beban puncak
: 1.270,70 MW
Defisit
:
-101,30 MW
SISTEM NIAS
Kapasitas terpasang : 12,18 MW
Daya mampu
:
4,50 MW
Beban puncak
:
9,30 MW
Defisit
: -4,80 MW
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
22
Pendek
2 x
2 x
2 x
5
3
139
90
2,1
2,3
5
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
MW
80%
2 x
2 x
2
1
2
2
1
1
1
1
340,8 MW
1.986
Progress
x
x
x
x
x
x
x
x
220
5
5
7,5
100
87
200
110
7
200
110
110
55
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
40%
20%
COD
Keterangan
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2012
2013
2013
2013
2013
2014
2014
2014
2014
PLN
PLN
PLN
IPP
IPP
IPP
IPP
Perpres 71
IPP
IPP
IPP
PLN
PLN
PLN
IPP
IPP
PLN
IPP
IPP
IPP
1.646 MW
MW
23
Tabel 4.9
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sumatera Utara
NO.
DARI
1
2
3
4
5
6
Padang Sidempuan
PLTP Sarulla
PLTA Asahan 1
Simangkok
Galang
Binjai
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Dolok Sanggul
Tanjung Marowa
Galang
Galang
P. Sidempuan
Lima Puluh
Kuala Namu
Porsea
PLTU Kuala Tanjung
PLTA Asahan III
PLTP Sorik Merapi
Tanjung Pura
KIM
KIM
KIM 2
PLTU Sumut Infrastucture
KE
PLTP Sarulla
Simangkok
Simangkok
Galang
Binjai
PLTU Pangkalan Susu
JUMLAH 275 kV
Incomer ( Tele - Tarutung)
Kuala Namu
Namurambe
Tanj. Marowa
Panyabungan
Incomer (K.Tanjung -Kisaran)
Incomer (Sei Rotan - Perbaungan)
Simangkok
Kuala Tanjung
Simangkok
Panyabungan
Incomer (Binjai - P.Brandan)
KIM 2
Medan Pancing
Medan Selayang
Lamhotma
JUMLAH 150 kV
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
COD
275
275
275
275
275
275
138
194
16
318
160
160
986
14
34
80
20
140
40
30
10
6
22
46
30
2
20
30
20
544
46,91
43,50
79,07
46,98
40,46
46,55
2010
2010
2010
2010
2010
2010
10
12,60
10,83
12,5
10
2009
2009
2010
2010
2010
2010
2010
2010
2012
2012
2014
2012
2012
2012
2012
2012
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
34,443
Tabel 4.10
Rencana Pengembangan Gardu Induk Provinsi Sumatera Utara
NO.
LOKASI
1
2
3
4
5
6
Simangkuk
Asahan 1
Padang Sidempuan
Galang
Sarulla
Binjai
7
8
9
10
11
12
13
Paya Geli
Kisaran
Labuhan
Gunung Para
KIM
Tele
Lamhotma
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Aek Kanopan
Gunung Tua
Dolok Sanggul
Kuala namu
Tanjung Marowa
Sidikalang Ext LB
Denai
Denai
Namurambe
Namurambe
Mabar
Tebing Tinggi
Sidikalang
Sibolga
Penyabungan
RASIO TRAFO
(kV)
275/150
275/18
275/150
275/150
275/150
275/150
Jumlah 275/150 kV
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
NEW/EXTENSION
New
Kit / New
IBT / New
IBT / New
IBT / New
IBT / New
KAPASITAS
(MVA)
Extension
Extension
Extension
Extension
Extension
Extension
Extension
500
1000
500
1000
3.000
60
30
60
30
60
20
10
Extension
Extension
New
New
Extension
Extension
Extension
Extension
Extension
Extension
Extension
Extension
Extension
Extension
New
30
30
30
60
2 LB
2 LB
60
2 LB
60
2 LB
60
60
30
60
30
PROGRESS
(%)
20,137
COD
2010
2010
2010
2010
2010
2010
2009
2009
2009
2009
2009
2009
2009
20
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2010
24
NO.
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
Pembangkit
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
LOKASI
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
P. Sidempuan Ext LB
Lima Puluh
Namurambe
Tanjung Marowa
Galang
Pematang Siantar
P. Sidempuan
Tanjung Marowa
Kuala namu
Kuala Tanjung
PLTU Kuala Tanjung
PLTA Asahan III
GIS Listrik
Rantau Prapat
Tanjung Pura
KIM 2
Medan Pancing
Lamhotma
Medan Selayang
KIM
Sicanang
Lima Puluh
Medan Pancing
Medan Selayang
Kisaran
54
55
Porsea
Binjai
150/20
150/20
Jumlah 150/20 kV
NEW/EXTENSION
Extension
New
Extension
Extension
New
Extension
Extension
Extension
Extension
Extension
New
New
Extension
Extension
New
New
New
Extension
New
Extension
Extension
Extension
Extension
Extension
Extension
Extension
Extension
KAPASITAS
(MVA)
2 LB
30
2 LB
2 LB
4 LB
60
60
60
60
2 LB
2 LB
2 LB
60
20
30
120
30
3 LB
30
6 LB
30
30
60
60
60
PROGRESS
(%)
30
60
1.670
0,466
17,5
20
COD
2010
2010
2010
2010
2010
2011
2011
2011
2011
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2014
2014
2014
Tabel 4.11
Program Listrik Perdesaan Provinsi Sumatera Utara
KEGIATAN
2010
2011
2012
2013
2014
1.550
7.500
7.550
7.525
7.575
300
300
350
350
80
80
80
80
260/13.250
260/13.250
280/14.250
290/14.750
310/15.750
650
650
700
770
840
600
600
610
650
650
PLTS 50 Wp Tersebar
PLTS Terpusat 15 kW
PLTMH (kW)
60
25
Tabel 4.12
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Sumatera Utara
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
1.986
1.530
4.670
31.700
4
1.360
320
1.400
71.250
3.610
3.110
-
2.988,2
187,5
189,3
22,2
1,6
7,4
1,9
12,2
74,1
39,6
3.524,1
26
Gambar 4.3
Kondisi Kelistrikan Provinsi Sumatera Barat
SISTEM INTERKONEKSI
SUMBAGSEL
Kapasitas terpasang : 2.529,70 MW
Daya mampu
: 1.597,70 MW
Beban puncak
: 1.704,70 MW
Defisit
:
-107,00 MW
SISTEM MENTAWAI
Kapasitas terpasang : 3,19 MW
Daya mampu
: 2,05 MW
Beban puncak
: 0,95 MW
Surplus
: 1,10 MW
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
27
Pendek
5
6
Jangka
Menengah/Panjang
Progress
MW
MW
2 x
2 x
11,0 MW
507
1,1
1,5
3
6
1,4
0,6
1,4
4
10
2
8
112
10
2,5
110
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
7%
COD
Keterangan
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2014
PLN
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
Perpres 71
IPP
IPP
IPP
496 MW
MW
28
Tabel 4.15
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sumatera Barat
NO.
DARI
1
2
Kiliranjao
Padang Sidempuan
3
4
5
6
7
8
9
10
11
Maninjau
Padang Luar
Bangko
PLTU Sumbar Pesel
Bungus
Pariaman
Kiliranjao
PLTP Kerinci
PLTP Muara Labuh
KE
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
COD
275
275
266
600
866
42
32
246
50
180
4
52
20
14
640
5
7,5
2010
2010
Payakumbuh
Payakumbuh
JUMLAH 275 kV
Padang Luar
Payakumbuh
Sungai Penuh
Bungus
Kambang
Incomer (L.Alung - Maninjau)
Teluk Kuantan
Incomer (Bangko - Sungai Penuh)
Kambang
JUMLAH 150 kV
150
150
150
150
150
150
150
150
150
46
2010
2010
2010
2010
2011
2011
2011
2011
2014
Tabel 4.16
Rencana Pengembangan Gardu Induk
Provinsi Sumatera Barat
NO.
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
PROGRESS
(%)
COD
1
2
Kiliranjao
Payakumbuh
275/150
275/150
Jumlah 275/150 kV
IBT / New
IBT / New
250
500
750
2009
2010
Padang Luar
150/20
Extension
60
2009
Padang Panjang
150/20
Extension
30
2009
Salak
150/20
Extension
2009
Maninjau
150/20
Extension
20
1 LB
7
8
9
10
11
12
13
14
15
16
Padang Luar
Payakumbuh
Bungus
PLTU Sumbar Pesel
Sungai Penuh
Simpang Empat
Maninjau
Pariaman
Sungai Penuh
PLTP Sungai Penuh
150/20
150/20
150/20
Pembangkit
150/20
150/20
150/20
150/20
150/20
Pembangkit
Extension
Extension
Extension
New
New
Extension
Extension
Extension
Extension
New
2 LB
1 LB
2 LB
2 LB
30
60
30
2 LB
2 LB
2 LB
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
17
18
19
20
21
22
Kambang
Bungus Ext LB
Kiliranjao Ext LB
PLTP Kerinci
Payakumbuh
Simpang Haru
150/20
150/20
150/20
Pembangkit
150/20
150/20
Jumlah 150/20 kV
New
Extension
Extension
New
Extension
Extension
30
2 LB
1 LB
4 LB
30
30
320
2010
20
100
100
100
2011
2011
2011
2011
2012
2013
29
Tabel 4.17
Program Listrik Perdesaan Provinsi Sumatera Barat
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
2.600
7.600
7.500
7.550
7.600
90
450
500
500
500
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi (Unit/kVA)
250/12.500
250/12.500
250/13.000
250/13.500
250/14.500
700
700
730
800
850
650
650
700
750
800
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
507
1.506
1.070
940,1
158,2
64,2
32.850
4
2.040
1.320
66.000
3.780
3.550
-
23,0
1,6
13,2
12,6
77,5
37,1
1.327,5
30
SISTEM BENGKALIS
Kapasitas terpasang : 16,46 MW
Daya mampu
: 8,16 MW
Beban puncak
: 8,60 MW
Defisit
: -0,44 MW
SISTEM INTERKONEKSI
SUMBAGSEL
Kapasitas terpasang : 2.529,70 MW
Daya mampu
: 1.597,70 MW
Beban puncak
: 1.704,70 MW
Defisit
:
-107,00 MW
SISTEM TEMBILAHAN
Kapasitas terpasang : 10,28 MW
Daya mampu
: 5,85 MW
Beban puncak
: 7,50 MW
Defisit
: -1,65 MW
31
SISTEM BAGANSIAPIAPI
Kapasitas terpasang : 9,70 MW
Daya mampu
: 5,00 MW
Beban puncak
: 6,15 MW
Defisit
: -1,15 MW
SISTEM Pkl.
Pkl. KERINCI
Kapasitas terpasang : 3,47 MW
Daya mampu
: 1,84 MW
Beban puncak
: 2,01 MW
Defisit
: -0,17 MW
SISTEM Psr.
Psr. PENGARAIAN
Kapasitas terpasang : 0,50 MW
Daya mampu
: 0,45 MW
Beban puncak
: 0,36 MW
Surplus
: 0,09 MW
SISTEM SEBERIDA
Kapasitas terpasang : 3,22 MW
Daya mampu
: 1,38 MW
Beban puncak
: 1,84 MW
Defisit
: -0,46 MW
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
32
Pendek
5
5
6
Jangka
Menengah/Panjang
Progress
MW
MW
MW
2
2
2
1
2
1
16,0 MW
283
x
x
x
x
x
x
10
7
7
100
7
100
5
MW
MW
MW
MW
MW
MW
MW
1%
1%
COD
Keterangan
2010
2010
2010
2011
2011
2011
2012
2012
2013
2014
PLN
PLN
PLN
Perpres 71
Perpres 71
IPP
PLN
IPP
PLN
PLN
267 MW
MW
33
Tabel 4.21
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Riau
NO.
DARI
1
2
Garuda Sakti
Rengat
3
4
5
6
7
8
9
10
11
12
Garuda Sakti
Bangkinang
Garuda Sakti
Dumai
Teluk Kuantan
Dumai
Kulim/Pasir Putih
Kulim/Pasir Putih
Rengat
Pangkalan Kerinci
KE
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
275
275
300
440
740
70
220
40
56
194
134
70
134
220
134
1.272
2,5
Payakumbuh
Garuda Sakti
JUMLAH 275 kV
Kulim/Pasir Putih
Pasir Pangaraian
New Garuda Sakti
KID Dumai/New Dumai
Rengat
Bagan Siapi-api
Perawang
Pangkalan Kerinci
Tembilahan
Rengat
JUMLAH 150 kV
150
150
150
150
150
150
150
150
150
150
COD
2010
2014
2009
2010
2010
2010
2011
2012
2012
2012
2012
2012
Tabel 4.22
Rencana Pengembangan Gardu Induk Provinsi Riau
NO.
LOKASI
1
2
Garuda Sakti
Rengat
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Kulim
Garuda Sakti Ext LB
Kandis
Kulim
Pasir Pangarayan
Bangkinang Ext LB
New Garuda Sakti
Garuda Sakti Ext LB
KID Dumai
Dumai Ext LB
Rengat
Teluk Kuantan Ext LB
Dumai
Bagan Batu
Perawang
Kulim Ext LB
19
20
21
22
23
24
25
26
27
28
Pangkalan Kerinci
Pangkalan Kerinci Ext LB
Tembilahan
Rengat Ext LB
Bagan Siapi-api
Dumai Ext LB
Bangkinang
Duri
Kulim
New Garuda Sakti
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
PROGRESS
(%)
COD
275/150
275/150
Jumlah 275/150 kV
IBT / New
IBT / New
500
250
750
2010
2014
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
New
Extension
New
Extension
New
Extension
New
Extension
New
Extension
New
Extension
Extension
Extension
New
Extension
30
2 LB
10
30
30
2 LB
60
2 LB
30
2 LB
30
3 LB
60
20
30
4 LB
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2011
2011
2012
2012
2012
2012
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
New
Extension
New
Extension
New
Extension
Extension
Extension
Extension
Extension
30
2 LB
30
2 LB
30
2 LB
30
60
60
60
630
2012
2012
2012
2012
2012
2012
2013
2013
2013
2014
34
Tabel 4.23
Program Listrik Perdesaan Provinsi Riau
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.500
6.250
6.275
6.300
6.325
100
100
100
100
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi (Unit/kVA)
320/20.750
320/20.750
340/22.750
360/24.750
380/26.750
800
800
820
940
1,000
820
820
900
920
1,030
*)
9/3.500
10/3.750
10/3.750
7/2.000
4/1.000
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Cat: jaringan termasuk Prov. Kepri
Volume
283
2.012
1.380
426,6
305,5
125,2
26.650
8
400
320
1.720
115.750
4.360
4.490
40
14.000
18,7
3,2
2,2
1,9
17,9
111,9
48,8
5,8
1.067,7
SISTEM RANAI
Kapasitas terpasang : 4,57 MW
Daya mampu
: 2,95 MW
Beban puncak
: 2,77 MW
Surplus
: 0,18 MW
SISTEM Tj.
Tj. UBAN
Kapasitas terpasang : 5,46 MW
Daya mampu
: 4,35 MW
Beban puncak
: 4,05 MW
Surplus
: 0,30 MW
SISTEM BATAM
Kapasitas terpasang : 365,93 MW
Daya mampu
: 235,00 MW
Beban puncak
: 202,10 MW
Surplus
: 32,90 MW
SISTEM Tj.
Tj. BALAI KARIMUN
Kapasitas terpasang : 17,18 MW
Daya mampu
: 11,50 MW
Beban puncak
: 16,70 MW
Defisit
: -5,20 MW
SISTEM Tj.
Tj. BATU
Kapasitas terpasang : 5,46 MW
Daya mampu
: 2,91 MW
Beban puncak
: 4,40 MW
Defisit
: -1,49 MW
SISTEM Tj.
Tj. PINANG
Kapasitas terpasang : 45,76 MW
Daya mampu
: 31,30 MW
Beban puncak
: 35,80 MW
Defisit
: -4,50 MW
SISTEM DABO SINGKEP/
DAEK LINGGA
Kapasitas terpasang : 3,75 MW
Daya mampu
: 2,25 MW
Beban puncak
: 2,09 MW
44MW
Surplus
: 0,16
sistem belum dapat memenuhi beban puncak yang ada sehingga mengalami
defisit sebesar 460 MW. Adapun pada tahun-tahun selanjutnya kondisi
Sistem Sumatera berada pada kondisi baik.
Tabel 4.25
Neraca Daya Sistem Sumatera
URAIAN
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
37
Tabel 4.26
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Kepulauan Riau
Rencana
Pendek
PLTD
PLTD
PLTD
PLTD
PLTD
PLTU
PLTU
PLTU
PLTU
PLTD
PLTU
PLTU
Batam:
PLTGU
PLTGU
PLTGU
PLTMG
PLTGU
PLTGU
PLTU
Panaran 2
Panaran 1
Tj. Uncang
Tj. Uncang
Tj. Uncang
Tj. Uncang
Tj. Kasam
5
5
5
6
3
30
7
2 x
Progress
MW
MW
MW
MW
MW
MW
MW
Keterangan
PLN
PLN
PLN
PLN
PLN
PLN
Perpres 71
IPP
IPP
PLN
IPP
IPP
IPP
IPP
PLN Batam
PLN Batam
IPP
PLN Batam
IPP
2 x
2 x
4
6
6
15
10
MW
MW
MW
MW
MW
1
2
2
1
2
20
40
5,5
54
40
55
MW
MW
MW
MW
MW
MW
2010
2011
2011
2011
2012
2013
2014
74%
MW
90,0 MW
495
COD
2010
2010
2010
2010
2010
2010
2010
2012
2012
2014
2014
2014
2 x
2 x
22
JUMLAH
Total
Jangka
Menengah/Panjang
x
x
x
x
x
405 MW
MW
Tabel 4.27
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Kepulauan Riau
NO.
1
2
3
4
5
DARI
Tanjung Kasam
Tanjung Sauh
Pulau Ngenang
Tanjung Taluk
Sribintan
KE
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
6
10
12
60
70
158
Tanjung Sauh
Pulau Ngenang
Tanjung Taluk
Sribintan
Air Raja
JUMLAH
PROGRESS
(%)
COD
2010
2010
2010
2010
2010
Tabel 4.28
Rencana Pengembangan Gardu Induk Provinsi Kepulauan Riau
NO.
1
2
1
2
3
6
7
8
9
10
11
12
13
LOKASI
Muka Kuning
Nongsa
Tanjung Taluk/Lobam
Sribintan
Air Raja
Tanjung Uncang
Sei Baloi
Sei Baloi
Batu Besar
Sei Harapan
Tanjung Kasam
Tanjung Sengkuang
Rempang
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah
NEW/EXTENSION
New
New
New
New
New
New
New
New
New
New
New
New
New
KAPASITAS
(MVA)
30
30
30
30
30
60
60
60
30
60
60
60
30
570
PROGRESS
(%)
COD
2009
2010
2010
2010
2010
2011
2012
2013
2012
2012
2012
2013
2014
38
Tabel 4.29
Program Listrik Perdesaan Provinsi Kepulauan Riau
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.750
6.250
6.275
6.300
6.325
PLTS Terpusat 15 kW
80
80
80
80
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
495
158
570
655,5
20,2
30,3
25.150
8
-
17,6
3,2
-
726,7
SISTEM MUKOMUKO-MUKO
Kapasitas terpasang : 3,12 MW
Daya mampu
: 2,10 MW
Beban puncak
: 1,02 MW
Surplus
: 1,08 MW
SISTEM INTERKONEKSI
SUMBAGSEL
Kapasitas terpasang : 2.529,70 MW
Daya mampu
: 1.597,70 MW
Beban puncak
: 1.704,70 MW
Defisit
:
-107,00 MW
SISTEM MANNA
Kapasitas terpasang : 5,83 MW
Daya mampu
: 1,70 MW
Beban puncak
: 1,96 MW
Defisit
: -0,26 MW
40
Tabel 4.31
Neraca Daya Sistem Sumatera
URAIAN
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
Pendek
Jangka
Menengah/Panjang
Manna
Lebong
Hululais
Hululais
Simpang Aur
Simpang Aur
JUMLAH
Total
2
4
1
1
2
2
- MW
156
x
x
x
x
x
x
2
3
55
55
6
9
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
2011
2011
2013
2014
2014
2014
IPP
IPP
PLN
PLN
IPP
IPP
156 MW
MW
41
Tabel 4.33
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Bengkulu
NO.
1
2
3
4
5
6
DARI
KE
Pagar Alam
Kambang
Pekalongan/Curup
PLTP Hulu Lais
PLTA Simpang Aur 1
PLTA Simpang Aur 2
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
150
48
123
45
120
12
12
360
Manna
Mukomuko
Pulo Baai
Pekalongan
Musi
PLTA Simpang Aur 1
JUMLAH
PROGRESS
(%)
COD
2009
2010
2010
2013
2014
2014
Tabel 4.34
Rencana Pengembangan Gardu Induk Provinsi Bengkulu
NO.
1
2
3
4
5
6
7
8
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
Extension
New
New
New
Extension
Extension
New
Extension
60
30
30
30
2 LB
2 LB
2 LB
60
Simpang Tiga
Manna
Mukomuko
Pulo Baai
Pekalongan Ext LB
Pekalongan
PLTP Hulu Lais
Simpang Tiga
Jumlah
PROGRESS
(%)
15
COD
2009
2009
2010
2010
2010
2011
2012
2014
210
Tabel 4.35
Program Listrik Perdesaan Provinsi Bengkulu
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.000
12.500
12.550
12.600
12.625
250
250
250
250
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi (Unit/kVA)
100
360/16.750
380/17.750
360/16.750
1.300
1.300
1.320
400/18.750
1.400
420/19.750
1.500
950
950
1.150
1.320
1.400
42
Tabel 4.36
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Bengkulu
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
156
360
210
248,4
99,8
21,8
53.275
8
1.100
1.920
89.750
6.820
5.770
-
37,3
3,2
5,8
19,8
138,0
44,3
618,5
43
Gambar 4.7
Kondisi Kelistrikan Provinsi Jambi
SISTEM INTERKONEKSI
SUMBAGSEL
Kapasitas terpasang : 2.529,70 MW
Daya mampu
: 1.597,70 MW
Beban puncak
: 1.704,70 MW
Defisit
:
-107,00 MW
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
44
Pendek
Sarolangun
Sungai Penuh
Sungai Penuh
2 x
Jangka
Menengah/Panjang
MW
1 x
1 x
JUMLAH
Total
14,0 MW
124
55
55
Progress
COD
Keterangan
10,00%
Des 2009
2013
2014
IPP
PLN
PLN
MW
MW
110 MW
MW
Tabel 4.39
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Jambi
NO.
DARI
KE
TEGANGAN
(kV)
PANJANG
(kms)
380
420
800
65
380
20
465
1
2
Betung
Aur Duri
Aur Duri
Rengat
275
275
3
4
5
Sarolangun
Betung
PLTP Sungai Penuh
JUMLAH 275 kV
Bangko
Aur Duri
Sungai Penuh
JUMLAH 150 kV
150
150
150
PROGRESS
(%)
COD
2014
2014
66
2010
2011
2011
45
Tabel 4.40
Rencana Pengembangan Gardu Induk Provinsi Jambi
NO.
RASIO TRAFO
(kV)
LOKASI
1
2
3
Bangko
Muara Bungo
Aur Duri
Aur Duri
5
6
7
8
9
Sarolangun
Bangko Ext LB
Aur Duri Ext LB
Payo Selincah
Muara Bungo
NEW/EXTENSION
KAPASITAS
(MVA)
PROGRESS
(%)
COD
275/150
275/150
275/150
Jumlah 275/150 kV
IBT / New
IBT / New
IBT / New
250
250
250
750
2009
2009
2014
150/20
Extension
30
2009
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
New
Extension
Extension
Extension
Extension
30
1 LB
2 LB
60
30
150
2010
2010
2011
2013
2013
Tabel 4.41
Program Listrik Perdesaan Provinsi Jambi
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.050
12.500
12.575
12.600
12.650
100
250
250
250
300
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi
(Unit/kVA)
340/15.750
340/15.750
360/16.750
380/17.750
400/18.750
1.000
1.000
1.100
1.250
1.360
1.450
1.450
1.460
1.500
1.550
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
124
1.265
900
53.375
8
1.150
1.820
84.750
5.710
7.410
-
194,4
221,8
75,1
37,3
3,2
6,1
19,8
98,3
84,2
740,2
46
SISTEM INTERKONEKSI
SUMBAGSEL
Kapasitas terpasang : 2.529,70 MW
Daya mampu
: 1.597,70 MW
Beban puncak
: 1.704,70 MW
Defisit
:
-107,00 MW
sistem belum dapat memenuhi beban puncak yang ada sehingga mengalami
defisit sebesar 460 MW. Adapun pada tahun-tahun selanjutnya kondisi
Sistem Sumatera berada pada kondisi baik.
Tabel 4.43
Neraca Daya Sistem Sumatera
URAIAN
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
48
Tabel 4.44
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Sumatera Selatan
Rencana
PLTG
PLTG
PLTG
PLTGU
PLTU
PLTU
PLTU
PLTGU
PLTG
PLTP
PLTU
PLTU
PLTP
PLTP
PLTU
Talang Dukuh
Keramasan (sewa)
Borang
Keramasan
Talang Duku
Musi Rawas
Simpang Belimbing
Gunung Megang, ST Cycle
Keramasan (sewa)
Lumut Balai
Sumsel - 2 (Keban Agung)
Banjarsari
Lumut Balai
Rantau Dadap
Sumsel 2 Mulut Tambang
JUMLAH
Total
Pendek
Jangka
Menengah/Panjang
20 MW
100 MW
19,5
50,00%
50,00%
86
2 x
6
2 x
7
2 x 113,5
30
-100
2 x 55
2 x 112,5
200
2 x 55
2 x 110
200
139,5 MW
1.474
Progress
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
10,00%
COD
Keterangan
Des 2009
2009
2010
2011
2011
2011
2011
2012
2013
2013
2013
2013
2014
2014
2014
PLN
PLN
PLN
PLN
IPP
IPP
IPP
IPP
PLN
IPP
IPP
IPP
IPP
IPP
IPP
1.334 MW
MW
Tabel 4.45
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sumatera Selatan
NO.
DARI
2
3
4
5
6
7
8
9
10
11
12
13
14
KE
TEGANGAN
(kV)
PANJANG
(kms)
275
2
2
70
47
35
55
45
1
50
50
190
1
62
40
65
711
Incomer 2 PI
JUMLAH 275 kV
Borang
Pagar Alam
Sekayu
Betung
Kayu Agung
Incomer ( Keramasan - Mariana)
Lahat
PLTP Rantau Dadap
Lahat
Incomer (PLTU S.Belimbing - Lahat)
Muara Dua
Baturaja
Muara Rupit
JUMLAH 150 kV
150
150
150
150
150
150
150
150
150
150
150
150
150
PROGRESS
(%)
COD
2014
2009
2009
2010
2010
2010
2010
2013
2014
2011
2011
2012
2012
2013
Tabel 4.46
Rencana Pengembangan Gardu Induk Provinsi Sumatera Selatan
NO.
LOKASI
1
2
3
4
Lahat
Lubuk Linggau
Betung
PLTU Sumsel-5 (Bayung Lencir)
5
6
7
8
9
Borang
Betung
Gumawang
Tanjung Api-api
Borang Ext LB
RASIO TRAFO
(kV)
275/150
275/150
275/150
275/150
Jumlah 275/150 kV
150/20
150/20
150/20
150/20
150/20
NEW/EXTENSION
IBT / New
IBT / New
IBT / New
IBT / New
Extension
Extension
Extension
New
Extension
KAPASITAS
(MVA)
500
250
500
250
1.500
30
30
30
30
2 LB
PROGRESS
(%)
COD
2009
2009
2014
2014
100
100
2009
2009
2009
2009
2009
49
NO.
LOKASI
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
Bukit Siguntang
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
150/20
Pembangkit
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
70/20
Jumlah 70/20 kV
NEW/EXTENSION
Extension
Extension
Extension
Extension
New
New
Extension
New
Extension
Extension
Extension
New
Extension
New
Extension
Extension
New
New
New
Extension
Extension
New
Extension
New
Extension
Extension
New
Extension
Extension
New
Extension
Extension
Extension
KAPASITAS
(MVA)
3 LB
1 LB
2 LB
60
30
30
1 LB
30
1 LB
1 LB
2 LB
4 LB
30
30
30
2 LB
2 LB
4 LB
2 LB
1 LB
PROGRESS
(%)
COD
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
2013
2013
2013
2013
2014
100
2 LB
2 LB
2 LB
2 LB
2 LB
1 LB
30
60
30
30
1 LB
60
570
30
30
2009
Tabel 4.47
Program Listrik Perdesaan Provinsi Sumatera Selatan
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
2.900
13.000
12.750
12.800
12.850
100
350
350
350
350
400/18.750
400/18.750
420/19.750
1.500
1.500
1.610
1.800
1.900
1.600
1.600
1600
1.680
1.850
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi (Unit/kVA)
440/20.750
460/21.750
Tabel 4.48
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Sumatera Selatan
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
1.474
713
2.100
54.300
8
1.500
2.120
99.750
8.310
8.330
-
2.405,2
117,6
144,9
38,0
3,2
8,0
20,2
111,7
75,4
2.924,1
51
Gambar 4.9
Kondisi Kelistrikan Provinsi Kepulauan Bangka Belitung
SISTEM PADANG
Kapasitas terpasang : 7,74 MW
Daya mampu
: 4,40 MW
Beban puncak
: 3,78 MW
Surplus
: 0,06 MW
SISTEM KOBA
Kapasitas terpasang : 4,59 MW
Daya mampu
: 2,34 MW
Beban puncak
: 2,25 MW
Surplus
: 0,09 MW
SISTEM BELITUNG
Kapasitas terpasang : 37,20 MW
Daya mampu
: 24,20 MW
Beban puncak
: 18,99 MW
Surplus
: 5,21 MW
SISTEM MENTOK
Kapasitas terpasang : 7,78 MW
Daya mampu
: 4,20 MW
Beban puncak
: 3,40 MW
Surplus
: 0,80 MW
SISTEM TOBOALI
Kapasitas terpasang : 5,54 MW
Daya mampu
: 3,41 MW
Beban puncak
: 3,15 MW
Surplus
: 0,26 MW
SISTEM NASIK
Kapasitas terpasang : 0,25 MW
Daya mampu
: 0,20 MW
Beban puncak
: 0,12 MW
Surplus
: 0,08 MW
SISTEM SELIU
Kapasitas terpasang : 0,15 MW
Daya mampu
: 0,09 MW
Beban puncak
: 0,05 MW
Surplus
: 0,04 MW
2010
2011
2012
2013
2014
GWH
266
280
294
310
326
Komersial
GWH
34
35
35
36
37
Publik
GWH
27
31
35
41
46
Industri
GWH
31
33
35
37
39
GWH
358
378
400
424
449
Total Kebutuhan
Pertumbuhan
7,3
5,7
5,8
5,9
5,9
9,8
9,7
9,6
9,5
9,4
2,0
2,0
2,0
2,0
2,0
11,8
11,7
11,6
11,5
11,4
MW
MW
74
78
82
87
92
47
110
169
164
183
Daya Tambahan
MW
64
63
24
60
Cadangan Daya
MW
37
95
87
101
151
52
Cangkang-Belitung
HSD Pangkal Pinang (sewa)
HSD Toboali (sewa)
3 Babel (Air Anyer)
Cangkang-Belitung
Cangkang-Bangka
3 Babel (Air Anyer)
4 Babel (Belitung)
New Bangka 3
Bangka (Kemitraan)
Bangka
JUMLAH
Total
Pendek
7
10
5
30
7
5
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
48%
2 x
2 x
64,0 MW
211
Progress
30
16,5
14
10
30
MW
MW
MW
MW
MW
48%
7%
COD
Keterangan
2009
2010
2010
2010
2010
2010
2011
2011
2013
2013
2014
IPP
PLN
PLN
Perpres 71
IPP
IPP
Perpres 71
Perpres 71
IPP
IPP
IPP
147 MW
MW
53
Tabel 4.51
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Kepulauan Bangka Belitung
NO.
DARI
1
2
3
4
Air Anyir
Air Anyir
Pangkal Pinang
Pangkal Pinang
Suge
KE
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
44
112
200
200
556
50
50
Pangkal Pinang
Sungai Liat
Kelapa
Air Gegas
JUMLAH 150 kV
Tanjung Pandan/Dukong
JUMLAH 70 kV
70
PROGRESS
(%)
67,5
COD
2009
2009
2010
2010
2009
Tabel 4.52
Rencana Pengembangan Gardu Induk Provinsi Kepulauan Bangka Belitung
NO.
1
2
3
4
5
6
7
8
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
Pembangkit
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
Jumlah
New
New
New
New
New
Extension
New
New
KAPASITAS
(MVA)
PROGRESS
(%)
2 LB
60
30
30
30
30
2 LB
30
210
COD
2009
2009
2009
2010
2010
2012
2009
2009
Tabel 4.53
Program Listrik Perdesaan Provinsi Kepulauan Bangka Belitung
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.750
7.750
7.800
7.850
7.500
PLTS Terpusat 15 kW
PLT Angin(kW)
80
80
80
80
220/12.000
240/13.000
260/14.000
210/11.500
700
650
700
750
820
650
700
740
860
890
1/250
210/11.500
6/1.500
4/1.000
2/500
54
Tabel 4.54
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Kepulauan Bangka Belitung
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
211
606
210
32.650
5
320
1.140
62.000
3.620
3.840
13
3.250
384,7
18,5
7,5
22,8
0,2
1,9
11,3
75,7
30,9
1,9
555,5
55
Gambar 4.10
Kondisi Kelistrikan Provinsi Lampung
SISTEM WIRALAGA
Kapasitas terpasang : 0,98 MW
Daya mampu
: 0,37 MW
Beban puncak
: 0,29 MW
Surplus
: 0,08 MW
SISTEM PUGUNG TAMPAK
Kapasitas terpasang : 0,57 MW
Daya mampu
: 0,34 MW
Beban puncak
: 0,33 MW
Surplus
: 0,01 MW
SISTEM BENGKUNAT
Kapasitas terpasang : 0,24 MW
Daya mampu
: 0,16 MW
Beban puncak
: 0,13 MW
Surplus
: 0,03 MW
SISTEM KRUI
Daya mampu
: 2,04 MW
Beban puncak
: 2,20 MW
Defisit
: -0,16 MW
: 0,16 MW
: 0,25 MW
: -0,09 MW
SISTEM INTERKONEKSI
SUMBAGSEL
Kapasitas terpasang : 2.529,70 MW
Daya mampu
: 1.597,70 MW
Beban puncak
: 1.704,70 MW
Defisit
:
-107,00 MW
SISTEM PULAU SABESI
Kapasitas terpasang : 0,090 MW
Daya mampu
: 0,075 MW
Beban puncak
: 0,049 MW
Surplus
: 0,026 MW
2010
2011
2012
2013
2014
Kebutuhan
Aceh
GWH
1.378
1.546
1.733
1.942
2.176
Sumatera Utara
GWH
7.008
7.543
8.124
8.756
9.441
Riau
GWH
2.412
2.614
2.831
3.062
3.306
Sumbar
GWH
2.332
2.510
2.698
2.897
3.108
S2JB
GWH
3.305
3.535
3.783
4.053
4.347
Lampung
GWH
1.935
2.083
2.249
2.437
2.649
Total Kebutuhan
GWH
18.371
19.830
21.419
23.147
25.026
Pertumbuhan
Susut & Losses (T&D)
Susut Pemakaian Sendiri
7,6
7,9
8,0
8,1
8,1
11,3
11,2
11,1
11,0
10,9
2,0
2,0
2,0
2,0
2,0
3.832
4.133
4.460
4.816
5.202
MW
2.729
643
3.318
1.476
4.728
664
5.297
1.552
6.743
1.764
MW
-460
661
931
2.033
3.305
Beban Puncak
Daya Terpasang
MW
MW
Daya Tambahan
Cadangan Daya
56
Pendek
Jangka
Menengah/Panjang
Ulubelu #1
Lampung (Tarahan)
Kalianda
Lampung Tengah
Ulubelu #2
Rajabasa
Ulubelu #3
Rajabasa
Ulubelu #4
JUMLAH
Total
1
2
2
2
1
1
1
1
1
x
x
x
x
x
x
x
x
x
55
100
6
6
55
110
55
110
55
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
34%
COD
Keterangan
2011
2011
2011
2011
2012
2013
2013
2014
2014
PLN
Perpres 71
IPP
IPP
PLN
IPP
IPP
IPP
IPP
664 MW
664
MW
57
Tabel 4.57
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Lampung
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
DARI
KE
Sribawono
Bukit Kemuning
PLTU Tarahan Baru
Pagelaran
Liwa
Gumawang
PLTP Ulu Belu
Menggala
Natar
PLTP Rajabasa
PLTP Ulubelu 3 dan 4
Teluk Betung
Kalianda
PLTP Wai Ratai
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
150
150
150
150
150
150
150
150
150
150
150
150
150
150
140
74
1
80
200
91
40
120
60
40
20
60
90
40
1.056
96,2
Seputih Banyak
Kotabumi (Uprating dari 1 x 240 mm2)
Incomer (New Tarahan - Kalianda)
Kota Agung
Incomer (B.Kemuning - Besai)
Menggala
pi Incomer (Pagelaran-Batutegi)
Seputih Banyak
Gedong Tataan
Kalianda
PLTP Ulubelu 1 dan 2
Teluk Ratai
Bakauheni
Teluk Ratai
JUMLAH
100
51,75
COD
2009
2009
2010
2010
2010
2010
2011
2012
2012
2013
2013
2013
2014
2014
Tabel 4.58
Rencana Pengembangan Gardu Induk Provinsi Lampung
NO.
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
1
2
3
4
5
6
7
8
9
10
11
12
Teluk Betung
Sutami
Seputih Banyak
Sribawono Ext LB
Adijaya
PLTU Tarahan Baru (Perpres)
Kotabumi
Kota Agung
Pagelaran Ext LB
Liwa
Menggala
Adijaya
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
150/20
150/20
150/20
150/20
150/20
Extension
Extension
New
Extension
Extension
New
Extension
New
Extension
New
Extension
Extension
60
30
60
2 LB
2 LB
4 LB
60
30
2 LB
30
3 LB
30
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Ulu Belu
Seputih Banyak
New Tarahan
Gedong Tataan
Natar Ext LB
Kalianda
PLTP Rajabasa
Bukit Kemuning
Metro
Tegineneng
Teluk Ratai
Teluk Betung Ext LB
Menggala
Sukarame
Bakauheni / Ketapang
Kalianda
Teluk Ratai
PLTP Wai Ratai
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Pembangkit
Jumlah
New
Extension
Extension
New
Extension
Extension
New
Extension
Extension
Extension
New
Extension
Extension
Extension
New
Extension
Extension
New
20
2 LB
60
30
2 LB
2 LB
2 LB
30
30
60
30
2 LB
30
30
30
2 LB
2 LB
2 LB
650
PROGRESS
(%)
97.25
100
100
100
83.38
COD
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2011
2011
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
58
Tabel 4.59
Program Listrik Perdesaan Provinsi Lampung
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.200
13.500
13.550
13.600
13.650
350
400
400
400
80
80
80
80
PLTS Terpusat 15 kW
PLTMH (kW)
100
290/14.750
290/14.750
300/15.250
320/16.250
340/7.250
1.300
1.300
1.350
1.480
1.570
1.150
1.150
1.250
1.320
1.420
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
664
1.056
650
57.500
8
1.650
320
1.540
78.250
7.000
6.290
-
1.342,4
111,1
52,6
40,2
3,2
8,8
1,9
21,3
144,1
47,9
1.773,5
59
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
60
Tabel 4.61
Neraca Daya Sistem Interkoneksi Jawa-Madura-Bali
Uraian
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
61
Tabel 4.62
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Banten
Rencana
PLTU
PLTU
PLTU
PLTU
PLTP
2 Banten (Labuan)
2 Banten (Labuan)
1 Banten (Suralaya)
3 Banten (Teluk Naga/Lontar)
Rawa Dano
JUMLAH
Total
Pendek
1 x
Jangka
Menengah/Panjang
Progress
COD
Keterangan
99%
99%
88%
60%
2009
2010
2010
2011
2014
Perpres 71
Perpres 71
Perpres 71
Perpres 71
IPP
300 MW
300 MW
625 MW
3 x
1 x
1.225,0 MW
2.280
315 MW
110 MW
1.055 MW
MW
Tabel 4.63
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Region Banten dan DKI Jakarta
NO.
DARI
1
2
3
4
5
6
Balaraja
Suralaya New
Balaraja
Durikosambi (GIS)
Balaraja
Lengkong
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
Balaraja New
Durikosambi
Taman Rasuna/Pancoran (GIS)
Curug/Lippo Karawaci
Labuan PLTU
Labuan PLTU
Menes II
Saketi II
Senayan Baru
Angke
Gandul
Cawang
New Tangerang
Gandul
Cikupa
Kelapa Gading
Pondok Indah (UGC)
Bogor Baru
Cibinong
Antasari/CSW II/Kenvil
Lautan Stell
Gandaria 150
Gandaria 150 (GIS)
Lengkong
Bintaro II
Semanggi Barat (Box)
Gedung Pola
Duren Tiga
New Senayan
Tanah Tinggi (GIS)
Jatiwaringin
Rangkasbitung II
Kedung Badak II
Ciawi Baru
Muaratawar
Bogor baru
Malingping
Mangga Besar II/G.Sahari
Millenium
Muarakarang II/Kapuk
Cakung TownShip
Muarakarang
KE
Inc.(Slya-Gdl)
Suralaya Old
Suralaya Baru
Kembangan
Kembangan
Inc. (Blrja-Gndul)
JUMLAH 500 kV
Balaraja
Petukangan
Duren Tiga
Inc. (Cldug-Ckupa)
Saketi II
Menes II
Asahimas
Rangkasbitung II
Kembangan
Ancol
Serpong
Duren Tiga
Cengkareng
Petukangan
Balaraja
Incomer (Pgsan-Plpng)
Gandul
Sentul
Sentul
(Drtga/Kemang-Kenvil)
Inc. (Blrja-Citra)
Cibinong
Cibinong
Serpong
Bintaro
Semanggi Timur (Box)
Manggarai
Kemang
Senayan
Inc. (Gmblm-Plmas)
Inc. (Pdklp-Jtngn)
Kopo
Depok III
Cibadak Baru II
Inc. (Bkasi-Kdsapi)
Cianjur
Saketi II
Kemayoran
Inc. (Lautan-Citra)
Inc (Mkrang-Dksbi)
Inc. (Kdspi-Bekasi)
Angke
TEGANGAN
(kV)
500
500
500
500
500
500
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
PANJANG
(kms)
2
3
80
6
80
2
173
20
52
9
4
46
20
110
59
22
10
40
10
14
28
23
2
14
20
18
10
4
24
24
40
14
1
4
6
6
4
24
34
46
52
40
91
80
16
6
10
10
11
PROGRESS
(%)
COD
96,2
100
2009
2010
2011
2012
2012
2013
100
51,52
100
100
2009
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
2012
100
79,35
73,62
62
NO.
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
DARI
KE
Karet
Inc.(Dksbi-Mkrng)
Inc.(Mpang_Karetlm)
Cileungsi II
Cibinong
Asahimas
Bogor Baru
Cianjur
Inc. (Cmgis-Depok III)
Ubrug 150
Kedung Badak
Cilegon Baru
Lengkong
Bintaro
Serpong
Inc. (Cbdru-Jbstn)
Pelabuhan Ratu
Inc.(Cldug-Cikupa)
Inc. (Priok-Plpng)
Karet
Depok III
Inc (Bkasi-Ksbru)
Kedung Badak
Inc. (Menes - Asahimas)
JUMLAH 150 kV
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
PROGRESS
(%)
8
4
5
10
30
10
10
64
10
50
10
10
10
18
18
20
70
10
10
10
12
10
20
30
1.537
COD
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
Tabel 4.64
Rencana Pengembangan Gardu Induk Region Banten dan DKI Jakarta
NO.
LOKASI
1
2
3
4
5
6
7
8
9
10
11
12
13
Gandul
Balaraja
Kembangan
Cawang
Gandul
Cilegon
Muaratawar
Balaraja
Depok III/Rawadenok
Cawang (GIS)
Durikosambi
Kembangan
Lengkong
14
Karet Lama
15
16
17
18
19
20
21
22
23
24
25
26
27
Plumpang
Teluk Naga
Senayan Baru (GIS)
Muarakarang
Balaraja New
Citrahabitat
Pasar Kemis
Curug/Lippo Karawaci
Gandul
Kemayoran
Lengkong
Taman Rasuna Said (GIS)
Puncak Ardi Mulya
RASIO TRAFO
(kV)
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
JUMLAH 500/150 kV
150/70
JUMLAH 150/70 kV
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
KAPASITAS
(MVA)
500
500
166
166
166
166
500
500
500
500
1.000
500
5.164
100
100
60
60
120
60
60
60
60
60
60
60
60
120
60
PROGRESS
(%)
COD
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2013
2013
2013
2010
65,07
99,74
45
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
63
NO.
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
LOKASI
Menes II
Cimanggis
Jatake
Miniatur
MuaraKarang
Kelapa Gading (GIS)
Pondok Indah (GIS)
Bogor Baru
Kopo
Saketi II
Cikande
Semen Cibinong
Cibinong
Puncak Ardi Mulya
Gandaria 150 (GIS)
New Senayan
Tanah Tinggi (GIS)
Taman Rasuna Said (GIS)
Bintaro II (GIS)
Antasari/CSW II (GIS)
Lippo Curug
Lautan Steel
Ciledug
Durentiga (GIS)
Kebonsirih (GIS)
Legok
Danayasa (GIS)
Durikosambi
Tangerang Baru
Cipinang (GIS)
Kandangsapi (GIS)
Manggabesar
Lengkong Ext
Balaraja
Gedung Pola
Manggarai
Dukuh Atas
Ketapang
Mangga Besar
Kebon Sirih
Gambir Lama
Duren Tiga
Kemang
Senayan
Jatiwaringin
Balaraja New
Kedung Badak II
Rangkasbitung II
Cibadak Baru
Serang
Ciawi Baru
Sentul
Cibinong
Malingping
Cilegon Lama
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
KAPASITAS
(MVA)
120
60
60
60
60
60
120
60
60
120
60
60
60
60
180
120
120
60
120
120
60
180
60
60
60
120
60
60
60
60
60
60
60
60
120
120
120
120
120
120
120
120
120
120
120
60
120
120
60
60
120
60
60
60
60
PROGRESS
(%)
57,64
89,7
89,99
100
100
100
100
20
0
0
86
15
99,95
COD
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
64
NO.
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
RASIO TRAFO
(kV)
Mangga Besar II GIS/Gunung Sahari
150/20
Muarakarang II/Kapuk (PIK)
150/20
Millenium
150/20
Abadi GunaPapan
150/20
Grogol (GIS)
150/20
Durikosambi II (GIS)/Daanmogot
150/20
Semanggi Barat (GIS)
150/20
Cakung Township
150/20
Citrahabitat
150/20
Jatirangon II/Cibubur
150/20
Bogor Kota (GIS)
150/20
Asahimas II
150/20
Bogor II
150/20
Cileungsi II/Jonggol
150/20
Cimanggis II/Kotakembang
150/20
Lembursitu Baru
150/20
Depok III/Rawadenok
150/20
Pelabuhan Ratu II
150/20
Ciawi Baru
150/20
Puncak Ardi Mulya
150/20
Cilegon Baru II
150/20
Legok
150/20
Tigaraksa
150/20
Tangerang Baru
150/20
Plumpang
150/20
Teluk Naga
150/20
Durikosambi
150/20
Lippo Curug
150/20
Bayah
150/20
Serang
150/20
Kedung Badak II
150/20
Menes II
150/20
Cibadak Baru II
150/20
Kelapa Gading (GIS)
150/20
Bintaro II
150/20
Sepatan
150/20
Pondok Indah (GIS)
150/20
Kemayoran II
150/20
Ciledug II/Alam Sutra
150/20
Karet New
150/20
Pasar Kemis
150/20
Kandangsapi (GIS)
150/20
Depok II (GIS)
150/20
Bekasi II
150/20
Kracak Baru
150/20
Lembursitu Baru
150/20
Depok III/Rawadenok
150/20
JUMLAH 150/20 kV
Depok Baru
70/20
Bunar
70/20
JUMLAH 70/20 kV
LOKASI
KAPASITAS
(MVA)
120
100
180
60
60
120
120
100
60
100
120
60
120
120
120
120
60
60
60
60
120
60
60
60
60
60
60
120
60
60
60
60
120
60
60
60
60
100
200
60
60
60
200
120
120
60
60
9.920
30
30
60
PROGRESS
(%)
20
74,03
0
0
98,39
99
88,66
COD
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2011
2011
65
Tabel 4.65
Program Listrik Perdesaan Provinsi Banten
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.950
9.250
9.300
9.350
9.375
PLTS Terpusat 15 kW
PLTMH (kW)
50
57
100
100
300/15.000
320/15.500
320/15.500
340/16.500
360/17.500
900
900
950
1.050
1.090
800
800
860
900
1.000
Volume
2.280
1.710
15.244
3.063,0
877,8
978,3
39.225
8
307
0
1.640
80.000
4.890
4.360
0
27,4
3,2
0,6
15,1
94,7
40,7
5.100,8
66
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
Tabel 4.67
Neraca Daya Sistem Interkoneksi Jawa-Madura-Bali
Uraian
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
Rencana
PLTGU
PLTGU
PLTGU
PLTGU
Muara Karang
Muara Karang
Priok Extension
Priok Extension
JUMLAH
Total
Pendek
Jangka
Menengah/Panjang
500 MW
194 MW
500 MW
243 MW
694,0 MW
1.437
Progress
COD
Keterangan
69,88%
69,88%
2009
2010
2011
2012
PLN
PLN
PLN
PLN
743 MW
MW
68
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
1.337,0
300
0,2
1.337,2
69
Gambar 4.13
Kondisi Kelistrikan Provinsi Jawa Barat
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
70
1 Jabar (Indramayu)
Cikarang Listrindo
Cikotok
Girimukti, Cianjur
Muara Tawar Blok #5
Muara Tawar Add-On 2,3,4
2 Jabar (Pelabuhan Ratu)
Cikarang Listrindo
Cirebon
Wayang Windu
Darajat
Muara Tawar Add-On 2,3,4
Kamojang 5
Tangkuban Perahu I
Karaha Bodas
Salak
Patuha
Darajat
Upper Cisokan PS
Kamojang 6
Tangkuban Perahu I
Indramayu Baru
Rajamandala
Jatigede
Patuha
Wayang Windu
Cisolok-Cisukarame
Cibuni
Tampomas
Tangkuban Perahu II
Karaha Bodas
JUMLAH
Total
Pendek
3 x
330
100
4
8
Jangka
Menengah/Panjang
MW
MW
MW
MW
1 x
3 x
1.102,0 MW
7.538
1
1
3
1
1
1
1
2
1
4
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
2
2
x
x
x
x
x
x
x
234
150
350
50
660
120
55
350
60
55
30
40
60
55
250
40
55
1000
47
110
60
120
50
10
45
30
55
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
81%
2010
2010
2010
2010
2011
2011
2011
2011
2011
2012
2012
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
Perpres 71
IPP
IPP
IPP
PLN
PLN
Perpres 71
IPP
IPP
IPP
IPP
PLN
PLN
PLN
IPP
IPP
IPP
IPP
PLN
PLN
PLN
PLN
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
52%
69,00%
6.436 MW
MW
71
Tabel 4.72
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Region Jawa Barat
NO.
DARI
1
2
3
4
5
6
7
8
Ujungberung
Paiton
Indramayu PLTU
Indramayu PLTU
Tambun
Tambun
Upper Cisokan PLTA (Kit)
PLTU Indramayu
9
10
11
12
13
14
15
16
17
NO.
DARI
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
Dago Pakar
Braga (GIS)
Malangbong II
Malangbong
Cikedung
Cikijing
Cibabat II (GIS)
Karang Nunggal
Dayeuhkolot/Cigereleng II
Ujung Berung New
Bekasi Utara/Tarumanegara
Tambun New
Bandung Timur II
Bandung Selatan
Kosambi Baru
Jatiluhur II
Kanci
Kiaracondong II
PLTP Patuha
Panasia II
Arjawinangun II
Cikumpay II/Sadang
Rengasdengklok II
Kadipaten 150
Majalaya II
Subang II
Kuningan II
Cibeureum
Padalarang
Ujungberung
Bekasi
Babakan II
PLTP Tangkuban Perahu I
PLTP Karaha Bodas
Tambun II
Bandung Selatan II/Ketapang
Cibabat III
Indramayu New
PLTP Cisolok-Cisukarame
PLTP Tampomas
PLTP Tangkuban Perahu II
59
60
61
62
Wayang Windu
Tanggeung
Arjawinangun
PLTP Cibuni
KE
Inc. (Mdcan-Bdsln)
Grati 3rd
Cibatu
Mandirancan
Cibatu
Inc. (Bkasi-Cibinong)
Incomer (Cibng-Sglng)
Cibatu
JUMLAH 500 kV
Sukamandi
Bandung Utara
Kosambi baru
Cigereleng
Pabuaran
Inc. (Bkasi-Ksbru)
Inc. (Sragi-Brebes)
Padalarang
Inc. (Gdmkr-Cbatul)
KE
Bandung Utara
Cigereleng
New Tasikmalaya
Cikijing
Inc. (Jtbrg - Hrgls)
Mandirancan
Inc. (Cbbat - Cbrem)
Tasikmalaya New
Inc. (Bdsln-Cgrlg)
Rancaekek
Inc. (Bkasi-Ksbru)
Tambun
Ujungberung
Cigereleng
Bekasi
PLTA Jatiluhur
Inc. (PLTU Kanci-Brebes)
Inc. (Bdsln-Ubrng)
Lagadar
Inc. (Pnsia-Bdslni)
Inc.(Arjwn-Mdcan)
Inc. (Crata-Ckpay)
Inc (Ksbru-Bkasi)
Inc. (Sragi-Ujbrg)
Rancakasumba
Perwakarta
Inc. (Ckjing - Mdcan)
Cibabat II
Cibabat
Bandung Utara
Kosambi baru
Inc.(Kanci-Ubrng)
Bandung Utara
Garut
Inc. (Pdklp-Tmbun)
Incomer (Cnjur-Bdsln)
Padalarang
Indramayu
Pelabuhan Ratu
Inc. (Rancaengkek - Cikasungka)
PLTP Tangkuban Perahu I
JUMLAH 150 kV
Sentosa
Cianjur
Palimanan
Inc. (Cianjur-Tangeung)
JUMLAH 70 kV
TEGANGAN
(kV)
500
500
500
500
500
500
500
500
150
150
150
150
150
150
150
150
150
TEGANGAN
(kV)
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
70
70
70
70
PANJANG
(kms)
1
80
260
260
40
2
60
270
973
98
26
74
138
50
20
44
89
1
PANJANG
(kms)
2
16
94
80
40
60
12
32
3
10
2
10
18
26
118
20
12
16
70
10
30
10
4
20
30
30
20
7
18
40
86
28
10
20
10
10
12
10
60
35
5
1.687
14
100
10
50
174
PROGRESS
(%)
COD
2011
2012
2014
2014
2014
2014
2014
2014
93
PROGRESS
(%)
37,5
69,13
30,68
85
2009
2009
2009
2010
2010
2010
2010
2010
2010
COD
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
2009
2010
2012
2014
72
Tabel 4.73
Rencana Pengembangan Gardu Induk Region Jawa Barat
NO.
LOKASI
1
2
3
4
5
6
7
8
9
Ujung berung
Muaratawar
Muaratawar
Cibatu
Cibatu
Mandirancan
Upper Cisokan PS
Indramayu PLTU 1000
Tambun
10
11
12
Kadipaten
Kanci
Banjar
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
Haurgeulis
Padalarang Baru
Tegal Herang
Fajar Surya.W
Jatibarang
Tambun Ext.
Jababeka
Ganda Mekar
Rancakasumba/Panyadap
Dawuan
Lagadar
Sukamandi
Padalarang Baru
Cikarang Lippo
Patuha
Sukatani /Gobel
Cibatu
Dago Pakar
Cikijing
Bekasi Utara/Tarumajaya
Braga (GIS)
Cikedung
Cibabat II (GIS)
Dayeuhkolot (GIS)
Karang Nunggal
Sunyaragi
Malangbong Baru
Poncol Baru
Rancaekek
Cigereleng
Cikumpay
Cikasungka
Bandung Utara
Cianjur
Teluk Jambe
Mekarsari
Garut
Bekasi
Kosambi Baru
Cirata Baru
RASIO TRAFO
(kV)
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
500/150
JUMLAH 500/150 kV
150/70
150/70
150/70
JUMLAH 150/70 kV
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
KAPASITAS
(MVA)
1.000
500
500
500
1.000
3.500
100
60
30
190
60
60
60
30
60
60
60
60
60
60
60
60
60
60
30
60
60
120
60
120
120
60
120
120
30
60
120
120
60
60
60
60
60
60
60
60
60
60
120
30
PROGRESS
(%)
COD
2011
2012
2012
2012
2014
2014
2014
2014
2014
2011
2012
2012
80
99
99,68
54,99
80
100
100
80
100
0
0
0
15
0
15
70
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
73
NO.
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
LOKASI
Lagadar
Tambun
Padalarang Baru
Kamojang
Tasikmalaya New
Bandung Timur II
Jatiluhur II
Kanci
Tasikmalaya
Kiaracondong II (GIS)
Muaratawar
Kamojang
Darajat
Ciamis
Jababeka
Pabuaran
Ciamis
Cibeureum
Maligi
Pinayungan
Dawuan
Kiarapayung
Garut
Fajar Surya.W
Mandirancan
Ujung berung
Haurgeulis
Bandung Selatan
Bandung Selatan
Cikedung
Cibabat II (GIS)
Tasikmalaya
Arjawinangun II
Cikumpay II/Sadang
Majalaya II
Subang II
Kadipaten II
Rengasdengklok II
Kuningan II
Patuha
Rancakasumba/Panyadap
Lagadar
Sunyaragi
Panasia II
Cikasungka
Ujung Berung New
Sukatani/Gobel
Babakan II
Sukamandi
Parung Mulya
Cianjur
Bandung Selatan II/Ketapang
Tambun II
Cibabat III
New Ujungberung
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
JUMLAH 150/20 kV
KAPASITAS
(MVA)
60
120
60
30
60
180
120
60
60
120
120
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
120
120
120
120
120
120
120
60
60
60
60
120
60
60
60
120
60
60
120
120
120
120
60
6.930
PROGRESS
(%)
99,75
COD
2011
2011
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
74
NO.
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
RASIO TRAFO
(kV)
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
JUMLAH 70/20 kV
LOKASI
Cangkring
Babakan
Sumadra
Tanggeung
Kuningan
Arjawinangun
Subang
Pangandaran
Pameungpeuk
Babakan
Arjawinangun
Parakan
Santosa
Cangkring
Sumedang
KAPASITAS
(MVA)
20
30
30
30
30
30
30
30
30
30
30
60
30
20
30
460
PROGRESS
(%)
COD
2009
2009
2010
2010
2010
2010
2011
2011
2011
2011
2011
2012
2012
2012
2012
Tabel 4.74
Program Listrik Perdesaan Provinsi Jawa Barat
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
2.400
8.000
8.100
8.150
8.175
100
100
100
100
PLTS Terpusat 15 kW
PLTMH (kW)
260/13.000
260/13.000
270/13.500
290/14.500
310/15.500
750
750
800
880
940
850
850
870
920
970
75
Tabel 4.75
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Jawa Barat
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
7.538
2.373
11.080
8.172,3
875,2
681,6
34.825
8
400
0
1.390
69.500
4.120
4.460
0
24,3
3,2
2,2
13,5
79,3
43,2
9.894,8
76
Gambar 4.14
Kondisi Kelistrikan Provinsi Jawa Tengah
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
77
1 Jateng (Rembang)
Tanjung Jati B Exp
2 Jateng (Cilacap Baru/Adipala)
Dieng
Dieng
Ungaran
Baturaden
Guci
Jawa Tengah (Infrastruktur)
JUMLAH
Total
Pendek
2 x
Jangka
Menengah/Panjang
315 MW
2
1
1
1
1
2
1
630,0 MW
4.055
x
x
x
x
x
x
x
660
660
55
60
55
110
55
1.000
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
89%
18,00%
-
2010
2012
2013
2013
2014
2014
2014
2014
2014
Perpres 71
IPP
Perpres 71
IPP
IPP
IPP
IPP
IPP
IPP
3.425 MW
MW
78
Tabel 4.78
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Region Jawa Tengah dan D. I. Yogyakarta
NO.
DARI
KE
1
2
3
4
5
6
Tanjung Jati
Rawalo/Kesugihan
Pemalang
Cilacap PLTU
Jateng PLTU
Mandirancan
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Wonogiri
Wonosari
Pati
Palur
Blora
Jekulo
Jekulo
Cilacap PLTU
Temanggung
Kudus
Kebasen II/Bala Pulang
Purwodadi
Palur II/Gondangrejo
Tanjung jati
Wonosobo
Bumiayu
Bumiayu
Pekalongan
Pracimantoro/Muntoronadi
Kebasen
Batang
Pemalang New
Pekalongan II/Kajen
Pemalang
Pemalang New
Rawalo
Rawalo New /Kesugihan
PLTP Baturaden
PLTP Guci
PLTP Ungaran
Inc Tx (Ungar-Pedan)
Inc (Pedan-Tasik)
Inc. (Ungar-Mdcan)
Rawalo
Pemalang
Tx (Ungar-Pedan)
JUMLAH 500 kV
Wonosari
Solo Baru
Rembang
Solo Baru
Rembang
Kudus
Pati
Rawalo
Wonosobo
Purwodadi
Inc. (Kbsen-Bmayu)
Ungaran
Inc.(Palur-Jajar)
Sayung
Secang
Kebasen
Kalibakal
Batang
Inc.(Pctan-Wngri)
Pemalang
Wleri
(inc Btang-Wleri)
Inc. (Pklon-Pmlang)
Pekalongan
Pemalang
Gombong
Rawalo Old
Inc. (Rawalo - Kalibakal)
Inc. (Kalibakal - Bumiayu)
Ungaran
JUMLAH 150 kV
TEGANGAN
(kV)
PANJANG
(kms)
500
500
500
500
500
500
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
PROGRESS
(%)
260
8
2
60
60
400
790
63
9
66
23
58
22
33
44
22
63
2
49
10
120
96
87
72
33
10
57
62
40
20
61
16
86
10
20
20
40
1.314
COD
100
100
2010
2010
2013
2013
2014
2014
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2012
2012
2012
2012
2013
2013
2013
2013
2014
2014
2014
2014
2014
100
20
20
19
Tabel 4.79
Rencana Pengembangan Gardu Induk Region Jawa Tengah dan D. I. Yogyakarta
NO.
LOKASI
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Bumiayu
Wonosobo
Pandeanlamper
Kalibakal
Pedan
Mangkunegaran
Sanggrahan
Rawalo New
Jekulo
RASIO TRAFO
(kV)
500/150
500/150
500/150
500/150
500/150
JUMLAH 500/150 kV
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
KAPASITAS
(MVA)
1.000
500
1.000
500
3.000
30
60
60
60
60
60
60
60
60
PROGRESS
(%)
45,31
COD
2011
2012
2013
2013
2013
2009
2009
2009
2009
2009
2009
2009
2010
2010
79
NO.
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
LOKASI
Pekalongan
Klaten
Bringin
Tambaklorok
Pati
Rawalo
Kaliwungu
Dieng
Kebasen II/Balapulang
Gondangrejo/Palur II
Bantul
Gombong
Ungaran
Lomanis
Majenang
Blora
Kentungan
Sayung
Temanggung
Brebes
Kebumen
Kedungombo
Simpang Lima (GIS)
Purworejo
Batang
Mojosongo
Tanjung Jati
Purwodadi
Banyudono
Solo Baru/Solo Baru
Semanu
Randugarut (GIS)
Secang
Cepu
Bawen
Pracimantoro/Nguntoronadi
Sanggrahan
Sragen
Kudus
Pekalongan II/Kajen
Sragen
Purbalingga
Wonosari
Brebes
Wates
Mrica
Rembang
Tambaklorok
Pandeanlamper
Masaran
Majenang
Bawen
Godean
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
JUMLAH 150/20 kV
KAPASITAS
(MVA)
60
60
60
60
60
60
30
30
60
60
60
60
60
60
30
60
60
60
30
60
30
16
60
60
60
60
60
60
60
60
60
60
30
60
60
60
60
60
60
120
120
60
60
60
60
60
60
60
60
60
30
60
60
3.556
PROGRESS
(%)
15
15
15
COD
2010
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
80
Tabel 4.80
Program Listrik Perdesaan Provinsi Jawa Tengah
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
400
3.500
3.525
3.550
3.575
PLTS Terpusat 15 kW
200
150
150
150
100
PLTMH (kW)
220/11.750
220/11.750
230/12.250
245/13.000
260/13.750
700
700
740
750
800
580
580
690
720
780
*)
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Cat: transmisi, GI & jaringan termasuk Prov. DIY
Volume
4.055
2.104
6.616
14.550
9
900
0
1.175
62.500
3.690
3.350
0
5.667,0
427,6
269,8
10,2
3,4
3,6
11,6
71,0
33,4
6.497,5
81
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
Tabel 4.82
Neraca Daya Sistem Interkoneksi Jawa-Madura-Bali
Uraian
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
2010
2011
2012
2013
2014
700
3.500
3.225
3.550
3.575
PLTS Terpusat 15 kW
PLT Angin(kW)
80
80
80
80
PLTS 50 Wp Tersebar
83
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
14.550
4
0
320
10,2
1,6
1,9
13,7
84
Gambar 4.16
Kondisi Kelistrikan Provinsi Jawa Timur
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
85
Pendek
1 x
Jangka
Menengah/Panjang
660 MW
2 x
2 x
1
2
1
2
1
660,0 MW
3.535
x
x
x
x
x
315
350
815
55
55
55
55
400
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
82%
75%
6%
30,00%
2010
2011
2012
2012
2013
2014
2014
2014
2014
Perpres 71
Perpres 71
Perpres 71
IPP
PLN
PLN
PLN
PLN
IPP
2.875 MW
MW
86
Tabel 4.87
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Region Jawa Timur dan Bali
NO.
DARI
1
2
3
4
Paiton New
Ngimbang
Surabaya Selatan
Bangil
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
Padangsambian
Probolinggo
Grati
Ketapang
Banaran
Babat
Ponorogo II
Kraksaan
Perak
Celukan Bawang PLTU
Ngimbang New
Ngimbang New
Kapal
Banyuwangi
Paciran/Brondong
Kabel Jawa Madura
Tanjung Awar-awar PLTU
Jawa
Negara
Antosari
Banaran
Cerme
Krian
Sidoarjo
Buduran II/Sedati
Bringkang/Bambe
Pacitan 150 kV
Pacitan 150 kV
Wlingi II
Kalisari
Tulung Agung II
Tandes New
Kediri New
Bali Timur
NO.
DARI
39
40
41
42
43
44
45
46
47
48
49
Waru/Buduran
Purwosari/Sukorejo II
Simogunung/Gsari
Pandaan II
Kebonagung New
PLTP Wilis/Ngebel
PLTU Bali Timur
Sanur II
PLTP Ijen
PLTP Iyang Argopuro
PLTU Madura
50
Manyar
KE
Paiton Old
Inc. (Krian-Ungar)
Grati
Inc. (Piton-Kediri)
JUMLAH 500 kV
Pesanggaran
Gondangwetan
Gondangwetan
Gilimanuk
Suryazigzag
Tuban
Manisrejo
Probolinggo
Ujung
Incomer (Pmron-Glnuk)
Mliwang
Babat
Padangsambian
Ketapang (Cable head)
Lamongan
Suramadu
Babat
Bali 3,4
Antosari
Kapal
Manisrejo
Inc. (Sgmdu-Lmgan)
Driyorejo
Inc. (Bdran-Bngil)
Inc.(Bngil-Waru)
Karangpilang
Ponorogo II
PLTU Pacitan
Kediri
Surabaya Selatan
Kediri
Tandes
Kediri Baru
Inc.(Gnyar-Sanur)
KE
Bangil/Porong
Inc. (Pier-Pakis)
Inc.(Swhan-Waru)
Inc. (Bangil-Lawang)
Kebonagung
Pacitan 2
Amlapura
Inc.(Gnyar-Sanur)
Banyuwangi
Probolinggo
Sampang
JUMLAH 150 kV
Maspion Stell
JUMLAH 70 kV
TEGANGAN
(kV)
500
500
500
500
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
TEGANGAN
(kV)
150
150
150
150
150
150
150
150
150
150
150
70
PANJANG
(kms)
3
1
145
8
157
15
68
37
3
25
60
59
60
10
6
150
40
18
7
44
6
36
12
89
47
142
2
11
24
3
10
59
124
67
12
80
10
10
10
PANJANG
(kms)
66
10
10
20
30
60
40
10
60
30
20
1.712
1
1
PROGRESS
(%)
COD
87,37
9,18
2009
2010
2012
2014
66,82
62,39
74,75
1,28
PROGRESS
(%)
2009
2009
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2011
2011
2011
2011
2011
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2013
COD
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2012
87
Tabel 4.88
Rencana Pengembangan Gardu Induk Region Jawa Timur dan Bali
NO.
LOKASI
1
2
3
4
5
Ngimbang
Paiton
Mandirancan
Krian
Surabaya Selatan
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
Sekarputih
Bangil (GIS)
Kapal
Antosari
Nusa Dua
Babadan
Waru
Sumenep
Bumicokro
Perak
Sampang
Driyorejo
Kertosono 150 kV
Jember
Sekarputih
Kediri Baru
Sawahan
Celukanbawang PLTU
Padang Sambian
Sanur
Ubud/Payangan
Bondowoso
Bangkalan
Kapal
Kuta/Pemecutan
Manisrejo
Pemaron
Surabaya Selatan
Bangil
Paciran/Brondong
Pakis/Malang Timur
Situbondo
Ngimbang New
Kraksaan
Baturiti
Negara
Bringkang/Bambe
Banyuwangi
Kebonagung New
Buduran II/Sedati
Krembangan
Purwosari/Sukorejo II
Ponorogo II
Lumajang
Lamongan
Sidoarjo/Porong
Tulungagung II
RASIO TRAFO
(kV)
500/150
500/150
500/150
500/150
500/150
JUMLAH 500/150 kV
150/70
150/70
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
KAPASITAS
(MVA)
500
500
500
500
1.000
3.000
100
60
60
30
60
60
60
60
60
30
60
60
60
60
60
60
60
30
30
60
30
30
60
60
60
60
60
60
60
60
60
60
60
30
30
30
120
60
60
120
60
120
120
60
60
120
60
PROGRESS
(%)
98,94
99,25
96,52
96,34
99,61
100
94,15
97,08
99,62
100
100
100
45
98,8
15
1`5
15,25
15
COD
2010
2011
2012
2012
2012
2010
2010
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
2012
88
NO.
LOKASI
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
Probolinggo
Sengkaling
Kasih Jatim
Wlingi II
Pacitan 150 kV
Nusa Dua
Padang Sambian
Bali Timur/Kubu
Gunungsari/Simogunung (GIS)
Kupang
Bojonegoro
Gondang Wetan
Manyar
Kalisari
Pandaan II
Wonokromo
Mojoagung
Gianyar
Sanur New
Amplapura
Kenjeran
Kebonagung
Gembong
Ngawi
Darmo Grand (GIS)
Karangpilang
Bondowoso
Bangil New
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
Tarik
Pare
Trenggalek
Polehan
Nganjuk
Turen
Magetan
Sengguruh PLTA
Mranggen/Maospati
Blimbing
Karangkates
Tarik
Caruban
Tulungagung
Ploso
Pare
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
JUMLAH 150/20 kV
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
JUMLAH 70/20 kV
KAPASITAS
(MVA)
60
60
60
60
120
60
60
30
120
60
60
60
60
60
120
60
60
60
120
30
60
60
120
60
60
60
30
60
4.780
10
20
30
30
30
30
30
20
30
30
30
30
30
30
30
30
440
PROGRESS
(%)
15
15
COD
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2009
2009
2011
2011
2012
2012
2012
2012
2012
2012
2013
2014
2014
2014
2014
2014
89
Tabel 4.89
Program Listrik Perdesaan Provinsi Jawa Timur
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.500
7.000
7.100
7.150
7.175
100
100
100
100
PLTS Terpusat 15 kW
PLTMH (kW)
100
200/10.750
22O/10.750
215/11.500
230/12.250
250/13.250
700
700
720
780
810
600
600
660
710
800
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Cat: transmisi, GI & jaringan termasuk Prov. Bali
Volume
3.535
1.870
7.980
29.925
8
500
0
1.115
58.500
3.710
3.370
0
5.440,5
270,0
405,9
20,9
3,2
2,5
11,9
71,7
35,1
6.261,7
90
SISTEM INTERKONEKSI
JAMALI
Kapasitas terpasang : 22.679 MW
Daya mampu
: 17.453 MW
Beban puncak
: 17.234 MW
Surplus
:
219 MW
Keterangan:
- Pemadaman di Region Jakarta & Banten: 159 MW
- Pemadaman di Region Jawa Barat: 51 MW
91
2014 kapasitas sistem belum dapat memenuhi beban puncak yang ada
sehingga mengalami defisit.
Tabel 4.91
Neraca Daya Sistem Interkoneksi Jawa-Madura-Bali
Uraian
2010
2011
2012
2013
2014
Kebutuhan
Rumah tangga
GWh
53.778
60.565
68.257
76.964
86.814
Publik
GWh
7.980
8.900
9.926
11.070
12.345
Komersial
GWh
24.615
27.689
31.081
34.824
38.951
Industri
GWh
47.484
49.337
51.208
53.101
55.018
GWh
146.491
9,4
160.471
9,5
175.958
9,7
193.129
9,8
8,9
Total Kebutuhan
133.856
9,3
9,3
9,2
9,1
9,0
4,0
4,0
4,0
4,0
4,0
13,3
13,2
13,1
13,0
12,9
Pertumbuhan
MW
23.084
25.240
27.624
30.264
33.188
Daya Terpasang
MW
19.257
26.484
21.858
18.804
16.687
Daya Tambahan
MW
4.311
4.219
3.383
2.630
4.882
Cadangan Daya
MW
484
5.463
-2.383
-8.830
-11.619
92
Tabel 4.92
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Bali
Rencana
PLTU
PLTU
PLTU
Pendek
Jangka
Menengah/Panjang
Celukan Bawang
Bali Timur
Celukan Bawang
2 x
JUMLAH
Total
- MW
580
130 MW
100 MW
250 MW
Progress
COD
Keterangan
6,00%
2012
2013
2013
IPP
IPP
IPP
580 MW
MW
Tabel 4.93
Program Listrik Perdesaan Provinsi Bali
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.700
6.500
6.500
6.000
6.050
PLTS Terpusat 15 kW
PLTMH (kW)
80
80
100
100
240
240
240
240
175/10.000
17510.000
190/10.750
200/11.250
220/12.250
550
550
560
600
650
500
500
530
610
630
2/500
2/500
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
580
767,0
26.750
6
360
960
960
54.250
2.910
2.770
4
1.000
18,7
2,4
2,0
5,8
10,3
62,3
30,5
1,0
899,9
93
SISTEM SINGKAWANG
Kapasitas terpasang : 47,13 MW
Daya mampu
: 42,84 MW
Beban puncak
: 43,00 MW
Defisit
: -1,60 MW
SISTEM SANGGAU
Kapasitas terpasang : 14,10 MW
Daya mampu
: 10,90 MW
Beban puncak
: 10,58 MW
Surplus
:
0,32 MW
SISTEM PUTUSSIBAU
Kapasitas terpasang : 8,71 MW
Daya mampu
: 4,37 MW
Beban puncak
: 4,25 MW
Surplus
: 0,12 MW
SISTEM PONTIANAK
Kapasitas terpasang : 175,80 MW
Daya mampu
: 123,10 MW
Beban puncak
: 130,00 MW
Defisit
:
-6,90 MW
SISTEM KETAPANG
Kapasitas terpasang : 21,07 MW
Daya mampu
: 17,80 MW
Beban puncak
: 16,92 MW
Surplus
:
0,88 MW
SISTEM SINTANG
Kapasitas terpasang : 15,59 MW
Daya mampu
: 13,30 MW
Beban puncak
: 11,83 MW
Surplus
:
1,47 MW
SISTEM NANGAH PINOH
Kapasitas terpasang : 6,79 MW
Daya mampu
: 5,30 MW
Beban puncak
: 3,93 MW
Surplus
: 1,37 MW
SISTEM SEKADAU
Kapasitas terpasang : 2,10 MW
Daya mampu
: 1,20 MW
Beban puncak
: 1,10 MW
Surplus
: 0,10 MW
Tabel 4.95
Neraca Daya Provinsi Kalimantan Barat
Uraian
Kebutuhan
Rumah Tangga
2010
2011
2012
2013
2014
GWH
808
874
943
1.017
1.094
Komersial
GWH
249
270
293
317
342
Publik
GWH
137
151
166
183
201
Industri
GWH
112
118
125
131
137
GWH
1.306
1.414
1.527
1.648
1.775
Total Kebutuhan
Pertumbuhan
8,2
8,2
8,0
7,9
7,7
4,5
4,5
4,5
4,5
4,5
17,3
17,2
17,1
17,0
16,9
MW
291
315
340
367
395
106
160
155
251
502
Daya Tambahan
MW
MW
57
100
259
208
Cadangan Daya
MW
-128
-155
-85
143
315
12,8
12,7
12,6
12,5
12,4
95
Tabel 4.96
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Kalimantan Barat
Rencana
PLTD
PLTD
PLTD
PLTM
Import
PLTD
PLTD
PLTU
PLTU
PLTU
PLTU
PLTU
Import
PLTU
Pendek
30
20
5
1,5
Jangka
Menengah/Panjang
MW
MW
MW
MW
100
7,5
4
27,5
50
10
25
50
100
4
4 x
2
2
2
2
2
x
x
x
x
x
2 x
JUMLAH
Total
56,5 MW
624
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
3,00%
3,00%
3,00%
2010
2010
2010
2010
2012
2013
2013
2013
2013
2013
2013
2014
2014
2014
PLN
PLN
PLN
PLN
IPP
PLN
PLN
Perpres 71
Perpres 71
IPP
IPP
PLN
IPP
IPP
1%
0%
2%
2%
567 MW
MW
Tabel 4.97
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Kalimantan Barat
NO.
1
DARI
Singkawang
KE
TEGANGAN
(kV)
PANJANG
(kms)
275
396
396
126
32
40
184
7
180
6
120
180
100
110
180
1.265
Mambong
JUMLAH 275 kV
2
3
4
5
6
7
8
9
10
11
12
13
Singkawang
Sei Raya
PLTU Singkawang (Perpres)/Kura2
Siantan
PLTU Gambut Pontianak (IPP)
Tayan
PLTU Parit Baru (IPP)
Singkawang
Bengkayang
Sanggau
Ngabang
Sintang
Sambas
Kota Baru,
Incomer 2 phi
Tayan
Mempawah
Sanggau
Parit Baru
Bengkayang
Ngabang
Sekadau
Tayan
Sekadau
JUMLAH 150 kV
150
150
150
150
150
150
150
150
150
150
150
150
PROGRESS
(%)
COD
2014
5
2,5
5
5
2,5
2,5
2009
2009
2010
2010
2011
2011
2011
2012
2013
2013
2013
2014
Tabel 4.98
Rencana Pengembangan Gardu Induk Provinsi Kalimantan Barat
NO.
LOKASI
Singkawang
2
3
4
5
6
7
8
9
10
RASIO TRAFO
(kV)
275/150
Jumlah 275/150 kV
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
NEW/EXTENSION
New
New
Extension
New
Extension
Extension
Extension
Extension
Extension
Extension
KAPASITAS
(MVA)
100
100
30
2 LB
30
2 LB
2 LB
2 LB
30
30
30
PROGRESS
(%)
COD
2014
100
65
2009
2009
2009
2009
2009
2009
2009
2009
2010
96
NO.
11
12
13
14
15
16
17
18
19
20
21
22
23
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
LOKASI
Tayan (GI Baru)
Siantan Ext LB
Sanggau (GI Baru)
Tayan Ext LB
Singkawang
Bengkayang (GI Baru)
Singkawang Ext LB
Sekadau (GI Baru)
Sanggau Ext LB
Ngabang (GI Baru)
Tayan Ext LB
Sintang (GI Baru)
Sanggau Ext LB
NEW/EXTENSION
New
Extension
New
Extension
Extension
New
Extension
New
Extension
New
Extension
New
Extension
KAPASITAS
(MVA)
30
2 LB
30
2 LB
30
30
2 LB
30
2 LB
PROGRESS
(%)
COD
2010
2010
2011
2011
2012
2012
2012
2013
2013
2013
2013
2014
2014
30
2 LB
60
2 LB
390
Tabel 4.99
Program Listrik Perdesaan Provinsi Kalimantan Barat
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
2.950
14.500
14.525
14.575
14.550
PLTS Terpusat 15 kW
100
350
350
350
400
PLTMH (kW)
420/19.750
400/18.750
450/21.250
470/22.250
490/23.250
1.000
950
1.000
1.100
1.200
1.000
1.100
1.150
1.230
1.270
2/500
1/250
1/ 250
3/750
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
624
1.661
490
805,1
265,1
90,5
61.100
9
1.550
0
2.230
105.250
5.250
5.750
7
1.750
42,8
3,4
8,0
21,6
134,3
68,6
1,0
1.440,5
97
SISTEM SAMPIT
Kapasitas terpasang : 26,88 MW
Daya mampu
: 16,85 MW
Beban puncak
: 17,65 MW
Defisit
: -0,80 MW
12
SISTEM INTERKONEKSI
BARITO
Kapasitas terpasang : 321,09 MW
Daya mampu
: 246,23 MW
Beban puncak
: 308,90 MW
Defisit
: -62,67 MW
98
SISTEM BUNTOK
Kapasitas terpasang : 6,91 MW
Daya mampu
: 4,28 MW
Beban puncak
: 4,04 MW
Surplus
: 0,24 MW
SISTEM SUKAMARA
Kapasitas terpasang : 1,78 MW
Daya mampu
: 1,21 MW
Beban puncak
: 0,96 MW
Surplus
: 0,25 MW
13
2010
2011
2012
2013
2014
Kebutuhan
Rumah Tangga
GWH
1.059
1.116
1.179
1.248
1.324
Komersial
GWH
429
496
574
664
770
Publik
GWH
162
173
185
198
211
Industri
GWH
298
305
314
323
332
GWH
1.947
2.091
2.252
2.432
2.636
Total Kebutuhan
Pertumbuhan
6,7
12,2
7,7
12,1
8,0
12,0
8,4
6,5
6,5
6,5
6,5
6,5
18,8
18,7
18,6
18,5
18,4
Beban Puncak
Daya Terpasang
MW
MW
433
464
500
539
584
239
310
446
460
790
Daya Tambahan
MW
78
145
28
344
151
Cadangan Daya
MW
-116
-9
-26
265
357
12,3
7,4
11,9
99
Pendek
2
2
3
1
Jangka
Menengah/Panjang
Progress
MW
MW
MW
MW
2
2
2
1
2
8,0 MW
328
x
x
x
x
x
1
7
7
60
120
25
1
MW
MW
MW
MW
MW
MW
MW
90%
2%
COD
Keterangan
2010
2010
2010
2010
2011
2011
2012
2013
2013
2014
2014
PLN
PLN
PLN
IPP
PLN
PLN
IPP
Perpres 71
IPP
PLN
IPP
320 MW
MW
100
Tabel 4.103
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Kalimantan Tengah
NO.
1
2
3
4
5
6
7
DARI
KE
Palangkaraya
PLTU P.Pisau (Perpres)/Selat
Kasongan (Sampit - P raya)
Tanjung
PLTGU Bangkanai
Sampit
PLTU Sampit
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
150
150
150
150
150
150
150
168
4
2
260
560
172
40
1.206
2,5
5
Sampit
Incomer 2 phi
Incomer phi
Buntok
Muara Teweh - Buntok - Tanjung
Pangkalan Bun
Sampit
JUMLAH
2,5
COD
2010
2010
2011
2011
2013
2012
2014
Tabel 4.104
Rencana Pengembangan Gardu Induk Provinsi Kalimantan Tengah
NO.
1
2
3
4
5
6
7
8
9
10
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah
New
Extension
New
Extension
Extension
New
Extension
New
Extension
New
KAPASITAS
(MVA)
PROGRESS
(%)
30
30
30
2 LB
2 LB
30
2 LB
30
2 LB
30
180
COD
2009
2010
2010
2010
2011
2011
2011
2011
2012
2012
Tabel 4.105
Program Listrik Perdesaan Provinsi Kalimantan Tengah
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.350
14.500
14.525
14.325
14.400
350
350
350
350
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi (Unit/kVA)
100
420/19.250
420/19.250
470/21.750
490/22.750
510/23.750
1.100
1.100
1.200
1.350
1.400
1.150
1.150
1.160
1.210
1.340
1/ 250
2/500
1/250
1/250
101
Tabel 4.106
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Kalimantan Tengah
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
328
1.206
180
455,8
230,9
51,0
61.100
8
1.500
0
2.310
106.750
6.150
6.010
5
1.250
42,8
3,2
7,7
22,0
104,4
101,0
0,7
1.019,6
102
Gambar 4.20
Kondisi Kelistrikan Provinsi Kalimantan Selatan
SISTEM INTERKONEKSI
BARITO
Kapasitas terpasang : 321,09 MW
Daya mampu
: 246,23 MW
Beban puncak
: 308,90 MW
Defisit
: -62,67 MW
SISTEM BATULICIN/PAGATAN
Kapasitas terpasang : 18,97 MW
Daya mampu
: 12,62 MW
Beban puncak
: 11,01 MW
Surplus
: 1,61 MW
SISTEM KOTABARU
Kapasitas terpasang : 12,20 MW
Daya mampu
: 6,95 MW
Beban puncak
: 6,75 MW
Surplus
: 0,20 MW
2010
2011
2012
2013
2014
Kebutuhan
Rumah Tangga
GWH
1.059
1.116
1.179
1.248
1.324
Komersial
GWH
429
496
574
664
770
Publik
GWH
162
173
185
198
211
Industri
GWH
298
305
314
323
332
GWH
1.947
2.091
2.252
2.432
2.636
Total Kebutuhan
Pertumbuhan
6,7
12,2
7,7
12,1
8,0
12,0
8,4
6,5
6,5
6,5
6,5
6,5
18,8
18,7
18,6
18,5
18,4
Beban Puncak
Daya Terpasang
MW
MW
433
464
500
539
584
239
310
446
460
790
Daya Tambahan
MW
78
145
28
344
151
Cadangan Daya
MW
-116
-9
-26
265
357
12,3
7,4
11,9
103
Pendek
20
30
10
10
Jangka
Menengah/Panjang
MW
MW
MW
MW
2 x
2 x
1 x
1 x
70,0 MW
418
65
7
4
100
100
MW
MW
MW
MW
MW
Progress
COD
Keterangan
50,00%
50,00%
9%
2010
2010
2010
2010
2011
2012
2013
2013
2014
PLN
PLN
PLN
PLN
Perpres 71
PLN
PLN
IPP
IPP
348 MW
MW
104
Tabel 4.109
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Kalimantan Selatan
NO.
1
2
3
4
5
6
7
8
9
DARI
KE
Barikin
Tanjung
Barikin
Seberang Barito
Asam-asam
PLTU Asam-asam (Perpres)
PLTU M. Tambang Kalsel-1(IPP)
Rantau (Barikin - Cempaka)
PLTU Kalsel
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
150
150
150
150
150
150
150
150
150
116
142
33
21
248
220
12
14
12
818
89,88
Tanjung
Perbatasan
Amuntai
Kayutangi
Batu licin
Mantuil
Rantau
Incomer 2 phi
Tanjung
JUMLAH
77,52
38
77,93
COD
2009
2009
2009
2009
2010
2010
2011
2012
2013
Tabel 4.110
Rencana Pengembangan Gardu Induk Provinsi Kalimantan Selatan
NO.
LOKASI
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Barikin Ext LB
Kapuas / Selat
Amuntai (GI baru )
Barikin Ext LB
Kayu Tangi (GI baru )
Seberang Barito Ext LB
Mantuil
Batu licin (GI Baru)
Asam-asam Ext LB
Barikin
Cempaka
Kasongan (GI Baru)
Trisakti
Kayu Tangi
Barikin
16
Plehari
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Extension
Extension
New
Extension
New
Extension
Extension
New
Extension
Extension
Extension
New
Extension
Extension
Extension
2 LB
30
30
2 LB
30
2 LB
30
30
2 LB
30
60
30
60
30
30
150/20
Jumlah
Extension
30
420
PROGRESS
(%)
84.82
100
100
100
100
100
94.1
100
COD
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2011
2011
2012
2012
2010
2014
Tabel 4.111
Program Listrik Perdesaan Provinsi Kalimantan Selatan
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.750
7.500
7.550
7.600
7.650
200
200
200
200
PLTS Terpusat 15 kW
PLTMH (kW)
Pem. Gardu Distribusi (Unit/kVA)
50
220/11.750
200/11.750
240/12.750
260/13.750
280/14.750
600
600
650
700
750
500
500
520
600
600
1/ 250
2/500
1/250
105
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
418
818
390
32.050
4
850
0
1.200
64.750
3.300
2.720
4
1.000
571,0
46,1
50,2
22,4
1,6
4,4
11,5
58,2
32,4
0,6
798,4
Gambar 4.21
Kondisi Kelistrikan Provinsi Kalimantan Timur
SISTEM NUNUKAN
Kapasitas terpasang : 15,25 MW
Daya mampu
: 4,95 MW
Beban puncak
: 4,77 MW
Surplus
: 0,18 MW
SISTEM SANGATTA
Kapasitas terpasang : 19,22 MW
Daya mampu
: 9,75 MW
Beban puncak
: 11,45 MW
Defisit
: -1,70 MW
SISTEM INTERKONEKSI
MAHAKAM
Kapasitas terpasang : 279,56 MW
Daya mampu
: 235,00 MW
Beban puncak
: 234,06 MW
Surplus
:
0,94 MW
SISTEM BULUNGAN
Kapasitas terpasang : 12,02 MW
Daya mampu
: 6,80 MW
Beban puncak
: 6,39 MW
Surplus
: 0,41 MW
SISTEM TANJUNG REDEP
Kapasitas terpasang : 20,80 MW
Daya mampu
: 11,42 MW
Beban puncak
: 10,32 MW
Surplus
: 1,10 MW
SISTEM BONTANG
Kapasitas terpasang : 34,59 MW
Daya mampu
: 23,60 MW
Beban puncak
: 14,92 MW
Surplus
: 8,68 MW
SISTEM PETUNG
Kapasitas terpasang : 12,30 MW
Daya mampu
: 6,80 MW
Beban puncak
: 7,44 MW
Defisit
: -0,64 MW
SISTEM LONGIKIS
Kapasitas terpasang : 2,45 MW
Daya mampu
: 1,97 MW
Beban puncak
: 1,82 MW
Surplus
: 0,15 MW
SISTEM MALINAU
Kapasitas terpasang : 5,81 MW
Daya mampu
: 4,80 MW
Beban puncak
: 1,78 MW
Surplus
: 3,02 MW
SISTEM SEBATIK
Kapasitas terpasang : 3,17 MW
Daya mampu
: 1,40 MW
Beban puncak
: 1,36 MW
Surplus
: 0,04 MW
SISTEM Tj.
Tj. SELOR
Kapasitas terpasang : 9,60 MW
Daya mampu
: 5,35 MW
Beban puncak
: 5,85 MW
Defisit
: -0,50 MW
SISTEM MELAK
Kapasitas terpasang : 14,20 MW
Daya mampu
: 6,82 MW
Beban puncak
: 5,62 MW
Surplus
: 1,20 MW
SISTEM KERANG
Kapasitas terpasang : 0,45 MW
Daya mampu
: 0,38 MW
Beban puncak
: 0,20 MW
Surplus
: 0,18 MW
SISTEM MUARA KOMAM
Kapasitas terpasang : 0,59 MW
Daya mampu
: 0,46 MW
Beban puncak
: 0,43 MW
Surplus
: 0,03 MW
SISTEM Tj.
Tj. ARU
Kapasitas terpasang : 0,45 MW
Daya mampu
: 0,18 MW
Beban puncak
: 0,11 MW
Surplus
: 0,07 MW
107
2010
2011
2012
2013
2014
Kebutuhan
Rumah Tangga
GWh
1.046
1.130
1.218
1.312
1.410
Komersial
GWh
573
627
682
737
794
Publik
GWh
220
236
252
268
286
Industri
GWh
364
398
431
463
496
GWh
2.203
2.391
2.582
2.780
2.986
Total Kebutuhan
Pertumbuhan
9,3
9,7
8,0
9,6
7,7
9,5
7,4
2,0
2,0
2,0
2,0
2,0
11,8
11,7
11,6
11,5
11,4
Beban Puncak
Daya Terpasang
MW
MW
446
484
522
562
603
169
277
275
529
693
Daya Tambahan
MW
113
262
180
261
Cadangan Daya
MW
-164
-200
15
148
352
9,8
8,5
9,4
108
Tabel 4.114
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Kalimantan Timur
Rencana
PLTD
PLTD
PLTMG
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTGB
PLTGB
PLTGB
PLTGB
PLTU
PLTG
PLTU
PLTU
PLTU
PLTU
PLTU
PLTU
PLTG
PLTU
PLTU
PLTU
PLTU
PLTG
PLTU
PLTU
PLTU
Excess Power
MFO Batakan
Bontang
MFO Tanjung Batu
HSD Tanah Grogot (sewa)
HSD Melak (sewa)
HSD Sangata (sewa)
HSD Tanjung Selor (sewa)
HSD Nunukan (sewa)
Sangata (sewa)
Tanjung Redep (sewa)
Tanjung Selor (sewa)
Malinau (sewa)
Tanah Grogot
Kaltim (Peaking)
Kota Bangun
Muara Jawa/Teluk Balikpapan
Kaltim Baru
Tanah Grogot
Kota Bangun
Muara Jawa/Teluk Balikpapan
Senipah
Petung
Melak
Nunukan
Berau
Senipah
Melak
Tanjung Selor
Kaltim
JUMLAH
Total
Pendek
4
40
14
20
4
2
2
2
2
9
6
6
2
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
90,00%
1
2
1
1
x
x
x
x
1
1
1
1
2
1
2
x
x
x
x
x
x
x
1 x
1 x
2 x
113,0 MW
823
Progress
7
50
5
100
50
7
5
100
40
7
7
7
7
40
7
7
100
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
2,00%
2,00%
COD
Keterangan
Des 2009
2009
2009
Peb 2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2011
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
IPP
PLN
PLN
PLN
IPP
IPP
PLN
PLN
IPP
IPP
IPP
IPP
PLN
IPP
IPP
IPP
IPP
710 MW
MW
Tabel 4.115
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Kalimantan Timur
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
DARI
Harapan Baru
Karang Joang
Kuaro
Muara Jawa
Bontang
Petung
PLTG Senipah (IPP)
Bontang
PLTU Kaltim/Kemitraan (IPP)
PLTU Muara Jawa (Perpres)
Berau
PLTU New Kaltim (Perpres)
Industri
Muara Jawa
Sembera
PLTU Kaltim Baru II/Sangata
KE
Bukuan
Kuaro
Perbatasan
Incomer 2 phi
Sambutan
Incomer 2 phi
Muara Jawa
Sangata
Muara Jawa
Muara Jawa
Tanjung Selor
Muara Jawa/Senipah
New Industri
Industri Baru
Embalut
Bontang
JUMLAH
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
150
20
155
93
48
90
8
24
65
50
24
4
10
50
160
50
520
1.371
PROGRESS
(%)
7,35
COD
2009
2009
2009
2009
2010
2010
2010
2011
2011
2011
2012
2013
2013
2014
2014
2014
109
Tabel 4.116
Rencana Pengembangan Gardu Induk Provinsi Kalimantan Timur
NO.
LOKASI
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Sembera
Embalut
Muara Jawa
New Industri
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Extension
New
Extension
New
New
Extension
New
Extension
New
Extension
Extension
Extension
New
New
New
Extension
60
30
2 LB
30
60
2 LB
30
60
30
2 LB
2 LB
30
30
30
60
2 LB
150/20
150/20
150/20
150/20
Jumlah
Extension
Extension
Extension
Extension
2 LB
2 LB
2 LB
2 LB
450
PROGRESS
(%)
54,89
100
COD
2009
2009
2009
2009
2010
2010
2010
2011
2011
2011
2011
2012
2012
2012
2013
2013
2014
2014
2014
2014
Tabel 4.117
Program Listrik Perdesaan Provinsi Kalimantan Timur
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.700
8.000
8.100
8.150
8.200
300
300
350
370
80
80
80
80
PLTS Terpusat 15 kW
PLTMH (kW)
100
210/11.500
800
1,000
1/ 250
210/11.500
850
230/12.500
250/13.500
270/14,500
900
1.000
1.100
900
950
1.000
1.020
2/500
1/250
1/250
1/250
110
Tabel 4.118
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Kalimantan Timur
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
823
1.371
450
979,9
297,2
113,1
34.150
7
1.320
320
1.170
63.500
4.650
4.870
6
1.500
23,9
3,1
7,3
1,9
14,0
61,8
54,6
0,3
1.557,1
111
Gambar 4.22
Kondisi Kelistrikan Provinsi Sulawesi Utara
SISTEM TAHUNA
Kapasitas terpasang : 11,09 MW
Daya mampu
: 4,66 MW
Beban puncak
: 4,42 MW
Surplus
: 0,24 MW
SISTEM MELONGUANE
Kapasitas terpasang : 1,47 MW
Daya mampu
: 0,77 MW
Beban puncak
: 0,63 MW
Surplus
: 0,14 MW
SISTEM LIRUNG
Kapasitas terpasang : 1,78 MW
Daya mampu
: 1,18 MW
Beban puncak
: 0,82 MW
Surplus
: 0,36 MW
SISTEM INTERKONEKSI
MINAHASA
Kapasitas terpasang : 185,17 MW
Daya mampu
: 133,50 MW
Beban puncak
: 153,00 MW
Defisit
: -19,50 MW
SISTEM TAGULANDANG
Kapasitas terpasang : 2,08 MW
Daya mampu
: 1,50 MW
Beban puncak
: 0,80 MW
Surplus
: 0,70 MW
SISTEM MOLIBAGU
Kapasitas terpasang : 2,73 MW
Daya mampu
: 2,38 MW
Beban puncak
: 1,91 MW
Surplus
: 0,47 MW
2010
2011
2012
2013
2014
GWH
808
865
933
1.012
1.101
Komersial
GWH
241
253
266
279
291
Publik
GWH
195
215
236
260
287
Industri
GWH
117
121
126
130
135
GWH
1.361
1.455
1.561
1.681
1.814
Total Kebutuhan
Pertumbuhan
6,3
6,9
7,3
7,7
7,9
3,5
3,5
3,5
3,5
3,5
13,3
13,2
13,1
13,0
12,9
Beban Puncak
Daya Terpasang
MW
MW
326
348
373
401
433
211
279
589
653
882
Daya Tambahan
MW
74
319
82
248
256
Cadangan Daya
MW
-41
249
298
500
705
9,8
9,7
9,6
9,5
9,4
112
Pendek
20
2,5
1,6
Jangka
Menengah/Panjang
MW
MW
MW
2 x
2 x
2 x
2 x
1
1
1
4
1
24,1 MW
301
x
x
x
x
x
20
25
25
4
0,7
0,5
1,2
20
20
25
20
25
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
3,00%
3,00%
99,32%
2010
2010
2010
2011
2011
2012
2012
2013
2013
2013
2013
2013
2013
2014
2014
PLN
PLN
PLN
PLN
Perpres 71
PLN
IPP
IPP
IPP
IPP
IPP
IPP
IPP
PLN
IPP
49%
277 MW
MW
113
Tabel 4.121
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sulawesi Utara
NO.
DARI
1
2
3
4
5
6
7
8
9
10
Lopana
Telling (New 150)
PLTU 2 Sulut (Perpres)
Ranomut Baru 150 (Paniki)
Kotamubagu/Otam
Lolak
Bintauna
PLTP Kotamubagu
PLTU Sulut (IPP)
PLTP Lahendong 5 dan 6
11
KE
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
150
150
150
150
150
150
150
150
150
150
96
16
36
56
72
210
1
32
8
20
547
4
4
56,17
70
100
52,73
COD
2009
2009
2010
2010
2010
2011
2011
2014
2014
2013
2011
Tabel 4.122
Rencana Pengembangan Gardu Induk
Provinsi Sulawesi Utara
NO.
LOKASI
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
PROGRESS
(%)
70,16
COD
150/70
150/70
Jumlah 150/70 kV
New
Extension
60
60
120
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
New
Extension
New
Extension
Extension
New
Extension
New
Extension
New
Extension
Extension
Extension
60
2 LB
30
2 LB
30
30
2 LB
30
2 LB
20
2 LB
2 LB
30
16
17
18
19
20
Buroko
Bintauna (GI Tapping)
Ranomut Baru 150 kV(Paniki)
Tomohon
Bitung Baru 150 kV (Kema)
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
Extension
New
Extension
Extension
Extension
2 LB
20
30
30
30
340
2011
2011
2012
2013
2013
21
Tasik Ria
70/20
Jumlah 70/20 kV
Extension
30
30
2014
100
100
100
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
2010
2010
2010
2011
114
Tabel 4.123
Program Listrik Perdesaan Provinsi Sulawesi Utara
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.600
9.000
9.000
9.171
9.150
225
225
225
300
240
240
240
240
PLTS Terpusat 15 kW
PLTMH (kW)
100
210/11.500
225/12.500
220/12.250
240/13.250
260/14.250
600
550
600
650
650
500
550
580
620
730
2/500
2/500
2/500
4/1.250
4/1.000
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
301
551
490
37.921
7
1.075
960
1.155
63.750
3.050
2.980
14
3.750
527,6
22,6
23,4
26,6
2,8
5,4
5,8
13,6
74,1
48,4
2,3
752,4
115
SISTEM BURUKI
Kapasitas terpasang : 3,32 MW
Daya mampu
: 2,76 MW
Beban puncak
: 2,01 MW
Surplus
: 0,75 MW
SISTEM MARISA TILAMUTA
Kapasitas terpasang : 6,47 MW
Daya mampu
: 3,20 MW
Beban puncak
: 3,20 MW
Surplus
: 0,00 MW
116
Tabel 4.125
Neraca Daya Sistem Sulawesi Utara, Tengah dan Gorontalo
Uraian
Kebutuhan
Rumah Tangga
2010
2011
2012
2013
2014
GWH
808
865
933
1.012
1.101
Komersial
GWH
241
253
266
279
291
Publik
GWH
195
215
236
260
287
Industri
GWH
117
121
126
130
135
GWH
1.361
1.455
1.561
1.681
1.814
Total Kebutuhan
Pertumbuhan
6,3
6,9
7,3
7,7
7,9
3,5
3,5
3,5
3,5
3,5
13,3
13,2
13,1
13,0
12,9
Beban Puncak
Daya Terpasang
MW
MW
326
348
373
401
433
211
279
589
653
882
Daya Tambahan
MW
74
319
82
248
256
Cadangan Daya
MW
-41
249
298
500
705
9,8
9,7
9,6
9,5
9,4
117
Tabel 4.126
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Gorontalo
Rencana
PLTD
PLTD
PLTM
PLTU
PLTU
PLTU
Jangka
Menengah/Panjang
Pendek
MW
MW
7
3
2 x
2 x
JUMLAH
Total
10,0 MW
MW
MW
MW
MW
1,2
25
20
6
Progress
COD
Keterangan
3,00%
3,00%
93,01%
47%
2010
2010
2011
2011
2012
2013
PLN
PLN
PLN
Perpres 71
IPP
IPP
30,00%
83 MW
93
MW
Tabel 4.127
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Gorontalo
NO.
1
2
3
4
5
DARI
KE
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
70
90
220
24
140
544
Botupingge
Botupingge
Marissa
Incomer
Buroko
JUMLAH
PROGRESS
(%)
100
100
100
COD
2010
2010
2010
2010
2010
Tabel 4.128
Rencana Pengembangan Gardu Induk Provinsi Gorontalo
NO.
1
2
3
4
5
RASIO TRAFO
(kV)
LOKASI
Botupingge (GI Baru)
PLTU Gorontalo Baru /Anggrek
Isimu (GI Baru)
Marissa GI Baru)
Botupingge
NEW/EXTENSION
150/20
150/20
150/20
150/20
150/20
Jumlah
New
New
New
New
Extension
KAPASITAS
(MVA)
PROGRESS
(%)
30
20
30
30
30
140
100
COD
2010
2010
2010
2010
2010
100
Tabel 4.129
Program Listrik Perdesaan Provinsi Gorontalo
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
2900
13757
13757
13750
13800
325
325
325
325
240
240
240
240
PLTS Terpusat 15 kW
PLTMH (kW)
100
360/16.500
360/16.500
390/18.000
410/19.000
430/20.000
800
800
850
900
980
800
800
830
950
1,000
1/250
2/500
2/500
1/250
118
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
160,3
22,5
10,9
57.964
8
1.400
960
1.950
90.000
4.330
4.380
6
1.500
40,6
3,2
7,2
5,8
20,4
114,9
72,5
0,9
459,2
119
Gambar 4.24
Kondisi Kelistrikan Provinsi Sulawesi Tengah
SISTEM TOLITOLI-TOLI
Kapasitas terpasang : 10,26 MW
Daya mampu
: 5,79 MW
Beban puncak
: 4,38 MW
Surplus
: 1,41 MW
SISTEM LUWUK
Kapasitas terpasang : 11,18 MW
Daya mampu
: 6,17 MW
Beban puncak
: 5,47 MW
Surplus
: 0,70 MW
SISTEM PALU
Kapasitas terpasang : 81,24 MW
Daya mampu
: 36,49 MW
Beban puncak
: 50,60 MW
Defisit
:-14,11 MW
SISTEM LEOK
Kapasitas terpasang: 3,35 MW
Daya mampu
: 1,92 MW
Beban puncak
: 1,83 MW
Surplus
: 0,09 MW
SISTEM BANGKIR
Kapasitas terpasang: 1,92 MW
Daya mampu
: 1,36 MW
Beban puncak
: 1,49 MW
Defisit
: -0,13 MW
SISTEM PALASA
Kapasitas terpasang: 1,67 MW
Daya mampu
: 1,00 MW
Beban puncak
: 0,69 MW
Surplus
: 0,31 MW
SISTEM KOTARAYA
Kapasitas terpasang: 1,70 MW
Daya mampu
: 1,05 MW
Beban puncak
: 1,03 MW
Surplus
: 0,02 MW
SISTEM BUNTA
Kapasitas terpasang: 1,49 MW
Daya mampu
: 1,39 MW
Beban puncak
: 1,13 MW
Surplus
: 0,26 MW
SISTEM MOUTONG
Kapasitas terpasang: 3,45 MW
Daya mampu
: 1,76 MW
Beban puncak
: 2,10 MW
Defisit
: -0,34 MW
SISTEM MOILONG
Kapasitas terpasang: 3,00 MW
Daya mampu
: 1,76 MW
Beban puncak
: 2,10 MW
Defisit
: -0,34 MW
SISTEM PARIGI
Kapasitas terpasang: 7,80 MW
Daya mampu
: 3,37 MW
Beban puncak
: 3,18 MW
Surplus
: 0,19 MW
SISTEM POSO
Kapasitas terpasang: 7,63 MW
Daya mampu
: 5,18 MW
Beban puncak
: 5,95 MW
Defisit
: -0,77 MW
SISTEM TENTENA
Kapasitas terpasang: 1,70 MW
Daya mampu
: 1,50 MW
Beban puncak
: 1,50 MW
Surplus
: 0,00 MW
SISTEM AMPANA
Kapasitas terpasang: 3,10 MW
Daya mampu
: 1,67 MW
Beban puncak
: 1,12 MW
Surplus
: 0,55 MW
SISTEM TOILI
Kapasitas terpasang: 3,00 MW
Daya mampu
: 1,50 MW
Beban puncak
: 1,31 MW
Surplus
: 0,19 MW
SISTEM KOLONEDALE
Kapasitas terpasang: 3,63 MW
Daya mampu
: 1,62 MW
Beban puncak
: 1,20 MW
Surplus
: 0,42 MW
SISTEM BANGGAI
Kapasitas terpasang: 2,25 MW
Daya mampu
: 1,12 MW
Beban puncak
: 1,10 MW
Surplus
: 0,02 MW
SISTEM BUNGKU
Kapasitas terpasang: 1,56 MW
Daya mampu
: 0,88 MW
Beban puncak
: 0,81 MW
Surplus
: 0,07 MW
120
2010
2011
2012
2013
2014
GWH
808
865
933
1.012
1.101
Komersial
GWH
241
253
266
279
291
Publik
GWH
195
215
236
260
287
Industri
GWH
117
121
126
130
135
GWH
1.361
1.455
1.561
1.681
1.814
Total Kebutuhan
Pertumbuhan
6,3
6,9
7,3
7,7
7,9
3,5
3,5
3,5
3,5
3,5
13,3
13,2
13,1
13,0
12,9
Beban Puncak
Daya Terpasang
MW
MW
326
348
373
401
433
211
279
589
653
882
Daya Tambahan
MW
74
319
82
248
256
Cadangan Daya
MW
-41
249
298
500
705
9,8
9,7
9,6
9,5
9,4
121
Tabel 4.132
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik Provinsi Sulawesi Tengah
Rencana
PLTD
PLTD
PLTD
PLTD
PLTD
PLTM
PLTM
PLTA
PLTA
PLTM
PLTM
PLTU
PLTU
PLTGU
PLTM
PLTM
PLTM
PLTM
PLTM
PLTM
PLTM
PLTM
PLTM
PLTU
PLTGU
PLTM
PLTM
PLTP
PLTP
Pendek
2 x
4
5
20
3
3
0,8
2
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
MW
COD
Keterangan
3,00%
3,00%
3,00%
3,00%
3,00%
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
PLN
PLN
PLN
PLN
PLN
PLN
PLN
IPP
IPP
IPP
PLN
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
IPP
46,26%
50
145
2,5
1
4
10
120
1,2
2,5
1,2
1,5
1,3
1,2
0,8
2,5
3,6
15
120
2,3
3,2
5
10
2 x
2 x
1 x
2 x
2 x
1 x
1 x
2 x
JUMLAH
Total
Progress
39,8 MW
583
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
65,00%
544 MW
MW
Tabel 4.133
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sulawesi Tengah
NO.
1
2
3
4
DARI
KE
TEGANGAN
(kV)
PANJANG
(kms)
360
360
140
280
20
440
PLTGU Senoro
Tentena
275
Talise
PLTA Poso
PLTU Palu (Kemitraan)
JUMLAH 275 kV
Pasang Kayu
Parigi
Incomer (Talise - Pasang Kayu)
JUMLAH 150 kV
150
150
150
PROGRESS
(%)
COD
2013
2010
2011
2011
Tabel 4.134
Rencana Pengembangan Gardu Induk Provinsi Sulawesi Tengah
NO.
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
PROGRESS
(%)
100
1
2
Talise Ext LB
Parigi Ext LB
150/70
150/70
Jumlah 150/70 kV
New
New
60
60
120
3
4
5
150/20
150/20
150/20
Jumlah 150/20 kV
New
Extension
Extension
20
30
20
70
100
COD
2010
2010
2010
2010
2014
122
Tabel 4.135
Program Listrik Perdesaan Provinsi Sulawesi Tengah
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.100
13.500
13.500
13.525
13.575
350
350
350
350
PLTS Terpusat 15 kW
PLTMH (kW)
80
380/16.750
350/17.000
850
1,000
-
380/18.500
400/19.500
850
360/17.500
920
1,000
1,100
1,000
1,050
1,140
1,180
4/1.000
2/500
1/250
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
583
800
190
823,1
153,8
11,5
57.200
8
1.480
0
1.870
89.250
4.720
5.370
7
1.750
40,1
3,2
7,7
19,6
108,6
85,5
1,1
1.254,2
123
SISTEM PASANGKAYU
Kapasitas terpasang : 0,84 MW
Daya mampu
: 0,74 MW
Beban puncak
: 0,56 MW
Surplus
: 0,18 MW
SISTEM MAMASA
Kapasitas terpasang : 0,80 MW
Daya mampu
: 0,70 MW
Beban puncak
: 0,42 MW
Surplus
: 0,28 MW
124
Tabel 4.137
Neraca Daya Sulawesi Selatan, Sulawesi Tenggara dan Sulawesi Barat
Uraian
2010
Kebutuhan
Rumah Tangga
2011
2012
2013
2014
GWH
1.622
1.712
1.803
1.896
1.992
Komersial
GWH
533
588
650
718
793
Publik
GWH
336
368
403
441
483
Industri
GWH
791
843
903
967
1.037
GWH
3.282
3.512
3.758
4.022
4.305
6,9
7,0
7,0
7,0
Total Kebutuhan
Pertumbuhan
7,0
2,0
2,0
2,0
2,0
2,0
14,8
14,7
14,6
14,0
14,4
Beban Puncak
Daya Terpasang
MW
MW
782
836
894
952
1.022
460
778
1.055
1.265
1.317
Daya Tambahan
MW
327
293
231
77
231
Cadangan Daya
MW
235
393
391
526
12,8
12,7
12,6
12,5
12,4
Pendek
Jangka
Menengah/Panjang
Mamuju
2 x
JUMLAH
Total
- MW
Progress
MW
COD
Keterangan
2014
IPP
14 MW
14
MW
Tabel 4.139
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sulawesi Barat
NO.
1
DARI
Mamuju
KE
Pasang Kayu
JUMLAH
TEGANGAN
(kV)
PANJANG
(kms)
150
160
160
PROGRESS
(%)
COD
2011
125
Tabel 4.140
Rencana Pengembangan Gardu Induk Provinsi Sulawesi Barat
NO.
1
2
3
4
5
RASIO TRAFO
(kV)
LOKASI
Pasang Kayu (GI Baru)
Polmas
Pasang Kayu Ext LB
Mamuju Ext LB
Mamuju
NEW/EXTENSION
150/20
150/20
150/20
150/20
150/20
Jumlah
New
Extension
Extension
Extension
Relokasi
KAPASITAS
(MVA)
30
30
2LB
2LB
30
90
PROGRESS
(%)
95,79
COD
2010
2010
2011
2011
2014
Tabel 4.141
Program Listrik Perdesaan Provinsi Sulawesi Barat
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.700
5.500
5.500
5.525
5.550
250
300
300
300
PLTS Terpusat 15 kW
PLTMH (kW)
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
14
160
90
29,4
27,2
5,4
23.770
8
1.150
-
51,3
3,2
6,3
-
122,8
126
SISTEM INTERKONEKSI
SULAWESI SELATAN
Kapasitas terpasang : 635,24 MW
Daya mampu
: 447,77 MW
Beban puncak
: 552,92 MW
Defisit
:-105,15 MW
SISTEM SELAYAR
Kapasitas terpasang : 6,49 MW
Daya mampu
: 3,80 MW
Beban puncak
: 2,70 MW
Surplus
: 1,10 MW
Tabel 4.143
Neraca Daya Sulawesi Selatan, Sulawesi Tenggara dan Sulawesi Barat
Uraian
Kebutuhan
Rumah Tangga
2010
2011
2012
2013
2014
GWH
1.622
1.712
1.803
1.896
1.992
Komersial
GWH
533
588
650
718
793
Publik
GWH
336
368
403
441
483
Industri
GWH
791
843
903
967
1.037
GWH
3.282
3.512
3.758
4.022
4.305
6,9
7,0
7,0
7,0
Total Kebutuhan
Pertumbuhan
7,0
2,0
2,0
2,0
2,0
2,0
14,8
14,7
14,6
14,0
14,4
Beban Puncak
Daya Terpasang
MW
MW
782
836
894
952
1.022
460
778
1.055
1.265
1.317
Daya Tambahan
MW
327
293
231
77
231
Cadangan Daya
MW
235
393
391
526
12,8
12,7
12,6
12,5
12,4
128
Tabel 4.144
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Sulawesi Selatan
Rencana
PLTM
PLTD
PLTD/G
PLTM
PLTGU
PLTU
PLTGU
PLTD
PLTU
PLTD
PLTU
PLTU
Pendek
Ranteballa
MFO Sulsel (sewa)
HSD Sulsel (sewa)
Sulsel
Sengkang, Open Cycle
Sulsel (Barru)
Sengkang
Selayar
Sulsel - 1 / Jeneponto Bosowa
Selayar
Takalar
Selayar
JUMLAH
Total
2 x 1,2
6 x 12,5
126
8
60
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
2 x
2 x
1 x
2 x
2 x
271,4 MW
965
50
180
2
200
2
100
4
Progress
COD
Keterangan
97,00%
5,00%
Akhir 2009
2010
2010
2010
2010
2011
2011
2012
2012
2014
2014
2014
IPP
PLN
PLN
PLN
IPP
Perpres 71
IPP
PLN
IPP
PLN
PLN
IPP
MW
MW
MW
MW
MW
MW
MW
40%
694 MW
MW
Tabel 4.145
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sulawesi Selatan
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
DARI
Sidrap
Maros (New)
Tanjungbunga
Sengkang
Siwa/Kera (New)
Sengkang
Tallo Lama
PLTU Sulsel (Perpres)/Barru
PLTU Takalar (Perpres 2)
PLTU Takalar (Perpres 2)
Palopo
Wotu (New)
PLTU Jeneponto (IPP-Bosowa)
PLTA Malea
KE
TEGANGAN
(kV)
PANJANG
(kms)
PROGRESS
(%)
150
150
150
150
150
150
150
150
150
150
150
150
150
150
308
64
23
130
160
70
10
4,62
20
20
170
100
4
70
1.154
54,49
50,97
98,98
Maros (New)
Sungguminasa
Bontoala
Siwa /Kera (New)
Palopo
Sidrap
Bontoala
Incomer 2 phi
Tip. 157
Tip. 158
Wotu (New)
Malili (New)
PLTU Takalar (Perpres 2)
Makale
JUMLAH
41,6
COD
2009
2009
2009
2010
2010
2010
2010
2010
2011
2011
2012
2012
2013
2013
Tabel 4.146
Rencana Pengembangan Gardu Induk Provinsi Sulawesi Selatan
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
LOKASI
Maros (GI Baru)
Sidrap Ext LB
Sungguminasa Ext LB
Tello
Bontoala (Uprating 150 kV)
Tanjung Bunga Ext LB
Sungguminasa
Pare-pare
Bulukumba
Barru
Palopo Ext LB
Sengkang Ext LB
Sengkang
Jeneponto
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
NEW/EXTENSION
New
Extension
Extension
Extension
New
Extension
Extension
Relokasi
Extension
Extension
Extension
Extension
Extension
Extension
KAPASITAS
(MVA)
30
2LB
2LB
60
60
2LB
60
30
30
30
2LB
2LB
30
30
PROGRESS
(%)
100
100
COD
2009
2009
2009
2009
2009
2009
2009
2009
2009
2010
2010
2010
2010
2010
129
NO.
LOKASI
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Mandai
Borongloe
RASIO TRAFO
(kV)
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
70/20
70/20
Jumlah 70/20 kV
NEW/EXTENSION
New
Extension
Extension
Relokasi
Extension
Extension
Extension
Extension
New
Extension
New
Relokasi
Extension
Extension
Extension
Extension
Relokasi
Extension
Extension
New
Relokasi
Relokasi
KAPASITAS
(MVA)
30
30
60
20
60
30
30
120
30
2LB
30
30
2LB
2LB
2LB
60
30
60
30
30
1.040
20
20
40
PROGRESS
(%)
100
100
23,36
COD
2010
2010
2010
2011
2011
2011
2012
2012
2012
2012
2012
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
2014
Tabel 4.147
Program Listrik Perdesaan Provinsi Sulawesi Selatan
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.500
5.500
5.500
5.525
5.550
250
300
326
350
300
300
300
300
PLTS Terpusat 15 Kw
PLTMH (kW)
100
330/15.250
360/17.250
1.250
1.250
1.300
1.350
1.400
900
900
1.000
1.210
1.370
*)
350/16.000
4/1.500
6/2.000
4/1.000
380/18.250
2/500
400/19.250
2/500
130
Tabel 4.148
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Sulawesi Selatan
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Cat: jaringan termasuk Prov. Sulbar
Volume
965
1.154
1.080
23.575
8
1.326
1.200
1.820
86.000
6.550
5.380
18
5.500
1.179,7
202,9
56,8
16,5
3,2
6,7
7,2
18,4
109,8
55,7
2,7
1.659,8
131
Gambar 4.27
Kondisi Kelistrikan Provinsi Sulawesi Tenggara
SISTEM LASUSUA
Kapasitas terpasang : 0,76 MW
Daya mampu
: 0,74 MW
Beban puncak
: 0,47 MW
Surplus
: 0,27 MW
SISTEM KENDARI
Kapasitas terpasang : 55,83 MW
Daya mampu
: 32,75 MW
Beban puncak
: 37,45 MW
Defisit
: -4,70 MW
SISTEM KOLAKA
Kapasitas terpasang : 9,52 MW
Daya mampu
: 7,06 MW
Beban puncak
: 8,10 MW
Defisit
: -1,04 MW
SISTEM LAMBUYA
Kapasitas terpasang : 7,57 MW
Daya mampu
: 4,40 MW
Beban puncak
: 4,20 MW
Surplus
: 0,20 MW
SISTEM KASSIPUTE
Kapasitas terpasang : 2,12 MW
Daya mampu
: 0,90 MW
Beban puncak
: 0,55 MW
Surplus
: 0,35 MW
SISTEM BAUBAU-BAU
Kapasitas terpasang : 19,87 MW
Daya mampu
: 12,05 MW
Beban puncak
: 9,91 MW
Surplus
: 2,14 MW
SISTEM WANGIWANGI-WANGI
Kapasitas terpasang : 2,63 MW
Daya mampu
: 1,11 MW
Beban puncak
: 1,07 MW
Surplus
: 0,04 MW
SISTEM RAHA
Kapasitas terpasang : 14,21 MW
Daya mampu
: 6,78 MW
Beban puncak
: 5,68 MW
Surplus
: 1,10 MW
2010
2011
2012
2013
2014
GWH
1.622
1.712
1.803
1.896
1.992
Komersial
GWH
533
588
650
718
793
Publik
GWH
336
368
403
441
483
Industri
GWH
791
843
903
967
1.037
GWH
3.282
3.512
3.758
4.022
4.305
6,9
7,0
7,0
7,0
Total Kebutuhan
Pertumbuhan
7,0
2,0
2,0
2,0
2,0
2,0
14,8
14,7
14,6
14,0
14,4
Beban Puncak
Daya Terpasang
MW
MW
782
836
894
952
1.022
460
778
1.055
1.265
1.317
Daya Tambahan
MW
327
293
231
77
231
Cadangan Daya
MW
235
393
391
526
12,8
12,7
12,6
12,5
12,4
132
Pendek
10
16
2
4
9
3
2
10
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
MW
MW
2 x
1 x
2 x
2 x
1 x
56,0 MW
181
2
0,8
0,5
10
5
2,4
10
2
5
10
25
2
5
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
69%
24,15%
17,33%
18,21%
69%
COD
Keterangan
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2012
2012
2012
2013
2013
2013
2013
2014
2014
Sewa
PLN
PLN
PLN
PLN
PLN
PLN
Perpres 71
PLN
PLN
PLN
Perpres 71
PLN
PLN
IPP
PLN
IPP
IPP
IPP
PLN
IPP
125 MW
MW
133
Tabel 4.151
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Sulawesi Tenggara
NO.
DARI
1
2
3
4
Kendari
PLTU Kolaka
Unahaa
PLTU Kendari
KE
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
70
20
200
30
320
50
50
Unahaa (New)
Kolaka
Kolaka (New)
Kendari
JUMLAH 150 kV
Kendari
JUMLAH 70 kV
70
PROGRESS
(%)
COD
2011
2012
2012
2013
2010
Tabel 4.152
Rencana Pengembangan Gardu Induk Provinsi Sulawesi Tenggara
NO.
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
KAPASITAS
(MVA)
PROGRESS
(%)
COD
Kendari 150 kV
150/70
Jumlah 150/70 kV
New
60
60
2011
2
3
4
5
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
New
New
New
Extension
30
30
30
30
120
2011
2012
2012
2013
6
7
8
70/20
70/20
70/20
Jumlah 70/20 kV
New
New
Extension
20
30
30
80
2009
2009
2009
Tabel 4.153
Program Listrik Perdesaan Provinsi Sulawesi Tenggara
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
4.100
15.500
15.500
15.525
15.575
PLTMH (kW)
350
350
350
350
160
160
250
250
PLTS Terpusat 15 kW
420/20.750
440/21.750
470/23.250
490/24.250
420/20.750
1.300
1.290
1.350
1.430
1.560
1.200
1.200
1.300
1.450
1.500
2/500
2/500
2/500
2/500
2/250
134
Tabel 4.154
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Sulawesi Tenggara
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
181
370
260
298,2
50,8
19,4
66.200
12
1.400
820
2.240
110.750
6.930
6.650
10
2.250
46,4
4,8
7,7
4,9
24,6
149,1
79,1
1,2
686,2
135
Gambar 4.28
Kondisi Kelistrikan Provinsi Nusa Tenggara Barat
SISTEM LOMBOK
Kapasitas terpasang : 117,93 MW
Daya mampu
: 82,95 MW
Beban puncak
: 112,10 MW
Defisit
: -29,15 MW
SISTEM BIMA
Kapasitas terpasang : 26,94 MW
Daya mampu
: 18,56 MW
Beban puncak
: 22,50 MW
Defisit
: -3,94 MW
SISTEM SUMBAWA
Kapasitas terpasang : 30,37 MW
Daya mampu
: 19,81 MW
Beban puncak
: 21,55 MW
Deffisit
: -1,75 MW
2010
2011
2012
2013
2014
GWh
426
460
498
541
587
Komersial
GWh
131
143
156
170
185
Publik
GWh
73
78
83
88
93
Industri
GWh
12
13
14
15
17
GWh
643
695
751
814
882
Total Kebutuhan
Pertumbuhan
7,4
8,0
8,2
8,3
8,3
5,0
5,0
5,0
5,0
5,0
12,3
12,2
12,1
12,0
12,0
Beban Puncak
Daya Terpasang
MW
MW
156
168
181
196
213
85
167
226
269
385
Daya Tambahan
MW
85
64
49
125
60
Cadangan Daya
MW
14
63
94
197
233
7,3
7,2
7,1
7,0
7,0
136
Pendek
15
20
10
2
10
3
25
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
MW
3,00%
3,00%
3,00%
3,00%
2 x
2 x
1 x
2 x
1 x
2 x
85,0 MW
383
Progress
0,9
25
10
1,7
1,5
7
10
25
30
10
25
10
25
15
25
10
15
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
5%
7%
COD
Keterangan
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2012
2012
2012
2013
2013
2013
2013
2013
2013
2014
2014
2014
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
Perpres 71
Perpres 71
IPP
IPP
PLN
IPP
IPP
PLN
PLN
PLN
IPP
IPP
IPP
PLN
IPP
IPP
298 MW
MW
137
Tabel 4.157
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Nusa Tenggara Barat
NO.
DARI
1
2
3
4
5
6
7
8
Ampenan
Jeranjang
Sengkol
Sengkol
PLTU IPP
Ampenan
Selong
PLTP Sembalun
9
10
11
12
13
14
15
PLTU Bonto
Ni'u/Bima
PLTU Badas
Labuhan
PLTP Hu'u
PLTU Sumbawa
PLTU Sumbawa
KE
TEGANGAN
(kV)
PANJANG
(kms)
150
150
150
150
150
150
150
150
13
52
52
48
26
48
36
60
335
23
75
38
165
61
17
96
474
Jeranjang
Sengkol
Selong
Kuta
Selong
Tanjung
Pringgabaya
GI Pringgabaya
JUMLAH 150 kV
Ni'u/Bima
Dompu
Incomer (Labuhan -Tano)
Tano
Dompu
Labuhan
Tano
JUMLAH 70 kV
70
70
70
70
70
70
70
PROGRESS
(%)
COD
2010
2010
2010
2010
2011
2011
2011
2013
2010
2010
2010
2010
2014
2012
2012
Tabel 4.158
Rencana Pengembangan Gardu Induk Provinsi Nusa Tenggara Barat
NO.
LOKASI
RASIO TRAFO
(kV)
150/20
150/20
NEW/EXTENSION
New
New
KAPASITAS
(MVA)
30
30
PROGRESS
(%)
COD
1
2
Ampenan
Jeranjang
2010
2010
3
4
5
6
7
8
9
Sengkol
Selong
Kuta
Tanjung
Pringgabaya
Ampenan
Ampenan
150/20
150/20
150/20
150/20
150/20
150/20
150/20
Jumlah 150/20 kV
New
New
New
New
New
Extension
Extension
60
30
30
30
30
30
30
300
2010
2010
2010
2011
2011
2012
2013
10
11
12
13
14
15
Dompu
Ni'u/Bima
Labuhan
Tano
Labuhan
Dompu
70/20
70/20
70/20
70/20
70/20
70/20
Jumlah 70/20 kV
New
New
New
New
Extension
Extension
30
30
30
20
30
20
160
2010
2010
2010
2011
2012
2012
Tabel 4.159
Program Listrik Perdesaan Provinsi Nusa Tenggara Barat
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.900
17.500
17.550
17.555
17.600
PLTS Terpusat 15 kW
100
500
500
500
550
600
600
650
650
PLTMH (kW)
PLT ANGIN (kW)
Pem. Gardu Distribusi (Unit/kVA)
550/27.500
550/27.500
560/28.000
580/29.000
600/30.000
1.125
1.100
1.200
1.250
1.330
1.150
1.150
1.160
1.350
1.450
2/500
2/500
2/500
2/500
138
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
383
809
460
655,2
33,9
28,6
74.105
13
2.150
2.500
2.840
142.000
6.005
6.260
8
2.000
51,9
5,0
8,8
15,0
27,3
194,9
101,0
2,0
1.123,5
139
Gambar 4.29
Kondisi Kelistrikan Provinsi Nusa Tenggara Timur
SISTEM ENDE
Kapasitas terpasang : 9,49 MW
Daya mampu
: 6,24 MW
Beban puncak
: 4,95 MW
Surplus
: 1,28 MW
SISTEM KALABAHI
Kapasitas terpasang : 3,98 MW
Daya mampu
: 2,29 MW
Beban puncak
: 2,49 MW
Defisit
: -0,20 MW
SISTEM ATAMBUA
Kapasitas terpasang : 5,74 MW
Daya mampu
: 3,70 MW
Beban puncak
: 4,20 MW
Defisit
: -0,50 MW
SISTEM LABUHANBAJO
Kapasitas terpasang : 1,70 MW
Daya mampu
: 1,70 MW
Beban puncak
: 1,25 MW
Surplus
: 0,45 MW
SISTEM LARANTUKA
Kapasitas terpasang : 4,57 MW
Daya mampu
: 3,25 MW
Beban puncak
: 2,37 MW
Surplus
: 0,88 MW
SISTEM RUTENG
Kapasitas terpasang : 4,88 MW
Daya mampu
: 2,87 MW
Beban puncak
: 3,67 MW
Defisit
: -0,80 MW
SISTEM BAJAWA
Kapasitas terpasang : 4,41 MW
Daya mampu
: 2,19 MW
Beban puncak
: 2,67 MW
Defisit
: -0,48 MW
SISTEM WAITABULA
Kapasitas terpasang : 1,41 MW
Daya mampu
: 0,59 MW
Beban puncak
: 0,75 MW
Defisit
: -0,16 MW
SISTEM KUPANG
Kapasitas terpasang : 45,72 MW
Daya mampu
: 38,35 MW
Beban puncak
: 30,48 MW
Surplus
:
7,87 MW
SISTEM MAUMERE
Kapasitas terpasang : 8,44 MW
Daya mampu
: 6,32 MW
Beban puncak
: 5,87 MW
Surplus
: 0,45 MW
SISTEM SOE
Kapasitas terpasang : 3,97 MW
Daya mampu
: 2,39 MW
Beban puncak
: 2,99 MW
Defisit
: -0,60 MW
SISTEM LEWOLEBA
Kapasitas terpasang : 2,42 MW
Daya mampu
: 1,46 MW
Beban puncak
: 1,61 MW
Defisit
: -0,15 MW
SISTEM WAINGAPU
Kapasitas terpasang : 4,84 MW
Daya mampu
: 3,08 MW
Beban puncak
: 3,40 MW
Defisit
: -0,32 MW
SISTEM WAIKABUBAK
Kapasitas terpasang : 3,02 MW
Daya mampu
: 1,10 MW
Beban puncak
: 1,17 MW
Defisit
: -0,07 MW
SISTEM BA
BAA/LOBALAIN
Kapasitas terpasang : 2,30 MW
Daya mampu
: 1,39 MW
Beban puncak
: 1,64 MW
Defisit
: 13
-0,25 MW
SISTEM KEFAMENANU
Kapasitas terpasang : 4,49 MW
Daya mampu
: 2,10 MW
Beban puncak
: 2,75 MW
Defisit
: -0,65 MW
140
2010
2011
2012
2013
2014
GWh
222
237
255
273
294
Komersial
GWh
89
97
105
113
122
Publik
GWh
66
70
75
81
86
Industri
GWh
10
10
10
10
11
GWh
386
415
445
478
513
Total Kebutuhan
Pertumbuhan
7,5
7,4
7,4
7,3
7,3
7,3
7,2
7,1
7,0
7,0
2,0
2,0
2,0
2,0
2,0
9,3
9,2
9,1
9,0
9,0
Beban Puncak
Daya Terpasang
MW
MW
98
106
113
121
130
42
67
145
155
170
Daya Tambahan
MW
26
80
15
19
53
Cadangan Daya
MW
-30
41
47
53
92
141
Tabel 4.162
Rencana Penambahan Kapasitas Pembangkit Tenaga Listrik
Provinsi Nusa Tenggara Timur
Rencana
PLTB
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTD
PLTP
PLTP
PLTD
PLTD
PLTMH
PLTP
PLTU
PLTU
PLTU
PLTM
PLTD
PLTD
PLTD
PLTD
PLTP
PLTP
PLTM
PLTD
PLTD
PLTD
PLTD
PLTP
PLTB
PLTB
PLTD
PLTD
PLTD
PLTD
PLTD
PLTP
PLTP
PLTP
PLTU
PLTU
Maubesi
MFO (Relokasi)
Atambua
Kalabahi
Waingapu
Soe
HSD Ruteng (sewa)
HSD Bajawa (sewa)
HSD Soe (sewa)
HSD Kefamenanu (sewa)
HSD Atangbua (sewa)
HSD Larantuka (sewa)
HSD Maumere (sewa)
HSD Sumba Timur (sewa)
Adonara
Ulumbu (ADB)
Aulumbu (APBN)
Lembata
Ende
Mauhau
Ulumbu
Atambua
2 NTT (Kupang Baru)
1 NTT (Ropa-Ende)
Wanokaka
Sabu
Rote Ndao
Adonara
Maumere
Ulumbu
Bukapiting
Kambaniru
MFO New Kupang
Lembata
Ende
Larantuka
Oka Larantuka
Mondu
Maubesi
New Atambua
Bajawa
Labuan Bajo
Maumere
Larantuka
Bukapiting
Atadei
Sukoria
Larantuka
Waingapu
JUMLAH
Total
Pendek
0,5
4
2
0,8
1
2
0,8
0,5
0,5
0,8
0,85
0,3
0,8
0,5
0,5
5
5
Jangka
Menengah/Panjang
Progress
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
4 x
2 x
2 x
2 x
2 x
2
2
2
2
25,9 MW
192
x
x
x
x
1
2,5
0,5
3
6
16,5
7
1,6
0,3
0,5
0,5
2,5
3
6
2
7,5
1
2,5
2,5
3
0,5
0,5
7,5
2,5
2,5
2,5
2,5
6
2,5
2,5
4
4
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
27,51%
1,56%
6%
74%
27,51%
COD
Keterangan
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
2014
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
Perpres 71
Perpres 71
IPP
PLN
PLN
PLN
PLN
PLN
PLN
IPP
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
PLN
IPP
IPP
IPP
IPP
166 MW
MW
142
Tabel 4.163
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Nusa Tenggara Timur
NO.
1
2
3
4
5
6
7
DARI
KE
TEGANGAN
(kV)
PANJANG
(kms)
70
70
70
70
70
70
70
21
62
102
61
10
230
30
516
Maulafa
Naibonat
Nonohamis/Soe
Atambua
Incomer (Ende-Maumere)
Maumere
Ropa
JUMLAH
PROGRESS
(%)
COD
2010
2010
2010
2010
2010
2010
2014
Tabel 4.164
Rencana Pengembangan Gardu Induk Provinsi Nusa Tenggara Timur
NO.
1
2
3
4
5
6
7
8
9
LOKASI
RASIO TRAFO
(kV)
NEW/EXTENSION
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
70/20
Jumlah
New
New
New
New
New
New
New
New
New
KAPASITAS
(MVA)
PROGRESS
(%)
60
20
20
20
20
20
20
10
20
210
COD
2010
2010
2010
2010
2010
2010
2010
2010
2010
Tabel 4.165
Program Listrik Perdesaan Provinsi Nusa Tenggara Timur
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
4753
20000
19760
19000
18950
PLTMH (kW)
450
500
500
500
600
600
650
650
PLTS Terpusat 15 kW
400/21.250
370/20.500
400/22.000
430/23.500
450/24.500
1.550
1.620
1.750
1.900
1.500
1.500
1.600
1.750
1.800
4/1.000
4/1.000
1.530
4/1.000
3/750
2/500
143
Tabel 4.166
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Nusa Tenggara Timur
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
192
516
210
361,0
17,1
15,0
82.463
14
1.950
2.500
2.050
111.750
7.350
8.150
17
4.250
57,8
5,6
10,7
15,0
20,1
205,0
87,0
1,7
795,9
144
Gambar 4.30
Kondisi Kelistrikan Provinsi Maluku
SISTEM NAMLEA
Kapasitas terpasang : 5,03 MW
Daya mampu
: 2,16 MW
Beban puncak
: 1,98 MW
Surplus
: 0,18 MW
SISTEM MAKO
Kapasitas terpasang : 2,26 MW
Daya mampu
: 1,49 MW
Beban puncak
: 1,22 MW
Surplus
: 0,27 MW
SISTEM PIRU
Kapasitas terpasang : 2,81 MW
Daya mampu
: 1,94 MW
Beban puncak
: 1,49 MW
Surplus
: 0,45 MW
SISTEM BULA
Kapasitas terpasang : 1,10 MW
Daya mampu
: 0,84 MW
Beban puncak
: 0,78 MW
Surplus
: 0,06 MW
SISTEM MASOHI
Kapasitas terpasang : 6,82 MW
Daya mampu
: 3,90 MW
Beban puncak
: 3,60 MW
Surplus
: 0,30 MW
SISTEM AMBON
Kapasitas terpasang : 63,07 MW
Daya mampu
: 26,50 MW
Beban puncak
: 28,55 MW
Defisit
: -2,05 MW
SISTEM DOBO
Kapasitas terpasang : 2,90 MW
Daya mampu
: 1,22 MW
Beban puncak
: 1,12 MW
Surplus
: 0,10 MW
SISTEM TUAL
Kapasitas terpasang : 10,39 MW
Daya mampu
: 5,40 MW
Beban puncak
: 4,90 MW
Surplus
: 0,50 MW
SISTEM SAUMLAKI
Kapasitas terpasang : 2,62 MW
Daya mampu
: 1,68 MW
Beban puncak
: 1,43 MW
Surplus
: 0,25 MW
SISTEM LANGGUR
Kapasitas terpasang : 10,39 MW
Daya mampu
: 4,50 MW
Beban puncak
: 1,65 MW
Surplus
: 2,85 MW
2010
2011
2012
2013
2014
GWH
327
360
393
427
462
Komersial
GWH
83
87
90
93
97
Publik
GWH
71
76
81
87
94
Industri
GWH
Total Kebutuhan
Pertumbuhan
10
GWH
489
530
572
616
663
7,5
8,4
8,0
7,7
7,5
7,8
7,7
7,6
7,5
7,5
2,0
2,0
2,0
2,0
2,0
9,8
9,7
9,6
9,5
9,5
Beban Puncak
Daya Terpasang
MW
MW
108
116
126
135
145
43
106
123
128
204
Daya Tambahan
Cadangan Daya
MW
MW
64
42
20
10
9
6
80
73
47
106
145
Pendek
10
25
2
2
Jangka
Menengah/Panjang
MW
MW
MW
MW
2
2
2
2
39,0 MW
120
x
x
x
x
0,5
2,5
2,5
6
2
1
10
15
4
4
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
3,00%
3,00%
3,00%
3,00%
2010
2010
2010
2010
2012
2012
2012
2013
2013
2013
2013
2013
2013
2014
PLN
PLN
PLN
PLN
PLN
IPP
IPP
PLN
PLN
PLN
PLN
Perpres 71
IPP
IPP
0%
81 MW
MW
146
Tabel 4.169
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Maluku
NO.
1
2
3
4
5
6
DARI
KE
PLTU Waai
PLTU Waai
Passo
Masohi
PLTA Isal II
PLTP Tulehu
TEGANGAN
(kV)
PANJANG
(kms)
70
70
70
70
70
70
55
33
42
43
186
40
399
Sirimao
Passo
Sirimao
Kairatu
Masohi
Incomer Waai - Paso
JUMLAH
PROGRESS
(%)
COD
2010
2010
2010
2011
2014
2013
Tabel 4.170
Rencana Pengembangan Gardu Induk Provinsi Maluku
NO.
1
2
3
4
5
RASIO TRAFO
(kV)
LOKASI
Sirimao (GI Baru)
Passo (GI Baru)
Masohi (GI Baru)
Kairatu (GI Baru)
Sirimao
NEW/EXTENSION
70/20
70/20
70/20
70/20
70/20
Jumlah
KAPASITAS
(MVA)
New
New
New
New
Extension
PROGRESS
(%)
40
20
20
20
30
130
COD
2010
2010
2011
2011
2014
Tabel 4.171
Program Listrik Perdesaan Provinsi Maluku
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
2.850
12.000
12.100
12.100
12.120
PLTMH (kW)
100
100
150
180
160
160
240
240
PLTS Terpusat 15 kW
295/15.750
270/14.500
640
560
6/2.250
640
280/15.000
660
310/16.500
330/17.500
750
800
720
600
660
660
3/750
2/500
2/500
147
Tabel 4.172
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Maluku
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
120
399
130
186,2
30,8
8,9
29.370
8
530
800
1.485
79.250
3.490
3.200
13
4.000
35,8
3,2
2,9
4,8
18,5
108,9
60,6
2,5
463,3
148
Gambar 4.31
Kondisi Kelistrikan Provinsi Maluku Utara
SISTEM TERNATE
Kapasitas terpasang : 17,80 MW
Daya mampu
: 11,20 MW
Beban puncak
: 13,70 MW
Surplus
: -2,50 MW
SISTEM TOBELO
Kapasitas terpasang : 5,87 MW
Daya mampu
: 2,85 MW
Beban puncak
: 3,55 MW
Defisit
: -0,70 MW
SISTEM JAILOLO
Kapasitas terpasang : 3,19 MW
Daya mampu
: 1,45 MW
Beban puncak
: 1,72 MW
Defisit
: -0,27 MW
SISTEM SUBAIM
Kapasitas terpasang : 1,09 MW
Daya mampu
: 0,37 MW
Beban puncak
: 0,66 MW
Surplus
: 0,29 MW
SISTEM MABAMABA-BULI
Kapasitas terpasang : 0,75 MW
Daya mampu
: 0,71 MW
Beban puncak
: 0,35 MW
Surplus
: 0,36 MW
SISTEM WEDA
Kapasitas terpasang : 0,89 MW
Daya mampu
: 0,76 MW
Beban puncak
: 0,32 MW
Surplus
: 0,44 MW
SISTEM PATANI
Kapasitas terpasang : 0,78 MW
Daya mampu
: 0,44 MW
Beban puncak
: 0,28 MW
Surplus
: 0,16 MW
SISTEM BACAN
Kapasitas terpasang : 2,30 MW
Daya mampu
: 1,90 MW
Beban puncak
: 2,19 MW
Defisit
: -0,29 MW
SISTEM DOFA
Kapasitas terpasang : 1,14 MW
Daya mampu
: 0,41 MW
Beban puncak
: 0,55 MW
Defisit
: -0,14 MW
SISTEM SOFIFI
Kapasitas terpasang : 1,48 MW
Daya mampu
: 0,76 MW
Beban puncak
: 1,08 MW
Defisit
: -0,32 MW
SISTEM SANANA
Kapasitas terpasang : 2,45 MW
Daya mampu
: 1,25 MW
Beban puncak
: 1,30 MW
Defisit
: -0,05 MW
Tabel 4.173
Neraca Daya Sistem Maluku dan Maluku Utara
Uraian
Kebutuhan
Rumah Tangga
2010
2011
2012
2013
2014
GWH
327
360
393
427
462
Komersial
GWH
83
87
90
93
97
Publik
GWH
71
76
81
87
94
Industri
GWH
Total Kebutuhan
Pertumbuhan
10
GWH
489
530
572
616
663
7,5
8,4
8,0
7,7
7,5
7,8
7,7
7,6
7,5
7,5
2,0
2,0
2,0
2,0
2,0
9,8
9,7
9,6
9,5
9,5
Beban Puncak
Daya Terpasang
MW
MW
108
116
126
135
145
43
106
123
128
204
Daya Tambahan
Cadangan Daya
MW
MW
64
42
20
10
9
6
80
73
47
106
149
Pendek
2 x
5
2
2
2
3
2
2
1,5
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
MW
MW
2 x
2 x
2 x
1 x
2 x
24,5 MW
100
1,6
3,2
1,6
14
2
1
3
1
4
1
3
2
4
5
5
7
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
Progress
COD
Keterangan
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
3,00%
2010
2010
2010
2010
2010
2010
2010
2010
2011
2011
2011
2011
2012
2012
2013
2013
2013
2014
2014
2014
2014
2014
2014
2014
PLN
PLN
PLN
PLN
PLN
PLN
PLN
IPP
PLN
PLN
PLN
Perpres 71
IPP
IPP
PLN
PLN
IPP
PLN
PLN
PLN
IPP
IPP
IPP
IPP
18%
75 MW
MW
150
Tabel 4.175
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Maluku Utara
NO.
1
DARI
KE
PLTP Jailolo
TEGANGAN
(kV)
PANJANG
(kms)
70
128
128
Ternate
JUMLAH
PROGRESS
(%)
COD
2014
Tabel 4.176
Program Listrik Perdesaan Provinsi Maluku Utara
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
3.100
13.500
13.600
13.600
13.650
100
100
150
180
240
240
190
240
PLTS Terpusat 15 kW
PLTMH (kW)
40
420/20.750
440/21.750
400/20.750
1.100
1.100
1.210
1.350
1.400
950
1.000
1.000
1.050
1.160
7/3.250
4/1.000
3/750
480/23.750
2/500
500/24.750
2/500
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Volume
100
128
-
168,4
7,9
-
57.450
8
570
910
2.240
111.750
6.160
5.160
18
6.000
40,3
3,3
3,5
5,5
21,0
103,4
83,9
3,1
440,1
151
SISTEM BIAK
Kapasitas terpasang : 13,83 MW
Daya mampu
: 9,25 MW
Beban puncak
: 7,71 MW
Surplus
: 1,54 MW
SISTEM UREFASEI
Kapasitas terpasang : 0,38 MW
Daya mampu
: 0,31 MW
Beban puncak
: 0,13 MW
Surplus
: 0,18 MW
SISTEM JAYAPURA
Kapasitas terpasang : 77,92 MW
Daya mampu
: 36,35 MW
Beban puncak
: 42,89MW
Defisit
: -6,54 MW
SISTEM NABIRE
Kapasitas terpasang : 12,15 MW
Daya mampu
: 4,16 MW
Beban puncak
: 6,80 MW
Defisit
: -2,64 MW
SISTEM TIMIKA
Kapasitas terpasang : 15,14 MW
Daya mampu
: 8,27 MW
Beban puncak
: 9,70 MW
Defisit
: -1,43 MW
SISTEM TANAH MERAH
Kapasitas terpasang : 0,57 MW
Daya mampu
: 0,50 MW
Beban puncak
: 0,20 MW
Surplus
: 0,30 MW
SISTEM MERAUKE
Kapasitas terpasang : 13,21 MW
Daya mampu
: 10,15 MW
Beban puncak
: 9,69 MW
Surplus
: 0,46 MW
152
SISTEM SERUI
Kapasitas terpasang : 5,70MW
Daya mampu
: 2,87 MW
Beban puncak
: 2,79 MW
Surplus
: 0,08 MW
SISTEM WARBOR
Kapasitas terpasang : 0,080 MW
Daya mampu
: 0,076 MW
Beban puncak
: 0,037 MW
Surplus
: 0,039 MW
SISTEM SARMI
Kapasitas terpasang : 2,05 MW
Daya mampu
: 1,50 MW
Beban puncak
: 0,64 MW
Surplus
: 0,86 MW
SISTEM GENYEM
Kapasitas terpasang : 2,03MW
Daya mampu
: 1,34 MW
Beban puncak
: 0,91 MW
Surplus
: 0,43 MW
SISTEM WAMENA
Kapasitas terpasang : 3,01 MW
Daya mampu
: 2,58 MW
Beban puncak
: 2,85 MW
Defisit
: -0,27 MW
SISTEM AGATS
Kapasitas terpasang : 0,28MW
Daya mampu
: 0,20 MW
Beban puncak
: 0,20 MW
Surplus
: 0,00 MW
SISTEM ARSO
Kapasitas terpasang : 2,56 MW
Daya mampu
: 1,30 MW
Beban puncak
: 1,87 MW
Defisit
: -0,57 MW
SISTEM KEP
KEPPI
Kapasitas terpasang : 0,22MW
Daya mampu
: 0,20 MW
Beban puncak
: 0,14 MW
Surplus
: 0,06 MW
2010
2011
2012
2013
2014
Kebutuhan
Rumah Tangga
GWh
408
439
471
504
538
Komersial
GWh
225
249
271
292
312
Publik
GWh
88
93
99
104
109
Industri
GWh
14
14
14
14
14
GWh
735
796
856
915
974
Total kebutuhan
Pertumbuhan
9,4
8,3
7,5
6,9
6,5
9,8
9,7
9,6
9,5
9,4
2,4
2,4
2,4
2,4
2,4
12,2
12,1
12,0
11,9
11,8
Beban Puncak
MW
165
179
192
205
218
Daya Terpasang
MW
30
97
129
183
286
Daya Tambahan
MW
68
35
58
108
40
Cadangan Daya
MW
-67
-47
-5
86
108
153
Pendek
12,5
3,2
6,5
10,5
Jangka
Menengah/Panjang
MW
MW
MW
MW
COD
Keterangan
25,00%
2010
2010
2010
2010
2011
2011
2012
2012
2012
2012
2012
2013
2013
2013
2013
2013
2013
2013
2013
2013
2014
2014
2014
2014
2014
PLN
PLN
PLN
PLN
PLN
Perpres 71
PLN
PLN
PLN
Perpres 71
IPP
PLN
PLN
PLN
PLN
PLN
IPP
IPP
IPP
IPP
PLN
PLN
PLN
PLN
IPP
25,00%
3,00%
2 x
2 x
2 x
1 x
1
2
1
2
x
x
x
x
1 x
32,7 MW
208
Progress
5
10
10
5
7
7
7
10
5
2,6
1,3
2
7
15
7
7
5
5
2,5
2
7
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
12%
0%
175 MW
MW
154
Tabel 4.180
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Papua
NO.
1
2
3
4
DARI
KE
PLTU Hautekamp
PLTA Genyem
PLTU Pomako
PLTU Jayapura
TEGANGAN
(kV)
PANJANG
(kms)
70
70
70
70
40
165
60
90
355
Yarmokh
Waena
Timika
Jayapura
JUMLAH
PROGRESS
(%)
COD
2010
2011
2011
2013
Tabel 4.181
Rencana Pengembangan Gardu Induk Provinsi Papua
NO.
1
2
3
4
5
RASIO TRAFO
(kV)
LOKASI
Yarmokh (GI Baru)
Waena (GI Baru)
Genyem (GI Baru)
Timika (GI Baru)
Yarmokh
NEW/EXTENSION
70/20
70/20
70/20
70/20
70/20
Jumlah
KAPASITAS
(MVA)
New
New
New
New
Extension
PROGRESS
(%)
30
30
20
20
30
130
COD
2010
2011
2011
2011
2012
Tabel 4.182
Program Listrik Perdesaan Provinsi Papua
KEGIATAN
PLTS 50 Wp Tersebar
2010
2011
2012
2013
2014
450
8.000
8.000
8.500
8.025
400
450
450
500
480
560
530
560
PLTS Terpusat 15 kW
PLTMH (kW)
80
450/23.750
450/23.750
480/25.250
500/26.250
520/27.250
1.200
1.200
1.250
1.350
1.450
1.100
1.050
1.140
1.220
1.340
4/1.500
6/2.000
4/1.000
*)
4/1.000
4/1.000
155
Tabel 4.183
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Papua
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
Cat: jaringan termasuk Prov. Papua Barat
Volume
208
355
130
319,6
22,1
9,1
32.975
9
2.130
2.130
2.400
126.250
6.450
5.850
22
6.500
23,1
3,6
13,0
12,8
28,3
175,5
74,6
3,8
685,4
156
Gambar 4.33
Kondisi Kelistrikan Provinsi Papua Barat
SISTEM MANOKWARI
Kapasitas terpasang : 14,28 MW
Daya mampu
: 7,50 MW
Beban puncak
: 10,13 MW
Defisit
: -2,63 MW
SISTEM SORONG
Kapasitas terpasang : 22,23 MW
Daya mampu
: 17,20 MW
Beban puncak
: 17,38 MW
Defisit
: -0,18 MW
SISTEM BINTUNI
Kapasitas terpasang : 0,42 MW
Daya mampu
: 0,42 MW
Beban puncak
: 0,40 MW
Surplus
: 0,02 MW
SISTEM TEMINABUAN
Kapasitas terpasang : 1,10 MW
Daya mampu
: 0,80 MW
Beban puncak
: 0,36 MW
Surplus
: 0,44 MW
SISTEM FAKFAK-FAK
Kapasitas terpasang : 6,25 MW
Daya mampu
: 1,95 MW
Beban puncak
: 1,80 MW
Surplus
: 0,15 MW
SISTEM WONDAMA
Kapasitas terpasang : 0,42 MW
Daya mampu
: 0,42 MW
Beban puncak
: 0,40 MW
Surplus
: 0,20 MW
SISTEM KAIMANA
Kapasitas terpasang : 3,41MW
Daya mampu
: 1,73 MW
Beban puncak
: 1,52 MW
Surplus
: 0,21 MW
2010
2011
2012
2013
2014
Kebutuhan
Rumah Tangga
GWh
408
439
471
504
538
Komersial
GWh
225
249
271
292
312
Publik
GWh
88
93
99
104
109
Industri
GWh
14
14
14
14
14
GWh
735
796
856
915
974
Total kebutuhan
Pertumbuhan
9,4
8,3
7,5
6,9
6,5
9,8
9,7
9,6
9,5
9,4
2,4
2,4
2,4
2,4
2,4
12,2
12,1
12,0
11,9
11,8
Beban Puncak
MW
165
179
192
205
218
Daya Terpasang
MW
30
97
129
183
286
Daya Tambahan
MW
68
35
58
108
40
Cadangan Daya
MW
-67
-47
-5
86
108
157
Pendek
Sanggeng/Manokwari
HSD Sorong (sewa)
HSD Fak-Fak (sewa)
HSD Manokwari (sewa)
Walesi I (ekspansi)
Sorong
Sorong
Walesi II (Cascade)
Andai
Prafi (Manokwari)
Walesi II (Cascade)
Kombemur (Fak-Fak)
Andai
Sorong
Kombemur (Fak-Fak)
Sorong
3,2
10,5
1,5
9
0,5
10
Jangka
Menengah/Panjang
MW
MW
MW
MW
MW
MW
25,00%
3,00%
3,00%
1 x
1 x
1 x
1 x
JUMLAH
Total
34,7 MW
100
Progress
10
1
7
2,5
1
3,3
7
15
3,3
15
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
COD
Keterangan
2010
2010
2010
2010
2010
2010
2011
2012
2012
2013
2013
2013
2013
2013
2014
2014
PLN
PLN
PLN
PLN
PLN
IPP
IPP
PLN
IPP
PLN
PLN
PLN
IPP
IPP
PLN
IPP
65 MW
MW
Tabel 4.186
Rencana Pengembangan Jaringan Transmisi Tenaga Listrik
Provinsi Papua Barat
NO.
1
DARI
PLTU Klain (Sorong)
KE
Sorong
JUMLAH
TEGANGAN
(kV)
PANJANG
(kms)
70
60
60
PROGRESS
(%)
COD
2013
158
Tabel 4.187
Program Listrik Perdesaan Provinsi Papua Barat
KEGIATAN
2010
2011
2012
2013
2014
PLTS 50 Wp Tersebar
1.708
8.000
8.000
8.000
8.025
PLTMH (kW)
400
450
450
500
480
530
530
530
PLTS Terpusat 15 kW
Tabel 4.188
Rekapitulasi Infrastruktur dan Kebutuhan Investasi
Provinsi Papua Barat
No
1
2
3
4
Uraian
Pembangkit Tenaga Listrik (MW)
Transmisi Tenaga Listrik (kms)
Gardu Induk (MVA)
Program EBT dan Jaringan
- PLTS 50 Wp Tersebar
- PLTS Terpusat 15 kW
- PLTMH (kW)
- PLT Angin (kW)
- Gardu Distribusi (Unit/kVA)
- JTM (kms)
- JTR (kms)
- PLTD (Unit/kW)
100
60
146,8
5,0
-
33.733
8
1.800
2.070
23,7
3,2
10,6
12,5
201,7
159