NIM : 21010116120029
KELAS : A
BAR CHART
2. Lintasan kritis :
pekerjaan Pile and cap west – substructure west – construct in situ span – surface bridge –
finished
Makna lintasan kritis bagi seorang site manager adalah pekerjaan yang tidak boleh terjadi
keterlambatan, karena jika terjadi keterlambatan pada pekerjaan lintasan kritis maka akan
berdampak keterlambatan pada seluruh kegiatan proyek tersebut.
3. Pekerjaan yang boleh terlambat :
a. Pile and cap east
TF = LFj – duration – Esi
= 13 – 10 – 0 = 3
FF = EFj – duration - ESi
= 10 – 10 – 0 = 0
b. Substructure east
TF = LFj – duration – Esi
= 61 – 22 – 10 = 29
FF = EFj – duration - ESi
= 32 – 22 – 10 = 0
c. Pile and cap center
TF = LFj – duration – Esi
= 19 – 6 – 10 = 3
FF = EFj – duration – Esi
= 16 – 6 – 10 = 0
d. Substructure center
TF = LFj – duration – Esi
= 34 – 15 – 16 = 3
FF = EFj – duration - ESi
= 31 – 15 – 16 = 0
e. Construct Precast span
TF = LFj – duration – Esi
= 66 – 5 – 32 = 29
FF = EFj – duration - ESi
= 66 – 5 – 32 = 29
Pekerjaan yang tidak boleh terlambat :
a. Pile and cap west
TF = LFj – duration – Esi
= 10 – 10 – 0 = 0
FF = EFj – duration - ESi
= 10 – 10 – 0 = 0
b. Substructure west
TF = LFj – duration – Esi
= 34 – 24 – 10 = 0
FF = EFj – duration - ESi
= 34 – 24 – 10 = 0
c. Construct in situ span
TF = LFj – duration – Esi
= 66 – 32 – 34 = 0
FF = EFj – duration - ESi
= 66 – 32 – 34 = 0
d. Surface bridge
TF = LFj – duration – Esi
= 71 – 5 – 66 = 0
FF = EFj – duration - ESi
= 71 – 5 – 66 = 0
e. Finished
TF = LFj – duration – Esi
= 84 – 13 – 71 = 0
FF = EFj – duration - ESi
= 84 – 13 – 71 = 0
4. Apabila pekerjaan substructure center terlambat 10 hari maka proyek akan terlambat secara
keseluruhan. Karena waktu keterambatan maksimum yang diijinkan adalah 7 hari. Apabila
lebih dari itu maka akan berdampak keterlambatan dalam penyelesaian proyek dari waktu
yang telah direncakan.