KAPASITAS
A B
Dengan data ini, maka dapat ditentukan berapa kebutuhan waktu secara
total.
CPOF – Waktu Proses
Waktu Proses (menit)
Work Center Total
Prod A Prod B Prod C
Drilling 42.25 42.25 217.15 301.65
Cutting 185.85 155.8 303.45 645.10
Milling 164.00 164 185.25 513.25
Assembly 96.25 28.175 158.55 282.98
Finishing 89.45 89.45 276 454.90
Packaging 20.85 1.5 4.15 26.50
TOTAL 2224.38
Langkah 1: Menghitung alokasi waktu untuk satu unit produk dan menentukan
nilai totalnya
Karena total 2224,38 untuk 3 item produk, maka 1 item produk membutuhkan
2224,38/3 = 741,45 menit
CPOF - Perhitungan Proporsi & waktu
per mesin
Waktu Proses (menit)
Work Center Total Proporsi Jan Feb Mar Apr Mei Jun
Prod A Prod B Prod C
Drilling 42.25 42.25 217.15 301.65 0.135611 20,110.00 25,137.50 40,220.00 21,115.50 45,247.50 25,640.25
Cutting 185.85 155.8 303.45 645.10 0.290014 43,006.67 53,758.33 86,013.33 45,157.00 96,765.00 54,833.50
Milling 164.00 164 185.25 513.25 0.230739 34,216.67 42,770.83 68,433.33 35,927.50 76,987.50 43,626.25
Assembly 96.25 28.175 158.55 282.98 0.127216 18,865.00 23,581.25 37,730.00 19,808.25 42,446.25 24,052.88
Finishing 89.45 89.45 276 454.90 0.204507 30,326.67 37,908.33 60,653.33 31,843.00 68,235.00 38,666.50
Packaging 20.85 1.5 4.15 26.50 0.011913 1,766.67 2,208.33 3,533.33 1,855.00 3,975.00 2,252.50
Kapasitas dibutuhkan per bulan 148,291.67 185,364.58 296,583.33 155,706.25 333,656.25 189,071.88
Kapasitas tersedia per bulan 224,640.00 224,640.00 224,640.00 224,640.00 224,640.00 224,640.00
200.000,00
100.000,00
-
Jan Capacity Available
Feb
Mar Capacity Needed
Apr
Mei
Jun
Pada bulan Maret dan Mei, diketahui dari grafik kapasitas tersedia (capacity
available) tidak mampu memenuhi kebutuhan untuk produksi MPS bulan Maret
dan Mei tersebut.
30.000,00
20.000,00
10.000,00
-
Kapasitas per mesin
Drilling
Cutting
Milling Kebutuhan Mesin
Assembly
Finishing
Packaging
Misal: bulan Januari, konsumsi waktu setiap mesin berbeda. Terlihat dari grafik bahwa
Cutting Machine melampaui kapasitas tersedia 43,006.67 > 37.440.
Dalam konteks RCCP hal detail per bulan maupun per mesin tidak diperhatikan, sehingga
keputusan MPS valid, hanya didasarkan pada nilai rata-rata kapasitas dibutuhkan seluruh
periode perencanaan harus lebih kecil dari rata-rata kapasitas tersedia.
Karena rata-rata kapasitas tersedia (224.640) > rata-rata kapasitas dibutuhkan (218.112)
maka MPS dapat dinyatakan valid, perencanaan dapat dilanjutkan ke MRP.
Bill of Labor Approach - BOLA
• Diperlukan data yang sama dengan CPOF, hanya
berbeda urutan perhitungannya.
Cij =
=
BOLA - Data MPS
400.000,00
300.000,00
200.000,00
100.000,00
-
Jan Capacity Available
Feb
Mar Capacity Needed
Apr
Mei
Jun
Analisa: diketahui dari grafik bahwa bulan Maret dan Mei kapasitas tersedia tidak
mencukupi untuk produksi.
Namun karena ini masih merupakan RCCP, maka keputusan validitas MPS hanya
didasarkan pada rata-rata nilai kapasitas tersedia harus lebih besar sama dengan
(>=) rata-rata nilai kapasitas dibutuhkan.
30.000,00
20.000,00
10.000,00
-
Kapasitas Tersedia
Drilling
Cutting
Milling Kapasitas Dibutuhkan
Assembly
Finishing
Packaging
Misal: bulan Januari, konsumsi waktu setiap mesin berbeda. Terlihat dari grafik
bahwa Cutting Machine melampaui kapasitas tersedia 44,328.03 > 37.440.
Dalam konteks RCCP hal detail per bulan maupun per mesin tidak diperhatikan,
sehingga keputusan MPS valid, hanya didasarkan pada nilai rata-rata kapasitas
dibutuhkan seluruh periode perencanaan harus lebih kecil dari rata-rata kapasitas
tersedia.
Resource Profile Approach
• Mirip seperti BOLA
• Memperhatikan Lead Time Offset
Pemahaman Lead Time Offset
• Dalam perencanaan material, semua komponen yang dibutuhkan
biasanya sudah siap sesaat sebelum waktu duedate-nya (atau
kurang sedikit dari waktu lead time-nya).
• Perlu dipahami bahwa seluruh komponen tidak perlu diproduksi
dari awal secara bersama-sama. Misalnya, jika ada komponen yang
biaya inventori-nya sangat tinggi, maka sebaiknya produk tersebut
belum dipesan sebelum waktu yang tepat.
• Oleh karena itulah, dibutuhkan lead time offset. Dimana komponen
yang memiliki lead time offset tidak mesti dikerjakan dari awal atau
tidak selalu dikerjakan pada saat duedate-nya.
• Komponen yang harus selesai sebelum duedate-nya biasanya
memiliki lead time yanglebih pendek.
So? What is Lead time?
Kapasitas Tersedia
300.000,00
250.000,00
200.000,00
150.000,00
100.000,00
50.000,00
-
Jan Kapasitas Tersedia
Feb
Mar Kapasitas Dibutuhkan
Apr
Mei
Jun
RPA – Kapasitas Mesin Bulan Januari
Kapasitas Tersedia
Kapasitas Tersedia
80.000,00
70.000,00
60.000,00
50.000,00
40.000,00
30.000,00
20.000,00
10.000,00
-
Kapasitas Tersedia
Drilling
Cutting
Milling Kapasitas Tersedia
Assembly
Finishing
Packaging
Contoh 2
Susunan bahan dari Lampu LAXX
(SUPER BILL OF MATERIAL)
Lamps
LAXX
Base Socket
Shades
Assembly Assembly
45
Capacity planning using overall factors (CPOF)
46
CPOF (Contoh)
Work Historical Month Total
Center Proportion Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Hours
Lamp Assembly 0.455 1,501.5 1,501.5 1,501.5 1,501.5 1,501.5 1,501.5 1,501.5 1,601.6 1,901.9 1,901.9 1,901.9 1,901.9 19,719.7
Oven 0.046 148.5 148.5 148.5 148.5 148.5 148.5 148.5 158.4 188.1 188.1 188.1 188.1 1,950.3
Base Forming 0.227 749.1 749.1 749.1 749.1 749.1 749.1 749.1 799.0 948.9 948.9 948.9 948.9 9,838.2
Plastic Molding 0.091 300.3 300.3 300.3 300.3 300.3 300.3 300.3 320.3 380.4 380.4 380.4 380.4 3,943.9
Socket Assembly 0.182 600.6 600.6 600.6 600.6 600.6 600.6 600.6 640.6 760.8 760.8 760.8 760.8 7,887.9
Total Capacity
Reqirements 3,300 3,300 3,300 3,300 3,300 3,300 3,300 3,520 4,180 4,180 4,180 4,180
Lamp LAXX
Lamp Assembly 0.10 hr
Oven 0.01 hr
Base Forming 0.05 hr
Plastic Molding 0.02 hr
Socket Assembly 0.04 hr
0.22 hr
• January
– Total capacity requirement = 0.22 x 15000= 3300
– Historical proportion for Lamp Assembly = 0.10 / 0.22 = 0.45
– Lamp Assembly capacity requirement = 0.455 x 3300 = 1501.5
47
Bill of Labor Approach (BOL)
• Data yang diperlukan: sama dengan CPOF
n
a b
k 1
ik kj
48
BOL (Contoh)
Work Center Month Total
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Hours
Lamp Assembly 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,600 1,900 1,900 1,900 1,900 19,700
Oven 150 150 150 150 150 150 150 160 190 190 190 190 1,970
Base Forming 750 750 750 750 750 750 750 800 950 950 950 950 9,850
Plastic Molding 300 300 300 300 300 300 300 320 380 380 380 380 3,942
Socket Assembly 600 600 600 600 600 600 600 640 760 760 760 760 7,880
Total Capacity
Reqirements 3,300 3,300 3,300 3,300 3,300 3,300 3,300 3,520 4,180 4,180 4,180 4,180
Lamp LAXX
Lamp Assembly 0.10 hr
Oven 0.01 hr
Base Forming 0.05 hr
Plastic Molding 0.02 hr
Socket Assembly 0.04 hr
• January
– Lamp Assembly capacity requirement = 0.10 x 15000 = 1500
49
BOL:BillTwo
of labor
products, two month, two work centersRCCP
Master schedule
Product Month Month
P1 P2 M1 M2 M1 M2
Workcenter Product Workcenter
WC1 a11 a12 P1 b11 b12 WC1 c11 c12
c11
a11b11 a12 b21
n
c a11b12 a12 b22
cij aik bkj 12
k 1
c 21
a 21b11 a22 b21
c 22
a21b12 a 22 b22
50
Resource profile approach (RP)
• Metode perhitungan mirip BOL +
mempertimbangkan lead-time offset
51
RPA (Contoh)
Month Total
Work Center Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Hours
Lamp Assembly 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,600 1,900 1,900 1,900 1,900 19,700
Oven 150 150 150 150 150 150 160 190 190 190 190 0 1,820
Base Forming 750 750 750 750 750 800 950 950 950 950 0 0 8,350
Plastic Molding 300 300 300 300 300 300 320 380 380 380 380 0 3,642
Socket Assembly 600 600 600 600 600 600 640 760 760 760 760 0 7,280
Total Capacity
Reqirements 3,300 3,300 3,300 3,300 3,300 3,350 3,570 3,880 4,180 4,180 3,230 1,900
• July
– Lamp Assembly = 0.1 x 15000 (MPS July) = 1500
– Oven = 0.01 x 16000 (MPS August) = 160
– Base forming = 0.05 x 19000 (MPS September) = 950
52
Time to
RPA:Two products, two work centers, three
Resource Profile
month horizon, three month lead time
Master schedule RCCP
Due Date Month Month
2 1 0 M1 M2 M3 Work M1 M2 M3
Product Product Center
a112 a111 a110 b11 b12 b13 WC1 c11 c12 c13
p1 p1
p2 a212 a212 a210 p2 b21 b22 b23 WC2 c21 c22 c23
Work Center 1
2 1 0
c11
a110b12 a111b13 a210b22 a211b23
p2 a222 a221 a220
c11
a110b13 a210b23
Work Center 2
c 21
a120b11 a121b12 a112b13 a220b21 a221b22 a222b23
c 22
a120b12 a121b13 a220b22 a221b23
c 23
a120b13 a220b23
53
Pemilihan metoda RCCP
• Ukuran lot diasumsikan lot-for-lot
• Metoda BOL lebih direkomendasikan daripada
Metoda CPOF
• Resource profile approach produk yang
manufacture leadtime lama (contoh : airplane,
machine tools)
54
RCCP Decisions
• Capacity available
Capacity available = time available x utilization x efficiency
J F M A M J J A S ON D
Month
Alternatif untuk meningkatkan kapasitas : (1) over time, (2) subcontracting, (3)
alternating routing, (4) tambah tenaga kerja
Jika penambahan kapasitas tidak bisa memenuhi capacity required Revisi
MPS
55