Process Group: Initaiting Keyword: to do for along time Analisa: project charter telah dibuat dan diberikan ke PM. Jadi langkah selanjutnya adalah mendapaktan dukungan dari CEO. Kesalahan: project charter belum dibuat.
Contoh Review 2
Knowledge Area: bab1
Process Group: Initaiting Keyword: the type of PMO least level of control over project Analisa: The type of PMO: Supportive : provide templates, trainging, OPA, EEF. Control is low Controlling : support, compliance. Control is moderate. Directive : control project direcly Kesalahan: karena membacanya can have varying leves of authority jadi dikira yang paling tinggi controlnya. Ternyata pertanyaanya the least level of control
Contoh Review 3
Knowledge Area: stakeholder
Process Group: Initaiting Keyword: project management plan Analisa: di dalam project management plan ada communication plan di mana communication plan itu ada communication matrix yg menjelaskan role dari stakeholder Kesalahan: tidak baca do not have a role in determining
Contoh Review 4
Knowledge Area: time
Process Group: planning Keyword: take most project time and resource Analisa: jika refer to knowledge area actovoty time di dalam planning paling banyak 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule Sehingga memerlukan banyak project time.
Kesalahan: ternyata yg dimaksud adalah process group mana yang palingan
banyak memerlukan time dan resource.
Contoh Review 5
Knowledge Area: stakeholder
Process Group: closing Keyword: documenting, updating records, lesson learned Analisa: activity yang dilakukan adalah documenting, updating records, lesson learned, perfomorming audt dilakukan pada fase close project or phase Kesalahan: ternyata ada performing audit yg da pada close procurement