STUDI KELAYAKAN
OLEH :
1
MAKSUD DAN TUJUAN
2
LINGKUP PEKERJAAN
4. Jadwal proyek
6. Pelaporan
3
EVALUASI LOKASI PLT BIOMASA
4
POSISI LOKASI PLTBm sintang 10 MW
5
TATA LETAK PEMBANGKIT LISTRIK
(PLANT LAYOUT)
2 1. ASH YARD
1 2. WATER POND
3. BOILER
4. LIVE STORAGE
5. R.O. WATER PLANT
4 6. CONTROL ROOM
7. COOLING TOWER
8. ADMIN. BUILDING
9. MAIN GATE
3
5
7 6
8
9 6
DIAGRAM ALIR PLTBm
DIAGRAM ALIR PLT BIOMASA
(LIMBAH (LIMBAH
PABRIK PABRIK
KELAPAKELAPA
SAWIT SAWIT)
& KAYU KARET)
7
Parameter karakteristik bahan bakar
utama sbb :
Descriptions Kernel EFB Fiber Rubber Combina
Cake wood tion
Component (%) 50% 20% 10% 20% 100%
Proximate Analysis
Volatile Matter 59.36 79.34 75.8 71.81 67.49%
Fixed Carbon 18.78 8.36 12.1 15.25 15.32%
Ash 1.86 4.5 3 2.71 2.67%
Moisture 20 7.8 51 10.24 18.71%
Low Heating Value, kCal/kg 4,019 3,397 3,721 4,089 3,879
Ultimate Analysis (dry basis)
Carbon 49.37 43.52 45.08 49 47.70%
Hydrogen 5.65 5.72 6.1 5.87 5.75%
Oxygen 44.52 48.9 47.06 43.97 45.54%
Nitrogen 0.44 1.2 1.61 0.3 0.68%
Sulphur (less than 0.3) 0.02 0.66 0.15 0.01 0.16%
8
KONSUMSI BAHAN BAKAR BIOMASA UTAMA
10
BIOMASS LIVE STORAGE & ASH YARD
SPECIFICATION
LIVE STORAGE
Period 15 day
ASH DISPOSAL
Content 0.03 %
Period 365 day
11
SIMULATION FROM GATE CYCLE
12
PERALATAN UTAMA PLTBm sintang 10 MW
13
1. GENERATOR
Unit : 1 Unit
Kapasitas : 10 MW
Voltage generator : 11,5 kV
Rotasi : 3,000 rpm
Frekuensi : 50 Hz
Netral : Resistant grounded
Koneksi : YN
2. GENERATOR TRANSPORMER
Unit : 1 Unit
Impendansi : 11%
14
JADWAL PENYELESAIAN PEMBANGKIT
Description (Month)
Feasibility Study (completed) Mei 2017
Power Purchase Agreement Signing October 2017
Financial Close Feb 2018
EPC Contract Signing March 2018
Site Preparation April 2018
Construction start : April 2018
Fabrication April 2018
Civil work April 2018
Shipment October 2018
Erection/Construction Feb 2019
run/Individual test July 2019
Finishing Nov 2019
Plant Commissioning Start Dec 2019
COD March 2020
15
16
ANALISA FINANSIAL
Description Total Cost (USD)
Direct Cost
17
FINANCIAL PARAMETER
18