Double pipe lube oil-crude oil exchanger.

6,900 lb/hr of a 26 API lube oil


must be cooled from 450 to 350o F by 72,500 lb/hr of 340 API mid-
continent crude oil. the crude oil will be heated from 300 to 310o F.

A fouling factor of 0.003 should be provided for each stream, and the
allowable pressure drop on each stream will be 10 psi.

A number of 20-ft hairpins of 3-by 2-in. IPS pipe are available. How many
must be used, and how shall they be arranged? The viscosity of the crude
oil may be obtained from Fig.14. For the lube oil, viscosities are 1.4
centipoises at 500o F, 3.0 at 400o F, and 7.7 at 300o F. these viscosities are

( )
great enough to introduce an error if =1 is assumed.

Ganda pipa lube penukar minyak minyak mentah. 6.900 / jam dari
minyak pelumas 26 API harus didinginkan 450-350o F dengan 72.500 /
hr dari 34 API pertengahan benua minyak mentah. minyak mentah akan
dipanaskan 300-310o F.

Faktor fouling dari 0,003 harus disediakan untuk setiap aliran, dan
penurunan tekanan yang diijinkan pada setiap aliran akan menjadi 10 psi.

Sejumlah jepit rambut 20-ft 3-oleh 2-in. IPS pipa yang tersedia. Berapa
banyak harus digunakan, dan bagaimana akan mereka diatur? Viskositas
minyak mentah dapat diperoleh dari Gbr.14. Untuk minyak pelumas,
viskositas adalah 1,4 centipoises pada 500 M, 3,0 pada 400o F, dan 7,7
pada 300o F. viskositas ini cukup besar untuk memperkenalkan kesalahan
jika (/) = 1 diasumsikan.

it will impossible to put the 72,500 lb/hr of crude into a single pipe or
annulus, since the flow area of each is too small. assume, as a trial, that it
will be employed in two parallel streams.

itu akan mustahil untuk menempatkan 72.500 / hr minyak mentah ke


dalam pipa tunggal atau anulus, karena daerah aliran masing-masing
terlalu kecil. berasumsi, sebagai percobaan, yang akan digunakan dalam
dua aliran paralel.

This is equivalent to more than six 20-ft hairpins or 240 lin feet. since two
parallel streams are employed, use eight hairpins or 320 lin. feet. The
hairpins should have the annuli connected in series and the tube in two
parallel banks of four exchangers. The corrected UD will be UD = Q/A =
427,000/320 X 0.622 X 87.5 = 24.5.

The corrected dirt factor will be Rd = 1/UD - 1/Uc = 1/24.5 - 1/34,0 =


0.0114.

Hal ini setara dengan lebih dari enam jepit rambut 20-ft atau 240 kaki lin.
sejak dua aliran paralel bekerja, menggunakan delapan jepit rambut atau
320 lin. kaki. The jepit rambut harus memiliki annuli dihubungkan secara
seri dan tabung di dua bank paralel empat penukar. UD dikoreksi akan UD
= Q / A = 427.000 / 320 X 0,622 X 87,5 = 24,5.

Faktor kotoran dikoreksi akan RD = 1 / UD - 1 / Uc = 1 / 24,5-1 / 34,0 =


0,0114.

Allowable Pp = 10.0 psi

if the flow had not been divided, the pressure drop would be nearly eight
times as great, or about 60 psi

Diijinkan Pp = 10,0 psi

jika aliran belum dibagi, penurunan tekanan akan hampir delapan kali
lebih besar, atau sekitar 60 psi