KANDUNGAN
1.0 Gambaran Keseluruhan 6.0 Pelan Susunatur Tapak
Pengurusan Tapak 6.1 Pengenalan
2.0 Dokumen Kontrak 6.2 Lokasi projek
2.1 Pengenalan 6.3 Utiliti sedia ada
2.2 Pengenalan jenis kontrak 7.0 Pihak Berkuasa
2.3 Kandungan Dokumen Kontrak 7.1 Pengenalan
3.0 Program Kerja 7.2 Penguasa Tempatan Tempatan
3.1 Pengenalan (PBT)
3.2 Mobilisasi 7.3 Agensi-agensi Kerajaan
3.3 Aplikasi Lukisan 7.4 Prosidur
3.4 Jadual Kerja 8.0 Kawalan Inventori Dan
3.5 Keperluan Sumber Prosedur
4.0 Carta Organisasi Projek 8.1 Pengenalan
4.1 Pengenalan 8.2 Prosidur Pentadbiran Inventori
LP 6 4.2 Aliran kuasa
4.3 Polisi gunatenaga kerja syarikat
9.0 Kawalan Keselamatan
9.1 Pengenalan
5.0 Keselamatan, Kesihatan dan 9.2 Jenis-jenis kawalan keselamatan
Alam Sekitar 9.3 Kawalan Tapak
5.1 Pengenalan 9.4 Personnel
5.2 Manual Dan Prosedur 9.5 Prosidur Pemantauan
PENGURUSAN TAPAK 5.3 Akta-akta dan Peraturan 9.6 Prosidur Laporan
1
11/4/2017
PERSEKITARAN PERUNDANGAN
Undang-undang Substantif: Kontrak dalam kata mudah
adalah persetujuan antara dua atau
1. Kontrak lebih pihak untuk melakukan atau tidak
melakukan sesuatu bagi mendapatkan
2. Tort (Kesalahan Sivil) sesuatu sebagai balasan.
3. Pengguna Undang-undang kontrak di Malaysia
berasaskan “common-law” dan dikawal
4. Amalan Perdagangan oleh Akta Kontrak 1950 (Pindaaan
1974) bersama beberapa provisi
5. Perlembagaan dalam Akta Relief Spesifik 1950.
Namun, prinsip-prinsip dalam “common
6. Percukaian law” masih terpakai di negara ini menerusi
peruntukan dalam seksyen 3 dan 5 Akta
7. ________ dll. Undang-Undang Sivil 1956.
Ini kerana Akta Kontrak 1950 bukanlah
suatu Akta yang lengkap dan menyeluruh
bagi mengawal selia semua elemen-
elemen dalam undang-undang kontrak.
2
11/4/2017
3
11/4/2017
4
11/4/2017
5
11/4/2017
Pemilik Perunding
Design & BUild
Kontraktor
Arkitek Sub-
Kontraktor/In-
House Design
6
11/4/2017
7
11/4/2017
Over and above the common methods of contract procurement described above,
(i) ‘Develop and construct’ contract: this is similar to a there exist other types of contracts that are being utilized by the local construction
design and build contract, but a concept design is industry. These are essentially variations of the conventional methods and have been
developed to address specific uses. Such contracts include, inter alia, the following:
prepared by independent professionals engaged by
the employer before the design and build contractor is (i) ‘Build, operate and transfer 50 contract’:
(ii) (ii) ‘Serial contract’:
selected ; (iii) (iii) ‘Continuation contract’:
(ii) ‘Design and manage’ contract: This is similar to a (iv) (iv) ‘Periodic contract’:
(v) (v) ‘Partnering contract’:
management contract, but the contractor is also (vi) vi) ‘Independent contract’:
(vii) Engineering, Procurement, Construction and Commissioning ("EPCC")
responsible for detailed design or for managing the design (viii)TProject Management Contractor (PMC)
process; (ix) EPIC - Engineering Procurement Installation Commisioning
(iii) ‘Design and construction management’ contract: This
is similar to construction management but the
construction manager is also responsible for detailed
design or for managing the design process.
8
11/4/2017
2.3.1 Kontrak
Konventional: Work Program Specification (Conventional)
Jabatan Kerja Raya Malaysia
LA
1.0 GENERAL
1.1. This specification describes the requirements for the preparation,
submittal, update and revision of the Contractor’s Work Program. The
requirements are in addition to the provisions under Clause 12.0 of
the Condition of Contract.
9
11/4/2017
SURAT SETUJU-TERIMA 1.4. The Work Program shall be produced by the Contractor
TENDER LETTER OF ACCEPTANCE OF TENDER
OLEH KONTRAKTOR UTAMA KEPADA
in the following phases:
SUBKONTRAKTOR DINAMAKAN
BY MAIN CONTRACTOR TO NOMINATED SUB-CONTRACTOR 1.4.1. Initial Work Program. An Initial Work Program for
……………………………………………….
the first three months of work.
……………………………………………….
………………………………………………. 1.4.2. Accepted Work Program. A Work Program
(Kontraktor Utama)
(Main Contractor)
(incorporating the Initial Work Program) for the totality of the
Tarikh ........................................... Works, which shall be submitted to the S.O. for his
Date : approval. If the S.O. does not approve it, this Work Program
Kepada, To,
shall be revised and resubmitted for acceptance as set out
………………………………………………… in the Contract.
…………………………………………………
…………………………………………………
(Subkontraktor Dinamakan)
(Nominated Sub-Contractor)
Tuan,
1.4.3. Revised Work Program. Any revision to the Accepted Work 2.0 SUBMISSION OF WORK PROGRAM
Program approved by S.O shall be termed as Revised Work
Program. 2.1 Within fourteen (14) days after the date of the Letter of Acceptance, the
Contractor shall submit to the S.O. for his information on Initial Work Program
1.4.4. Tracking Report. Accepted/Revised Work Program updated showing the order in which the Contractor proposes to carry the works
anticipated in the first three months following the award of the contract. The
with actual progress and saved on at least a monthly basis for Initial Work Program shall have regard to the completion date and any other
progress tracking and record purposes. milestones, and/or restraints set out in the contract.
1.5. Approval by the S.O. of any phase of the Contractor’s Work 2.2 Within twenty eight (28) days after the date of the Letter of Acceptance [or
Program does not make the Work Program a contract document, such other time as may be specified in the Contract], the Contractor shall
submit to the S.O. for his review and acceptance a Work Program for the
or mandate that the Works shall be constructed strictly in whole Contract (incorporating the Initial Work Program) showing the order of
accordance with the Work Program. The Contractor at all times procedure in which the Contractor proposes to carry out the Works. This Work
remains responsible for the construction of the Works in Program becomes the Accepted Work Program upon acceptance by the S.O. The
accordance with Clause 6.0 of the Condition of Contract Accepted Work Program shall have regard to the contract completion dates and any
other milestones, and/or restraints set out in the Contract. Thereafter, if the actual
progress does not conform to the Accepted Work Program, the S.O. is entitled to
require the Contractor to submit to the S.O. for acceptance a revised Work Program
showing the order of procedure and periods necessary to ensure completion of the
Works by the contract completion dates.
10
11/4/2017
3.2 Mobilisasi
2.4 The Contractor shall supply the S.O. with electronic Tarikh milik tapak
copy of each Work Program, together with a print out bar
- Rujuk klausa 38.2 JKR 203A (Rev. 1 /2010)
chart or tabular report in a pre-agreed format. All Work
Programs shall be prepared and submitted using Microsoft • Employer is obligated to give possession of site to allow
Project 2003 software or latest version or equivalent. The contractor to carry out his work.
software shall be capable of producing Work Programs and • The date of possession is stated in letter of acceptance sent
information that complies with the requirements of this clause to contractor and appendix of condition of contract in contract
documents.
and shall be in a format that can be read by commercially • Usually the date of submission of the construction site is 2
available proprietary planning software. weeks after the date (LA)
• Within 2 weeks - the purpose to provide opportunities for the
4.1.1 The Work Program must be presented in a Works Breakdown contractor to provide necessary preparations before starting
work on site
Structure (WBS) format to designated level approved by JKR or its
representatives.
MAX 60 DAYS
11
11/4/2017
PAM2006
Commencement and completion (Refer to Clause 21.1)
• The contractor must be given full or exclusive possession of the
site – the whole site even though some parts may not be needed
until a later stage of the project
• The contractor is entitled to assume unrestricted possession of the
whole site to enable him to plan his work accordingly – unless
there is agreement to the contrary
• The architect will issue instruction to fix the date for site possession
if :
A) the date of commencement is not specified
B) the date specified becomes invalidated which is not due to
contractor’s fault
e.g: deferment of possession of site by the employer to A
new date
• The architect has the power to defer the possession of site for any
reason
• If the date of possession is deferred, the date of completion will be
revised accordingly.
12
11/4/2017
13
11/4/2017
No. Tajuk Akta Aktiviti Pembinaan No. Tajuk Akta Aktiviti Pembinaan
Terbabit Terbabit
1 Pencemaran Udara – EQA 1974 Tapak Pembinaan 8 Undang2 berkaitan dgn. Akta Keselamatan dan Tapak Pembinaan
Pembakaran Keselamatan pekerja di Kesihatan Pekerja 1994
Terbuka tapak binaan. (AKKP 1994) dan Akta Kilang
2 Pencemaran Udara EQ (Control of Emission from Tapak Pembinaan dan Jentera 1967 (AKJ 1967)
Disel Engines) regulations 1998
3 Scheduled waste EQ (Clean Air) Regulations 1978 Tapak Pembinaan 9 Akta2, Peraturan dan Tapak Pembinaan
Perintah berkaitan dgn.
4 Pencemaran Bising EQA 1974 Tapak Pembinaan ISO 14001 EMS
Local Govt Act 1976
5 Pencemaran Air EQA 1974 Tapak Pembinaan
Environmental Quality (Sewage
and Industrial Effluents) 10 Jenis Kimia & Kawalan Explosive Act 1957 (Act 207) Tapak Pembinaan
Regulations 1979 & Rules 1923 & Persekitaran
6 Pencemaran Tanah EQA 1974 Tapak Pembinaan 11 Akta2, Peraturan dan Peraturan2 Kerajaan Tapak Pembinaan
(termasuk `siltation’, Perintah berkaitan dgn. tempatan. & Persekitaran
habuk) JPJ, Kumbahan, Bekalan
7 Tree Preservation Act 172 Town & Country 1976 Tapak Pembinaan Letrik, Uniform Building
By Laws (UBBL) dll.
14
11/4/2017
15
11/4/2017
(1) No person shall handle any refrigerant environmentally hazardous substance unless he has
received the approved training in the reclamation and recycling of any refrigerant
environmentally hazardous substance and is in possession of an approved machine for the
activity.
16
11/4/2017
Always wear: safety glasses and gloves to keep debris from getting into
your eyes and to prevent frostbite.
R-410A adalah penyejuk tekanan tinggi yang paling biasa digunakan hari ini. Pemulihan wap vapor recovery, yang paling biasa;
“Push-pull method”
Kerja-kerja Pemulihan memerlukan penggunaan tangki, hos, pancarongga Pemulihan cecair (liquid recovery method), yang semakin
dan peralatan pemulihan yang berbeza.
popular.
Apabila bekerja dengan penyejuk tekanan tinggi, pastikan anda
menggunakan “set” manifold dengan “low-side gauge” yang boleh baca Perlu sentiasa ingat untuk menggunakan “filter-dryer or particulate
tekanan sehingga sekurang-kurangnya 500 psig dan “high-side gauge” yang filter” pada unit pemulihan penyejuk anda.
boleh baca sehingga sekurang-kurangnya 800 psig.
Juga penting ialah guna “acid core dryer” apabila membuat
Pastikan anda menggunakan pemasangan hos yang diberi nilai oleh UL “recovery” daripada “burnedout system”.
untuk kegunaan tekanan tinggi.
Asid dan bahan zarahan akan merosakan sistem pemulihan
Tolok digunakan pada set manifold tradisional tidak dapat membaca tahap
penyejuk anda. Jika anda gunakan penapis yang sesuai pada setiap
tekanan yang dihadapi dengan penyejuk tekanan tinggi.
kerja pemulihan penyejuk anda, peralatan boleh tahan bertahun-
tahun tanpa sebarang masalah.
17
11/4/2017
Connect a hose with a low-loss fitting on both ends to the discharge side of
the recovery equipment. Connect the other end of this hose to the tank liquid
port on the recovery cylinder.
18
11/4/2017
19
11/4/2017
20
11/4/2017
21.1 The Contractor shall comply in all respects (including the giving of
all notices and the paying of all fees required) with any law, regulation
or by-law, or any order or directive issued by any public authority or
public service company (hereinafter referred to as "Statutory
Requirements"), relating to the Works or, in the case of public
authority or public service company, with those systems the same are
or will be connected. The Contractor shall submit to the S.O. all
approvals received by the Contractor in connection therein. The
Contractor shall keep the Government indemnified against all
penalties and liability of every kind for breach of any such Statutory
Requirements.
21
11/4/2017
Rujuk LP3
RUJUKAN
a) Manual Sistem Pengurusan Bersepadu (JKR)
b) Akta Keselamatan dan Kesihatan Pekerjaan 1994
c) Akta Kilang dan Jentera 1974
d) Standard Specifications for Building Works 2014 (JKR
20800-0183-14)
SECTION A : PRELIMINARIES AND GENERAL CONDITIONS
22
11/4/2017
Site security
Considerations in terms of :
1. Materials theft/security
1.1 Logistics
1.2 Outbuildings
1.3 Site office
1.4 Metal theft
1.5 Cable theft
23
11/4/2017
The likelihood is quite high but the impact is relatively low. Using rough numeric values,
a high likelihood is 5, a low impact is 1 – the risk score is thus 5 x 1 = 5. Referencing the
table below, it can be seen that the resultant raw risk is Amber.
Note here that the precise numbers used will vary according to the risk appetite (see
below) of the assessor. Also note that likelihood is often conditioned by local
circumstances and demography, as well as relative attractiveness of target assets to
criminals or other malicious elements.
24
11/4/2017
25
11/4/2017
Delay
No barrier is impenetrable if an attacker is determined enough to 9.4 Personnel
break it. The measure should therefore be in terms of the delay
provided. The fitting of an intruder alarm will detect a crime but will Policy and Process
not prevent theft unless sufficient delay can be caused to slow the All security operations on site should be performed in accordance with the
Site Security Policy, which should be owned by the site manager or
action of a burglar. Any delay during the committing of crime operator and which will support a number of processes. These processes
increases the danger to a criminal that they will be caught and should be developed by the guard force operator in agreement with the
manager and operator and should underpin the Site Security Policy. These
therefore acts as a deterrent to completion of the crime. It is not processes should be managed, monitored and their performance
just whether a solution can be defeated that should be taken into measured and form part of the service level agreement above.
account but how long it takes to defeat and what effort is required. The Site Security Policy should explicitly state the requirements of site
security and the means and xtent of its enforcement. It should define, for
Response example, the classes of person to be granted access, the requirements for
If a criminal is not completely deterred then at some point a form of gaining site access (such as agreement to exit searches, for example), the
powers of the guard force and all other requirements for security. A clear
response is required. Response could be actions of a security guard condition for site access must be explicit acceptance of the Site Security
or the arrival of police. To determine the security provisions the Policy and persons not accepting it should be denied access.
The Site Security Policy should also cover the obligations and responsibilities
form of response must be known. If it is going to take fifteen of personnel employed on or visiting the site. This should include traffic
minutes for guards or police to arrive then the delay provided circulation, responsibility for reporting safety or security breaches and the
should match this. requirement to cooperate with the guard force.
26
11/4/2017
Rujuk kepada “Site Security Policy” Rujuk kepada “Site Security Policy”
27
11/4/2017
28
11/4/2017
29
11/4/2017
30
11/4/2017
ISI KANDUNGAN
BIL PERKARA
31