METODE KERJA KING POST Dibuat Oleh
Disetujui Oleh
7 . Metode Kerja
7.3 Pekerjaan King Post
Distribution List
Daftar Isi
7.3.1 Umum
7.3.2 Spesifikasi
7.3.3 Target Quantity
7.3.4 Sumberdaya dan Alat
7.3.4.1 Tenaga
7.3.4.2 Alat
7.3.5 Material
7.3.6 Schedule
7.3.7 Metode Konstruksi
7.3.7.1 Work Squence (Urutan Kerja)
7.3.7.2 Detail Of Work (Detail Pelaksanaan)
7.3.7.3 Typical Cycle Time For Construction
7.3.8 Tabel Quality Control
7.3.9 Safety Work Analysis
S H E P LA N
: 984
: 1/2
:2
: 31 Januari 2011
: Tito Ari Bawono
: Surachman Ambar
Q S H E PL
No PKP
Halaman
Revisi
Tanggal
Dibuat oleh
Revision Status
Distribution List
Keterangan
Tanggal terima
QSHE P
No PKP
Halaman
Revisi
Tanggal
Dibuat oleh
7.2.1 Umum
Pekerjaan king post dimulai setelah pekerjaan pengecoran bored pile selesai dilaksanakan. Nilai S
pile yang dipasang king post yaitu 22±2. Besar nilai slump ini diatur untuk memudahkan dalam p
pemasangan baja king post.
Pemasangan King Post pada proyek ini sebesar 67,069 Kg.
7.2.2 Spesifikasi
1
Dibuat oleh :
Disetujui :
Dibuat oleh :
Disetujui :
METODE KERJA KING POST
Operator 2
Specialist 3
Harian 3
Welder 2
Surveyer 2
Total 12
Kapasitas
No Nama Alat Jumlah Satuan
1 Theodolite
2 Patok
3 Tali (Rafia/Tambang)
4 Mesin grab
5 Truk Mixer
6 Bucket concrete pump
7 Concrete Water Stop
8 Pipa
9 Pipa Tremi
10 Integral penetron
11 Vibrator
12 Excavator
13 Dump truck
14 Diafragma wall
15 Crane service
16
17
18
19
20
21
22
23
1
2
3
4
5
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :
Dibuat oleh :
Disetujui :
organisasi terlampir 02
Unit Remaks
METODE KERJA KING POST
7.2.6 SCHEDULE
5/21/2018
T O
O N
C
P 39 P 38 P 37 P 36 P 35 P 34 33 32 31 30
JUMLAH TTK 8 8 8 10 8 9 10 8 8 8
PROGRESS 8 8 8 10 8 9 10 8 8 8
SISA VOLUME 0 0 0 0 0 0 0 0 0 0
Time Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri
07/02/11 25 13/02/11 25 20/02/11 25 27/02/11 25 08/03/11 25 15/03/11 25 22/03/11 25 31/03/11 25 07/04/11 25 14/04/11
07/02/11 25 14/02/11 25 21/02/11 25 28/02/11 25 08/03/11 25 15/03/11 25 23/03/11 25 31/03/11 25 07/04/11 25 14/04/11
08/02/11 25 15/02/11 25 22/02/11 25 01/03/11 25 09/03/11 25 16/03/11 25 24/03/11 25 01/04/11 25 08/04/11 25 15/04/11
09/02/11 25 16/02/11 25 23/02/11 25 01/03/11 25 10/03/11 25 17/03/11 25 24/03/11 25 02/04/11 25 09/04/11 25 16/04/11
09/02/11 25 16/02/11 25 23/02/11 25 02/03/11 25 11/03/11 25 18/03/11 25 25/03/11 25 03/04/11 25 10/04/11 25 16/04/11
10/02/11 25 17/02/11 25 24/02/11 25 03/03/11 25 11/03/11 25 18/03/11 25 26/03/11 25 03/04/11 25 10/04/11 25 17/04/11
11/02/11 25 18/02/11 25 25/02/11 25 04/03/11 25 12/03/11 25 19/03/11 25 27/03/11 25 04/04/11 25 11/04/11 25 18/04/11
11/02/11 25 18/02/11 25 25/02/11 25 04/03/11 25 13/03/11 25 20/03/11 25 27/03/11 25 05/04/11 25 12/04/11 25 19/04/11
05/03/11 25 20/03/11 25 28/03/11 25
06/03/11 25 29/03/11 25
5 200.000 5 200 200.00
250 200 225 250 200 200
START 1/24/2011 1/26/2011 2/1/2011 2/8/2011 2/15/2011 2/22/2011 3/3/2011 3/12/2011 3/22/2011 2/24/2011
FINISH 2/8/2011 2/15/2011 2/17/2011 2/19/2011 2/21/2011 3/3/2011 3/12/2011 3/21/2011 3/30/2011 3/3/2011
H
27/08/11 25 18/08/11 25
28/08/11 25 18/08/11 25
19/08/11 25
O
20/08/11 25
JUMLAH TTK 6 7 7 10 12 7 6
T
PROGRESS 6 7 7 10 12 7 6
SISA VOLUME 0 0 0 0 0 0 0
START 9/23/2011 9/15/2011 9/7/2011 8/27/2011 6/24/2011 8/9/2011 5/26/2011
FINISH 9/29/2011 9/22/2011 9/14/2011 9/6/2011 7/6/2011 8/6/2011 8/1/2011
MOB 9/9/2011 7/9/2011
25 24 23 22 21 20 19
30 29 28 26
TOTAL
8 8 10 8 111
8 8 10 8 111
0 0 0 0 0
H Ri H Ri H Ri H
25 21/04/11 25 28/04/11 25 06/05/11 25
25
25
21/04/11
22/04/11
25
25
28/04/11
29/04/11
25
25
07/05/11
07/05/11
25
25 P 25 24 23 22 21 20 19
25 23/04/11 25 30/04/11 25 08/05/11 25
25 23/04/11 25 30/04/11 25 09/05/11 25 7 8 7 12 12 6 6
25 24/04/11 25 01/05/11 25 09/05/11 25 7 8 7 12 12 6 6
25 25/04/11 25 02/05/11 25 10/05/11 25 0 0 0 0 0 0 0
25 26/04/11 25 03/05/11 25 11/05/11 25 4/22/2011 5/24/2011 5/21/2011 5/27/2011 6/8/2011 6/16/2011 5/14/2011
03/05/11 25 5/2/2011 5/17/2011 5/22/2011 6/3/2011 6/20/2011 6/22/2011 5/20/2011
04/05/11 25 6/6/2011
Dibuat oleh:
Disetujui :
H Ri H
25 26/07/11 25
25 26/07/11 25
25 27/07/11 25
25 28/07/11 25
25 28/07/11 25
25 29/07/11 25
TOTAL
6 6 61
6 6 61
0 0 0
5/26/2011 5/14/2011
8/1/2011 5/25/2011
19 18
17 16 15
TOTAL GRAND TOTAL
JUMLAH TTK 10 9 9 28 264
PROGRESS 10 9 9 28 264
SISA VOLUME 0 0 0 0 0
START 4/30/2011 4/19/2011 4/14/2011
FINISH 5/11/2011 4/26/2011 4/28/2011
19 18
TOTAL
6 6 64 JUMLAH TTK
6 6 64 PROGRESS
0 0 0 SISA VOLUME
5/14/2011 5/6/2011
5/20/2011 5/12/2011
5/14/2011 Ri H Ri H Ri H
03/07/11 25 10/07/11 25 18/07/11 25
H Ri H 03/07/11 25 11/07/11 25 19/07/11 25
25 27/06/11 25 04/07/11 25 12/07/11 25 19/07/11 25
25 28/06/11 25 05/07/11 25 12/07/11 25 20/07/11 25
25 28/06/11 25 05/07/11 25 13/07/11 25 21/07/11 25
25 29/06/11 25 06/07/11 25 14/07/11 25 21/07/11 25
25 30/06/11 25 07/07/11 25 15/07/11 25 22/07/11 25
25 01/07/11 25 08/07/11 25 15/07/11 25 23/07/11 25
08/07/11 25 16/07/11 25 24/07/11 25
Feb Mar Apr May Jun Jul Aug Sep Oct
Schdule Detail Jumlah Tiang Mulai Selesai Kapasitas Durasi
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 36 37 38 39 36
P 39 8 7-Feb 11-Feb 1.6 5
P 38 8 12-Feb 17-Feb 1.6 5
P 37 8 18-Feb 23-Feb 1.6 5
P 36 10 23-Feb 2-Mar 1.6 6
P 35 8 3-Mar 8-Mar 1.6 5
P 34 9 8-Mar 14-Mar 1.6 6
15-Mar 21-Mar 1.6 6
H
P 33 10
P 32 8 22-Mar 27-Mar 1.6 5
P 31 8 27-Mar 1-Apr 1.6 5
O
P 30 8 2-Apr 7-Apr 1.6 5
P 29 8 8-Apr 13-Apr 1.6 5
T
P 28 10 13-Apr 20-Apr 1.6 6
P 26 8 20-Apr 25-Apr 1.6 5
21-Apr 25-Apr 1.6 4
N
P 25 A 7
Schedule Detail
O
P 22 A 12 7-May 15-May 1.6 8
P 21 A 12 15-May 23-May 1.6 8
C
P 20 A 6 24-May 27-May 1.6 4
P 19 A 6 28-May 1-Jun 1.6 4
P 18 A 6 1-Jun 5-Jun 1.6 4
P 17 A 10 5-Jun 11-Jun 1.6 6
P 16 A 9 12-Jun 18-Jun 1.6 6
P 15 A 9 18-Jun 24-Jun 1.6 6
P 18 B 6 24-Jun 27-Jun 1.6 4
P 19 B 6 28-Jun 2-Jul 1.6 4
P 20 B 7 2-Jul 7-Jul 1.6 4
P 21 B 12 7-Jul 15-Jul 1.6 8
P 22 B 10 16-Jul 22-Jul 1.6 6
P 23 B 7 23-Jul 27-Jul 1.6 4
P 24 B 7 28-Jul 1-Aug 1.6 4
P 25 B 6 2-Aug 5-Aug 1.6 4
Total 264
Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Operator 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Manpower
Specialist 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Manpower
Harian 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Welder 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Surveyer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Total 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
Oct
37 38 39
1 1
2 2 72
3 3 108
3 3 108
2 2 72
2 2 72
12 12 432
METODE KERJA KING POST
Flow Chart
Pemasangan Follower atau Meja - Follower dikunci dengan WF yang dilas pada casing Bored
King Post
Pemasangan King Post - King Post dimasukkan kedalam follower dengan crane service da
besi yang dilas ke pengait king cross
Dibuat oleh :
`
METODE KERJA KING POST
Boring Rig
Crawler Crane
Hari 2 Hari 3
No. Pile No Item Aktivitas Quantity Unit 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 16 17 18 19 20 21 22 23 24 1 2 3 4 5
H
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
2
Pasang Pipa Tremi
O
2 Jam
4 Pengecoran
5 Pembuangan Lumpur
T
6 Pembersihan
N
1 Persiapan Pembersihan daerah kerja
Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
3
Pasang Pipa Tremi
3
O N
C
2 Jam
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
Q S H E P LA N
No PKP : 984
Halaman : 1/4
Revisi :0
O H
T
2 Jam
2 jam
2 jam
2 jam
2 jam
Pemeriksaan Oleh
Act. Main Activity Spesifikasi dan Referensi Kriteria Wika-Jakon JO
Ref. dokumen yang lain Penerimaan Construction ENG
SC Supervisor QC
Manager
5 Bored Pile Construction
5.1 Position of Bored Pile Shop Drawings Approval/Acceptable H S W - S/R
5.2 Position of Boring Method Statement 7.2 ± 25mm H S W - S/R
5.3 Drilling & Excavation
5.3.1 Excavation Record Method Statement 7.2 Approval/Acceptable - S R W S/R
5.3.2 Verticality of Bored Hole Method Statement 7.2 ≤1/100 S W R - S/R
5.3.3 Depth of Bored Hole Shop Drawings Approval/Acceptable H S R - S/R
5.3.4 Polymer Mixing Viscosity: V V ≥ 42 Sec H S W - W
PH Method Statement 7.2 PH ≥ 8 H S W - W
Density: D D < 1.03 g/cm3 H S W - W
5.3.5 Bottom Cleaning Sedimentation Method Statement 7.2 Less than 10 cm H ` W - S/R
5.4 Reinforcement Bar with Sonic Pipe `
5.4.1 Fabrication Shop Drawings Approval/Acceptable H H S/S - S/R
5.4.2 Splicing Joint Shop Drawings Approval/Acceptable H S W - S/R
5.4.3 Position of Re-Bar Cage Shop Drawings Approval/Acceptable H S W - S/R
5.5 Concreting
5.51 Casting Concrete Method Statement 7.2 Approval/Acceptable - S W - S/R
6 Laboratory Test
6.1 Compressive Concrete Strength Method Statement 7.2 σ 28 ≥ 30 mpa - H S/R W S/R
K: Alat : 3
B: Metode : Pekerja terlalu dekat alat pancang patah tulang,luka berat 4 1 H KEP.174/MEN/1986 4
E: tertabrak,terbentur Bahan : 5
2 Handling material spun pile NR F: Tenaga : patah tulang,luka berat 4 1 H Permenaker RI 04/MEN/1985 2
di lokasi kerja
K: Alat : Sling putus 3
B: Metode : Tidak ada kenek untuk membantu KEP.174/MEN/1986 4
tugas operator alat berat dalam
handling spun pile
H
E: Terjepit,tertimpa,terbentur Bahan :
3 Operasional Pemancangan R F: Getaran Tenaga : Gangguan kesehatan,aset warga 3 3 H 1
rusak UU No. 1 tahun 1970
O
K: Alat : Karakteristik alat Keputusan Menteri 2
Tenaga Kerja Kep.
51/MEN/1999
T
B: Metode : KEP.174/MEN/1986 3
E: Bahan : 4
N T 5
O
F: Kebisingan Tenaga : Gangguan pendengaran 2 3 M UU No. 1 tahun 1970 1
K: Alat : Karakteristik alat Keputusan Menteri 2
C
Tenaga Kerja Kep.
51/MEN/1999
B: Metode : KEP.174/MEN/1986 3
E: Bahan : 4
E: terbentur,terjepit Bahan : 5
TR = Tingkat Resiko
Disetujui oleh, Disetujui oleh,
P2K3 Pusat Kadiv Operasi I
Disetujui :
H
Safety Officer
Untuk saat ini belum memungkinkan tidak ada laporan gangguan Safety Officer
kesehatan
O
Belum memungkinkan tidak ada laporan aset warga Safety Officer
yang rusak
T
Untuk saat ini belum memungkinkan IK,briefing sudah 1 5-Nov-10
dilaksanakan
Instruksi kerja,safety briefing,rambu- Uji baku mutu memenuhi 1 5-Nov-10
rambu,sosialisasi+pendataan terhadap
warga sekitar
N T Belum memungkinkan
Belum memungkinkan
Surachman Ambar