Anda di halaman 1dari 17

PEMERINTAH KOTA MEDAN

DINAS KESEHATAN
Alamat : Jl. Rotan, Petisah Tengah, Kec.
Medan Petisah, Kota Medan, Sumatera Utara 20111

DETAIL ENGINEERING DESIGN


PEKERJAAN :
PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH (IPAL)
DINAS KESEHATAN KOTA MEDAN
PUSKESMAS SUKARAMAI

TAHUN ANGGARAN 2021


S_3
DAFTAR ISI HAL

1. LAYOUT BANGUNAN DAN JARINGAN PIPA PUSKESMAS SUKARAMAI ..................... 1


2. LAYOUT TAMAN IPAL ............................................................................................. 2
3. LAYOUT IPAL ......................................................................................................... 3
4. FLOW SCHEMATIC DIAGRAM IPAL........................................................................... 4
5. DENAH ................................................................................................................ 5
6. BAK KONTROL......................................................................................................... 6
7. PONDASI BIOREAKTOR ........................................................................................... 7
8. EQUALISASI............................................................................................................. 8
9. KOLAM INDIKATOR & KLORINASI............................................................................ 9
10. CANOPY.................................................................................................................. 10
11. PAGAR HARMONIKA............................................................................................... 11
12. DENAH TPS ............................................................................................................ 12
13. TAMPAK TPS .......................................................................................................... 13
14. POTONGAN TPS ..................................................................................................... 14
15. DETAIL ................................................................................................................... 15
GUDANG OBAT

JALAN
LABORATORIUM DAN
PEMERINTAH KOTA MEDAN

KITCHEN
P= 5 m PEKERJAAN

PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)

RGD
RUANG ADMINITRASI LOKASI

DAN GIZI PUSKESMAS SUKARAMAI

P= 11 m P= 10 m

MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)

P= 8 m P= 10 m
BK BK BK

WC

PAVING BLOCK ................................................


NIP ............... ................ .......

P= 12 m

JALAN
RUANG PEJABAT PELAKSANA TEKNIS
KEPALA PUSKESMAS
PUSKESMAS KEGIATAN (PPTK)

IPAL
P= 5 m SUKARAMAI
P= 2 m P= 2 m
P= 5 m P= 2 m
BK

................................................
NIP ............... ................ .......
JALAN JALAN JALAN

LEGENDA IPAL
SYMBOL KETERANGAN JUMLAH
BK BAK KONTROL 4 BUAH
PIPA 4" Baru 40 m
PIPA 3" Baru 15 m DETAIL ENGINEERING DESIGN
PIPA 2" Baru 11 m
Bobokan Keramik 21 m
LAYOUT IPAL Bobokan Beton 5m
SCALE : 1 : NTS Pembongkaran Paving 30 m
IPAL Pembongkaran Paving Area IPAL 36 m2
P= ...
ARAH PANAH & PANJANG PIPA -------
A3
PEMERINTAH KOTA MEDAN

PEKERJAAN

PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)

LOKASI

BAR SCREEN
PUSKESMAS SUKARAMAI

FINE SCREEN
MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)

................................................
NIP ............... ................ .......

PONDASI EQUALISASI
DUDUKAN MESIN PEJABAT PELAKSANA TEKNIS
KEGIATAN (PPTK)
IPAL

................................................
NIP ............... ................ .......

IPAL

LAYOUT TAMAN IPAL


SCALE : 1 : 40
DETAIL ENGINEERING DESIGN

A3
PEMERINTAH KOTA MEDAN

PEKERJAAN
OUTPUT
PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
(IPAL)

BAR SCREEN
LOKASI

PUSKESMAS SUKARAMAI

FINE SCREEN
MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)


DARI BAR/FINE SCREEN

................................................
NIP ............... ................ .......

PONDASI EQUALISASI
DUDUKAN MESIN PEJABAT PELAKSANA TEKNIS
IPAL KEGIATAN (PPTK)

................................................
NIP ............... ................ .......

IPAL

LAYOUT TAMAN IPAL


SCALE : 1 : 40
DETAIL ENGINEERING DESIGN

A3
PEMERINTAH KOTA MEDAN

PEKERJAAN

PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)

SCHEMATIC FLOW DIAGRAM IPAL LOKASI

PUSKESMAS SUKARAMAI

MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)

BAK KONTROL
SEPTICTANK
LIMBAH CAIR KAMAR
MANDI/CLOSET
................................................
NIP ............... ................ .......

SHOWER

WATER
PEJABAT PELAKSANA TEKNIS
FLOW METER
WASTAFEL KEGIATAN (PPTK)
WC WATER
FLOW METER
VALVE
BAK KONTROL
BODY FRP t 8-10 mm
LIMBAH CAIR CHLORINATOR
WASTAFEL, WC
KE SALURAN
BAR SCREN FINE SCREN
KOTA

BAR SCREN & INLET PUMP


EKUALISASI BIOREAKTOR KOLAM IKAN /
FINE SCREN
INDIKATOR
INLET DARI SLUDGE ................................................
NIP ............... ................ .......

IPAL

DETAIL ENGINEERING DESIGN

A3
PEMERINTAH KOTA MEDAN

PEKERJAAN

PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)

LOKASI

PUSKESMAS SUKARAMAI

MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)

DENAH DUDUKAN BIOREKTOR


SCALE : 1 ; 25

TAMPAK SAMPING KANAN


SCALE : 1 ; 35

................................................
NIP ............... ................ .......

PEJABAT PELAKSANA TEKNIS


KEGIATAN (PPTK)

................................................
NIP ............... ................ .......

IPAL

DETAIL ENGINEERING DESIGN

TAMPAK DEPAN TAMPAK SAMPING KIRI


SCALE : 1 ; 35 SCALE : 1 ; 35

A3
700
150 400 150
700
PEMERINTAH KOTA MEDAN

Pas. Batu Bata 75 75 400 75 75


B

75
Fin.Plester PEKERJAAN

Penutup Plat Beton

150

75
Ukr. 550x550x80 PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
A A (IPAL)

400

400
700

700
LOKASI

PUSKESMAS SUKARAMAI

75
PIPA PVC Ø 4"

150

75
B
MENYETUJUI
LAYOUT BAK KONTROL 75 75 TAMPAK ATAS BAK KONTROL
SCALE : 1 : 20 SCALE : 1 : 20 PEJABAT PEMBUAT KOMITMEN (PPK)

80
Besi Ø8 - 100 Besi Ø8 - 100
Penutup Plat Beton
Penutup Plat Beton Ukr. 550x550x80 Penutup Plat Beton
550 550
Ukr. 550x550x80 Ukr. 550x550x80
+ 0.100 + 0.100
M.T.A ± 0.000 M.T.A ± 0.000 ................................................
NIP ............... ................ .......

Tanah Urug Tanah Urug

,6
PEJABAT PELAKSANA TEKNIS

01
PIPA PVC Ø 4" PIPA PVC Ø 4"

Ø1
KEGIATAN (PPTK)

Tanah Asli / Tanah Asli /


Existing Existing
Pas. Batu Bata - 0.700 Pas. Batu Bata - 0.700
Fin.Plester - 0.800 Fin.Plester - 0.800
- 0.850 - 0.850
Cor Beton Cor Beton
Pasir Urug 150 400 150 Pasir Urug 150 400 150 ................................................
NIP ............... ................ .......

Tanah Asli 700 Tanah Asli 700


Dipadatkan Dipadatkan
POTONGAN A-A POTONGAN B-B
SCALE : 1 : 20 SCALE : 1 : 20

IPAL

BAK KONTROL
SCALE : 1 : 20 DIM 400x400 ALL'S BMR-C

DETAIL ENGINEERING DESIGN

A3
B
PEMERINTAH KOTA MEDAN
Sloof 300x200
Besi 6Ø12 Cor Beton
200 Sengkang Ø8-200 Urugan Sirtu PEKERJAAN

200
+ 0.200
Stek Besi
Ø8-200 L.500mm + 0.100

500
± 0.000

300
- 0.100 PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
(IPAL)

200
1900
1500

1100

1900
Tanah Asli
A A Tanah Urug LOKASI

Pondasi. Batu Kali

1000
600
- 0.700 PUSKESMAS SUKARAMAI

Pasir Urug - 0.800


Tanah Asli 300
Dipadatkan
200

200
600

DETAIL A MENYETUJUI
SCALE : 1 : 25
PEJABAT PEMBUAT KOMITMEN (PPK)
200
B 1500 200 600 200
1900 800
3100

DENAH PONDASI BIOREKTOR


SCALE : 1 : 25

DETAIL A
................................................
1900 800 NIP ............... ................ .......

1500
+ 0.200 + 0.200
+ 0.100 + 0.100
PEJABAT PELAKSANA TEKNIS
± 0.000 ± 0.000 KEGIATAN (PPTK)
- 0.100 - 0.100

- 0.700 - 0.700
- 0.800 - 0.800

300 300 300 300 300


................................................
600 1100 600 200 600 600 700 600
NIP ............... ................ .......
3100 1900

POTONGAN A-A
SCALE : 1 : 25

IPAL

PONDASI BIO REAKTOR


SCALE : 1 : 25
DETAIL ENGINEERING DESIGN

A3
Besi Ø8 - 100
Tutup Plat Beton t=80mm
Pipa 4"
+ 0.100
1500 ± 0.000
150 525 150 525 - 0.110
150

B D
PEMERINTAH KOTA MEDAN

150
C FINE SCREEN BAR SCREEN C PEKERJAAN

- 0.850

500
800
- 0.950
A A - 1.000
PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
(IPAL)

150
150 500 150
LOKASI
D 800
PUSKESMAS SUKARAMAI
DENAH POTONGAN D
EQUALISASI SCALE : 1 : 25
Besi Ø8 - 100 SCALE : 1 : 25

2700 Tutup Plat Beton t=80mm


Pipa 4" + 0.10 MENYETUJUI

± 0.00 PEJABAT PEMBUAT KOMITMEN (PPK)


- 0.11
OUTLET Ø 4" INLET Ø 4"

Tanah Urug
FINE SCREN BAR SCREN
Pas. Batu Bata
Fin. Plester aci
Lantai Rabat Beton - 0.85
Pasir Urug
- 0.95 ................................................
Tanah Asli NIP ............... ................ .......
- 0.100
1300
150 525 150 525 150 PEJABAT PELAKSANA TEKNIS
KEGIATAN (PPTK)
B 1500

TAMPAK ATAS EQUALISASI


POTONGAN C-C
SCALE : 1 : 25
SCALE : 1 : 25

1400 2600
Waremesh m6 1 lapis Waremesh m6 1 lapis
400 Atau Besi Ø 6 - 150 Cor Beton 400 315 200 Atau Besi Ø 6 - 150
+ 0.100 + 0.100
................................................
± 0.000 ± 0.000 NIP ............... ................ .......

0
10
Ø1

INLET Ø 4" OUTLET Ø 4"


IPAL

Tanah Urug Tanah Urug

Lantai Kerja Lantai Kerja


DETAIL ENGINEERING DESIGN
Pasir Urug - 1.225 Pasir Urug - 1.225
Tanah Asli - 1.275 Tanah Asli - 1.275
- 1.325 - 1.325

1100 2300

POTONGAN B-B
POTONGAN A-A SCALE : 1 : 25
SCALE : 1 : 25

A3
340 340 Pas. Batu Bata
Fin. Cat + 1.000
PEMERINTAH KOTA MEDAN
+ 0.800
2300 300
500 375 300 450 300 375 + 0.550 PEKERJAAN

C D Tutup Plat besi


siku 40.40.2mm
+ 0.250

260 300

950
A A PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH

500
± 0.000

250
(IPAL)

1000

1000

350

200
B B - 0.350

500

440
- 0.500 LOKASI

Pas. Batu Bata - 0.550


Trasram Fin. Cat PUSKESMAS SUKARAMAI
C D Cor Beton
460 260 360 260 460 Pasir Urug t=5cm
500 1800 Tanah Dipadatkan
500 150 1500 150
DENAH KOLAM INDIKATOR 2300
SCALE : 1 : 40
MENYETUJUI
POTONGAN A-A
SCALE : 1 : 40 PEJABAT PEMBUAT KOMITMEN (PPK)

340 340
340 340 Pas. Batu Bata + 1.000 + 1.000
+ 1.000 Fin. Cat + 1.000
+ 0.800
+ 0.800 + 0.800
300
+ 0.600
+ 0.550 + 0.550
200

+ 0.550 Tutup Plat besi


siku 40.40.2mm
+ 0.250 + 0.250
+ 0.250 + 0.250
260 360 260
950

± 0.000 ± 0.000 ................................................


± 0.000 ± 0.000
NIP ............... ................ .......
350

- 0.220
- 0.350

950
- 0.350
950

- 0.500
- 0.500
- 0.550 PEJABAT PELAKSANA TEKNIS
- 0.550 Pas. Batu Bata
Pas. Batu Bata Trasram Fin. Cat KEGIATAN (PPTK)
Trasram Fin. Cat
- 0.850 150 290 150 260 150 Cor Beton
- 0.850 Cor Beton
Pasir Urug t=5cm
Pasir Urug t=5cm 1000
Tanah Dipadatkan
Tanah Dipadatkan 500 500
500 150 1500 150
2300

POTONGAN B-B POTONGAN C-C POTONGAN D-D


SCALE : 1 : 40 SCALE : 1 : 40
SCALE : 1 : 40

................................................
NIP ............... ................ .......

IPAL

TAMPAK DEPAN
SCALE : 1 : 40 DETAIL ENGINEERING DESIGN

KOLAM INDIKATOR DAN KLORINASI


SCALE : 1 : 40 ALL'S BMR

A3
hollow zingalum
40x40x2,3mm + 3.785

+ 3.450

+ 3.235

PEMERINTAH KOTA MEDAN

PEKERJAAN

hollow hollow
40x40x2,3mm 40x40x2,3mm PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
(IPAL)

hollow LOKASI

40x40x2,3mm PUSKESMAS SUKARAMAI

MENYETUJUI

+ 0.200 PEJABAT PEMBUAT KOMITMEN (PPK)

± 0.000
DENAH CANOPY
SCALE : 1 : 35

TAMPAK SAMPING KIRI


SCALE : 1 ; 35

................................................
NIP ............... ................ .......

zingalum
zingalum hollow PEJABAT PELAKSANA TEKNIS
KEGIATAN (PPTK)
+ 3.785
+ 3.785
40x40x2,3mm

+ 3.450
+ 3.450

+ 3.235
+ 3.235

................................................
NIP ............... ................ .......
hollow
40x40x2,3mm

hollow IPAL
40x40x2,3mm

DETAIL ENGINEERING DESIGN

+ 0.200
+ 0.200
± 0.000
± 0.000

TAMPAK DEPAN
SCALE : 1 ; 35
TAMPAK SAMPING KANAN
SCALE : 1 ; 35

A3
Kawat Pengikat DETAIL A Pengikat Besi Ø 8
Pipa Besi Ø1/2" + 1.350
+ 1.300

Plate t=5mm
Nuts 12mm PEMERINTAH KOTA MEDAN
Kunci Gembok
Kawat Harmonika PEKERJAAN
Kawat Harmonika Kawat Harmonika
Pengaku Besi Ø 8
Kait Harmonika DETAIL KUNCI PAGAR
SCALE : 1 : 10

Kawat Pengikat Pengikat Besi Ø 6 PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)
Pipa Besi Ø1/2" Pipa Besi Ø1/2"

Pipa Besi Ø1" Pipa Besi Ø1" + 0.300


LOKASI
Pasangan Bata merah + 0.150
PUSKESMAS SUKARAMAI
Sloof Uk. 15x15 cm ± 0.000
Sengkang Ø6 - 200
Lantai Kerja
Tanah Asli - 0.200
Dipadatkan
- 0.300
MENYETUJUI

- 0.350 PEJABAT PEMBUAT KOMITMEN (PPK)

300 2100 300 300

DETAIL A
TAMPAK MUKA DALAM SCALE : 1 : 20

SCALE : 1 : 20

150
+ 1.350 Ø6 - 200 + 1.350
................................................
+ 1.300 4Ø6 + 1.300 NIP ............... ................ .......

150
PEJABAT PELAKSANA TEKNIS
KEGIATAN (PPTK)

Pengaku Besi Ø 8
DETAIL SLOOF
Kawat Harmonika SCALE : NTS
Pipa Besi Ø 1"

Pipa Besi Ø1/2" Pipa Besi Ø 1/2"

Pipa Besi Ø1" + 0.300 + 0.300


................................................
+ 0.150 Pasangan Bata merah + 0.150 NIP ............... ................ .......

± 0.000 Sloof Uk. 15x15 cm ± 0.000


Lantai Kerja
Cor Beton - 0.150
- 0.200 Tanah Asli
Pasir Urug Dipadatkan
- 0.300 - 0.200 IPAL
Tanah Asli
Dipadatkan
- 0.350
300 1700 300 150
TAMPAK PINTU PAGAR 250
SCALE : 1 : 20
DETAIL ENGINEERING DESIGN

TAMPAK SAMPING
SCALE : 1 : 20

A3
B
800 2000 2000 800

PEMERINTAH KOTA MEDAN

PEKERJAAN

800
PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
(IPAL)

LOKASI

PUSKESMAS SUKARAMAI

1000
2000

MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)

1000 1000

A ................................................
NIP ............... ................ .......

PEJABAT PELAKSANA TEKNIS


KEGIATAN (PPTK)
2000

................................................
NIP ............... ................ .......
800

IPAL

DENAH BANGUNAN (TPS) DETAIL ENGINEERING DESIGN


SCALE : 1 : 30

A3
PEMERINTAH KOTA MEDAN

PEKERJAAN

PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)

LOKASI

PUSKESMAS SUKARAMAI

MENYETUJUI

PEJABAT PEMBUAT KOMITMEN (PPK)

TAMPAK DEPAN TAMPAK BELAKANG


SCALE : 1 : 40
SCALE : 1 : 40

................................................
NIP ............... ................ .......

PEJABAT PELAKSANA TEKNIS


KEGIATAN (PPTK)

................................................
NIP ............... ................ .......

IPAL

DETAIL ENGINEERING DESIGN


TAMPAK SAMPING KIRI TAMPAK SAMPING KANAN
SCALE : 1 : 40 SCALE : 1 : 40

A3
PEMERINTAH KOTA MEDAN

PEKERJAAN

PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH


(IPAL)

LOKASI
NOK ATAP NOK ATAP
RENG X BAJA RINGAN RENG X BAJA RINGAN
ATAP ZINCALUME ATAP ZINCALUME PUSKESMAS SUKARAMAI

PROFIL C BAJA RINGAN PROFIL C BAJA RINGAN


100x50x20 100x50x20
553

553
RENG X BAJA RINGAN RENG X BAJA RINGAN
ATAP ZINCALUME ATAP ZINCALUME
1774

1774
MENYETUJUI
PROFIL C BAJA RINGAN PROFIL C BAJA RINGAN
1221

1221
100x50x20 100x50x20 PEJABAT PEMBUAT KOMITMEN (PPK)
RING BALK 150x150 RING BALK 150x150

PASANGAN BATA Plafond GRC Plafond GRC


FINISH CAT +2.450 +2.450
5174

5174
2350

2350
................................................
2750

2750
NIP ............... ................ .......
PASANGAN BATA PASANGAN BATA
FINISH CAT FINISH CAT

PEJABAT PELAKSANA TEKNIS


1500

1500

1500
DETAIL A Keramik Dinding Keramik Dinding Keramik Dinding
PAS. BATU BATA PAS. BATU BATA
KEGIATAN (PPTK)
LANTAI RABAT BETON T=100mm LANTAI RABAT BETON T=100mm
PAS. BATU BATA TRASSRAM PAS. BATU BATA TRASSRAM
150 150 150 150
400

400
SLOOF 150x150mm SLOOF 150x150mm
±0.000 ±0.000
SALURAN SALURAN
100 400 150

100 400 150


650

650
TANAH URUG TANAH URUG
TANAH ASLI TANAH ASLI

200 200 200 200


500 3500 500 500 3500 500
................................................
4500 4500 NIP ............... ................ .......

POTONGAN A POTONGAN B
SCALE : 1 : 30 SCALE : 1 : 30

IPAL

DETAIL ENGINEERING DESIGN

A3
RABAT BETON
T=100mm PEMERINTAH KOTA MEDAN

PASIR URUG PEKERJAAN

T=50mm
KERAMIK DINDING PENGADAAN INSTALASI PENGOLAHAN AIR LIMBAH
(IPAL)

LOKASI

PUSKESMAS SUKARAMAI
PAS. BATU BATA
TRASSRAM

tumpuan
SLOOF 150x150

Ø10-120
RABAT BETON
400

MENYETUJUI

T=100mm PEJABAT PEMBUAT KOMITMEN (PPK)

SALURAN
100 400 150

lapangan
Ø10-150
TANAH ASLI
500

................................................
NIP ............... ................ .......
TANAH URUG

tumpuan
PONDASI. BATU KALI PEJABAT PELAKSANA TEKNIS

Ø10-120
KEGIATAN (PPTK)

PASIR URUG
TANAH ASLI Besi 6Ø12
DIPADATKAN 200 Besi 4Ø12
200 Sengkang Ø8-200
Sengkang Ø8-200
150

200

150
500
................................................
NIP ............... ................ .......
DETAIL KOLOM DETAIL RING BALK
DETAIL A SCALE : 1 : 15 SCALE : 1 : 15

SCALE : 1 : 15

IPAL

DETAIL ENGINEERING DESIGN

A3

Anda mungkin juga menyukai