ERECTION
METHOD
Project : PT. DESI (_____________) (_____________) (_____________)
Alamat : Brengkok, Lamongan

MANUAL LIFTING METHODE PLAN

Structure Erection

A. Introduction

Scope
Applied to all job of installation “Structure Erection”.
Di lampirkan untuk aktifitas pemasangan “Erektion Strukture”.

B. Team/Man Power
1. Erection Team
a. Prepared Toolbox Meeting, safety training course to train team members about safety.
Persiapan Toolbox Meeting, untuk memberikan penjelasan tentang keselamatan kerja
kepada semua anggota tim.
b. Main Responsibillity. Bertanggung jawab atas proses pemasangan
c. Process the Erection work in the line with project schedule, design and approved safety
procedures. Memastikan proses berjalan sesuai jadwal, desain dan peraturan K3
d. Follow strictly all instructions of Erection Superintendents. engikuti petunjuk pasti dari
pengawas
e. Prepare adequately ; qualified labors and certificated, equipments and tools to the Erection
effectively. Memastikan persiapan ; pekerja dalam tim yang berkompeten dan bersertifikat
resmi, Mesin dan alat yang layak agar proses pemasangan dapat berjalan dengan baik dan
aman.
f. Organize and monitor all team members about every aspect. Mengatur dan memantau dari
segala aspek aktifitas pemasangan.

Page 1 of 4
2. Erection Team.
Supervisor : 1 Person
Signal Man : 1 Person
Rigger : 1 Person
Operator : 1+2 Person
Mechanical : 4 Person

3. Material Control
a. Responsible for the storage of Material. Bertanggung jawab atas alat/bagian perlengkapan
dari proses pemasangan.
b. Controls out going material to the Erection process. Memantau dan memastikan pemakaian
alat/bagian perlengkapan saat proses pemasangan.

4. Erection Superintendent/SPV
a. Lead the Toolbox Meeting with Safety Officer before starting the activity. Memimpin dan
mengarahkan Toolbox Meeting sebelum memulai aktifitas.
b. Perform 100% pre-check and pre-inspection. Berperan sepenuhnya dalam persiapan dan
pemeriksaan untuk kebutuhan dalam aktifitas.
c. Main Responsibilities. Bertanggung jawab dalam proses pekerjaan.
d. Monitoring the Erection team to make sure the Erection activity was processed in line with
project schedule, design and approved safety procedures. Memantau proses tim
pemasangan untuk memastikan proses tersebut berjalan sesuai jadwal, desain dan
peraturan K3.
e. Check to carry out site with the Erection team to make sure all of steps and prepared were
done adequately. Memeriksa secara langsung bersama tim pemasangan untuk
memastikan semua tahapan dan persiapan berjalan memenuhi kebutuhan dengan baik.
f. Prepare site Daily Report for his scope of work. Mempersiapkan Laporan harian untuk
aktifitas pemasangan tersebut.

5. HSE.
a. Main Responsibilities. Bertanggung jawab dalam menjalankan peraturan K3.
b. Liaise with client HSE to make sure the Erection procedures is comply with client HSE
system. Bekerja sama dengan HSE Klien untuk memastikan proses pemasangan sesuai
dengan peraturan yang di tetapkan HSE klien .
c. Organized site safety system. Mengatur sistem K3 di lokasi kerja.

Page 2 of 4
d. Prepare safety training to all workers on site, also risk assessment. Memberikan
pengarahan,pemahaman dan penjelasan tentang keselamatan di area kerja, serta resiko
pekerjaan.
e. Analyze all safety information ; records to raise and recognize new risk and hazard may
occur during the Erection process. Analisa semua informasi ; laporkan dan cari bahaya baru
yang dapat timbul selama proses pemasangan berlangsung.

B. Safety Procedure
1. Personal Protective Equipment (PPE) Alat Pelindung Diri (APD)
Man power on job site must be wearing with minimum PPE as below. Pekerja di area kerja wajib
menggunakan APD seperti:
a. Safety Helmet (Pelindung Kepala)
b. Safety Shoes (Sepatu Keselamatan)
c. Long-sleeved clothes and pants that are worth to weared (Baju lengan panjang dan celana
panjang yang layak di kenakan.)
d. Masker
2. Job Specific PPE
APD untuk aktifitas tertentu
a. Full Body Harness with Double Hook ; for all working at heights and must be attached to
static line all the time. Full Body Harness dengan 2 pengait : untuk pekerja yang bekerja di
ketinggian dan wajib mencantolkan hook safety harnesnya setiap saat.
b. Safety Gloves ; when worker handling steel material Sarung tangan keselamatan : di gunakan
untuk aktifitas yang bersentuhan dengan material besi(tajam dan berat).
c. Additional requirement ; Life line should be used to ensure safe anchor point for safety
harnesses, Scaffolding and working plateform. Kebutuhan Tambahan : Life line harus
terikat/di pasang pada titik tumpu yang kuat untuk mengaitkan safety harness.
d. Safety Glasses ; when cutting and grinding must be use safety glasses. Kacamata
keselamatan di gunakan pada saat mengerinda dan pemotongan benda kerja.
e. Welding mask; use when worker weld workpieces, to avoid uv ligt and spark from welding.
Topeng las; digunakan pada saat ada pengelasan pada benda kerja
3. All Erector worker must attend induction training prior to commencing work at site.Semua
Anggota tim pemasangan wajib di orientasi/Induksi
4. Toolbox Meeting must be held; Purpose of the Toolbox Meeting is to communicate the activity
to be done during that shift, The hazard involved and the control measures in place to manage
the risk. Wajib adanya Toolbox Meeting sebelum memulai aktifitas. Toolbox Meeting

Page 3 of 4
bertujuan menyampaikan aktifitas yang harus di lakukan ,berikut potensi bahaya yang timbul
dan pengendaliannya di area kerja.
5. The Order special Requirement such as safety glass, earmuffler,etc will follow with site
requirement. Kebutuhan khusus seperti; kacamata keselamatan, pelindung telinga di sesuai
dengan kebutuhan di area kerja.
6. Erection team are not allowed go up and down by columns or other structurs, ladder or
scaffolding must be used for this purpose. Tim pemasangan tidak di ijinkan naik dan turun
melalui struktur bangunan(Kolom atau struktur lainnya yang tidak layak di gunakan sebagai
akses naik dan turun), harus melalui tangga atapun perancah yang di sediakan.
7. Life line shall be installed on the rail girder and walkway/working plateform also. Lifeline harus
terpasang di area Rail Girder dan berikut papan alas untuk bekerja.
8. Safe access must be provided to the rail girder at all time. The most commont method for rail
girder acces is by using scaffolding spesifically installed for this purpose. Akses yang aman
harus terpasang untuk naik ke atas rail girder, cara yang layak biasanya menggunakan
perancah secara khusus di gunakan untuk tujuan tersebut.
9. Free zone of other activity before the Erection process start and barricaded area crane
operation. Netralisir area dari aktifitas lainnya sebelum proses pemasangan di mulai dan
pasang barikade serta rambu di area operasi kran
10. Area and Tools Inspection must be reported before the Erection process. Pemeriksaan lokasi
dan peralatan yang di laporkan sebelum proses pemasangan di mulai.

MATERIAL DATA

 Rafter : 320 Kg
 ACCESSORIES : 20 Kg
(BOLT)
 ALAT BANTU ANGKAT : 70+30Kg
(Webbing/Wire sling, Hook Block crane, Shackle, Chain/Lever Block)
 TOTAL LOAD : 440 Kg
 SAFETY FACTOR : 440x1.5=660 Kg

KEKUATAN BEBAN MAKS PERANCAH

 BEBAN MAKS PER SET : 675 Kg


 2 SET SCAFFOLDING : 2 x 675 Kg =1350 Kg

Beban yang mampu di angkat oleh scaffolding adalah 1350 kg, sedangkan beban rafter
maks adalah 660 kg jadi pengangkatan menggunakan scaffolding aman.
 Gambar Mapping scaffolding ada di baliknya.
Page 4 of 4
APPROVED BY : OWNER: PROJECT NAME:
THE EAST JAVA WASTE TREATMENT U
CONST RUC
T

Y
PT. TOKYU CONSTRUCTION INDONESIA

TOK

IO
N
SHOP DRAWING FACILITY CONSTRUCTION PROJECT
CLASSIFICATION OF WORKS:
PREPARED : Asrull
STEEL STRUCTURE WORK
CHECKED : Ridwan / Ardho
DRAWING TITLE:

WORK METODE MANUAL ERECTION SUBMITTED : Deny M. Ramdan


( .................................... ) ( .................................... ) NO DESCRIPTION BY APPR. DATE OFFICE & LABORATORY DRAWING NO. : MD/OL/TEI-TCI/05/09/01A Date : 18-09-2021
APPROVED BY : OWNER: PROJECT NAME:
THE EAST JAVA WASTE TREATMENT U
CONST RUC
T

Y
PT. TOKYU CONSTRUCTION INDONESIA

TOK

IO
N
SHOP DRAWING FACILITY CONSTRUCTION PROJECT
CLASSIFICATION OF WORKS:
PREPARED : Asrull
STEEL STRUCTURE WORK
CHECKED : Ridwan / Ardho
DRAWING TITLE:

WORK METODE MANUAL ERECTION SUBMITTED : Deny M. Ramdan


( .................................... ) ( .................................... ) NO DESCRIPTION BY APPR. DATE OFFICE & LABORATORY DRAWING NO. : MD/OL/TEI-TCI/03/09/1A Date : 18-09-2021