Project Charter Document:

Project Name : Penanaman Tanaman Sayuran Dengan Cara Hidroponik Toko XYZ

Company : Toko XYZ

Focus Area : Sistem Penanaman

Product : Sayuran

Project Time : 20 September 2021 – 22 Desember 2022

Cost Estimation : Rp 25.000.000

Tabel Aktivitas

No Aktivitas Mendahului Durasi Budget (jt)


1 A ( Melakukan interview pada 2 2
stakeholder)
2 B (Prototyping) 5 5
3 C (Pembuatan Sistem) B 6 6
4 D (Presentasi Produk Akhir) A 5 5
5 E (Deploying Website) C,D 4 4

A. Diagram Network
B. Perhitungan Maju Mundur

Perhitungan Maju:

EF(i-j) = ES(i-j) + t(i-j)


EF(1-2) = ES(1-2) + D = 0 + 2 = 2

EF(1-3) = ES(1-3) + D = 0 + 5 = 5
EF(2-4) = ES(2-4) + D = 2 + 5 = 7
EF(3-4) = ES(3-4) + D = 5 + 6 = 11
EF(4-5) = ES(4-5) + D = 11 + 4 = 15

Perhitungan Mundur:

LS(i-j) = LF(i-j) – t
LS (5-4) = EF (5-4) – D = 15-4 = 11
LS (4-3) = EF (4-3) – D = 11-6 = 5
LS (4-2) = EF (4-2) – D = 11-5 = 6
LS (2-1) = EF (2-1) – D = 6-2 = 4
LS (3-1) = EF (3-1) – D = 5-5 = 0

C. Jalur Kritis dan Lamanya Waktu Proyek


Total Float:
A = TF(1,2) = 6-0-2 = 4
B = TF (1,3) = 5-0-5 = 0
C = TF (3,4) = 11-5-6 = 0
D = TF (2,4) = 11-2-5 = 4
E = TF (4,5) = 15-11-4 = 0
Jalur Kritis: 3-4-5 / B-C-E
Dan lamanya waktu proyek adalah 15 Bulan

Gant Chart
AKTIVITAS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 BIAYA/JT
B 5
C 6
E 4
A 2
D 5
TOTAL 22JT
2 2 2 2 2 2 2 1 1 1 1 1 1 1 1
BIAYA/BLN
2 4 6 8 10 12 14 15 16 17 18 19 20 21 22 22 JT