• Non-Routine Lift
A lift refers to lifting operations that are complex, carried out for the
first time or lifting close to the lifting capacity of the crane.
Pengangkatan mengacu pada pengangkatan rumit, dilakukan untuk
pertama kali atau pengangkatan yang mendekati kapasitas crane
NON-ROUTINE LIFTS
• Non-routine lifts are those which do not meet all criteria for routine lifts, the
degree of planning can vary considerably and will depend on the type of
requirement to be used. Class 2 lifting operation may be repeatedly performed
and simple but may need a more detailed planning.
• Pengangkatan non-rutin adalah pengangkatan yang tidak memenuhi semua
kriteria pengangkatan rutin, tingkat perencanaan dapat bervariasi dan
tergantung pada kompleksitas (rumit) dan kebutuhan. Aktifitas pengangkatan
Kelas 2 dapat dilakukan berulang tetapi mungkin memerlukan rencana yang
lebih rinci.
Document to be completed and approved by CONTRACTOR before commencing
class 2 lifting operation:
Dokumen yang harus dilengkapi dan disetujui oleh CONTRACTOR sebelum
melakukan aktifitas pengangkatan kelas 2:
NON-ROUTINE LIFTS
• Method Statement (MoS) including potential risk that might occur in the lifting
operation;/Langkah kerja, termasuk potensial risiko yang mungkin terjadi dalam
aktifitas pengangkatan
• Job Safety Analysis (JSA)/Analisa risiko kerja
• Permit to Work (PTW);/Izin kerja
• Lift Plan represent load not more than 25 tonne and less than 75 tonne or
utilization crane ≤ 85% of the rated load chart; / Rencana pengangkatan yang
menunjukkan beban 25 ton dan ≤ 75 ton atau penggunaan kapasitas crane ≤
85%
• STARRT Card;/Kartu keselamatan untuk memulai aktifitas pengangkatan
• Pre-Lift Checklist Lifting Operation at least 1 checklist per day if location is
not changed and new checklist in case of change in location;/Lembar
pemeriksaan sebelum pengangkatan. Di isi 1 kali perhari jika lokasi tidak
berubah dan pemeriksaan baru jika berubah lokasi
• Summary Checklist – Lifting Operation Class 2 & 3./Lembar Ringkasan
Pemeriksaan
5
ROUTINE VERSUS NON-ROUTINE LIFTS
It is a misperception to assume that so long as the weight of
the load is below a certain tonnage, it can be classified as a
routine lift and therefore require less planning or
supervision/Ini adalah persepsi yang salah untuk
mengasumsikan bahwa selama
berat beban dibawah tonase
tertentu, itu dapat diklasifikasikan
sebagai pengangkatan rutin oleh
karena itu perencanaan dan
pengawasan dapat dilakukan
lebih sedikit (minimal)
ROUTINE VERSUS NON-ROUTINE LIFTS
Based on Industry past experiences, most crane accidents
happened during routine lift rather than non-routine lift/Dari
pengalaman sebelumnya, banyak kecelekaan pesawat
angkut (crane) dalam aktifitas pengangkatan terjadi pada
pengangkatan rutin bukan non-rutin
8
PLANNING THE LIFTING OPERATIONS
All lifting operations should be planned to ensure that they are carried out
safely and that ALL foreseeable hazards are identified and any risks
eliminated/Semua aktifitas pengangkatan harus direncanakan untuk
memastikan bahwa semua dilakukan dengan aman dan risiko bahaya yang
diidentifikasi telah teridentifikasi dan dihilangkan
WARNING:
Only tested and certified cranes, lifting gear and equipment should be used.
This equipment can be recognised by its identification or plate number and
Safe Working Load (SWL) or Working Load Limit (WLL) markings and shall
have the current colour code/Hanya pesawat angkut, alat bantu tersertifikat
yang dapat digunakan. Peralatan bantu angkat harus dapat diidentifikasi
kapasitas (SWL) dan harus memiliki kode warna yang valid
PLANNING THE LIFTING OPERATIONS
Planning Should Include & Allow For The Following
14
PREPARATION OF LIFTING OPERATIONS
1. Job Safety Analysis/Analisa risiko dan keselamatan kerja
2. All control (physical and working methods) are required to eliminate the
hazard/Semua control (fisik dan cara kerja) yang disyaratkan untuk
menghilangkan bahaya
3. Conflicting tasks in area/Tugas yang saling bertentangan di area kerja
4. Area of lifting operation including exclusion zone/Lokasi dimana
pengangkatan termasuk zona paparannya
5. Number of personnel required/Jumlah personil yang dibutuhkan
6. Environmental conditions (weather forecast)/Kondisi lingkungan
7. Tools and equipments/Alat dan perlengkapan yang sesuai
8. Contingency Plan/Rencana Cadangan
9. Emergency response Management system/Sistem Manajemen
tanggap darurat
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT
16
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT
1. Identification Number (ID No.)/Nomor
identitas
2. Valid Colour Code/Kode warna yang berlaku
3. Dimension (diameter, length, etc.)/Dimensi
(diameter, Panjang, dll)
4. Manufacturer’s stamp/Label pabrikan
5. Year of Manufacturer’s/Tahun pembuatan
Burn
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
20
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
21
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
22
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
23
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
24
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
Crane
25
PRE & POST USE EXAMINATION OF
LIFTING EQUIPMENT – DAMAGE
EQUIPMENT
26
METHOD OF SLINGING THE LOAD
27
METHOD OF SLINGING THE LOAD
1. General lifting operation, utilization WLL sling should be a
maximum of 80% of the load if one sling is used to lift the
load/Aktifitas pengangkatan umum, maksimal pemanfaatan
kapasitas sling sebaiknya 80% dari berat beban jika satu
sling digunakan
3t slings 3t slings
1.5t
Take 50% off your slings when double wrap and choke
Your Slings are no longer worth 3t each but 1.5t
Make sure the load and slings match
METHOD OF SLINGING THE LOAD
Hitch factor shall be
considered:
30
METHOD OF SLINGING THE LOAD
31
METHOD OF SLINGING THE LOAD
EXECUTION LIFTING OPERATIONS
33
EXECUTION LIFTING OPERATIONS
1. Do you have PTW for this job?/Apakah anda telah memiliki izin kerja?
2. Are you experienced, competent and trained to do the work?/Apakah
anda berpengalaman, kompeten dan telah mendapatkan pelatihan untuk
bekerja?
3. Do you Lift Plan Approved?/Apakah anda memiliki rencana
pengangkatan yang telah disetujui?
4. Did you perform job safety analysis or risk assessment?/Apakah anda
telah melakukan analisa keselamatan kerja atau penilaian risiko kerja?
5. Did you perform pre-lift checklist of lifting operation?/Apakah anda telah
melakukan pemeriksaan sesaat sebelum pengangkatan?
34
EXECUTION LIFTING OPERATIONS
35
EXECUTION LIFTING OPERATIONS
36
EXECUTION LIFTING OPERATIONS
37
HOW DO ACCIDENTS OCCUR?
Instability
1
2 Lack of Communication
Lack of Training 3
Inadequate Maintenance or Inspection
4
CRANE INCIDENT
Machinery & Structural
Failure to use Outriggers (22%) Failure (11%)
High Winds
(2%)
45
BAD RIGGING PRACTICES...
BAD RIGGING PRACTICES...
Scaffold tube as
leverage to jack up
pipe for fit-up.
Webbing sling
tied with wires.
47
47
BAD RIGGING PRACTICES...
Safety Latch not engaged
Pipe to be
joint welded
49
49
BAD RIGGING PRACTICES...
Knots in Slings
50
BAD RIGGING PRACTICES...
51
BAD RIGGING PRACTICES...
52
BAD RIGGING PRACTICES...
53
BAD RIGGING PRACTICES...
55
BAD RIGGING PRACTICES...
Damaged Safety
Latch
Over pulled…
(under Direct Supervision..?)
Signs of over-tightening…
56
BAD RIGGING PRACTICES...
Improper use of
Vertical I-beam Clamp
57
BAD RIGGING PRACTICES...
Sideways, over-pulled
58
BAD RIGGING PRACTICES...
59
BAD RIGGING PRACTICES...
60
BAD RIGGING PRACTICES...
•1250
Reduction in sling
capacity
61
BAD RIGGING PRACTICES...
62
BAD RIGGING PRACTICES...
63
BAD RIGGING PRACTICES...
Two hoist
connections into
One slinging
point
Bad practice
66
BAD RIGGING PRACTICES...
• Hoisting arrangement
wrapped around
scaffolding tube under
loaded conditions
• High-Risk potential to
damage and collapse
scaffolding frame
68
BAD RIGGING PRACTICES...
Chain block at to
larger angle
70
BAD RIGGING PRACTICES...
Uneven loading on
Chain Hoist load chain
as a result of the
suspension hook being
twisted before use
71
BAD RIGGING PRACTICES...
Sling twisted
Chain Block hooked to
the Beam Flange
74
BAD RIGGING PRACTICES...
75
BAD RIGGING PRACTICES...
• Hoisting arrangement
wrapped around
scaffolding board
under loaded
conditions
• High-Risk potential to
damage and collapse
scaffolding
76
BAD RIGGING PRACTICES...
77
BAD RIGGING PRACTICES...
81
GOOD RIGGING PRACTICES...
83
GOOD RIGGING PRACTICES...
85
LASHING BELTS...
Use as Intended/Gunakan
sesuai
peruntukkannya
86
LASHING BELTS...
88
LASHING BELTS...
89
TEMPORARY SUPPORTS...
90
TEMPORARY SUPPORTS...
Grinding Disc,
inserted for the
elevation required.
DESIGN 1
91
TEMPORARY SUPPORTS...
DESIGN 3
DESIGN 2
92
TEMPORARY SUPPORTS...
Suspended by Scaffolding GI wire used for lashing
scaffold boards
93
93
TEMPORARY SUPPORTS...
95
Incorrect securing of spools
TEMPORARY SUPPORTS...
96
TEMPORARY SUPPORTS...
Pipe placed on
incorrect temporary
support
TEMPORARY SUPPORTS...
Unstable & Unsafe cribbing collapsed and caused a fatality on another project