Judul : Analisis Keterlambatan Proyek Pembangunan Bandar Udara Baru


Banggai Laut dengan Metode Fault Tree Analysis
Mahasiswa : Agustinus Dimas Bramudya
NRP : 6012221055

Telah diseminarkan pada:


Hari : …………………………………………………………………………
Tanggal : ………………………………………………………………………….
Tempat : …………………………………………………………………………

Mengetahui / menyetujui:
Dosen Penguji: Calon Dosen Pembimbing:
1……………………………………… 1.………………………………………
NIP: NIP:

2……………………………………… 2………………………………………
NIP: NIP:

3……………………………………… 3………………………………………
…. ….
NIP: NIP:

1
ANALISIS KETERLAMBATAN PROYEK BANDAR UDARA
BARU BANGGAI LAUT DENGAN METODE FAULT TREE
ANALYSIS

Nama Mahasiswa : Agustinus Dimas Bramudya


NRP : 6012221055
Dosen Konsultasi : Dr. Farida Rachmawati, ST, MT.

ABSTRAK

Industri konstruksi memiliki peran yang sangat penting dalam mendukung


pembangunan infrastruktur suatu negara. Salah satu proyek infrastruktur yang
menjadi perhatian adalah Proyek Pembangunan Bandar Udara Banggai Laut
Sulawesi Tengah. Pembangunan bandar udara ini bertujuan untuk membuka
daerah Kabupaten Banggai Laut sebagai daerah terisolir dan mengembangkan
potensi pariwisata di Banggai Laut. Pada proses berjalannya pekerjaan, proyek ini
telah mengalami beberapa kali keterlambatan yang cukup signifikan.
Keterlambatan proyek konstruksi bandar udara dapat berasal dari berbagai
faktor, seperti perencanaan yang tidak tepat, masalah finansial, kendala sumber
daya manusia, konflik kepentingan, dan lain sebagainya. Oleh karena itu, penting
untuk memahami akar penyebab keterlambatan proyek tersebut dengan cara yang
sistematis dan komprehensif. Salah satu metode untuk menganalisis faktor
keterlambatan proyek adalah menggunakan metode Fault Tree Analysis (FTA).
Metode FTA adalah salah satu pendekatan analisis risiko yang telah terbukti
efektif dalam mengidentifikasi penyebab utama dari suatu peristiwa yang tidak
diinginkan. Dengan menerapkan FTA, penelitian ini akan mencoba memahami
faktor-faktor apa yang mungkin telah berkontribusi terhadap keterlambatan
proyek ini. Hasil penelitian ini diharapkan dapat memberikan masukan berharga
kepada para pemangku kepentingan untuk meningkatkan efisiensi dan efektivitas
manajemen proyek infrastruktur yang kompleks seperti Bandar Udara Banggai
Laut.

Kata kunci: analisis keterlambatan proyek, fault tree analysis, proyek konstruksi
bandara

2
BANGGAI LAUT AIRPORT PROJECT DELAY ANALYSIS
USING FAULT TREE ANALYSIS METHOD

By : Agustinus Dimas Bramudya


Student Identity Number : 6012221055
Advisor 1 : Dr. Farida Rachmawati, ST, MT.

ABSTRACT

The construction industry plays a crucial role in supporting the


development of a country's infrastructure. One of the infrastructure projects of
particular concern is the Banggai Laut Airport Development Project in Central
Sulawesi. The construction of this airport aims to open up the remote region of
Banggai Laut and develop its tourism potential. During the course of the project,
it has experienced several significant delays.
Construction project delays at airports can result from various factors
such as inadequate planning, financial issues, human resource constraints,
conflicting interests, and more. Therefore, it is essential to systematically and
comprehensively understand the root causes of these project delays. One method
for analyzing delay factors is by utilizing the Fault Tree Analysis (FTA) method.
The FTA method is one of the risk analysis approaches that has proven to
be effective in identifying the primary causes of undesirable events. By applying
FTA, this research aims to comprehend the factors that may have contributed to
the delay of this project. The findings of this study are expected to provide
valuable insights to stakeholders for improving the efficiency and effectiveness of
complex infrastructure project management, such as the Banggai Laut Airport.

Keyword: airport construction project, fault tree analysis, project delay analysis

3
DAFTAR ISI

Judul Penelitian i
Lembar Pengesahan ii
Abstrak iii
Daftar Isi v
Daftar Gambar vi
Daftar Tabel vii
BAB 1 PENDAHULUAN 1
1.1 Latar Belakang 1
1.2 Perumusan Masalah 2
1.3 Tujuan Penelitian 2
1.4 Manfaat Penelitian 2
1.5 Batasan Penelitian 2
BAB 2 TINJAUAN PUSTAKA 5
2.1 State of The Art Penelitian 5
2.2 Proyek Konstruksi 7
2.3 Keterlambatan Proyek 7
2.3.1 Penyebab Keterlambatan Proyek 7
2.4 Metode Fault Tree Analysis 9
2.4.1 Simbol – simbol dalam Fault Tree Analysis 10
2.4.2 Tahapan dalam Diagram Fault Tree Analysis (FTA) 13
2.4.3 Kelebihan dan Kekurangan Metode Fault Tree Analysis 16
2.4.4 Teori Reliabilitas 17
BAB 3 METODE PENELITIAN 19
3.1 Diagram Alir Penelitian 19
3.2 Uraian Tahapan Penelitian 20
3.2.1 Tahap Pendahuluan 20
3.2.2 Pengumpulan Data 20
3.2.3 Analisis Data dengan Fault Tree Analysis 20
3.2.4 Pelaporan 21
3.3 Hasil Penelitian 21
3.4 Rencana dan Jadwal Kegiatan Penelitian 22
Daftar Pustaka23

4
DAFTAR GAMBAR

Gambar 3.1 Diagram Alir Penelitian 19

5
DAFTAR TABEL

Tabel 2.1a State of the Art Penelitian 5


Tabel 2.1b State of the Art Penelitian (Lanjutan) 5
Tabel 2.2 Simbol Kejadian pada Fault Tree Analysis 11
Tabel 2.3 Simbol Gerbang pada Fault Tree Analysis 12
Tabel 2.4 Simbol Transfer pada Fault Tree Analysis 13
Tabel 3.4 Rencana dan Jadwal Kegiatan Penelitian 22