TUGAS INDIVIDU

MATERIAL REQUIREMENT PLANNING (MRP)

Disusun Sebagai Salah Satu Syarat Untuk Memenuhi Tugas Mata Kuliah
Perencanaan dan Pengendalian Produksi
Dosen Pengampu: Sukanta, S.T., M.T.

Disusun oleh:

RIYADI AJI MUSTOFA


1810631140041
Kelas B

PROGRAM STUDI TEKNIK INDUSTRI


FAKULTAS TEKNIK
UNIVERSITAS SINGAPERBANGSA KARAWANG
2020
Tugas
Hitunglah Planned Order Release dari MRP, dimana status persediaan awal nol, Schedule receipt
25 pada perioda ke 2, lead time 1 bulan.
Periode (Bulan) 1 2 3 4 5 6
Demand 100 125 90 105 120 90

Jawab

Diketahui:
Kasus = On hand = Past Due = Due Date
Status persediaan awal = 0
Schedule Receipt = 25 (pada periode 25)
Lead Time=1 bulan
Untuk Safety Stock (SS) saya pakai100, dengan Lot Size sebesar 100

a. Pada Periode Pertama (Bulan Ke-1)


1. Gross Requirement
=100
2. Schedule Receipt
=0
3. Periode Available Balance I 1 (PAB I 1)
= Persediaan Awal + Schedule Receipt – Gross Requirement
= 0 + 0 – 100
= −100
4. Net Requirement
= Safety Stock (SS) – PAB I 1
= 100 – (−100)
=200
5. Planned Order Receipt (PORc)
=Karenanilai Net Requirement adalah 200 dengan kelipatan Lot Size 25, maka
nilai Planned Order Receipt (PORc)nya adalah 225.
6. Periode Available Balance II (PAB II)
=Planned Order Receipt (PORc) + PAB I 1 = 225 + (−100) = 125

b. Pada Periode Kedua (Bulan Ke-2)


1. Gross Requirement
= 125
2. Schedule Receipt
=25
3. Periode Available Balance I 2 (PAB I 2)
= PAB I I 1 + Schedule Receipt – Gross Requirement
= 125 + 25 – (125) =25
4. Net Requirement
=Safety Stock (SS) – PAB I 2
= 100 – 25
= 75
5. Planned Order Receipt (PORc)
= Karena nilai Net Requirement adalah 75 dengan kelipatan Lot Size 25, maka
nilai Planned Order Receipt (PORc)nya adalah 100.
6. Periode Available Balance I I 2 (PAB I I 2)
= Planned Order Receipt (PORc) + PAB I 2= 100 + 25 = 125
c. Pada Periode Ketiga (Bulan Ke-3)
1. Gross Requirement
= 90
2. Schedule Receipt
=0
3. Periode Available Balance I 3 (PAB I 3)
= PAB I I 2+ Schedule Receipt – Gross Requirement
= 125 + 0 – 90
= 35
4. Net Requirement
= Safety Stock (SS) – PAB I 3
= 100 – 35
= 65
5. Planned Order Receipt (PORc)
= Karena nilai Net Requirement adalah 65 dengan kelipatan Lot Size 25, maka
nilai Planned Order Receipt (PORc)nya adalah 75.
6. Periode Available Balance I I 3 (PAB I I 3)
= Planned Order Receipt (PORc) + PAB I 3= 100 + 35
= 110

d. Pada Periode Keempat (Bulan Ke-4)


1. Gross Requirement
= 105
2. Schedule Receipt
=0
3. Periode Available Balance I 4 (PAB I 4)
= PAB I I 3+ Schedule Receipt – Gross Requirement
= 110 + 0 – 105
=5
4. Net Requirement
= Safety Stock (SS) – PAB I 4
= 100 – 5
= 95
5. Planned Order Receipt (PORc)
= Karena nilai Net Requirement adalah 95 dengan kelipatan Lot Size 25, maka
nilai Planned Order Receipt (PORc)nya adalah 100.
6. Periode Available Balance I I 4 (PAB I I 4)
= Planned Order Receipt (PORc) + PAB I 4
= 100 + 5
= 105

e. Pada Periode Kelima (Bulan Ke-5)


1. Gross Requirement
= 120
2. Schedule Receipt
=0
3. Periode Available Balance I 5 (PAB I 5)
= PAB I 4+ Schedule Receipt – Gross Requirement
=105 + 0 – 120
= – 15
4. Net Requirement
= Safety Stock (SS) – PAB I 5
= 100 – (–15)
= 115
5. Planned Order Receipt (PORc)
= Karena nilai Net Requirement adalah 115 dengan kelipatan Lot Size 25,
maka nilai Planned Order Receipt (PORc)nya adalah 125.
6. Periode Available Balance I I 5 (PAB I I 5)
= Planned Order Receipt (PORc) + PAB I 5
= 125 + (–15)
= 110

f. Pada Periode Keenam (Bulan Ke-6)


1. Gross Requirement
= 90
2. Schedule Receipt
=0
3. Periode Available Balance I 6 (PAB I 6)
= PAB I I 5+ Schedule Receipt – Gross Requirement
= 110 + 0 – 90
= 20
4. Net Requirement
= Safety Stock (SS) – PAB I 6
= 100 – 20
= 80
5. Planned Order Receipt (PORc)
= Karena nilai Net Requirement adalah 80 dengan kelipatan Lot Size 25, maka
nilai Planned Order Receipt (PORc)nya adalah 100.
6. Periode Available Balance I I 5 (PAB I I 5)
= Planned Order Receipt (PORc) + PAB I 5
= 100 + 20
= 120

g. Mencari Planned Order Release (PORl)


Sebelum menentukan Planned Order Release (PORl), kita harus melihat terlebih
dahulu ketentuan dari Lead Time. Dikarenakan Lead Time 1 bulan, maka untuk
Planned Order Release (PORl) pada periode pertama diisi oleh Planned Order
Receipt (PORc) periode 2. Maka diperoleh hasil sebagai berikut:
1. Periode Pertama (Bulan ke-1)
= 100
2. Periode Kedua (Bulan ke-2)
= 75
3. Periode Ketiga (Bulan ke-3)
= 100
4. Periode Keempat (Bulanke-4)
= 125
5. Periode Kelima (Bulan ke-5)
= 100
6. Periode Keenam (Bulanke-6)
=0

h. Tabel Material Requirement Planning (MRP)


Menggunakan Perhitungan MRP (Fogarty, 1991)XMATERIAL REQUIREMENT
PLANNING
Part No : 5632234 Discription Assy
Part Name : Case SS 25
Stock on Hand :0 Lead Time 1
 
Beginning Inventory Periode
1 2 3 4 5 6
Gross Requirement 100 125 90 105 120 90
Schduled Receipts 0 25 0 0 0 0
PAB I 0 -100 25 35 5 -15 20
Net Requirement 200 75 65 95 115 80
Planned Order Receipts 225 100 75 100 125 100
Planned Order Release 100 75 100 125 100 0
PAB II 125 125 110 105 110 120