LAPORAN ESTIMASI BIAYA KONSTRUKSI

RUMAH TINGGAL DUA LANTAI

Disusun Oleh:

Fransiskus X.E.H 2015410058


Antonio 2015410155
Stevanus Setyadi 2015410186
Fendy 2016410010
Evan Christopher 2016410021
Steven Winata 2016410033
Andreas Indra Wijaya 2016410034
Nicholas Ryan Bintoro 2016410093
Tryaldi Tama 2016410121
Gabriella Junico 2016410184

Dosen Pembimbing: Yohanes Lim Dwi Adianto, Ir., M.T.

UNIVERSITAS KATOLIK PARAHYANGAN

FAKULTAS TEKNIK PROGRAM STUDI TEKNIK SIPIL

(Terakreditasi Berdasarkan SK BAN-PT Nomor: 1788/SK/BAN-PT/Akred/S/VII/2018)

BANDUNG

2019
DAFTAR ISI

DAFTAR ISI ................................................................................................................ ii


BAB I PENDAHULUAN ............................................................................................ 1
1.1 Latar Belakang .............................................................................................. 1
1.2 Tujuan ........................................................................................................... 1
1.3 Metode dan Teknik Pembahasan .................................................................. 2
1.4 Metodologi .................................................................................................... 2
BAB II DESKRIPSI UMUM PROYEK ..................................................................... 4
2.1 Deskripsi Umum Proyek ............................................................................... 4
2.2 Spesifikasi Teknis ......................................................................................... 6
2.3 Work Breakdown Structure ........................................................................... 6
2.4 Sketsa WBS................................................................................................... 8
BAB III SURAT PENAWARAN KERJA ............................................................... 11
BAB IV KUANTIFIKASI PEKERJAAN ................................................................. 13
IV.1. Pekerjaan Persiapan .................................................................................... 13
IV.2. Pekerjaan Tanah dan Urugan ...................................................................... 13
IV.3. Pekerjaan Beton dan Struktur...................................................................... 14
IV.4. Pekerjaan Kap / Kuda-kuda + Atap ............................................................ 16
IV.5. Pekerjaan Dinding ....................................................................................... 16
IV.6. Pekerjaan Pintu dan Jendela ........................................................................ 17
IV.7. Pekerjaan Plafond........................................................................................ 20
IV.8. Pekerjaan Pengecatan .................................................................................. 20
IV.9. Pekerjaan Finishing Lantai dan Dinding..................................................... 21
IV.10. Pekerjaan Listrik ......................................................................................... 22
IV.11. Pekerjaan Sanitary dan Plumbing ............................................................... 23
IV.12. Pekerjaan Lain-lain ..................................................................................... 25
BAB V REKAPITULASI BIAYA PEMBANGUNAN RUMAH TINGGAL.......... 27
BAB VI HARGA SATUAN ...................................................................................... 28
BAB VII ANALISIS HARGA SATUAN ................................................................. 31
V.1. Pekerjaan Persiapan .................................................................................... 31
V.2. Pekerjaan Tanah dan Urugan ...................................................................... 32
V.3. Pekerjaan Beton dan Struktur...................................................................... 34

ii
V.4. Pekerjaan Atap ............................................................................................ 37
V.5. Pekerjaan Dinding ....................................................................................... 38
V.6. Pekerjaan Lantai + Plint .............................................................................. 39
V.7. Pekerjaan Pengecatan .................................................................................. 43
V.8. Pekerjaan Mechanical Electrical dan Plumbing ......................................... 43
V.9. Pekerjaan Kusen, Pintu, dan Jendela........................................................... 46
V.10. Pekerjaan Pagar ........................................................................................... 48
V.11. Pekerjaan Tangga ........................................................................................ 51
V.12. Pekerjaan Plafond........................................................................................ 53
V.13. Pekerjaan List Plafond................................................................................. 54
V.14. Pekerjaan Pengecatan Plafond .................................................................... 54
BAB VIII MASTER SCHEDULE DAN KURVA S .................................................. 55
DAFTAR PUSTAKA ................................................................................................ 56

iii
BAB I
PENDAHULUAN

1.1 Latar Belakang


Dewasa ini, mahasiswa diharapkan untuk memiliki keahlian, keterampilan, serta cara
mengatasi kesulitan dan tantangan yang terjadi di dunia kerja, salah satu diantaranya
adalah mengenai harga alat, bahan, dan lahan yang semakin melonjak naik dari suatu
konstruksi bangunan. Diharapkan mahasiswa teknik sipil dapat mengaplikasikan
ilmu yang telah dipelajari di bangku perkuliahan untuk mengatasi fenomena tersebut.

Fenomena tersebut mendorong mahasiswa program studi teknik sipil Universitas


Katolik Parahyangan secara khusus untuk dapat mengestimasi harga alat, bahan, dan
lahan dari struktur dan arsitektur rumah tinggal Bapak Alexander Claydius Lay di
Jalan Waru VII No. 12A RT 014 RW 09 Kelurahan Kapuk Kecamatan Cengkareng
Jakarta Barat secara optimal dan efisien.

1.2 Tujuan
Adapun penyusunan proposal ini mempunyai tujuan sebagai berikut:
1. Mengestimasi besar pengeluaran dan kebutuhan dari konstruksi.
2. Menganalisis metode pelaksanaan kontruksi yang tepat untuk diterapkan.
3. Mengetahui penjadwalan proyek konstruksi yang optimal.

1
1.3 Metode dan Teknik Pembahasan
Teknik pembahasan yang menjadi batasan dalam penyusunan proposal ini adalah
sebagai berikut:
1. Metode analisis harga satuan pekerjaan.
2. Metode pelaksanaan konstruksi yang direncanakan adalah pekerjaan
persiapan, pekerjaan struktur bawah, pekerjaan struktur atas, pekerjaan
arsitektur, pekerjaan mekanikal dan elektrikal.
3. Penjadwalan proyek yang akan dilaksanakan diimplementasikan dalam
bentuk bar chart dan kurva S.
4. Analisis harga satuan menggunakan Lampiran Peraturan Menteri Pekerjaan
Umum dan Perumahan Rakyat Nomor: 28/PRT/M/2016 tentang Analisis
Harga Satuan Pekerjaan dan Bidang Pekerjaan Umum.
5. Harga satuan bahan, peralatan, dan upah diperoleh dari Jurnal Harga Satuan
tahun 2018, Kota Bandung.
1.4 Metodologi
Metodologi adalah aturan, kegiatan, dan prosedur yang digunakan oleh pelaku untuk
menganalisis teori mengenai suatu cara atau metode. Metodologi ini disusun
berdasarkan batasan atau ruang lingkup yang telah ditentukan sebelumnya. Proses
pengerjaan penyusun adalah sebagai berikut:
1. Tahap Persiapan
Tahap pertama yang dilakukan adalah perumusan tujuan penyusunan
laporan berdasarkan latar belakang yang berasal dari tinjauan permasalaha.
Lalu dengan penentuan ruang lingkup pengerjaan dari batasan-batasan yang
ada dilakukan analisis menggunakan referensi yang menunjang. Setelah
ditentukan ruang lingkup pengerjaan dilanjutkan dengan penentuan data-
data yang diperlukan dalam proses pengerjaan aktual.
2. Penentuan Metode Pelaksanaan Konstruksi
Tahap kedua adalah meninjau data kondisi lingkungan, desain struktur atas,
desain struktur bawah, dan perencanaan instalasi air dan listrik. Data
tersebut ditinjau agar dapat merumuskan bagian dari setiap pekerjaan secara
detail. Metode pelaksanaan konstruksi direncanakan dengan menyusun
tahapan pekerjaan dengan mempertimbangkan efisiensi alat dan bahan serta
tingkat produktivitas pekerja.

2
3. Penjadwalan
Pada tahap penjadwalan akan dilakukan perhitungan durasi pekerjaan dari
produktivitas pekerja dan volume pekerjaan yang telah direncanakan.
4. Estimasi Biaya Konstruksi
Dengan analisis harga satuan Lampiran Permen PUPR 2018 dan Jurnal
Harga Satuan Kota Bandung diperoleh biaya total pekerjaan dari konstruksi
bangunan. Kemudian dari perhitungan biaya tak langsung seperti pajak,
biaya umum, biaya resiko tambahan, dano overhead didapatkan estimasi
biaya masing-masing pekerjaan konstruksi proyek.

3
BAB II
DESKRIPSI UMUM PROYEK

2.1 Deskripsi Umum Proyek


Menurut UU No 4 Tahun 1992 tentang Perumahan dan Permukiman, rumah adalah
bangunan yang berfungsi sebagai tempat tinggal atau hunian dan sarana pembinaan
keluarga. Dalam laporan estimasi biaya konstruksi ini, rumah tinggal yang
direncanakan terdiri dari 2 lantai yang beralamatkan di Jalan Waru VII No. 12A
RT 014 RW 09 Kelurahan Kapuk Kecamatan Cengkareng Jakarta Barat. Rumah
tersebut memiliki luas bangunan sebagai berikut.

Tabel 2.1 Luas bangunan


Lantai Luas Bangunan Satuan
1 243,622 m2
2 185,147 m2
Atap 186,900 m2

Akan tetapi pada data proyek diketahui bahwa luas bangunan sebesar 410 m2,
sehingga digunakan luas bangunan tersebut untuk mencari harga bangunan/m2.
Berikut merupakan gambar arsitektur dari rumah tinggal Bapak Alexander.

Gambar 2.1 Denah lantai bawah

4
Gambar 2.2 Denah lantai atas

Gambar 2.3 Gambar Denah Tampak Rumah

5
2.2 Spesifikasi Teknis
Karakterisitik material yang digunakan dalam bangunan ini adalah sebagai berikut:
1. Beton
Concrete beam, column, and slab (fc’) = 19,3 MPa
Mutu Beton = K-225
2. Cat Tembok
Cat dinding eksterior (ex Mowilex)
Cat dnding dalam (ex Catylac)
3. Keramik Lantai
Keramik eks Roman 30x30
Keramik eks Roman 40x40
Keramik eks Roman 30x60
Keramik eks Roman 60x60
Granit 60x60
4. Plafond
Gypsum tebal 9 mm

2.3 Work Breakdown Structure


Work Breakdown Structure (WBS) adalah suatu pengorganisasian proyek menjadi
struktur pelaporan hierarkis. WBS digunakan untuk melakukan breakdown atau
memecahkan setiap proses pekerjaan menjadi lebih detail. Dimaksudkan agar proses
perencanaan proyek memiłiki tingkatan yang lebih baik. WBS pada dasamya adalah
suatu daftar yang bersifat top down dan secara hierarkis menerangkan
komponen-komponen yang harus dibangun dan pekerjaan yang harus dilakukan.
Keuntungan dari WBS adalah sebagai berikut:
1. Memberikan daftar pekerjaan yang harus dilakukan.
2. Dasar estimasi, alokasi sumber daya dan menyusun jadwal serta
menghitung biaya.
3. Sebagai dasar perhitungan secara serius sebelum membangun suatu proyek.
Manfaat dari WBS antara lain:
1. Mempercepat proses penyelesaian proyek.
2. Mengetahui pencapaian yang diinginkan dalam suatu proyek.
3. Merencanakan proyek selanjutnya.

6
Namun, WBS memiliki beberapa manfaat utama, yaitu:
1. WBS yang melibatkan manajer fungsional dan personel dapat
meningkatkan akurasi dan kelengkapan penjelasan suatu proyek.
2. Dasar anggaran dan penjadwalan suatu proyek.
3. Sebagai alat kontrol pada proyek.

Pembagian Kerja dalam Proyek yang Dilakukan


I. Pekerjaan Persiapan
1. Pekerjaan pembersihan terdiri dari:
a. Pemasangan pagar sementara
II. Pekerjaan Struktur Bagian Atas
1. Pekerjaan balok terdiri dari:
a. Pengecoran
b. Pembesian
2. Pekerjaan rangka atap
3. Pekerjaan kolom:
a. Pengecoran
b. Pembesian
4. Pekerjaan pelat:
a. Pengecoran
b. Pembesian
III. Pekerjaan Struktur Bagian Bawah
1. Pekerjaan pondasi tapak terdiri dari:
a. Galian pondasi tapak
b. Pembuatan pondasi tapak
2. Pekerjaan pondasi batu belah
3. Pekerjaan sloof
a. Pengecoran
b. Pembesian

7
IV. Pekerjaan Arsitektur
1. Pekerjaan arsitektural terdiri dari:
a. Dinding
b. Kusen, pintu, dan jendela
c. Plafond

2.4 Sketsa WBS

Rumah 2 Lantai

Pekerjaan Pekerjaan Pekerjaan Pekerjaan


Tanah dan Arsitektur Pekerjaan Finishing
Persiapan Struktur
Urugan Mekanikal
dan
Elektrikal

Gambar 2.4 WBS general pekerjaan rumah 2 lantai

Pekerjaan Persiapan

Pemagaran Pembersihan Pemasangan Pekerjaan Tanah


Sementara Lapangan Bouwplank dan Urugan

Gambar 2.5 WBS pekerjaan persiapan

8
Pekerjaan Struktur Atas

Pekerjaan Pekerjaan Pekerjaan Pekerjaan Pelat


Rangka Atap Balok Kolom Lantai

Bekisting Bekisting Bekisting

Pembesian Pembesian Pembesian

Pengecoran Pengecoran Pengecoran

Gambar 2.6 WBS pekerjaan struktur bagian atas

Pekerjaan Struktur Bawah

Pekerjaan Pekerjaan Pondasi Pekerjaan


Pondasi Tapak Batu Belah Sloof

Penggalian Penggalian Bekisting

Pembuatan
Pembesian Pondasi Batu Pembesian
Belah

Pengecoran Pengecoran

Gambar 2.7 WBS pekerjaan struktur bagian bawah

9
Pekerjaan Arsitektural

Pekerjaan Pekerjaan Kusen, Pintu, Pekerjaan


Pagar
Dinding dan Jendela Plafond

Gambar 2.8 WBS pekerjaan arsitektural

Pekerjaan Mekanikal dan Elektrikal

Pekerjaan Elektrikal Pekerjaan Plumbing

Pemasangan Pemasangan Instalasi


Instalasi Listrik Air Kotor

Pemasangan Instalasi Pemasangan Instalasi


Lampu Air Bersih

Pemasangan Pemasagan Instalasi


Saklar dan Stop Air Panas
Kontak
Pemasangan
Instalasi Air Hujan

Gambar 2.9 WBS pekerjaan mekanikal dan elektrikal

Pekerjaan Finishing

Keramik Plesteran Acian Pengecatan

Gambar 2.10 WBS pekerjaan finishing

10
BAB III
SURAT PENAWARAN KERJA

PT. EVAN JAYA PERKASA

Jl. Ciumbuleuit No.94, Hegarmanah, Cidadap, Kota Bandung,


Jawa Barat, 40141

Nomor : 08/UD.RJ/X/2019

Lampiran :-

Hal : Penawaran Jasa

Kepada Yth,

Panitia Tender

Yang bertanda tangan dibawah ini:

Nama Perusahaan : PT. Evan Jaya Perkasa

Alamat Perusahaan : Jl. Ciumbuleuit No.94, Hegarmanah, Cidadap, Kota


Bandung, Jawa Barat, 40141

Setelah membaca dan mempelajari dengan seksama seluruh isi Dokumen


Tender dengan ini menyatakan:

1. Sanggup menyediakan bahan-bahan bangunan, peralatan, dan tenaga kerja


yang diperlukan serta melaksanakan:
Proyek : Rumah Tinggal 2 Lantai
Lokasi : Cengkareng, Jakarta Barat
2. Surat penawaran ini adalah sesuai dan mengikuti sepenuhnya ketentuan
dalam Dokumen Tender dan Addendum yakni:
Tanggal 9 April 2019 dengan jumlah harga sebesar Rp 2.102.100.000
(Dua Milyar Seratus Dua Juta Seratus Ribu Rupiah) sudah termasuk PPN,
dan dengan jangka waktu pelaksanaan 36 minggu kalender sejak

11
dikeluarkannya Surat Perintah Kerja (SPK) atau tanggal lain yang disepakati
bersama dengan masa retensi selama 12 minggu.
3. Dengan sistem pembayaran, sebagai berikut:
Tahap Progress Persentase Biaya
DP 10% 0% 10% Rp 210.210.000
Tahap 1 30% 15% Rp 315.315.000
Tahap 2 50% 20% Rp 420.420.000
Tahap 3 75% 25% Rp 525.525.000
Tahap 4 100% 25% Rp 525.525.000
Retensi 100% 5% Rp 105.105.000

4. Surat ini berlaku hingga 9 Juli 2019.

Bandung, 9 April 2019

PT. Evan Jaya Perkasa

Evan Christopher

12
BAB IV
KUANTIFIKASI PEKERJAAN

IV.1. Pekerjaan Persiapan

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

I PEKERJAAN PERSIAPAN

1 Pekerjaan Pembersihan m2 240.000 Rp 18,954 Rp 4,548,864

2 Pembuatan Gudang Bahan m2 12.000 Rp 927,817 Rp 11,133,804

Total Pekerjaan Tanah & Urugan Rp 15,682,668

IV.2. Pekerjaan Tanah dan Urugan

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

II PEKERJAAN TANAH & URUGAN


Pasang Bouwplank papan
1 m1 64.000 Rp 92,794 Rp 5,938,835
2/20 kaso 5/7 kayu borneo
Galian tanah untuk pondasi
2 termasuk pembuangan di m3 165.516 Rp 80,202 Rp 13,274,730
lokasi
Pembuangan 1 m3 tanah
3 m3 165.516 Rp 35,112 Rp 5,811,585
sejauh 30m
Pemadatan tanah pondasi
4 m2 148.605 Rp 74,118 Rp 11,014,268
dengan stamper
Urugan pasir bawah lantai
5 m3 25.020 Rp 152,081 Rp 3,805,062
tebal 12 cm
Urugan pasir bawah
6 m3 9.140 Rp 152,081 Rp 1,389,950
pondasi tebal 5 cm
Lantai Kerja bawah pondasi
7 m3 0.546 Rp 760,565 Rp 414,888
dan tie beam Tebal 5 cm
8 Pondasi batu kali m3 47.932 Rp 748,667 Rp 35,885,020

Total Pekerjaan Tanah & Urugan Rp 77,534,339

13
IV.3. Pekerjaan Beton dan Struktur

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

III PEKERJAAN BETON DAN STRUKTUR


Besi angkur pondasi batu
1 kg Rp 14,486 Rp -
kali
2 Beton Pondasi tapak

Beton K 225 m3 15.692 Rp 988,459 Rp 15,510,993

Besi ø 8 mm kg 61.355 Rp 14,486 Rp 888,797

Besi ø 10 mm kg 146.702 Rp 14,486 Rp 2,125,153

Besi ø 12 mm kg 0.000 Rp 14,486 Rp -

Besi ø 13 mm kg 0.000 Rp 14,486 Rp -

Besi ø 16 mm kg 0.000 Rp 14,486 Rp -

Bekisting untuk pondasi m2 10.240 Rp 171,283 Rp 1,753,941

3 Beton Tie Beam

Beton K 225 m3 8.216 Rp 988,459 Rp 8,120,786

Besi ø 8 mm kg 438.200 Rp 14,486 Rp 6,347,847

Besi ø 13 mm kg 898.724 Rp 14,486 Rp 13,019,084

Bekisting Sloof m2 94.875 Rp 179,808 Rp 17,059,314

4 Beton Kolom Lantai 1

Beton K225 m3 7.404 Rp 988,459 Rp 7,318,256

Besi ø 8 mm kg 351.637 Rp 14,486 Rp 5,093,878

Besi ø 10 mm kg 303.564 Rp 14,486 Rp 4,397,485

Besi ø 12 mm kg 713.476 Rp 14,486 Rp 10,335,544

Besi ø 13 mm kg 175.890 Rp 14,486 Rp 2,547,970

Besi ø 16 mm kg 164.364 Rp 14,486 Rp 2,381,015

Bekisting Kolom m2 178.636 Rp 441,216 Rp 78,816,983

5 Beton Kolom Lantai 2

Beton K225 m3 3.975 Rp 988,459 Rp 3,928,800

Besi ø 8 mm kg 168.878 Rp 14,486 Rp 2,446,403

Besi ø 10 mm kg 9.132 Rp 14,486 Rp 132,282

Besi ø 12 mm kg 544.068 Rp 14,486 Rp 7,881,471

Besi ø 13 mm kg 0.000 Rp 14,486 Rp -

Besi ø 16 mm kg 0.000 Rp 14,486 Rp -

Bekisting Kolom m2 98.020 Rp 441,216 Rp 43,247,949

6 Beton Balok Lantai 2

Beton K225 m3 15.594 Rp 988,459 Rp 15,413,644

14
Besi ø 8 mm kg 488.182 Rp 14,486 Rp 7,071,897

Besi ø 10 mm kg 37.946 Rp 14,486 Rp 549,686

Besi ø 12 mm kg 154.686 Rp 14,486 Rp 2,240,810

Besi ø 13 mm kg 1679.436 Rp 14,486 Rp 24,328,619

Besi ø 16 mm kg 699.969 Rp 14,486 Rp 10,139,885

Bekisting Balok m2 233.234 Rp 454,551 Rp 106,016,759

7 Beton Balok Atap

Beton K225 m3 5.876 Rp 988,459 Rp 5,808,286

Besi ø 8 mm kg 242.714 Rp 14,486 Rp 3,515,996

Besi ø 10 mm kg 0.000 Rp 14,486 Rp -

Besi ø 12 mm kg 10.668 Rp 14,486 Rp 154,539

Besi ø 13 mm kg 768.579 Rp 14,486 Rp 11,133,782

Besi ø 16 mm kg 0.000 Rp 14,486 Rp -

Bekisting Balok m2 105.377 Rp 454,551 Rp 47,899,174


Beton Plat Lantai 2 t =
8
12cm
Beton K225 m2 23.046 Rp 988,459 Rp 22,780,034

Besi ø 8 mm kg 2374.723 Rp 14,486 Rp 34,400,681

Bekisting Lantai m2 188.500 Rp 559,616 Rp 105,487,533


Beton Plat Dak Beton t =10
9 cm

Beton K225 m2 11.790 Rp 988,459 Rp 11,653,935

Besi ø 8 mm kg 1441.211 Rp 14,486 Rp 20,877,652

Bekisting Dak Beton m2 114.400 Rp 559,616 Rp 64,020,020

10 Struktur Tangga

Beton K-225 m2 4.260 Rp 988,459 Rp 4,210,837

Besi ø 8 mm kg 85.338 Rp 14,486 Rp 1,236,224

Besi ø 12 mm kg 686.495 Rp 14,486 Rp 9,944,695

Bekisting m2 29.010 Rp 422,166 Rp 12,247,023

Pasangan Bata Merah m3 3.915 Rp 641,712 Rp 2,512,304


Total Pekerjaan Beton Dan Struktur Rp 756,997,965

15
IV.4. Pekerjaan Kap / Kuda-kuda + Atap

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

IV PEKERJAAN KAP / KUDA-KUDA + ATAP


Rangka atap baja ringan
1 zincalum 0.75 mm m2 284.825 Rp 125,000.00 Rp 35,603,154
(Subkontraktor)
Atap genteng beton tipe
2 m2 284.825 Rp 135,639.50 Rp 38,633,552
safari ex. CP/setara
3 Nok genteng beton (flat) m1 22.080 Rp 124,700.60 Rp 2,753,389

4 Nok samping genteng beton m1 34.600 Rp 157,450.60 Rp 5,447,791


Nok genteng beton
5 buah 2 Rp 124,700.60 Rp 249,401
(segitiga)
Total Pekerjaan Kap/ Kuda-Kuda Atap Rp 82,687,287.03

IV.5. Pekerjaan Dinding

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

V PEKERJAAN DINDING

Lantai 1
Dinding bata merah ukuran
1 m2 396.196 Rp 128,036 Rp 50,727,367
(5x11x22) cm tebal 1/2 bata
Plesteran 1PC : 2PP tebal
2 m2 779.542 Rp 70,899 Rp 55,268,424
15 mm
3 Acian m2 694.442 Rp 40,595 Rp 28,191,012

Lantai 2
Dinding bata merah ukuran
1 m2 485.727 Rp 128,036 Rp 62,190,536
(5x11x22) cm tebal 1/2 bata
Plesteran 1PC : 2PP tebal
2 m2 971.454 Rp 70,899 Rp 68,874,685
15 mm
3 Acian m2 892.704 Rp 40,595 Rp 36,239,497

Total Pekerjaan Finishing Rp 301,491,521

16
IV.6. Pekerjaan Pintu dan Jendela

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

VI PEKERJAAN PINTU DAN JENDELA

P1 (Teakwood)

1 Kusen pintu m3 0.049 Rp 8,337,784 Rp 409,385

2 Daun pintu m2 1.880 Rp 610,840 Rp 1,148,380

P2 (PVC)

1 Kusen pintu m3 0.045 Rp 8,337,784 Rp 375,200

2 Daun pintu unit 1.000 Rp 195,000 Rp 195,000

P2A (PVC)

1 Kusen pintu m3 0.027 Rp 8,337,784 Rp 225,120

2 Daun pintu unit 1.000 Rp 195,000 Rp 195,000

P3 (Teakwood )

1 Kusen pintu m3 0.032 Rp 8,337,784 Rp 262,640

2 Daun pintu m2 2.820 Rp 610,840 Rp 1,722,570

PJ1 (Panel )

1 Kusen pintu m3 0.118 Rp 8,337,784 Rp 980,523

2 Daun pintu m2 2.025 Rp 610,840 Rp 1,236,952

3 Jendela kayu m2 2.558 Rp 700,000 Rp 1,790,250

4 Kaca m2 0.203 Rp 192,500 Rp 38,981

PJ2 (Teakwood )

1 Kusen pintu m3 0.103 Rp 8,337,784 Rp 859,209

2 Daun pintu m2 1.880 Rp 610,840 Rp 1,148,380

3 Kusen alm m3 1.914 Rp 255,639 Rp 489,293

4 Kaca m2 1.536 Rp 192,500 Rp 295,680

PJ3 (Panel )

1 Kusen pintu m3 0.154 Rp 8,337,784 Rp 1,283,602

2 Daun pintu m2 2.025 Rp 610,840 Rp 1,236,952

3 Kusen alm m3 3.840 Rp 255,639 Rp 981,654

4 Kaca m2 2.900 Rp 192,500 Rp 558,250

PJ4 ( Pintu Kaca )

1 Kusen pintu m3 0.131 Rp 8,337,784 Rp 1,093,917

2 Pintu Kaca rangka alm m2 6.300 Rp 1,115,771 Rp 7,029,357

3 Kaca m2 2.580 Rp 192,500 Rp 496,650

PJ5 ( Pintu Kaca )

17
1 Kusen pintu m3 0.122 Rp 8,337,784 Rp 1,014,708

2 Pintu Kaca rangka alm m2 5.130 Rp 1,115,771 Rp 5,723,905

3 Kusen alm m3 2.552 Rp 255,639 Rp 652,391

4 Kaca m2 1.440 Rp 192,500 Rp 277,200

PG2 ( Pintu Kaca )

1 Kusen pintu m3 0.088 Rp 8,337,784 Rp 733,725

2 Pintu Kaca rangka alm m2 5.738 Rp 1,115,771 Rp 6,401,736

J4

1 Kusen alm jendela m3 0.065 Rp 255,639 Rp 16,501

2 Kaca m2 0.300 Rp 192,500 Rp 57,750

J1

1 Kusen kayu m3 0.041 Rp 8,337,784 Rp 341,849

2 Kusen alm m3 1.085 Rp 255,639 Rp 277,368

J2

1 Kusen kayu m3 0.100 Rp 8,337,784 Rp 830,443

2 Kusen alm m3 4.032 Rp 255,639 Rp 1,030,737

3 Kaca m2 3.180 Rp 192,500 Rp 612,150

J3

1 Kusen kayu m3 0.120 Rp 8,337,784 Rp 1,001,785

2 Kusen alm m3 5.120 Rp 255,639 Rp 1,308,872

3 Kaca m2 4.200 Rp 192,500 Rp 808,500

PG ( Pintu besi ex wina )

1 Kusen kayu m3 0.098 Rp 8,337,784 Rp 814,601

2 Pintu besi unit 1 Rp 3,000,000 Rp 3,000,000

PJK ( Pintu teakwood )

1 Kusen kayu m3 0.152 Rp 8,337,784 Rp 1,266,509

2 Daun pintu m2 1.880 Rp 610,840 Rp 1,148,380

3 Kusen alm m3 4.590 Rp 255,639 Rp 1,173,383

4 Kaca m2 3.840 Rp 192,500 Rp 739,200

BV'

1 Exhouse fan unit 1 Rp 911,800 Rp 911,800

J1'

1 Kusen kayu m3 0.018 Rp 8,337,784 Rp 145,911

2 Exhouse fan unit 1 Rp 911,800 Rp 911,800

3 Kaca m2 0.570 Rp 192,500 Rp 109,725

18
PB

1 Kusen pintu m3 0.027 Rp 8,337,784 Rp 226,371

2 Pintu hollow m2 1.913 Rp 350,000 Rp 669,375

BV

1 Kusen pintu m3 0.049 Rp 8,337,784 Rp 411,887

J1'''

1 Kusen kayu m3 0.027 Rp 8,337,784 Rp 220,951

2 Exhouse fan unit 1 Rp 911,800 Rp 911,800

3 Kaca m2 1.050 Rp 192,500 Rp 202,125

J1''

1 Kusen kayu m3 0.021 Rp 8,337,784 Rp 175,093

2 Exhouse fan unit 1 Rp 911,800 Rp 911,800

3 Kaca m2 0.780 Rp 192,500 Rp 150,150

PB'

1 Kusen pintu m3 0.029 Rp 8,337,784 Rp 238,044

2 Pintu hollow m2 1.998 Rp 350,000 Rp 699,125

Total Pekerjaan Kusen dan Pintu Rp 60,180,595

19
IV.7. Pekerjaan Plafond

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

VII PEKERJAAN PLAFOND


Plafond Gypsum Board,
1 tebal 9 mm + rangka besi m2 210.335 Rp 172,646 Rp 36,313,496
hollow
2 Plafond Solar Tuff plate m2 65.000 Rp 150,000 Rp 9,750,000

3 List Plafond 10/10 m1 230.687 Rp 23,456 Rp 5,410,948

4 Pengecatan Plafond m2 185.100 Rp 16,071 Rp 2,974,705

Total Pekerjaan Plafond Rp 54,449,150

IV.8. Pekerjaan Pengecatan

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

VIII PEKERJAAN PENGECATAN

Lantai 1
Pengecatan Dinding
1 m2 192.400 Rp 31,996 Rp 6,156,034
Eksterior
Pengecatan Dinding
2 m2 419.205 Rp 31,996 Rp 13,412,892
Interior
Lantai 2
Pengecatan Dinding
1 m2 192.400 Rp 31,996 Rp 6,156,034
Eksterior
Pengecatan Dinding
2 m2 652.134 Rp 31,996 Rp 20,865,680
Interior
Total Pekerjaan Pengecatan Rp 46,590,640

20
IV.9. Pekerjaan Finishing Lantai dan Dinding

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

IX PEKERJAAN FINISHING LANTAI DAN DINDING

Lantai 1
Pemasangan keramik
1 m2 12.783 Rp 257,769 Rp 3,294,929
30x30 WC
Pemasangan keramik
2 m2 41.925 Rp 279,281 Rp 11,708,856
40x40
Pemasangan keramik
3 m2 22.700 Rp 304,876 Rp 6,920,676
60x60
Pemasangan keramik
4 m2 71.302 Rp 286,825 Rp 20,451,175
30x60 (Dinding WC)
5 Pemasangan Granit 60x60 m2 122.700 Rp 377,376 Rp 46,303,987

6 Plint Ubin Granit 10x 60 m1 67.600 Rp 41,613 Rp 2,813,011


Plint Ubin Keramik 10 x
7 m1 29.750 Rp 34,000 Rp 1,011,494
40
Plint Ubin Keramik 10 x
8 m1 18.000 Rp 30,439 Rp 547,905
60
Lantai 2
Pemasangan keramik
1 m2 14.580 Rp 257,769 Rp 3,758,268
30x30 WC
Pemasangan keramik
2 m2 30.500 Rp 279,281 Rp 8,518,071
40x40
Pemasangan keramik
3 m2 28.380 Rp 304,876 Rp 8,652,217
60x60
Pemasangan keramik
4 m2 114.550 Rp 286,825 Rp 32,855,771
30x60 (Dinding WC)
5 Pemasangan Granit 60x60 m2 97.750 Rp 377,376 Rp 36,888,466

6 Plint Ubin Granit 10x 60 m1 65.850 Rp 41,613 Rp 2,740,189


Plint Ubin Keramik 10 x
7 m1 35.200 Rp 34,000 Rp 1,196,793
40
Plint Ubin Keramik 10 x
8 m1 22.650 Rp 30,439 Rp 689,448
60
Total Finishing Lantai dan Dinding Rp 188,351,257

21
IV.10. Pekerjaan Listrik

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

X PEKERJAAN LISTRIK
Instalasi penerangan
1 (NYM 2x2,5 mm) + ttk 51 Rp 205,000 Rp 10,455,000
Fitting
Instalasi penerangan
2 lampu downlight (NYM ttk 34 Rp 245,000 Rp 8,330,000
2x2,5 mm) + Fitting
Instalasi stop kontak
3 ttk 47 Rp 200,000 Rp 9,400,000
(NYM 3x2,5 mm)
Instalasi stop kontak AC
4 ttk 6 Rp 200,000 Rp 1,200,000
(NYM 3x2,5 mm)
5 Instalasi lampu taman ttk 3 Rp 200,000 Rp 600,000

6 Instalasi line lampu ttk 0 Rp 200,000 Rp -

7 Instalasi line stop kontak ttk 0 Rp 200,000 Rp -

8 Instalasi line ac ttk 0 Rp 200,000 Rp -

9 Saklar tunggal (Broco) bh 12 Rp 13,000 Rp 156,000

10 Saklar seri (Broco) bh 16 Rp 18,000 Rp 288,000

11 Saklar hotel (Broco) bh 2 Rp 24,000 Rp 48,000

12 Outlet stop kontak (Broco) bh 38 Rp 14,000 Rp 532,000


Outlet stop kontak
13 AC/Pompa + water heater bh 8 Rp 52,000 Rp 416,000
(Broco)
Panel listrik (Hager isi 8
14 group, MCB ex Merlin bh 1 Rp 294,000 Rp 294,000
Gerin)
Kabel toevour dari meter
15 m' 6 Rp 44,400 Rp 266,400
PLN menuju panel listrik
16 Kartu jaminan listrik ls 1 Rp 1,500,000 Rp 1,500,000
Outlet stop kontak antena
17 bh 8 Rp 232,500 Rp 1,860,000
TV + instalasi kabel
Outlet stop kontak telepon
18 bh 2 Rp 242,000 Rp 484,000
+ instalasi kabel
Total Pekerjaan Listrik Rp 35,829,400

22
IV.11. Pekerjaan Sanitary dan Plumbing

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

XI PEKERJAAN SANITARY & PLUMBING

Pekerjaan instalasi pipa PVC lengkap fitting, klem, alat bantu, dll

Lantai 1

1 Instalasi air bersih dia 1/2" m' 12.240 Rp 19,455 Rp 238,130

2 Instalasi air bersih dia 3/4" m' 74.260 Rp 22,001 Rp 1,633,787

3 Instalasi air panas 1/2" m' 10.000 Rp 19,455 Rp 194,551


Instalasi air kotor dari
4 wastafel dan kitchen dia 1 m' 5.340 Rp 38,192 Rp 203,946
1/4"
Instalasi air kotor dari AC
5 m' 9.150 Rp 25,472 Rp 233,073
dia 1"
Instalasi air kotor dari WC
6 m' 3.570 Rp 129,590 Rp 462,637
dia 6"
Instalasi air kotor dari WC
7 m' 56.110 Rp 77,980 Rp 4,375,431
dia 4"
Instalasi air kotor dari WC
8 m' 38.880 Rp 59,762 Rp 2,323,550
dia 3"
Instalasi air kotor dari
9 m' 43.350 Rp 59,762 Rp 2,590,686
saluran air hujan dia 3"
Instalasi air kotor dari KM
10 m' 9.250 Rp 59,762 Rp 552,799
dia 3"
Lantai 2

1 Instalasi air bersih dia 1/2" m' 4.930 Rp 19,455 Rp 95,914

2 Instalasi air bersih dia 3/4" m' 51.860 Rp 22,001 Rp 1,140,966

3 Instalasi air panas 1/2" m' 3.000 Rp 19,455 Rp 58,365


Instalasi air kotor dia 1
4 m' 13.910 Rp 38,192 Rp 531,253
1/4"
Instalasi air kotor dari AC
5 m' 11.920 Rp 25,472 Rp 303,632
dia 1"
Instalasi air kotor dari WC
6 m' 10.730 Rp 59,762 Rp 641,247
dia 3"
Instalasi air kotor dari
7 m' 43.350 Rp 59,762 Rp 2,590,686
saluran air hujan dia 3"
Instalasi air kotor dari KM
8 m' 9.250 Rp 59,762 Rp 552,799
dia 3"
Pekerjaan Sanitary Fixtures

Lantai 1
Closed duduk ex. TOTO
1 bh 2 Rp 2,362,500 Rp 4,725,000
CW 421 J/SW420 JP
Lavatory ex. TOTO LW
2 bh 3 Rp 2,925,750 Rp 8,777,250
642 CJ
Kran taman ex TOTO
3 bh 4 Rp 305,250 Rp 1,221,000
T26-13
Jet washer/spray ex TOTO
4 bh 2 Rp 589,500 Rp 1,179,000
TB 19 CSNNS
Hand shower ex TOTO
5 bh 2 Rp 1,065,000 Rp 2,130,000
TX 433 SD
Floor drain dia 3" ex.
6 bh 3 Rp 342,750 Rp 1,028,250
TOTO TX 1 BV 1

23
7 Tissue Holder TX 703 AC bh 2 Rp 508,500 Rp 1,017,000

8 Kitchen sink stainless bh 1 Rp 350,000 Rp 350,000


Kran kitchen zink ex.
9 bh 1 Rp 609,750 Rp 609,750
TOTO TX 603KCS
Bath tub type komplit FB
10 bh 1 Rp 3,990,000 Rp 3,990,000
1700-70 kran TX 433 SD
Bak kontrol uk. 30x30 cm,
11 pasangan bata diplester bh 4 Rp 400,000 Rp 1,600,000
tutup plat beton
12 Septictank + rembesan unit 1 Rp 5,000,000 Rp 5,000,000

Lantai 2
Closed duduk ex. TOTO
1 bh 3 Rp 2,362,500 Rp 7,087,500
CW 421 J/SW420 JP
2 Closed jongkok ex. TOTO bh 1 Rp 440,000 Rp 440,000
Lavatory ex. TOTO LW
3 bh 5 Rp 2,925,750 Rp 14,628,750
642 CJ
Jet washer/spray ex TOTO
4 bh 4 Rp 589,500 Rp 2,358,000
TB 19 CSNNS
Hand shower type TS 309
5 bh 4 Rp 990,000 Rp 3,960,000
RYNZ
Floor drain dia 3" ex.
6 bh 9 Rp 342,750 Rp 3,084,750
TOTO TX 1 BV 1
Roof drain 4" cast iron
7 bh 10 Rp 63,000 Rp 630,000
dan talang PVC dia 3"
8 Tissue Holder TX 703 AC bh 3 Rp 508,500 Rp 1,525,500

Total Pekerjaan Sanitary & Plumbing Rp 84,065,201.18

24
IV.12. Pekerjaan Lain-lain

No Uraian Pekerjaan Unit Vol Harga Satuan Total Harga Total Tiap Pekerjaan

XII PEKERJAAN LAIN-LAIN

Pekerjaan Pagar

1 Pekerjaan galian tanah m3 12.180 Rp 80,202 Rp 976,860

2 Pondasi batu kali m3 7.980 Rp 748,667 Rp 5,974,361

3 Sloof beton m3 0.540 Rp 988,385 Rp 533,728

bekisting sloof m2 7.200 Rp 179,808 Rp 1,294,620

besi sloof kg 40.559 Rp 14,486 Rp 587,545

4 Kolom m3 0.203 Rp 988,385 Rp 200,642

bekisting kolom m2 3.840 Rp 441,216 Rp 1,694,268

besi kolom kg 36.169 Rp 14,486 Rp 523,951

5 Ring balok 15x15 cm m3 0.270 Rp 988,385 Rp 266,864

bekisting ring balok m2 2.400 Rp 454,551 Rp 1,090,921

besi ring balok kg 20.198 Rp 14,486 Rp 292,592


Pemasangan dinding bata
6 m2 10.565 Rp 122,244 Rp 1,291,508
1:5
7 Plester i 1: 5 m1 22.230 Rp 70,899 Rp 1,576,076

8 Acian 1: 5 m2 22.230 Rp 40,595 Rp 902,431

9 Pagar pintu luar m2 6.160 Rp 725,000 Rp 4,466,000


Pemasangan Keramik
10 m2 8.420 Rp 257,769 Rp 2,170,413
Hitam & Cream
Pemasangan batu alam
11 m2 3.850 Rp 140,000 Rp 539,000
Andesit
Pekerjaan Tangga

1 Keramik 30x30 m2 27.087 Rp 257,769 Rp 6,982,086

2 Pasangan Bata Merah m3 0.830 Rp 641,712 Rp 532,698

3 Plint ubin keramik 10x30 m3 0.372 Rp 37,767 Rp 14,050

4 Besi hollow 20x20 m1 45.680 Rp 5,833 Rp 266,451

5 Besi hollow 20x40 m1 43.547 Rp 8,500 Rp 370,148

Total Pekerjaan Lain-Lain Rp 32,547,213

25
Subtotal Pekerjaan Rp 1,736,407,236

Keuntungan (10%) Rp 173,640,724

Subtotal + Keuntungan Rp 1,910,047,959

Pembulatan Rp 1,911,000,000

PPN (10%) Rp 191,100,000

Total Pekerjaan Keuntungan +PPN Rp 2,102,100,000

Harga/m2 Rp 5,127,073

26
BAB V
REKAPITULASI BIAYA PEMBANGUNAN RUMAH TINGGAL

No. Uraian Pekerjaan Total Harga


I PEKERJAAN PERSIAPAN Rp 15,682,668
II PEKERJAAN TANAH DAN URUGAN Rp 77,534,339
III PEKERJAAN BETON DAN STRUKTUR Rp 756,997,965
IV PEKERJAAN KAP / KUDA-KUDA + ATAP Rp 82,687,287
V PEKERJAAN DINDING Rp 301,491,521
VI PEKERJAAN PINTU DAN JENDELA Rp 60,180,595
VII PEKERJAAN PLAFOND Rp 54,449,150
VIII PEKERJAAN PENGECATAN Rp 46,590,640
IX PEKERJAAN FINISHING LANTAI DAN DINDING Rp 188,351,257
X PEKERJAAN LISTRIK Rp 35,829,400
XI PEKERJAAN SANITARY DAN PLUMBING Rp 84,065,201
XII PEKERJAAN LAN-LAIN Rp 32,547,213
Sub total Rp 1,736,407,236
Jasa Pelaksanaan (10%) Rp 173,640,724
Total Rp 1,910,047,959
Pembulatan Rp 1,911,000,000
Pajak Penghasilan Negara (10%) Rp 191,100,000
Grand Total Rp 2,102,100,000
Harga/m2 Rp 5,127,073

27
BAB VI
HARGA SATUAN

Daftar Harga Upah Kota Bandung 2018


No Jenis Pekerjaan Harga Satuan Satuan
1 Kepala Tukang Batu Rp 151,600.00 hari / 8 jam
2 Kepala Tukang Kayu Rp 151,600.00 hari / 8 jam
3 Mandor Rp 177,000.00 hari / 8 jam
4 Pekerja Rp 101,036.00 hari / 8 jam
5 Tukang Aluminium Rp 126,300.00 hari / 8 jam
6 Tukang Batu Rp 126,300.00 hari / 8 jam
7 Tukang Kayu Rp 126,300.00 hari / 8 jam

Harga Bahan Bangunan Kota Bandung Edisi 37 2018


No Jenis Bahan Harga Satuan
1 Air Rp 6 ltr
2 Alumunium Daun Pintu Rp 49,720 m1
3 Ampelas Rp 5,000 lbr
Bak Kontrol uk. 30x30 cm, Pasangan Bata Diplester
4 Rp 400,000 unit
Tutup Plat Beton
5 Bata Merah Rp 798 bh
7 Bath Tub tipe FB 1700-70 Rp 2,925,000 bh
8 Batu Belah Rp 113,030 m3
9 Batu Pecah Mesin 2/3 Rp 145 kg
10 Besi Beton U-24 Rata-rata Rp 11,847 kg
11 Besi hollow 20x20 Rp 5,833 m1
12 Besi hollow 20x40 Rp 8,500 m1
13 Cat Dasar Rp 50,820 kg
14 Cat Penutup Rp 54,232 kg
15 Cat Tembok Vinilex Rp 20,000 kg
16 Cotton plaster Rp 15,000 bh
17 Compoun Rp 75,000 zak
18 Daun jendela 4x10 cm Rp 700,000 m2
19 Dolken 7-10 Rp 29,600 btg
20 Exhaust Fan H 145 W 45x45 cm Rp 911,800 unit
21 Fitting Lampu Rp 5,000 bh
22 Fitting Lampu Downlight Rp 45,000 bh
23 Floor drain dia 3" ex. TOTO TX 1 BV 1 Rp 342,750 bh
24 Genteng beton tipe safari ex. CP/setara Rp 9,000 bh
25 Granite Surface Matt Coal Rp 209,650 doos
26 Gypsum board (120x240x9) mm Rp 79,800 m1
27 Hand Shower ex TOTO TX 433 SD Rp 1,065,000 bh
28 Hand Shower tipe TS 309 RYNZ Rp 990,000 bh
29 Instalasi listrik Rp 200,000 titik
30 Jet Washer / spray ex TOTO TB 19 CSNNS Rp 589,500 bh
31 Kawat Beton Rp 18,571 kg
Kabel Toevour dari Meter PLN Menuju Panel Listrik
32 Rp 2,220,000 rol
(1 rol = 50 m)
33 Kaca Polos 5 mm ( ASAHI) Rp 192,500 m2
34 Kartu Jaminan Listrik Rp 1,500,000 ls

28
35 Kaso5/7 Rp 2,000,000 m3
36 Kayu Balok Albasia Rp 1,705,000 m3
37 Kayu Balok Borneo Super Rp 4,445,000 m3
38 Kitchen Sink Stainless Rp 350,000 bh
39 Kloset Duduk ex. TOTO CW 421 J/SW420 JP Rp 2,362,500 bh
40 Kloset Jongkok ex. TOTO Rp 440,000 bh
41 Kran Bath tub TX 433 SD Rp 1,065,000 bh
42 Kran Kitchen Zink ex. TOTO TX 603KCS Rp 609,750 bh
43 Kran Taman ex TOTO T26-13 Rp 305,250 bh
44 Kusen Alm Profil Natural 4m Edico Rp 220,000 btg
45 Lavatory ex. TOTO LW 642 CJ Rp 2,925,750 bh
46 List Gypsum Rp 8,500 m1
47 MCB ex Merlin Gerin Rp 25,000 bh
48 Minyak Bekisting Rp 40,000 ltr
49 Model Jalosi Standar Warna Biasa Rp 195,000 unit
Outlet Stop Kontak AC / Pompa + Water Heater
50 Rp 52,000 bh
(Broco)
51 Outlet Stop Kontak Antena TV Rp 32,500 bh
52 Outlet Stop Kontak (Broco) Rp 14,000 bh
53 Outlet Stop Kontak Telepon Rp 42,000 bh
54 Paku 1 cm s.d 2.5 cm Rp 19,250 kg
55 Paku 4 cm s.d 7 cm Rp 17,210 kg
56 Paku 8 cm s.d 12 cm Rp 17,210 kg
57 Paku Gypsum Rp 17,500 kg
58 Papan Terentang Rp 1,996,500 m3
59 Pasir Beton Rp 150 kg
60 Pasir Merah Rp 316,986 m3
61 Pasir Pasang Rp 132,278 m3
62 Pasir Urug Rp 100,000 m3
63 Panel Listrik Hager Isi 8 Grup Rp 94,000 bh
64 Pintu Besi Lipat Ex Wina Rp 3,000,000 unit
65 Pintu Hollow Rp 350,000 m2
66 Pipa Wavin 1/2" (4 m) Rp 21,100 btg
67 Pipa Wavin 3/4" (4 m) Rp 28,800 btg
68 Pipa Wavin 1" (4 m) Rp 39,300 btg
69 Pipa Wavin 1 1/4" (4 m) Rp 58,900 btg
70 Pipa Wavin 3" (4 m) Rp 96,100 btg
71 Pipa Wavin 4" (4 m) Rp 151,200 btg
72 Pipa Wavin 6" (4 m) Rp 307,300 btg
73 Plamuur Rp 13,500 kg
74 Plamir Tembok Rp 13,000 kg
75 Plint Ubin Granit Rp 8,500 m1
76 Plint Ubi Keramik 10x30 cm Rp 3,333 m1
77 Plint Ubi Keramik 10x40 cm Rp 3,019 m1
78 Plint Ubi Keramik 10x60 cm Rp 2,428 m1
79 Plywood 18 mm Rp 323,000 lbr
80 Ramset/Dina Bolt Rp 7,200 bh
81 Roof drain 4" Cast Iron dan Talang PVC Dia 3" Rp 63,000 bh
82 Rol Cat Rp 25,000 bh
83 Saklar Hotel (Broco) Rp 24,000 bh
84 Saklar Seri (Broco) Rp 18,000 bh
85 Saklar Tunggal (Broco) Rp 13,000 bh

29
86 Sealant Dextone Rp 34,000 tube
87 Septictank + Rembesan Rp 5,000,000 unit
88 Semen Tiga Roda Rp 1,376 kg
89 Semen Portland Rp 1,376 kg
90 Semen Warna Rp 13,250 kg
91 Seng Gelombang Rp 59,000 lbr
92 Skrup Fixer Rp 400 buah
93 Stamper Rp 295,000 hari
94 Teakwood 4 mm uk. Pintu Rp 48,400 lbr
95 Tepung Gypsum Rp 12,500 m1
96 Tissue Holder TX 703 AC Rp 508,500 bh
97 Ubin Keramik 30x30 Roman Rp 100,000 doos
98 Ubin Keramik 40x40 Roman Rp 120,750 doos
99 Ubin Keramik 60x60 Roman Rp 145,650 doos
100 Ubin Keramik 30x60 Roman Rp 128,000 doos
101 Ubin Keramik Hitam 40x40cm Rp 72,500.00 m2
102 Nok genteng beton (flat) Rp 5,500 bh
103 Nok samping Rp 13,000 bh
104 Nok segtiga Rp 4,000 bh
105 Lem Fox putih PVAc Rp 19,250 kg

30
BAB VII
ANALISIS HARGA SATUAN

V.1. Pekerjaan Persiapan

A. Pekerjaan Persiapan
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A.1. (K3) Pembersihan 1 m2 lapangan dan perataan
A Tenaga
Pekerja OH 0.1 Rp 101,036 Rp 10,104
mandor OH 0.05 Rp 177,000 Rp 8,850
B Harga satuan pekerjaan (A) Rp 18,954
A.2. 1 m2 pembuatan gudang bahan
A Tenaga
Pekerja OH 1 Rp 101,036 Rp 101,036
Tukang Batu OH 2 Rp 126,300 Rp 252,600
Kepala Tukang Batu OH 0.2 Rp 151,600 Rp 30,320
Mandor OH 0.05 Rp 177,000 Rp 8,850
Jumlah Harga Tenaga Kerja Rp 392,806
B Bahan
Dolken d 8/10 cm btg 1.7 Rp 29,600 Rp 50,320
kayu kelas III m3 0.21 Rp 1,705,000 Rp 358,050
Paku kg 0.3 Rp 17,210 Rp 5,163
Seng Gelombang lbr 1.5 Rp 59,000 Rp 88,500
PC kg 10.5 Rp 1,376 Rp 14,448
PB m3 0.03 Rp 251,000 Rp 7,530
Koral Beton m3 0.05 Rp 220,000 Rp 11,000
Jumlah Harga Bahan Rp 535,011
C Harga satuan pekerjaan (A+B) Rp 927,817

31
V.2. Pekerjaan Tanah dan Urugan

B. Pekerjaan Tanah dan Urugan


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
B.1. Pengukuran dan pemasangan 1 m' Bouwplank
A Tenaga
Pekerja OH 0.1 Rp 101,036 Rp 10,104
Tukang kayu OH 0.1 Rp 126,300 Rp 12,630
Kepala tukang OH 0.01 Rp 151,600 Rp 1,516
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 25,135
B Bahan
Kayu balok 5/7 m3 0.012 Rp 4,445,000 Rp 53,340
Paku 2''-3'' kg 0.02 Rp 17,210 Rp 344
Kayu papan 3/20 m3 0.007 Rp 1,996,500 Rp 13,976
Jumlah Harga Bahan Rp 67,660
C Harga satuan pekerjaan (A+B) Rp 92,794
B.2. Penggalian 1 m3 tanah biasa sedalam 1 m
A Tenaga
Pekerja OH 0.75 Rp 101,036 Rp 75,777
Mandor OH 0.025 Rp 177,000 Rp 4,425
B Harga satuan pekerjaan (A) Rp 80,202
B.3. (K3) Pembuangan 1 m3 tanah sejauh 30 meter
A Tenaga
Pekerja OH 0.33 Rp 101,036 Rp 33,342
Mandor OH 0.01 Rp 177,000 Rp 1,770
B Harga satuan pekerjaan (A) Rp 35,112
B.4. 1 m3 Pemadatan Tanah
A Tenaga
Pekerja OH 0.5 Rp 101,036 Rp 50,518
Mandor OH 0.05 Rp 177,000 Rp 8,850
Jumlah Tenaga Kerja Rp 59,368
B Peralatan
Pemadatan timbunan (Stamper) Sewa/hari 0.05 Rp 295,000 Rp 14,750
Jumlah Harga Peralatan Rp 14,750
C Harga satuan pekerjaan (A+B) Rp 74,118
B.5. Pengurugan 1 m3 dengan pasir urug
A Tenaga
Pekerja OH 0.3 Rp 101,036 Rp 30,311

32
Mandor OH 0.01 Rp 177,000 Rp 1,770
Jumlah Tenaga Kerja Rp 32,081
B Bahan
Pasir urug m3 1.2 Rp 100,000 Rp 120,000
Jumlah Harga Bahan Rp 120,000
C Harga satuan pekerjaan (A+B) Rp 152,081
B.6. Pengurugan 1 m3 dengan tanah merah
A Tenaga
Pekerja OH 0.3 Rp 101,036 Rp 30,311
Mandor OH 0.01 Rp 177,000 Rp 1,770
Jumlah Tenaga Kerja Rp 32,081
B Bahan
Tanah Merah m3 1.2 Rp 316,986 Rp 380,383
Jumlah Harga Bahan Rp 380,383
C Harga satuan pekerjaan (A+B) Rp 412,464
B.7. Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa slump (3-6) cm, w/c = 0,87
A Tenaga
Pekerja OH 1.2 Rp 101,036 Rp 121,243
Tukang batu OH 0.2 Rp 126,300 Rp 25,260
Kepala tukang OH 0.02 Rp 151,600 Rp 3,032
Mandor OH 0.06 Rp 177,000 Rp 10,620
Jumlah Tenaga Kerja Rp 160,155
B Bahan
Semen portland kg 230 Rp 1,376 Rp 316,480
Pasir beton kg 893 Rp 150 Rp 134,294
Kerikil (Maks 30 mm) kg 1027 Rp 145 Rp 148,436
Air Liter 200 Rp 6 Rp 1,200
Jumlah Harga Bahan Rp 600,410
C Harga satuan pekerjaan (A+B) Rp 760,565
B.8. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 PP
A Tenaga
Pekerja OH 1.5 Rp 101,036 Rp 151,554
Tukang batu OH 0.75 Rp 126,300 Rp 94,725
Kepala tukang OH 0.075 Rp 151,600 Rp 11,370
Mandor OH 0.075 Rp 177,000 Rp 13,275
Jumlah Harga Tenaga Kerja Rp 270,924
B Bahan
Batu belah m3 1.2 Rp 113,030 Rp 135,636
Semen portland kg 202 Rp 1,376 Rp 277,952

33
Pasir pasang m3 0.485 Rp 132,278 Rp 64,155
Jumlah Harga Bahan Rp 477,743
C Harga satuan pekerjaan (A+B) Rp 748,667

V.3. Pekerjaan Beton dan Struktur

C Pekerjaan Beton dan Struktur


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
C.1. Membuat 1 m3 beton mutu f'c = 19,3 Mpa
A Tenaga Kerja
Pekerja OH 1.65 Rp 101,036 Rp 166,709
Tukang Batu OH 0.275 Rp 126,300 Rp 34,733
Kepala Tukang OH 0.028 Rp 151,600 Rp 4,245
Mandor OH 0.083 Rp 177,000 Rp 14,691
Jumlah Harga Tenaga Kerja Rp 220,378
B Bahan
PC / Portland Cement kg 371 Rp 1,376 Rp 510,496
PB / Pasir Beton kg 698 Rp 150 Rp 104,969
Kr / Kerikil kg 1047 Rp 145 Rp 151,326
Air Liter 215 Rp 6 Rp 1,290
Jumlah Harga Bahan Rp 768,082
C Harga satuan pekerjaan (A+B) Rp 988,459
C.2. Pembesian 1 kg dengan besi polos atau besi ulir
A Tenaga
Pekerja OH 0.007 Rp 101,036 Rp 707
Tukang besi OH 0.007 Rp 126,300 Rp 884
Kepala tukang OH 0.0007 Rp 151,600 Rp 106
Mandor OH 0.0004 Rp 177,000 Rp 71
Jumlah Harga Tenaga Kerja Rp 1,768
B Bahan
Besi beton (polos / ulir) kg 1.05 Rp 11,847 Rp 12,439
Kawat beton kg 0.015 Rp 18,571 Rp 279
Jumlah Harga Bahan Rp 12,718
C Harga satuan pekerjaan (A+B) Rp 14,486
C.4. (K3) Pemasangan 1 m2 bekisting untuk pondasi
A Tenaga
Pekerja OH 0.52 Rp 101,036 Rp 52,539
Tukang kayu OH 0.26 Rp 126,300 Rp 32,838
Kepala tukang OH 0.026 Rp 151,600 Rp 3,942

34
Mandor OH 0.026 Rp 177,000 Rp 4,602
Jumlah Harga Tenaga Kerja Rp 93,920
B Bahan
Kayu kelas III m3 0.04 Rp 1,705,000 Rp 68,200
Paku 5 - 10 cm kg 0.3 Rp 17,210 Rp 5,163
Minyak bekisting Liter 0.1 Rp 40,000 Rp 4,000
Jumlah Harga Bahan Rp 77,363
C Harga satuan pekerjaan (A+B) Rp 171,283
C.5. (K3) Pemasangan 1 m2 bekisting untuk sloof
A Tenaga
Pekerja OH 0.52 Rp 101,036 Rp 52,539
Tukang kayu OH 0.26 Rp 126,300 Rp 32,838
Kepala tukang OH 0.026 Rp 151,600 Rp 3,942
Mandor OH 0.026 Rp 177,000 Rp 4,602
Jumlah Harga Tenaga Kerja Rp 93,920
B Bahan
Kayu kelas III m3 0.045 Rp 1,705,000 Rp 76,725
Paku 5 - 10 cm kg 0.3 Rp 17,210 Rp 5,163
Minyak bekisting Liter 0.1 Rp 40,000 Rp 4,000
Jumlah Harga Bahan Rp 85,888
C Harga satuan pekerjaan (A+B) Rp 179,808
C.6. (K3) Pemasangan 1 m2 bekisting untuk kolom
A Tenaga
Pekerja OH 0.66 Rp 101,036 Rp 66,684
Tukang kayu OH 0.33 Rp 126,300 Rp 41,679
Kepala tukang OH 0.033 Rp 151,600 Rp 5,003
Mandor OH 0.033 Rp 177,000 Rp 5,841
Jumlah Harga Tenaga Kerja Rp 119,207
B Bahan
Kayu kelas III m3 0.04 Rp 1,705,000 Rp 68,200
Paku 5 - 10 cm kg 0.4 Rp 17,210 Rp 6,884
Minyak bekisting Liter 0.2 Rp 40,000 Rp 8,000
Balok kayu kelas II m3 0.015 Rp 4,445,000 Rp 66,675
Plywood tebal 9 mm Lbr 0.35 Rp 323,000 Rp 113,050
Dolken kayu D8 - 10 cm -
Batang 2 Rp 29,600 Rp 59,200
panjang 4m
Jumlah Harga Bahan Rp 322,009
C Harga satuan pekerjaan (A+B) Rp 441,216
C.7. (K3) Pemasangan 1 m2 bekisting untuk balok
A Tenaga

35
Pekerja OH 0.66 Rp 101,036 Rp 66,684
Tukang kayu OH 0.33 Rp 126,300 Rp 41,679
Kepala tukang OH 0.033 Rp 151,600 Rp 5,003
Mandor OH 0.033 Rp 177,000 Rp 5,841
Jumlah Harga Tenaga Kerja Rp 119,207
B Bahan
Kayu kelas III m3 0.04 Rp 1,705,000 Rp 68,200
Paku 5 - 10 cm kg 0.4 Rp 17,210 Rp 6,884
Minyak bekisting Liter 0.2 Rp 40,000 Rp 8,000
Balok kayu kelas II m3 0.018 Rp 4,445,000 Rp 80,010
Plywood tebal 9 mm Lbr 0.35 Rp 323,000 Rp 113,050
Dolken kayu D8 - 10 cm -
Batang 2 Rp 29,600 Rp 59,200
panjang 4m
Jumlah Harga Bahan Rp 335,344
C Harga satuan pekerjaan (A+B) Rp 454,551
C.8. (K3) Pemasangan 1 m2 bekisting untuk lantai
A Tenaga
Pekerja OH 0.66 Rp 101,036 Rp 66,684
Tukang kayu OH 0.33 Rp 126,300 Rp 41,679
Kepala tukang OH 0.033 Rp 151,600 Rp 5,003
Mandor OH 0.033 Rp 177,000 Rp 5,841
Jumlah Harga Tenaga Kerja Rp 119,207
B Bahan
Kayu kelas III m3 0.04 Rp 1,705,000 Rp 68,200
Paku 5 - 10 cm kg 0.4 Rp 17,210 Rp 6,884
Minyak bekisting Liter 0.2 Rp 40,000 Rp 8,000
Balok kayu kelas II m3 0.015 Rp 4,445,000 Rp 66,675
Plywood tebal 9 mm Lbr 0.35 Rp 323,000 Rp 113,050
Dolken kayu D8 - 10 cm -
Batang 6 Rp 29,600 Rp 177,600
panjang 4m
Jumlah Harga Bahan Rp 440,409
C Harga satuan pekerjaan (A+B) Rp 559,616

36
V.4. Pekerjaan Atap

D Pekerjaan Atap
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
D.1. Pemasangan 1 m2 genteng beton
A. Tenaga
Pekerja OH 0.2 Rp 101,036 Rp 20,207
Tukang batu OH 0.1 Rp 126,300 Rp 12,630
Kepala tukang OH 0.01 Rp 151,600 Rp 1,516
Mandor OH 0.01 Rp 177,000 Rp 1,770
Jumlah Harga Tenaga Kerja Rp 36,123
B Bahan
Genteng beton buah 11 Rp 9,000 Rp 99,000
Paku biasa 2"-5" kg 0.03 Rp 17,210 Rp 516
Jumlah Harga Bahan Rp 99,516
C Harga satuan pekerjaan (A+B) Rp 135,640
D.2. Pemasangan 1 m' nok genteng beton
A. Tenaga
Pekerja OH 0.4 Rp 101,036 Rp 40,414
Tukang batu OH 0.2 Rp 126,300 Rp 25,260
Kepala tukang OH 0.02 Rp 151,600 Rp 3,032
Mandor OH 0.02 Rp 177,000 Rp 3,540
Jumlah Harga Tenaga Kerja Rp 72,246
B Bahan
Nok genteng beton buah 3.5 Rp 5,500 Rp 19,250
Paku biasa 1/2"-1" kg 0.05 Rp 17,210 Rp 861
Semen PC kg 10.8 Rp 1,376 Rp 14,861
Pasir pasang m3 0.032 Rp 132,278 Rp 4,233
Semen warna kg 1 Rp 13,250 Rp 13,250
Jumlah Harga Bahan Rp 52,454
C Harga satuan pekerjaan (A+B) Rp 124,701
D.3. Pemasangan 1 m' nok samping genteng beton
A. Tenaga
Pekerja OH 0.4 Rp 101,036 Rp 40,414
Tukang batu OH 0.2 Rp 126,300 Rp 25,260
Kepala tukang OH 0.02 Rp 151,600 Rp 3,032
Mandor OH 0.02 Rp 177,000 Rp 3,540
Jumlah Harga Tenaga Kerja Rp 72,246
B Bahan

37
Nok samping genteng beton buah 4 Rp 13,000 Rp 52,000
Paku biasa 1/2"-1" kg 0.05 Rp 17,210 Rp 861
Semen PC kg 10.8 Rp 1,376 Rp 14,861
Pasir pasang m3 0.032 Rp 132,278 Rp 4,233
Semen warna kg 1 Rp 13,250 Rp 13,250
Jumlah Harga Bahan Rp 85,204
C Harga satuan pekerjaan (A+B) Rp 157,451

V.5. Pekerjaan Dinding

E Pekerjaan Dinding
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
E.1. Pemasangan 1 m2 dinding bata merah ukuran (5x11x22) cm tebal 1/2 bata, campuran spesi 1PC:3PP
A Tenaga
Pekerja OH 0.3 Rp 101,036 Rp 30,311
Tukang batu OH 0.1 Rp 126,300 Rp 12,630
Kepala tukang OH 0.01 Rp 151,600 Rp 1,516
Mandor OH 0.015 Rp 177,000 Rp 2,655
Jumlah Harga Tenaga Kerja Rp 47,112
B Bahan
Bata merah buah 70 Rp 798 Rp 55,860
Semen portland kg 14.37 Rp 1,376 Rp 19,773
Pasir pasang m3 0.04 Rp 132,278 Rp 5,291
Jumlah Harga Bahan Rp 80,924
C Harga satuan pekerjaan (A+B) Rp 128,036
E.2. Pemasangan 1 m2 plesteran 1PC : 2PP tebal 15 mm
A Tenaga
Pekerja OH 0.3 Rp 101,036 Rp 30,311
Tukang batu OH 0.15 Rp 126,300 Rp 18,945
Kepala tukang OH 0.015 Rp 151,600 Rp 2,274
Mandor OH 0.015 Rp 177,000 Rp 2,655
Jumlah Harga Tenaga Kerja Rp 54,185
B Bahan
PC kg 10.224 Rp 1,376 Rp 14,068
PP m3 0.02 Rp 132,278 Rp 2,646
Jumlah Harga Bahan Rp 16,714
C Harga satuan pekerjaan (A+B) Rp 70,899
E.3. Pemasangan 1 m2 acian
A Tenaga

38
Pekerja OH 0.2 Rp 101,036 Rp 20,207
Tukang batu OH 0.1 Rp 126,300 Rp 12,630
Kepala tukang OH 0.01 Rp 151,600 Rp 1,516
Mandor OH 0.01 Rp 177,000 Rp 1,770
Jumlah Harga Tenaga Kerja Rp 36,123
B Bahan
Semen PC kg 3.25 Rp 1,376 Rp 4,472
Jumlah Harga Bahan Rp 4,472
C Harga satuan pekerjaan (A+B) Rp 40,595

V.6. Pekerjaan Lantai + Plint

F Pekerjaan Lantai + Plint


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
F.1. Pemasangan 1 m2 lantai ubin keramik ukuran (30x30) cm
A Tenaga
Pekerja OH 0.7 Rp 101,036 Rp 70,725
Tukang batu OH 0.35 Rp 126,300 Rp 44,205
Kepala Tukang OH 0.035 Rp 151,600 Rp 5,306
Mandor OH 0.035 Rp 177,000 Rp 6,195
Jumlah Harga Tenaga Kerja Rp 126,431
B Bahan
Ubin Keramik 30 x 30 Doos 1.05 Rp 100,000 Rp 105,000
Semen PC kg 10 Rp 1,376 Rp 13,760
Pasir pasang m3 0.045 Rp 132,278 Rp 5,953
Semen Warna kg 0.5 Rp 13,250 Rp 6,625
Jumlah Harga Bahan Rp 131,338
C Harga satuan pekerjaan (A+B) Rp 257,769
F.2. Memasang 1 m2 lantai keramik ukuran (40x40) cm
A Tenaga
Pekerja OH 0.7 Rp 101,036 Rp 70,725
Tukang batu OH 0.35 Rp 126,300 Rp 44,205
Kepala Tukang OH 0.035 Rp 151,600 Rp 5,306
Mandor OH 0.035 Rp 177,000 Rp 6,195
Jumlah Harga Tenaga Kerja Rp 126,431
B Bahan
Ubin Keramik 40 x 40 Doos 1.05 Rp 120,750 Rp 126,788
Semen PC kg 9.8 Rp 1,376 Rp 13,485
Pasir pasang m3 0.045 Rp 132,278 Rp 5,953

39
Semen Warna Kg 0.5 Rp 13,250 Rp 6,625
Jumlah Harga Bahan Rp 152,850
C Harga satuan pekerjaan (A+B) Rp 279,281
F.3. Memasang 1 m2 lantai keramik ukuran (60x60) cm
A Tenaga
Pekerja OH 0.7 Rp 101,036 Rp 70,725
Tukang batu OH 0.35 Rp 126,300 Rp 44,205
Kepala Tukang OH 0.035 Rp 151,600 Rp 5,306
Mandor OH 0.035 Rp 177,000 Rp 6,195
Jumlah Harga Tenaga Kerja Rp 126,431
B Bahan
Ubin Keramik 60 x 60 Doos 1.05 Rp 145,650 Rp 152,933
Semen PC kg 9.4 Rp 1,376 Rp 12,934
Pasir pasang m3 0.045 Rp 132,278 Rp 5,953
Semen Warna kg 0.5 Rp 13,250 Rp 6,625
Jumlah Harga Bahan Rp 178,444
C Harga satuan pekerjaan (A+B) Rp 304,876
F.4. Memasang 1 m2 lantai keramik ukuran (30x60) cm
A Tenaga
Pekerja OH 0.7 Rp 101,036 Rp 70,725
Tukang batu OH 0.35 Rp 126,300 Rp 44,205
Kepala Tukang OH 0.035 Rp 151,600 Rp 5,306
Mandor OH 0.035 Rp 177,000 Rp 6,195
Jumlah Harga Tenaga Kerja Rp 126,431
B Bahan
Ubin Keramik 30 x 60 Doos 1.050 Rp 128,000 Rp 134,400
Semen PC kg 9.75 Rp 1,376 Rp 13,416
Pasir pasang m3 0.045 Rp 132,278 Rp 5,953
Semen Warna kg 0.5 Rp 13,250 Rp 6,625
Jumlah Harga Bahan Rp 160,394
C Harga satuan pekerjaan (A+B) Rp 286,825
F.5. Memasang 1 m2 lantai granit ukuran (60x60) cm
A Tenaga
Pekerja OH 0.7 Rp 101,036 Rp 70,725
Tukang batu OH 0.35 Rp 126,300 Rp 44,205
Kepala Tukang OH 0.035 Rp 151,600 Rp 5,306
Mandor OH 0.035 Rp 177,000 Rp 6,195
Jumlah Harga Tenaga Kerja Rp 126,431
B Bahan

40
Granit Surface Matt Coal Doos 1.05 Rp 209,650 Rp 220,133
Semen PC kg 9.4 Rp 1,376 Rp 12,934
Pasir pasang kg 0.045 Rp 132,278 Rp 5,953
Semen warna m3 0.9 Rp 13,250 Rp 11,925
Jumlah Harga Bahan Rp 250,944
C Harga satuan pekerjaan (A+B) Rp 377,376
F.6. Pemasangan 1 m1 plint ubin granit ukuran 10cm x 60cm
A Tenaga
Pekerja OH 0.09 Rp 101,036 Rp 9,093
Tukang batu OH 0.09 Rp 126,300 Rp 11,367
Kepala Tukang OH 0.009 Rp 151,600 Rp 1,364
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 22,710
B Bahan
Plint Ubin Granit bh 1.84 Rp 8,500 Rp 15,640
Semen PC kg 1.12 Rp 1,376 Rp 1,541
Semen Warna kg 0.1 Rp 13,250 Rp 1,325
Pasir Pasang m3 0.003 Rp 132,278 Rp 397
Jumlah Harga Bahan Rp 18,903
C Harga satuan pekerjaan (A+B) Rp 41,613
F.7. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 60 cm
A Tenaga
Pekerja OH 0.09 Rp 101,036 Rp 9,093
Tukang batu OH 0.09 Rp 126,300 Rp 11,367
Kepala Tukang OH 0.009 Rp 151,600 Rp 1,364
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 22,710
B Bahan
Plint Ubin Keramik 10 cm x 60
bh 1.84 Rp 2,428 Rp 4,467
cm
Semen PC kg 1.12 Rp 1,376 Rp 1,541
Semen Warna kg 0.1 Rp 13,250 Rp 1,325
Pasir Pasang m3 0.003 Rp 132,278 Rp 397
Jumlah Harga Bahan Rp 7,730
C Harga satuan pekerjaan (A+B) Rp 30,439
F.8. Pemasangan 1 m1 plint ubin warna ukuran 10cm x 40cm
A Tenaga
Pekerja OH 0.09 Rp 101,036 Rp 9,093
Tukang batu OH 0.09 Rp 126,300 Rp 11,367
Kepala Tukang OH 0.009 Rp 151,600 Rp 1,364

41
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 22,710
B Bahan
Plint Ubin Keramik 10cm x40
bh 2.65 Rp 3,019 Rp 8,000
cm
Semen PC kg 1.14 Rp 1,376 Rp 1,569
Semen Warna kg 0.1 Rp 13,250 Rp 1,325
Pasir Pasang m3 0.003 Rp 132,278 Rp 397
Jumlah Harga Bahan Rp 11,290
C Harga satuan pekerjaan (A+B) Rp 34,000
F.9. Pemasangan 1 m1 plint Keramik ukuran 10cm x 30cm
A Tenaga
Pekerja OH 0.09 Rp 101,036 Rp 9,093
Tukang batu OH 0.09 Rp 126,300 Rp 11,367
Kepala Tukang OH 0.009 Rp 151,600 Rp 1,364
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 22,710
B Bahan
Plint Ubin Keramik 10cm x
bh 3.53 Rp 3,333 Rp 11,767
30cm
Semen PC kg 1.14 Rp 1,376 Rp 1,569
Semen Warna kg 0.1 Rp 13,250 Rp 1,325
Pasir Pasang m3 0.003 Rp 132,278 Rp 397
Jumlah Harga Bahan Rp 15,057
C Harga satuan pekerjaan (A+B) Rp 37,767

42
V.7. Pekerjaan Pengecatan

G Pekerjaan Pengecatan
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
G.1. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
A Tenaga
Pekerja OH 0.02 Rp 101,036 Rp 2,021
Tukang batu OH 0.063 Rp 126,300 Rp 7,957
Kepala Tukang OH 0.0063 Rp 151,600 Rp 955
Mandor OH 0.003 Rp 177,000 Rp 531
Jumlah Harga Tenaga Kerja Rp 11,464
B Bahan
Plamuur kg 0.1 Rp 13,500 Rp 1,350
Cat Dasar kg 0.1 Rp 50,820 Rp 5,082
Cat Penutup kg 0.26 Rp 54,232 Rp 14,100
Jumlah Harga Bahan Rp 20,532
C Harga satuan pekerjaan (A+B) Rp 31,996

V.8. Pekerjaan Mechanical Electrical dan Plumbing

H Pekerjaan Mechanical Electrical dan Plumbing


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
H.1. Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 1/2"
A Tenaga
Pekerja OH 0.036 Rp 101,036 Rp 3,637
Tukang batu OH 0.06 Rp 126,300 Rp 7,578
Kepala tukang batu OH 0.006 Rp 151,600 Rp 910
Mandor OH 0.002 Rp 177,000 Rp 354
Jumlah Harga Tenaga Kerja Rp 12,479
B Bahan
Pipa PVC 1/2" m 1.2 Rp 5,275 Rp 6,330
Perlengkapan % 35 Rp 1,846 Rp 646
Jumlah Harga Bahan Rp 6,976
C Harga satuan pekerjaan (A+B) Rp 19,455
H.2 Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 3/4"
A Tenaga
Pekerja OH 0.036 Rp 101,036 Rp 3,637
Tukang batu OH 0.06 Rp 126,300 Rp 7,578
Kepala tukang batu OH 0.006 Rp 151,600 Rp 910

43
Mandor OH 0.002 Rp 177,000 Rp 354
Jumlah Harga Tenaga Kerja Rp 12,479
B Bahan
Pipa PVC 3/4" m 1.2 Rp 7,200 Rp 8,640
Perlengkapan % 35 Rp 2,520 Rp 882
Jumlah Harga Bahan Rp 9,522
C Harga satuan pekerjaan (A+B) Rp 22,001
H.3. Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 1"
A Tenaga
Pekerja OH 0.036 Rp 101,036 Rp 3,637
Tukang batu OH 0.06 Rp 126,300 Rp 7,578
Kepala tukang batu OH 0.006 Rp 151,600 Rp 910
Mandor OH 0.002 Rp 177,000 Rp 354
Jumlah Harga Tenaga Kerja Rp 12,479
B Bahan
Pipa PVC 1" m 1.2 Rp 9,825 Rp 11,790
Perlengkapan % 35 Rp 3,439 Rp 1,204
Jumlah Harga Bahan Rp 12,994
C Harga satuan pekerjaan (A+B) Rp 25,472
H.4. Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 1 1/4"
A Tenaga
Pekerja OH 0.054 Rp 101,036 Rp 5,456
Tukang batu OH 0.09 Rp 126,300 Rp 11,367
Kepala tukang batu OH 0.009 Rp 151,600 Rp 1,364
Mandor OH 0.003 Rp 177,000 Rp 531
Jumlah Harga Tenaga Kerja Rp 18,718
B Bahan
Pipa PVC 1 1/4" m 1.2 Rp 14,725 Rp 17,670
Perlengkapan % 35 Rp 5,154 Rp 1,804
Jumlah Harga Bahan Rp 19,474
C Harga satuan pekerjaan (A+B) Rp 38,192
H.5. Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 3"
A Tenaga
Pekerja OH 0.081 Rp 101,036 Rp 8,184
Tukang batu OH 0.135 Rp 126,300 Rp 17,051
Kepala tukang batu OH 0.0135 Rp 151,600 Rp 2,047
Mandor OH 0.004 Rp 177,000 Rp 708
Jumlah Harga Tenaga Kerja Rp 27,989
B Bahan

44
Pipa PVC 3" m 1.2 Rp 24,025 Rp 28,830
Perlengkapan % 35 Rp 8,409 Rp 2,943
Jumlah Harga Bahan Rp 31,773
C Harga satuan pekerjaan (A+B) Rp 59,762
H.6. Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 4"
A Tenaga
Pekerja OH 0.081 Rp 101,036 Rp 8,184
Tukang batu OH 0.135 Rp 126,300 Rp 17,051
Kepala tukang batu OH 0.0135 Rp 151,600 Rp 2,047
Mandor OH 0.004 Rp 177,000 Rp 708
Jumlah Harga Tenaga Kerja Rp 27,989
B Bahan
Pipa PVC 4" m 1.2 Rp 37,800 Rp 45,360
Perlengkapan % 35 Rp 13,230 Rp 4,631
Jumlah Harga Bahan Rp 49,991
C Harga satuan pekerjaan (A+B) Rp 77,980
H.7. Pemasangan 1 m1 Pipa PVC Tipe AW Diameter 6"
A Tenaga
Pekerja OH 0.081 Rp 101,036 Rp 8,184
Tukang batu OH 0.135 Rp 126,300 Rp 17,051
Kepala tukang batu OH 0.0135 Rp 151,600 Rp 2,047
Mandor OH 0.004 Rp 177,000 Rp 708
Jumlah Harga Tenaga Kerja Rp 27,989
B Bahan
Pipa PVC 6" m 1.2 Rp 76,825 Rp 92,190
Perlengkapan % 35 Rp 26,889 Rp 9,411
Jumlah Harga Bahan Rp 101,601
C Harga satuan pekerjaan (A+B) Rp 129,590

45
V.9. Pekerjaan Kusen, Pintu, dan Jendela

I Pekerjaan Kusen, Pintu, dan Jendela


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
I.1 Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
A Tenaga
Pekerja OH 6 Rp 101,036 Rp 606,216
Tukang Kayu OH 18 Rp 126,300 Rp 2,273,400
Kepala Tukang OH 1.8 Rp 151,600 Rp 272,880
Mandor OH 0.3 Rp 177,000 Rp 53,100
Jumlah Harga Tenaga Kerja Rp 3,205,596

B Bahan
Balok kayu m3 1.1 Rp 4,445,000 Rp 4,889,500
Paku 10 cm kg 1.25 Rp 177,210 Rp 221,513
Lem kayu kg 1.1 Rp 19,250 Rp 21,175
Jumlah Harga Bahan Rp 5,132,188
C Harga satuan pekerjaan (A+B) Rp 8,337,784
I.2. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas 1
A Pekerja OH 0.8 Rp 101,036 Rp 80,829
Tukang Kayu OH 2.4 Rp 126,300 Rp 303,120
Kepala Tukang OH 0.24 Rp 151,600 Rp 36,384
Mandor OH 0.04 Rp 177,000 Rp 7,080
Jumlah Harga Tenaga Kerja Rp 427,413

B Papan kayu m3 0.025 Rp 5,147,000 Rp 128,675


Paku 1-2,5 cm kg 0.03 Rp 19,250 Rp 578
Lem kayu kg 0.3 Rp 19,250 Rp 5,775
Teakwood tebal 4mm
Lembar 1 Rp 48,400 Rp 48,400
ukuran(90x220)cm
Jumlah Harga Bahan Rp 183,428
C Harga satuan pekerjaan (A+B) Rp 610,840

I.3. Pemasangan 1 m3 kusen pintu (jendela) alumunium


A Tenaga
Pekerja OH 0.043 Rp 101,036 Rp 4,345
Tukang khusus alm OH 0.043 Rp 126,300 Rp 5,431
Kepala Tukang OH 0.0043 Rp 151,600 Rp 652
Mandor OH 0.0021 Rp 177,000 Rp 372
Jumlah Harga Tenaga Kerja Rp 10,799

46
B Bahan
Profil alumunium m 1.1 Rp 220,000 Rp 242,000
Skrup Fixer buah 2 Rp 400 Rp 800
Sealant tube 0.06 Rp 34,000 Rp 2,040
Jumlah Harga Bahan Rp 244,840
C Harga satuan pekerjaan (A+B) Rp 255,639
I.4. Pemasangan 1 m2 pintu kaca rangka alumunium
A Tenaga
Pekerja OH 0.085 Rp 101,036 Rp 8,588
Tukang alm/ kaca OH 0.085 Rp 126,300 Rp 10,736
Kepala Tukang OH 0.009 Rp 151,600 Rp 1,364
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 21,573
B Bahan
Pintu alumunium m 4.4 Rp 49,720 Rp 218,768
Profil Kaca m 4.5 Rp 192,500 Rp 866,250
Sealant tube 0.27 Rp 34,000 Rp 9,180
Jumlah Harga Bahan Rp 1,094,198
C Harga satuan pekerjaan (A+B) Rp 1,115,771

47
V.10. Pekerjaan Pagar

J Pekerjaan Pagar
J.1. Menggali 1 m3 tanah biasa sedalam 2 m
A Tenaga
Pekerja OH 0.9 Rp 101,036 Rp 90,932
Mandor OH 0.045 Rp 177,000 Rp 7,965
Harga satuan pekerjaan (A) Rp 98,897
J.2. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 PP
A Tenaga
Pekerja OH 1.5 Rp 101,036 Rp 151,554
Tukang batu OH 0.75 Rp 126,300 Rp 94,725
Kepala tukang OH 0.075 Rp 151,600 Rp 11,370
Mandor OH 0.075 Rp 177,000 Rp 13,275
Jumlah Harga Tenaga Kerja Rp 270,924
B Bahan
Batu belah m3 1.2 Rp 113,030 Rp 135,636
Semen portland kg 202 Rp 1,376 Rp 277,952
Pasir pasang m3 0.485 Rp 132,278 Rp 64,155
Jumlah Harga Bahan Rp 477,743
C Harga satuan pekerjaan (A+B) Rp 748,667
J.3. Membuat 1 m3 beton mutu f'c = 19,3 Mpa
A Tenaga Kerja
Pekerja OH 1.65 Rp 101,036 Rp 166,709
Tukang Batu OH 0.275 Rp 126,300 Rp 34,733
Kepala Tukang OH 0.028 Rp 151,600 Rp 4,245
Mandor OH 0.083 Rp 177,000 Rp 14,691
Jumlah Harga Tenaga Kerja Rp 220,378
B Bahan
PC / Portland Cement kg 371 Rp 1,376 Rp 510,422
PB / Pasir Beton kg 698 Rp 150 Rp 104,969
Kr / Kerikil kg 1047 Rp 145 Rp 151,326
Air Liter 215 Rp 6 Rp 1,290
Jumlah Harga Bahan Rp 768,007
C Harga satuan pekerjaan (A+B) Rp 988,385
J.4. Pembesian 1 kg dengan besi polos atau besi ulir
A Tenaga
Pekerja OH 0.007 Rp 101,036 Rp 707
Tukang besi OH 0.007 Rp 126,300 Rp 884

48
Kepala tukang OH 0.0007 Rp 151,600 Rp 106
Mandor OH 0.0004 Rp 177,000 Rp 71
Jumlah Harga Tenaga Kerja Rp 1,768
B Bahan
Besi beton (polos / ulir) kg 1.05 Rp 11,847 Rp 12,439
Kawat beton kg 0.015 Rp 18,571 Rp 279
Jumlah Harga Bahan Rp 12,718
C Harga satuan pekerjaan (A+B) Rp 14,486
J.5. (K3) Pemasangan 1 m2 bekisting untuk sloof
A Tenaga
Pekerja OH 0.52 Rp 101,036 Rp 52,539
Tukang kayu OH 0.26 Rp 126,300 Rp 32,838
Kepala tukang OH 0.026 Rp 151,600 Rp 3,942
Mandor OH 0.026 Rp 177,000 Rp 4,602
Jumlah Harga Tenaga Kerja Rp 93,920
B Bahan
Kayu kelas III m3 0.045 Rp 1,705,000 Rp 76,725
Paku 5 - 10 cm kg 0.3 Rp 17,210 Rp 5,163
Minyak bekisting Liter 0.1 Rp 40,000 Rp 4,000
Jumlah Harga Bahan Rp 85,888
C Harga satuan pekerjaan (A+B) Rp 179,808
J.6 (K3) Pemasangan 1 m2 bekisting untuk kolom
A Tenaga
Pekerja OH 0.66 Rp 101,036 Rp 66,684
Tukang kayu OH 0.33 Rp 126,300 Rp 41,679
Kepala tukang OH 0.033 Rp 151,600 Rp 5,003
Mandor OH 0.033 Rp 177,000 Rp 5,841
Jumlah Harga Tenaga Kerja Rp 119,207
B Bahan
Kayu kelas III m3 0.04 Rp 1,705,000 Rp 68,200
Paku 5 - 10 cm kg 0.4 Rp 17,210 Rp 6,884
Minyak bekisting Liter 0.2 Rp 40,000 Rp 8,000
Balok kayu kelas II m3 0.015 Rp 4,445,000 Rp 66,675
Plywood tebal 9 mm Lbr 0.35 Rp 323,000 Rp 113,050
Dolken kayu D8 - 10 cm -
Batang 2 Rp 29,600 Rp 59,200
panjang 4m
Jumlah Harga Bahan Rp 322,009
C Harga satuan pekerjaan (A+B) Rp 441,216
J.7. Pemasangan 1 m2 dinding bata merah ukuran (5x11x22) cm tebal 1/2 bata, campuran spesi 1PC:5PP
A Tenaga

49
Pekerja OH 0.3 Rp 101,036 Rp 30,311
Tukang batu OH 0.1 Rp 126,300 Rp 12,630
Kepala tukang OH 0.01 Rp 151,600 Rp 1,516
Mandor OH 0.015 Rp 177,000 Rp 2,655
Jumlah Harga Tenaga Kerja Rp 47,112
B Bahan
Bata merah buah 70 Rp 798 Rp 55,860
Semen portland kg 9.68 Rp 1,376 Rp 13,320
Pasir pasang m3 0.045 Rp 132,278 Rp 5,953
Jumlah Harga Bahan Rp 75,132
C Harga satuan pekerjaan (A+B) Rp 122,244
J.8. Pemasangan 1 m2 plesteran 1PC : 2PP tebal 15 mm
A Tenaga
Pekerja OH 0.3 Rp 101,036 Rp 30,311
Tukang batu OH 0.15 Rp 126,300 Rp 18,945
Kepala tukang OH 0.015 Rp 151,600 Rp 2,274
Mandor OH 0.015 Rp 177,000 Rp 2,655
Jumlah Harga Tenaga Kerja Rp 54,185
B Bahan
PC kg 10.224 Rp 1,376 Rp 14,068
PP m3 0.02 Rp 132,278 Rp 2,646
Jumlah Harga Bahan Rp 16,714
C Harga satuan pekerjaan (A+B) Rp 70,899
J.9. Pemasangan 1 m2 acian
A Tenaga
Pekerja OH 0.2 Rp 101,036 Rp 20,207
Tukang batu OH 0.1 Rp 126,300 Rp 12,630
Kepala tukang OH 0.01 Rp 151,600 Rp 1,516
Mandor OH 0.01 Rp 177,000 Rp 1,770
Jumlah Harga Tenaga Kerja Rp 36,123
B Bahan
Semen PC kg 3.25 Rp 1,376 Rp 4,472
Jumlah Harga Bahan Rp 4,472
C Harga satuan pekerjaan (A+B) Rp 40,595

50
V.11. Pekerjaan Tangga

K Pekerjaan Tangga
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
K.1. Membuat 1 m3 beton mutu f’c = 19,3 MPa
A Tenaga
Pekerja OH 1.65 Rp 101,036 Rp 166,709
Tukang batu OH 0.275 Rp 126,300 Rp 34,733
Kepala Tukang OH 0.028 Rp 151,600 Rp 4,245
Mandor OH 0.083 Rp 177,000 Rp 14,691
Jumlah Harga Tenaga Kerja Rp 220,378
B Bahan
Semen PC kg 371 Rp 1,376 Rp 510,496
Pasir Beton kg 698 Rp 150 Rp 104,969
Kerikil (Maks 30 mm) kg 1047 Rp 145 Rp 151,326
Air Liter 215 Rp 6 Rp 1,290
Jumlah Harga Bahan Rp 768,082
C Harga satuan pekerjaan (A+B) Rp 988,459
K.2. Pembesian 1 kg dengan besi polos atau besi ulir
A Tenaga
Pekerja OH 0.007 Rp 101,036 Rp 707
Tukang besi OH 0.007 Rp 126,300 Rp 884
Kepala Tukang OH 0.0007 Rp 151,600 Rp 106
Mandor OH 0.0004 Rp 177,000 Rp 71
Jumlah Harga Tenaga Kerja Rp 1,768
B Bahan
Besi Beton (polos/ulir) kg 1.05 Rp 11,847 Rp 12,439
Kawat Beton kg 0.015 Rp 18,571 Rp 279
Jumlah Harga Bahan Rp 12,718
C Harga satuan pekerjaan (A+B) Rp 14,486
K.3. Pemasangan 1 m2 bekisting untuk tangga
A Tenaga
Pekerja OH 0.66 Rp 101,036 Rp 66,684
Tukang kayu OH 0.33 Rp 126,300 Rp 41,679
Kepala Tukang OH 0.033 Rp 151,600 Rp 5,003
Mandor OH 0.033 Rp 177,000 Rp 5,841
Jumlah Harga Tenaga Kerja Rp 119,207
B Bahan
Kayu kelas III m3 0.03 Rp 1,705,000 Rp 51,150

51
Paku 5cm - 12 cm kg 0.4 Rp 17,210 Rp 6,884
Minyak bekisting Liter 0.15 Rp 40,000 Rp 6,000
Balok kayu kelas II m3 0.015 Rp 4,445,000 Rp 66,675
Plywood tebal 9 mm Lbr 0.35 Rp 323,000 Rp 113,050
Dolken Kayu d8-10cm - panjang
Batang 2 Rp 29,600 Rp 59,200
4m
Jumlah Harga Bahan Rp 302,959
C Harga satuan pekerjaan (A+B) Rp 422,166
K.4. Pemasangan 1 m3 pasangan bata merah
A Tenaga
Pekerja OH 2.4 Rp 177,000 Rp 424,800
Tukang batu OH 1.2 Rp 126,300 Rp 151,560
Mandor OH 0.24 Rp 177,000 Rp 42,480
Jumlah Harga Tenaga Kerja Rp 618,840
B Bahan
Bata merah buah 3.108 Rp 798 Rp 2,480
Portland cement kg 0.4 Rp 1,376 Rp 550
Pasir pasang m3 0.15 Rp 132,278 Rp 19,842
Jumlah Harga Bahan Rp 22,872
C Harga satuan pekerjaan (A+B) Rp 641,712
Arsitektur Tangga
K.5. Pemasangan 1 m2 lantai keramik 30x30
A Tenaga
Pekerja OH 0.7 Rp 101,036 Rp 70,725
Tukang batu OH 0.35 Rp 126,300 Rp 44,205
Kepala Tukang OH 0.035 Rp 151,600 Rp 5,306
Mandor OH 0.035 Rp 177,000 Rp 6,195
Jumlah Harga Tenaga Kerja Rp 126,431
B Bahan
Ubin keramik doos 1.05 Rp 100,000 Rp 105,000
Semen protland kg 10 Rp 1,376 Rp 13,760
Pasir pasang m3 0.045 Rp 132,278 Rp 5,953
Semen warna kg 0.5 Rp 13,250 Rp 6,625
Jumlah Harga Bahan Rp 131,338
C Harga satuan pekerjaan (A+B) Rp 257,769
K.6. Pemasangan 1 m2 plint ubin warna ukuran 10x30
A Tenaga
Pekerja OH 0.09 Rp 101,036 Rp 9,093
Tukang batu OH 0.09 Rp 126,300 Rp 11,367
Kepala Tukang OH 0.009 Rp 151,600 Rp 1,364

52
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 22,710
B Bahan
Plint ubin keramik 10cmx30cm bh 3.53 Rp 3,333 Rp 11,767
Semen protland kg 1.14 Rp 1,376 Rp 1,569
Semen warna kg 0.1 Rp 13,250 Rp 1,325
Pasir pasang m3 0.003 Rp 132,278 Rp 397
Jumlah Harga Bahan Rp 15,057
C Harga satuan pekerjaan (A+B) Rp 37,767

V.12. Pekerjaan Plafond

L Pekerjaan Plafond
No. Uraian` Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
L.1. Pemasangan 1 m2 Plafond Gypsum Board, tebal 9 mm + rangka besi hollow
A Tenaga
Pekerja OH 0.1 Rp 101,036 Rp 10,104
Tukang batu OH 0.05 Rp 126,300 Rp 6,315
Kepala Tukang OH 0.005 Rp 151,600 Rp 758
Mandor OH 0.005 Rp 177,000 Rp 885
Jumlah Harga Tenaga Kerja Rp 18,062
B Bahan
Hollow 4/4 Zincromate Btg 0.45 Rp 29,000 Rp 13,050
Hollow 2/4 Zincromate Btg 0.15 Rp 22,600 Rp 3,390
Gypsum board (120x240x9)mm Lbr 0.364 Rp 79,800 Rp 29,047
Paku Gypsum kg 0.11 Rp 17,500 Rp 1,925
Ramset/Dina Bolt Bh 4 Rp 7,200 Rp 28,800
Cotton plaster Bh 0.072 Rp 15,000 Rp 1,080
Compoun Zak 0.125 Rp 75,000 Rp 77,292
Jumlah Harga Bahan Rp 154,584
C Harga satuan pekerjaan (A+B) Rp 172,646

53
V.13. Pekerjaan List Plafond

M Pekerjaan ListPlafond
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
M.1. Pemasangan 1 m2 list Plafond Gypsum 10 cm
A Tenaga
Pekerja OH 0.05 Rp 101,036 Rp 5,052
Tukang batu OH 0.05 Rp 126,300 Rp 6,315
Kepala Tukang OH 0.005 Rp 151,600 Rp 758
Mandor OH 0.003 Rp 177,000 Rp 531
Jumlah Harga Tenaga Kerja Rp 12,656
B Bahan
List Gypsum m1 1.05 Rp 8,500 Rp 8,925
Tepung Gypsum kg 0.15 Rp 12,500 Rp 1,875
Jumlah Harga Bahan Rp 10,800
C Harga satuan pekerjaan (A+B) Rp 23,456

V.14. Pekerjaan Pengecatan Plafond

N Pekerjaan Pengecatan Plafond


No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
N.1. Pengecatan 1 m2 Plafond Gypsum
A Tenaga
Pekerja OH 0.05 Rp 101,036 Rp 5,052
Tukang Cat OH 0.009 Rp 100,000 Rp 900
Kepala Tukang OH 0.005 Rp 151,600 Rp 758
Mandor OH 0.003 Rp 177,000 Rp 531
Jumlah Harga Tenaga Kerja Rp 7,241
B Bahan
Cat Tembok Vinilex kg 0.2 Rp 20,000 Rp 4,000
Plamir Tembok kg 0.16 Rp 13,000 Rp 2,080
Rol Cat bh 0.01 Rp 25,000 Rp 250
Ampelas lbr 0.5 Rp 5,000 Rp 2,500
Jumlah Harga Tenaga Kerja Rp 8,830
C Harga satuan pekerjaan (A+B) Rp 16,071

54
BAB VIII
MASTER SCHEDULE DAN KURVA S

Minggu ke -

Uraian Durasi Bobot Bobot/minggu


No. Total Harga 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Pekerjaan (minggu) (%) (%)

PEKERJAAN Rp
I 2 0.90 0.452 0.452 0.452
PERSIAPAN 15,682,668

PEKERJAAN
Rp
II TANAH DAN 4 4.47 1.116 1.116 1.116 1.116 1.116
77,534,339
URUGAN

PEKERJAAN
Rp
III BETON DAN 14 43.60 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114 3.114
756,997,965
STRUKTUR

PEKERJAAN
Rp
IV KAP / KUDA- 3 4.76 1.587 1.587 1.587 1.587
82,687,287
KUDA + ATAP

PEKERJAAN Rp
V 12 17.36 1.447 1.447 1.447 1.447 1.447 1.447 1.447 1.447 1.447 1.447 1.447 1.447 1.447
DINDING 301,491,521

PEKERJAAN
Rp
VI PINTU DAN 6 3.47 0.578 0.578 0.578 0.578 0.578 0.578 0.578
60,180,595
JENDELA

PEKERJAAN Rp
VII 7 3.14 0.448 0.448 0.448 0.448 0.448 0.448 0.448 0.448
PLAFOND 54,449,150

PEKERJAAN Rp
VIII 9 2.68 0.298 0.298 0.298 0.298 0.298 0.298 0.298 0.298 0.298 0.298
PENGECATAN 46,590,640

PEKERJAAN
FINISHING Rp
IX 8 10.85 1.356 1.356 1.356 1.356 1.356 1.356 1.356 1.356 1.356
LANTAI DAN 188,351,257
DINDING

PEKERJAAN Rp
X 6 2.06 0.344 0.344 0.344 0.344 0.344 0.344 0.344
LISTRIK 35,829,400

PEKERJAAN
Rp
XI SANITARY DAN 8 4.84 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605
84,065,201
PLUMBING

PEKERJAAN Rp
XII 6 1.87 0.312 0.312 0.312 0.312 0.312 0.312 0.312
LAN-LAIN 32,547,213

Progres per minggu 0.452 0.452 1.116 1.116 1.116 1.116 3.114 3.114 3.114 3.114 3.114 4.561 4.561 4.561 4.561 4.561 4.561 7.100 7.443 7.443 5.787 4.431 5.787 3.331 2.987 2.694 0.760 0.611 0.298 0.298 0.611 0.611 0.611 0.298 0.298 0.298
Total Rp 1,736,407,236
Kumulatif progres per minggu (%) 0.452 0.90 2.02 3.14 4.25 5.37 8.48 11.60 14.71 17.82 20.94 25.50 30.06 34.62 39.18 43.74 48.30 55.40 62.85 70.29 76.08 80.51 86.30 89.63 92.61 95.31 96.07 96.68 96.98 97.27 97.88 98.50 99.11 99.40 99.70 100.00

55
DAFTAR PUSTAKA

Menteri Pekerjaan Umum dan Perumahan Rakyat. 2016. Peraturan Menteri


Pekerjaan Umum dan Perumahan Rakyat Nomor 28/PRT/M/2016 tentang
Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum.
Jurnal Harga Satuan Bahan Bangunan, Konstruksi, dan Interior Edisi 37 Tahun 2018
Kota Bandung, Jawa Barat.

56