Perhitungan "Tulangan BELAKANG" Dinding Bagian Bawah Stabilitas DPT Cantilever
Penulangan MOMEN
Momen Guling M = 17.31 kN.m/m
lebar penampang b = 1,000 mm
tinggi penampang h = 400 mm
selimut beton = 50 mm
tinggi efektif penampang d = 350 mm
Tegangan leleh baja fy = 240 Mpa
Tegangan hancur beton fc = 20 Mpa
MOMEN ultimit Mu = 1.4 M = 24.24 kN.m/m
rasio tul maks r maks = 0.0316
rasio tul min r min = 0.0029 (Tabel Gideon Hal. 50)
Mu/(fbd2) = Ru = 0.2328 Mpa
rasio tul perlu r = 0.0010 pakai p min
tulangan momen perlu As = 1,021 mm²
desain diameter tul momen = 12 mm
jumlah tul n = 10 buah
desain luas tul momen As = 1,131 mm² OK
jarak antar tul = 100 mm tulangan geser
10 mm - 100 mm
Penulangan GESER
Sigma beton fc = 20 MPa tulangan momen
Sigma geser ijin vc = 0.407 Mpa --> 1/11 √fc 12 mm - 100 mm
Gaya geser ijin = 142.30 kN --> d.vc
Gaya horisontal (Ph + Pw) = 21.08 kN
tul geser min 0.0018 Ag = 720 mm²
desain diameter tul geser = 10 mm
jumlah tul geser n = 10 buah
desain luas tul geser = 785 mm² OK
jarak antar tul = 100 mm
Penulangan MOMEN
Momen Guling M = 1.41 kN.m/m tulangan geser
lebar penampang b = 1,000 mm 10 mm - 143 mm
tinggi penampang h = 300 mm
selimut beton = 50 mm
tinggi efektif penampang d = 250 mm
Tegangan leleh baja fy = 240 Mpa tulangan momen
Tegangan hancur beton fc = 20 Mpa 12 mm - 143 mm
MOMEN Mu = 1.4 M = 1.98 kN.m/m
rasio tul maks r maks = 0.0316
rasio tul min r min = 0.0029 (Tabel Gideon Hal. 50)
Mu/(fbd2) = Ru = 0.0373 Mpa
rasio tul perlu r = 0.0002 pakai p min
tulangan momen perlu As = 729 mm²
desain diameter tul momen = 12 mm
jumlah tul n = 7 buah
desain luas tul momen As = 792 mm² OK
jarak antar tul = 143 mm
Penulangan GESER
Sigma beton fc = 20 MPa
Sigma geser ijin vc = 0.407 Mpa --> 1/11 √fc
Gaya geser ijin = 101.64 kN --> d.vc
Gaya horisontal Ph = 3.39 kN
tul geser min 0.0018 Ag = 540 mm²
desain diameter tul geser = 10 mm
jumlah tul geser n = 7 buah
desain luas tul geser = 550 mm² OK
jarak antar tul = 143 mm
2
Stabilitas DPT Cantilever
Perhitungan "Tulangan BAWAH" Pelat Fondasi Bagian Depan
Penulangan MOMEN
beban merata di dasar pelat depan p1 = 65.86 kN/m2
Momen jepit M1 di pelat depan (1/2 p1 B22) = 5.27 kN.m/m
lebar penampang b = 1,000 mm tulangan momen
tinggi penampang h = 500 mm 16 mm - 143 mm
selimut beton = 50 mm
tinggi efektif penampang d = 450 mm
Tegangan leleh baja fy = 240 Mpa
Tegangan hancur beton fc = 20 Mpa
MOMEN Mu = 1.4 M = 7.38 kN.m/m
rasio tul maks r maks = 0.0316
rasio tul min r min = 0.0029 (Tabel Gideon Hal. 50)
Mu/(fbd2) = Ru = 0.0429 Mpa
rasio tul perlu r = 0.0002 pakai p min
tulangan momen perlu As = 1,313 mm² tulangan geser
desain diameter tul momen = 16 mm 12 mm - 125 mm
jumlah tul n = 7 buah
desain luas tul momen As = 1,407 mm² OK
jarak antar tul = 143 mm
Penulangan GESER
Sigma beton fc = 21 MPa
Sigma geser ijin vc = 0.417 Mpa --> 1/11 √fc
Gaya geser ijin = 99.98 kN --> d.vc
Gaya vertikal (p1 B2) = 26.35 kN
tul geser min 0.0018 Ag = 900 mm²
desain diameter tul geser = 12 mm
jumlah tul geser n = 8 buah
desain luas tul geser = 905 mm² OK
jarak antar tul = 125 mm
Penulangan GESER
Sigma beton fc = 21 MPa
Sigma geser ijin vc = 0.417 Mpa --> 1/11 √fc
Gaya geser ijin = 99.98 kN --> d.vc
Gaya vertikal (p2 B4) = 18.00 kN
tul geser min 0.0018 Ag = 900 mm²
desain diameter tul geser = 12 mm
jumlah tul geser n = 8 buah
desain luas tul geser = 905 mm² OK
jarak antar tul = 125 mm
3
PERENCANAAN DINDING PENAHAN TANAH PASANGAN BATU
0,30
h H
b
d g4
b +d+g4
Ph Kondisi B :
Tekanan Air di muka dan belakang dinding sama, jadi saling meniadakan
pa = 0.5 x H^2 x gsat x ka
= 0.5 x 12.25 x 1.80 x 0.333 = 3.68 t
Kondisi C
P1 = 0.24 t Tekanan pada dinding per meter
P2 = 0.96 t pa = 1/2 x g x H2 x Ka - 2 x C x √ Ka
P3 = 0.5 t = 2.614 t
Pa = 3.68 t Tekanan air pada dinding arahnya tegak lurus dinding
Pah = 29.755 t Pw = 0.5 x H2 x gsat
Pav = 0.8939 t = 0.5 x 12.25 x 1.80 = 11.025 t
Pp1 = 0.675 t Pah = Pw + Pa x Cos Æ
Pp2 = 0.000 t = 11.03 + 2.614 x 0.940 = 29.755 t
Pav = Pa x Sin Æ
= 2.614 x 0.342 = 0.8939
Penyelesaian :
dc. Ic .c. Nc = 1.40 0.560 0 30.13 = 0
dq.iq.Df.g.Nq = 2.26 0.600 1 1.8 18.40 = 44.81
dg.ig.0.5.B.g.Ng = 1 0.481 0.5 1.8 11.20 = 4.85
Maka :
Qult = dc. Ic .c. Nc + dq.iq.Df.g.Nq+dy.iy.0.5.B.g.Ni
Qult = 0 44.811 4.849
= 49.660
Daya Dukung ijin
Sf = Qult / 3
= 16.55 t/m2 Qmax ≤ Qijin (OK)
0.30
Pas. Batu
3.00 H=2m
L = 50 m
3.50
0.50
1.80 m
No URAIAN
1 PENDEKATAN & ASUMSI
Tinggi dinding keseluruhan H = 3.50 m
Tinggi dinding efektif h = 3.00 m
Tebal pondasi telapak (poer) D = 0.50 m
Lebar efektif pondasi b = 1.20 m
Lebar pondasi B = 1.80 m
Lebar kaki bagian depan d = 0.30 m
Lebar kaki bagian belakang g4 = 0.30 m
Lebar atas = 0.30 m
Volume / m3 = 3.15 m3
2 GAYA-GAYA DINDING LATERAL
Tanah diatas muka air, pada kondisi kering. = 1.7 ton
Tekanan Air di muka dan belakang dinding sama, jadi saling meniadakan = 3.68 ton
Tekanan pada dinding per meter = 2.614 ton
3 STABILITAS DPT
Kontrol Stabilitas Guling = 2.492 ≥ 1.5 (OK)
Kontrol Stabilitas Geser = 1.925 > 1.5 (OK)
Daya Dukung pondasi Qmax = = 11.71 t/m2
Qmin = = 0.50 t/m2
Tekanan Dasar pondasi SF ijin = 16.55 t/m2
( t1) = 11.71 < q all = 16.55 ton/m2
( t2 ) = 0.50 > 0.00 ton/m2
PERHITUNGAN KUANTITAS GRAVITY WALLL PASANGAN BATU
L1 = 2.25 m2
L2 = 0.9 m2
L Total = 3.15 m2