RENCANA ANGGARAN BIAYA

Jenis Pekerjaan : Pembangunan STIKES


Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

A PEKERJAAN LANTAI DASAR 51,296,782,550.00

B PEKERJAAN LANTAI DUA 26,293,845,800.00

C PEKERJAAN LANTAI TIGA 25,433,895,800.00

D PEKERJAAN LANTAI EMPAT 25,269,015,800.00

E PEKERJAAN LANTAI LIMA 25,269,015,800.00

F PEKERJAAN LANTAI ENAM 25,216,804,550.00

G PEKERJAAN ATAP 7,292,759,000.00

Jumlah 186,072,119,300.00
PPN 10% 18,607,211,930.00
Total 204,679,331,230.00
Dibulatkan 204,679,300,000.00

.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

A PEKERJAAN LANTAI DASAR

I PEKERJAAN PERSIAPAN

- Pembersihan lokasi 5,412.00 m2 75,000.00 405,900,000.00


- Perataan tanah 5,412.00 m2 15,000.00 81,180,000.00
- Pengukuran dan pemasangan bouwplank 1,305.00 m1 145,000.00 189,225,000.00
- Direksi keet 24.00 m2 1,250,000.00 30,000,000.00
- Tempat tinggal pekerja & MCK 32.00 m2 2,250,000.00 72,000,000.00
- Pembuatan gudang matrial 18.00 m2 850,000.00 15,300,000.00
- Pembuatan bak lumpur Boor Pile 1.00 ls 15,000,000.00 15,000,000.00

Jumlah 808,605,000.00

II PEKERJAAN GALIAN, PONDASI DAN URUGAN

- Pondasi bore pile Ø30cm, t=18m 1,360.80 m3 8,500,000.00 11,566,800,000.00


- Bobok kepalaan bore pile 306.00 ttk 275,000.00 84,150,000.00
- Pondasi Foot Plat, type FP.1
- Galian tanah 2,187.00 m3 350,000.00 765,450,000.00
- Pasir urug, t=10 cm 145.80 m3 365,000.00 53,217,000.00
- Lantai kerja, t=5cm 72.90 m3 950,000.00 69,255,000.00
- Cor foot plat 670.50 m3 7,250,000.00 4,861,125,000.00
- Urugan tanah kembali 1,297.80 m3 225,000.00 292,005,000.00
- Pondasi Foot Plat, type FP.2
- Galian tanah 70.56 m3 350,000.00 24,696,000.00
- Pasir urug, t=10 cm 4.70 m3 365,000.00 1,716,960.00
- Lantai kerja, t=5cm 2.35 m3 950,000.00 2,234,400.00
- Cor foot plat 19.58 m3 7,250,000.00 141,984,000.00
- Urugan tanah kembali 43.92 m3 225,000.00 9,882,000.00
- Pondasi Foot Plat, type FP.3
- Galian tanah 14.40 m3 350,000.00 5,040,000.00
- Pasir urug, t=10 cm 0.96 m3 365,000.00 350,400.00
- Lantai kerja, t=5cm 0.48 m3 950,000.00 456,000.00
- Cor foot plat 3.96 m3 7,250,000.00 28,710,000.00
- Urugan tanah kembali 9.00 m3 225,000.00 2,025,000.00

Jumlah 17,909,096,760.00

III PEKERJAAN BETON

a Sloof Beton
- Sloof, type SL.1
- Pasir urug, t=5cm 22.08 m3 365,000.00 8,060,295.00
- Lantai kerja, t=5cm 22.08 m3 950,000.00 20,978,850.00
- Cor sloof 265.00 m3 7,850,000.00 2,080,218,600.00
- Sloof, type SL.2
- Pasir urug, t=5cm 26.26 m3 365,000.00 9,585,995.00
- Lantai kerja, t=5cm 26.26 m3 950,000.00 24,949,850.00
- Cor sloof 210.10 m3 7,850,000.00 1,649,316,400.00
b Kolom Beton
- Kolom beton type KL.1 223.20 m3 8,500,000.00 1,897,200,000.00
- Kolom beton type KL.2 63.00 m3 8,250,000.00 519,750,000.00
- Kolom beton type KL.3 6.00 m3 7,850,000.00 47,100,000.00
- Kolom beton type KL.4 14.40 m3 7,500,000.00 108,000,000.00
- Kolom beton type KP 7.43 m3 6,500,000.00 48,262,500.00
c Balok Beton
- Balok, type BL.1 655.38 m3 8,750,000.00 5,734,531,250.00
- Balok, type BL.2 77.15 m3 8,250,000.00 636,487,500.00
- Balok, type BL.3 55.76 m3 7,850,000.00 437,716,000.00
- Balok, type BL.4 0.95 m3 7,500,000.00 7,087,500.00
d Plat Lantai Beton
- Floor deck, 0,75mm 4,161.00 m2 225,000.00 936,225,000.00
- Wiremesh MØ8, 150x150 ( 2 lapis ) 4,161.00 m2 290,000.00 1,206,690,000.00
- Cor beton lantai, t=15cm 624.15 m3 1,525,000.00 951,828,750.00
e Tangga Beton
- Cor beton tangga 79.20 m3 5,500,000.00 435,600,000.00

Jumlah 16,759,588,490.00

IV PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 2,971.08 m2 185,000.00 549,649,800.00


- Plesteran dinding 5,942.16 m2 85,000.00 505,083,600.00
- Acian dinding 5,942.16 m2 45,000.00 267,397,200.00

Jumlah 1,322,130,600.00

V PEKERJAAN PLAFOND

- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 6,072.00 m2 185,000.00 1,123,320,000.00

Jumlah 1,123,320,000.00

VI PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.1 (kelas) 26.00 unit 7,495,000.00 194,870,000.00


- Kusen pintu, type PT.2 (janitor) 4.00 unit 1,250,000.00 5,000,000.00
- Kusen pintu, type PT.3 (shaft) 8.00 unit 750,000.00 6,000,000.00
- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00
- Kusen pintu PVC (toilet) 32.00 unit 950,000.00 30,400,000.00
- Kusen jendela, type JD.1 (kelas) 72.00 unit 9,160,000.00 659,520,000.00
- Kusen jendela, type JD.2 (kelas) 24.00 unit 474,000.00 11,376,000.00
- Kusen jendela, type JD.3 (tangga) 6.00 unit 13,350,000.00 80,100,000.00
- Kusen jendela, type JD.4 (koridor & r.duduk) 8.00 unit 4,980,000.00 39,840,000.00
- Kusen bovenlight, type BV.1 (toilet) 8.00 unit 4,700,000.00 37,600,000.00

Jumlah 1,075,706,000.00

VII PEKERJAAN PELAPIS LANTAI DAN DINDING

a Lantai
- Lantai R.kelas, granit tile 60x60 3,639.00 m2 450,000.00 1,637,550,000.00
- Lantai Teras, granit tile 60x60 1,336.00 m2 450,000.00 601,200,000.00
- Lantai toilet, keramik 40x40 270.00 m2 300,000.00 81,000,000.00
- Lantai tangga, granit tile 60x60 308.58 m2 450,000.00 138,861,000.00

b Dinding
- Dinding lift, granit tile 60x60 64.80 m2 540,000.00 34,992,000.00
- Dinding toilet, keramik 25x40 156.60 m2 225,000.00 35,235,000.00
- Plint dinding, granit tile 10x60 1,172.00 m1 75,000.00 87,900,000.00

Jumlah 2,616,738,000.00

VIII PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 559.00 ttk 250,000.00 139,750,000.00


- Instalasi titik stop kontak 12.00 ttk 250,000.00 3,000,000.00
- Instalasi titik saklar 62.00 ttk 250,000.00 15,500,000.00
- Instalasi AC 120.00 ttk 475,000.00 57,000,000.00
- Lampu downlight 203.00 bh 215,000.00 43,645,000.00
- Lampu TL inbow 2x40 watt 350.00 bh 550,000.00 192,500,000.00
Lampu baret outbow 6.00 bh 750,000.00 4,500,000.00
- Stop kontak 12.00 bh 75,000.00 900,000.00
- Saklar Tunggal 10.00 bh 75,000.00 750,000.00
- Saklar ganda 52.00 bh 85,000.00 4,420,000.00
- Panel box 4.00 bh 5,000,000.00 20,000,000.00
- MCB 76.00 bh 450,000.00 34,200,000.00
- AC split wall 120.00 unit 5,000,000.00 600,000,000.00
- Lift, kap 12 org 8.00 unit 875,000,000.00 7,000,000,000.00

Jumlah 8,116,165,000.00

IX PEKERJAAN INSTALASI DAN SANITAIR

- Instalasi air bersih 668.80 m1 35,000.00 23,408,000.00


- Instalasi air kotor 88.80 m1 125,000.00 11,100,000.00
- Instalasi air buangan 144.00 m1 125,000.00 18,000,000.00
- Instalasi air hujan 380.00 m1 47,000.00 17,860,000.00
- Closet duduk 32.00 bh 1,250,000.00 40,000,000.00
- Urinoir 16.00 bh 2,550,000.00 40,800,000.00
- Washtafel 24.00 bh 1,850,000.00 44,400,000.00
- Jet washer 32.00 bh 275,000.00 8,800,000.00
- Kran tangan 36.00 bh 275,000.00 9,900,000.00
- Cermin 24.00 m2 225,000.00 5,400,000.00
- Floor drain 36.00 bh 225,000.00 8,100,000.00
- Septictank & resapan ukr, 1,50mx2,00mx3,00m 4.00 bh 15,000,000.00 60,000,000.00

Jumlah 287,768,000.00

X PEKERJAAN RAILLING

- Railing tangga stainlessteel 40x40 & 40x60 225.60 m1 1,150,000.00 259,440,000.00

Jumlah 259,440,000.00

XI PEKERJAAN GRC

- Listplank GRC 298.60 m1 850,000.00 253,810,000.00

Jumlah 253,810,000.00

XII PEKERJAAN PENGECATAN

- Cat dinding 5,942.16 m2 45,000.00 267,397,200.00


- Cat plafond 6,072.00 m2 47,000.00 285,384,000.00
- Cat listplank GRC 298.60 m1 55,000.00 16,423,000.00

Jumlah 569,204,200.00

XIII PEKERJAAN DROP OFF

- Sloof, type SL.2


- Pasir urug, t=5cm 0.26 m3 365,000.00 94,900.00
- Lantai kerja, t=5cm 0.26 m3 950,000.00 247,000.00
- Cor sloof 2.08 m3 7,850,000.00 16,328,000.00
- Kolom beton type KL.2 7.20 m3 7,250,000.00 52,200,000.00
- Balok, type BL.2 5.50 m3 6,800,000.00 37,400,000.00
- Pas. dinding hebel 10cm 26.88 m2 185,000.00 4,972,800.00
- Plesteran dinding 53.76 m2 85,000.00 4,569,600.00
- Acian dinding 53.76 m2 45,000.00 2,419,200.00
- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 92.70 m2 185,000.00 17,149,500.00
- Instalasi titik lampu 5.00 ttk 425,000.00 2,125,000.00
- Lampu downlight 5.00 bh 215,000.00 1,075,000.00
- Listplank GRC 25.80 m1 850,000.00 21,930,000.00
- Cat dinding 53.76 m2 45,000.00 2,419,200.00
- Cat plafond 92.70 m2 47,000.00 4,356,900.00
- Cat listplank GRC 25.80 m1 55,000.00 1,419,000.00
- Rangka atap baja ringan 52.66 m2 175,000.00 9,215,500.00
- Atap genteng metalroof 52.66 m2 165,000.00 8,688,900.00
- Genteng nok metalroof 20.80 m1 125,000.00 2,600,000.00

Jumlah 189,210,500.00

XIV PEKERJAAN LAIN-LAIN


- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00
- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

A PEKERJAAN LANTAI DASAR

I PEKERJAAN PERSIAPAN 808,605,000.00

II PEKERJAAN GALIAN, PONDASI DAN URUGAN 17,909,096,760.00

III PEKERJAAN BETON 16,759,588,490.00

IV PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 1,322,130,600.00

V PEKERJAAN PLAFOND 1,123,320,000.00

VI PEKERJAAN KUSEN, PINTU DAN JENDELA 1,075,706,000.00

VII PEKERJAAN PELAPIS LANTAI DAN DINDING 2,616,738,000.00

VIII PEKERJAAN ELEKTRIKAL 8,116,165,000.00

IX PEKERJAAN INSTALASI DAN SANITAIR 287,768,000.00

X PEKERJAAN RAILLING 259,440,000.00

XI PEKERJAAN GRC 253,810,000.00

XII PEKERJAAN PENGECATAN 569,204,200.00

XIII PEKERJAAN DROP OFF 189,210,500.00

XIV PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 51,296,782,550.00

.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

B PEKERJAAN LANTAI DUA

I PEKERJAAN BETON

a Kolom Beton
- Kolom beton type KL.1 223.20 m3 8,250,000.00 1,841,400,000.00
- Kolom beton type KL.2 63.00 m3 8,000,000.00 504,000,000.00
- Kolom beton type KL.3 6.00 m3 7,600,000.00 45,600,000.00
- Kolom beton type KL.4 14.40 m3 7,250,000.00 104,400,000.00
- Kolom beton type KP 7.43 m3 6,250,000.00 46,406,250.00
b Balok Beton
- Balok, type BL.1 655.38 m3 8,500,000.00 5,570,687,500.00
- Balok, type BL.2 77.15 m3 8,000,000.00 617,200,000.00
- Balok, type BL.3 55.76 m3 7,650,000.00 426,564,000.00
- Balok, type BL.4 0.95 m3 7,250,000.00 6,851,250.00
c Plat Lantai Beton
- Floor deck, 0,75mm 6,072.00 m2 225,000.00 1,366,200,000.00
- Wiremesh MØ8, 150x150 ( 2 lapis ) 6,072.00 m2 290,000.00 1,760,880,000.00
- Cor beton lantai, t=15cm 910.80 m3 1,525,000.00 1,388,970,000.00
d Tangga Beton
- Cor beton tangga 79.20 m3 5,500,000.00 435,600,000.00

Jumlah 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 5,806.08 m2 185,000.00 1,074,124,800.00


- Plesteran dinding 11,612.16 m2 85,000.00 987,033,600.00
- Acian dinding 11,612.16 m2 45,000.00 522,547,200.00
- Dinding Partisi Exposed Kaca 8mm 2,835.00 m3 450,000.00 1,275,750,000.00

Jumlah 3,859,455,600.00

III PEKERJAAN PLAFOND

- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 6,072.00 m2 185,000.00 1,123,320,000.00

Jumlah 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.1 (kelas) 36.00 unit 7,495,000.00 269,820,000.00


- Kusen pintu, type PT.2 (janitor) 4.00 unit 1,250,000.00 5,000,000.00
- Kusen pintu, type PT.3 (shaft) 8.00 unit 750,000.00 6,000,000.00
- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00
- Kusen pintu PVC (toilet) 32.00 unit 950,000.00 30,400,000.00
- Kusen jendela, type JD.1 (kelas) 90.00 unit 9,160,000.00 824,400,000.00
- Kusen jendela, type JD.2 (kelas) 24.00 unit 474,000.00 11,376,000.00
- Kusen jendela, type JD.3 (tangga) 6.00 unit 13,350,000.00 80,100,000.00
- Kusen jendela, type JD.4 (koridor & r.duduk) 8.00 unit 4,980,000.00 39,840,000.00
- Kusen bovenlight, type BV.1 (toilet) 8.00 unit 4,700,000.00 37,600,000.00

Jumlah 1,315,536,000.00
V PEKERJAAN PELAPIS LANTAI DAN DINDING

a Lantai
- Lantai R.kelas, granit tile 60x60 3,639.00 m2 450,000.00 1,637,550,000.00
- Lantai Teras, granit tile 60x60 1,336.00 m2 450,000.00 601,200,000.00
- Lantai toilet, keramik 40x40 270.00 m2 300,000.00 81,000,000.00
- Lantai tangga, granit tile 60x60 308.58 m2 450,000.00 138,861,000.00

b Dinding
- Dinding lift, granit tile 60x60 64.80 m2 540,000.00 34,992,000.00
- Dinding toilet, keramik 25x40 156.60 m2 225,000.00 35,235,000.00
- Plint dinding, granit tile 10x60 1,172.00 m1 75,000.00 87,900,000.00

Jumlah 2,616,738,000.00

VI PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 559.00 ttk 250,000.00 139,750,000.00


- Instalasi titik stop kontak 12.00 ttk 250,000.00 3,000,000.00
- Instalasi titik saklar 62.00 ttk 250,000.00 15,500,000.00
- Instalasi AC 184.00 ttk 475,000.00 87,400,000.00
- Lampu downlight 203.00 bh 215,000.00 43,645,000.00
- Lampu TL inbow 2x40 watt 350.00 bh 550,000.00 192,500,000.00
Lampu baret outbow 6.00 bh 750,000.00 4,500,000.00
- Stop kontak 12.00 bh 75,000.00 900,000.00
- Saklar Tunggal 10.00 bh 75,000.00 750,000.00
- Saklar ganda 52.00 bh 85,000.00 4,420,000.00
- Panel box 4.00 bh 5,000,000.00 20,000,000.00
- MCB 76.00 bh 450,000.00 34,200,000.00
- AC split wall 184.00 unit 5,000,000.00 920,000,000.00

Jumlah 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR

- Instalasi air bersih 668.80 m1 35,000.00 23,408,000.00


- Instalasi air kotor 88.80 m1 125,000.00 11,100,000.00
- Instalasi air buangan 144.00 m1 125,000.00 18,000,000.00
- Instalasi air hujan 380.00 m1 47,000.00 17,860,000.00
- Closet duduk 32.00 bh 1,250,000.00 40,000,000.00
- Urinoir 16.00 bh 2,550,000.00 40,800,000.00
- Washtafel 24.00 bh 1,850,000.00 44,400,000.00
- Jet washer 32.00 bh 275,000.00 8,800,000.00
- Kran tangan 36.00 bh 275,000.00 9,900,000.00
- Cermin 24.00 m2 225,000.00 5,400,000.00
- Floor drain 36.00 bh 225,000.00 8,100,000.00

Jumlah 227,768,000.00

VIII PEKERJAAN RAILLING

- Railing tangga stainlessteel 40x40 & 40x60 225.60 m1 1,150,000.00 259,440,000.00


- Railing selasar & koridor, stainlessteel 40x40 & 40x60 266.00 m1 850,000.00 226,100,000.00

Jumlah 485,540,000.00

IX PEKERJAAN GRC

- Listplank GRC 298.60 m1 850,000.00 253,810,000.00

Jumlah 253,810,000.00

X PEKERJAAN PENGECATAN

- Cat dinding 11,612.16 m2 45,000.00 522,547,200.00


- Cat plafond 6,072.00 m2 47,000.00 285,384,000.00
- Cat listplank GRC 298.60 m1 55,000.00 16,423,000.00

Jumlah 824,354,200.00

XI PEKERJAAN LAIN-LAIN

- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00


- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

B PEKERJAAN LANTAI DUA

I PEKERJAAN BETON 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 3,859,455,600.00

III PEKERJAAN PLAFOND 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA 1,315,536,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING 2,616,738,000.00

VI PEKERJAAN ELEKTRIKAL 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR 227,768,000.00

VIII PEKERJAAN RAILLING 485,540,000.00

IX PEKERJAAN GRC 253,810,000.00

X PEKERJAAN PENGECATAN 824,354,200.00

XI PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 26,293,845,800.00

.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

C PEKERJAAN LANTAI TIGA

I PEKERJAAN BETON

a Kolom Beton
- Kolom beton type KL.1 223.20 m3 8,250,000.00 1,841,400,000.00
- Kolom beton type KL.2 63.00 m3 8,000,000.00 504,000,000.00
- Kolom beton type KL.3 6.00 m3 7,600,000.00 45,600,000.00
- Kolom beton type KL.4 14.40 m3 7,250,000.00 104,400,000.00
- Kolom beton type KP 7.43 m3 6,250,000.00 46,406,250.00
b Balok Beton
- Balok, type BL.1 655.38 m3 8,500,000.00 5,570,687,500.00
- Balok, type BL.2 77.15 m3 8,000,000.00 617,200,000.00
- Balok, type BL.3 55.76 m3 7,650,000.00 426,564,000.00
- Balok, type BL.4 0.95 m3 7,250,000.00 6,851,250.00
c Plat Lantai Beton
- Floor deck, 0,75mm 6,072.00 m2 225,000.00 1,366,200,000.00
- Wiremesh MØ8, 150x150 ( 2 lapis ) 6,072.00 m2 290,000.00 1,760,880,000.00
- Cor beton lantai, t=15cm 910.80 m3 1,525,000.00 1,388,970,000.00
d Tangga Beton
- Cor beton tangga 79.20 m3 5,500,000.00 435,600,000.00

Jumlah 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 5,806.08 m2 185,000.00 1,074,124,800.00


- Plesteran dinding 11,612.16 m2 85,000.00 987,033,600.00
- Acian dinding 11,612.16 m2 45,000.00 522,547,200.00
- Dinding Partisi Exposed Kaca 8mm 2,835.00 m3 450,000.00 1,275,750,000.00

Jumlah 3,859,455,600.00

III PEKERJAAN PLAFOND

- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 6,072.00 m2 185,000.00 1,123,320,000.00

Jumlah 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.1 (kelas) 36.00 unit 7,495,000.00 269,820,000.00


- Kusen pintu, type PT.2 (janitor) 4.00 unit 1,250,000.00 5,000,000.00
- Kusen pintu, type PT.3 (shaft) 8.00 unit 750,000.00 6,000,000.00
- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00
- Kusen pintu PVC (toilet) 32.00 unit 950,000.00 30,400,000.00
- Kusen jendela, type JD.1 (kelas) 90.00 unit 9,160,000.00 824,400,000.00
- Kusen jendela, type JD.2 (kelas) 24.00 unit 474,000.00 11,376,000.00
- Kusen jendela, type JD.3 (tangga) 6.00 unit 13,350,000.00 80,100,000.00
- Kusen jendela, type JD.4 (koridor & r.duduk) 8.00 unit 4,980,000.00 39,840,000.00
- Kusen bovenlight, type BV.1 (toilet) 8.00 unit 4,700,000.00 37,600,000.00

Jumlah 1,315,536,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING

a Lantai
- Lantai R.kelas, granit tile 60x60 1,728.00 m2 450,000.00 777,600,000.00
- Lantai Teras, granit tile 60x60 1,336.00 m2 450,000.00 601,200,000.00
- Lantai toilet, keramik 40x40 270.00 m2 300,000.00 81,000,000.00
- Lantai tangga, granit tile 60x60 308.58 m2 450,000.00 138,861,000.00

b Dinding
- Dinding lift, granit tile 60x60 64.80 m2 540,000.00 34,992,000.00
- Dinding toilet, keramik 25x40 156.60 m2 225,000.00 35,235,000.00
- Plint dinding, granit tile 10x60 1,172.00 m1 75,000.00 87,900,000.00

Jumlah 1,756,788,000.00

VI PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 559.00 ttk 250,000.00 139,750,000.00


- Instalasi titik stop kontak 12.00 ttk 250,000.00 3,000,000.00
- Instalasi titik saklar 62.00 ttk 250,000.00 15,500,000.00
- Instalasi AC 184.00 ttk 475,000.00 87,400,000.00
- Lampu downlight 203.00 bh 215,000.00 43,645,000.00
- Lampu TL inbow 2x40 watt 350.00 bh 550,000.00 192,500,000.00
Lampu baret outbow 6.00 bh 750,000.00 4,500,000.00
- Stop kontak 12.00 bh 75,000.00 900,000.00
- Saklar Tunggal 10.00 bh 75,000.00 750,000.00
- Saklar ganda 52.00 bh 85,000.00 4,420,000.00
- Panel box 4.00 bh 5,000,000.00 20,000,000.00
- MCB 76.00 bh 450,000.00 34,200,000.00
- AC split wall 184.00 unit 5,000,000.00 920,000,000.00

Jumlah 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR

- Instalasi air bersih 668.80 m1 35,000.00 23,408,000.00


- Instalasi air kotor 88.80 m1 125,000.00 11,100,000.00
- Instalasi air buangan 144.00 m1 125,000.00 18,000,000.00
- Instalasi air hujan 380.00 m1 47,000.00 17,860,000.00
- Closet duduk 32.00 bh 1,250,000.00 40,000,000.00
- Urinoir 16.00 bh 2,550,000.00 40,800,000.00
- Washtafel 24.00 bh 1,850,000.00 44,400,000.00
- Jet washer 32.00 bh 275,000.00 8,800,000.00
- Kran tangan 36.00 bh 275,000.00 9,900,000.00
- Cermin 24.00 m2 225,000.00 5,400,000.00
- Floor drain 36.00 bh 225,000.00 8,100,000.00
Jumlah 227,768,000.00
VIII PEKERJAAN RAILLING

- Railing tangga stainlessteel 40x40 & 40x60 225.60 m1 1,150,000.00 259,440,000.00


- Railing selasar & koridor, stainlessteel 40x40 & 40x60 266.00 m1 850,000.00 226,100,000.00
Jumlah 485,540,000.00
IX PEKERJAAN GRC

- Listplank GRC 298.60 m1 850,000.00 253,810,000.00

Jumlah 253,810,000.00
X PEKERJAAN PENGECATAN

- Cat dinding 11,612.16 m2 45,000.00 522,547,200.00


- Cat plafond 6,072.00 m2 47,000.00 285,384,000.00
- Cat listplank GRC 298.60 m1 55,000.00 16,423,000.00

Jumlah 824,354,200.00
XI PEKERJAAN LAIN-LAIN

- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00


- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

C PEKERJAAN LANTAI TIGA

I PEKERJAAN BETON 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 3,859,455,600.00

III PEKERJAAN PLAFOND 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA 1,315,536,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING 1,756,788,000.00

VI PEKERJAAN ELEKTRIKAL 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR 227,768,000.00

VIII PEKERJAAN RAILLING 485,540,000.00

IX PEKERJAAN GRC 253,810,000.00

X PEKERJAAN PENGECATAN 824,354,200.00

XI PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 25,433,895,800.00
.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

D PEKERJAAN LANTAI EMPAT

I PEKERJAAN BETON

a Kolom Beton
- Kolom beton type KL.1 223.20 m3 8,250,000.00 1,841,400,000.00
- Kolom beton type KL.2 63.00 m3 8,000,000.00 504,000,000.00
- Kolom beton type KL.3 6.00 m3 7,600,000.00 45,600,000.00
- Kolom beton type KL.4 14.40 m3 7,250,000.00 104,400,000.00
- Kolom beton type KP 7.43 m3 6,250,000.00 46,406,250.00
b Balok Beton
- Balok, type BL.1 655.38 m3 8,500,000.00 5,570,687,500.00
- Balok, type BL.2 77.15 m3 8,000,000.00 617,200,000.00
- Balok, type BL.3 55.76 m3 7,650,000.00 426,564,000.00
- Balok, type BL.4 0.95 m3 7,250,000.00 6,851,250.00
c Plat Lantai Beton
- Floor deck, 0,75mm 6,072.00 m2 225,000.00 1,366,200,000.00
- Wiremesh MØ8, 150x150 ( 2 lapis ) 6,072.00 m2 290,000.00 1,760,880,000.00
- Cor beton lantai, t=15cm 910.80 m3 1,525,000.00 1,388,970,000.00
d Tangga Beton
- Cor beton tangga 79.20 m3 5,500,000.00 435,600,000.00

Jumlah 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 5,806.08 m2 185,000.00 1,074,124,800.00


- Plesteran dinding 11,612.16 m2 85,000.00 987,033,600.00
- Acian dinding 11,612.16 m2 45,000.00 522,547,200.00
- Dinding Partisi Exposed Kaca 8mm 2,835.00 m3 450,000.00 1,275,750,000.00

Jumlah 3,859,455,600.00

III PEKERJAAN PLAFOND

- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 6,072.00 m2 185,000.00 1,123,320,000.00

Jumlah 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.1 (kelas) 36.00 unit 7,495,000.00 269,820,000.00


- Kusen pintu, type PT.2 (janitor) 4.00 unit 1,250,000.00 5,000,000.00
- Kusen pintu, type PT.3 (shaft) 8.00 unit 750,000.00 6,000,000.00
- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00
- Kusen pintu PVC (toilet) 32.00 unit 950,000.00 30,400,000.00
- Kusen jendela, type JD.1 (kelas) 72.00 unit 9,160,000.00 659,520,000.00
- Kusen jendela, type JD.2 (kelas) 24.00 unit 474,000.00 11,376,000.00
- Kusen jendela, type JD.3 (tangga) 6.00 unit 13,350,000.00 80,100,000.00
- Kusen jendela, type JD.4 (koridor & r.duduk) 8.00 unit 4,980,000.00 39,840,000.00
- Kusen bovenlight, type BV.1 (toilet) 8.00 unit 4,700,000.00 37,600,000.00
Jumlah 1,150,656,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING

a Lantai
- Lantai R.kelas, granit tile 60x60 1,728.00 m2 450,000.00 777,600,000.00
- Lantai Teras, granit tile 60x60 1,336.00 m2 450,000.00 601,200,000.00
- Lantai toilet, keramik 40x40 270.00 m2 300,000.00 81,000,000.00
- Lantai tangga, granit tile 60x60 308.58 m2 450,000.00 138,861,000.00

b Dinding
- Dinding lift, granit tile 60x60 64.80 m2 540,000.00 34,992,000.00
- Dinding toilet, keramik 25x40 156.60 m2 225,000.00 35,235,000.00
- Plint dinding, granit tile 10x60 1,172.00 m1 75,000.00 87,900,000.00

Jumlah 1,756,788,000.00

VI PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 559.00 ttk 250,000.00 139,750,000.00


- Instalasi titik stop kontak 12.00 ttk 250,000.00 3,000,000.00
- Instalasi titik saklar 62.00 ttk 250,000.00 15,500,000.00
- Instalasi AC 184.00 ttk 475,000.00 87,400,000.00
- Lampu downlight 203.00 bh 215,000.00 43,645,000.00
- Lampu TL inbow 2x40 watt 350.00 bh 550,000.00 192,500,000.00
Lampu baret outbow 6.00 bh 750,000.00 4,500,000.00
- Stop kontak 12.00 bh 75,000.00 900,000.00
- Saklar Tunggal 10.00 bh 75,000.00 750,000.00
- Saklar ganda 52.00 bh 85,000.00 4,420,000.00
- Panel box 4.00 bh 5,000,000.00 20,000,000.00
- MCB 76.00 bh 450,000.00 34,200,000.00
- AC split wall 184.00 unit 5,000,000.00 920,000,000.00

Jumlah 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR

- Instalasi air bersih 668.80 m1 35,000.00 23,408,000.00


- Instalasi air kotor 88.80 m1 125,000.00 11,100,000.00
- Instalasi air buangan 144.00 m1 125,000.00 18,000,000.00
- Instalasi air hujan 380.00 m1 47,000.00 17,860,000.00
- Closet duduk 32.00 bh 1,250,000.00 40,000,000.00
- Urinoir 16.00 bh 2,550,000.00 40,800,000.00
- Washtafel 24.00 bh 1,850,000.00 44,400,000.00
- Jet washer 32.00 bh 275,000.00 8,800,000.00
- Kran tangan 36.00 bh 275,000.00 9,900,000.00
- Cermin 24.00 m2 225,000.00 5,400,000.00
- Floor drain 36.00 bh 225,000.00 8,100,000.00

Jumlah 227,768,000.00

VIII PEKERJAAN RAILLING

- Railing tangga stainlessteel 40x40 & 40x60 225.60 m1 1,150,000.00 259,440,000.00


- Railing selasar & koridor, stainlessteel 40x40 & 40x60 266.00 m1 850,000.00 226,100,000.00

Jumlah 485,540,000.00

IX PEKERJAAN GRC

- Listplank GRC 298.60 m1 850,000.00 253,810,000.00


Jumlah 253,810,000.00

X PEKERJAAN PENGECATAN

- Cat dinding 11,612.16 m2 45,000.00 522,547,200.00


- Cat plafond 6,072.00 m2 47,000.00 285,384,000.00
- Cat listplank GRC 298.60 m1 55,000.00 16,423,000.00

Jumlah 824,354,200.00

XI PEKERJAAN LAIN-LAIN

- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00


- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

D PEKERJAAN LANTAI EMPAT

I PEKERJAAN BETON 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 3,859,455,600.00

III PEKERJAAN PLAFOND 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA 1,150,656,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING 1,756,788,000.00

VI PEKERJAAN ELEKTRIKAL 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR 227,768,000.00

VIII PEKERJAAN RAILLING 485,540,000.00

IX PEKERJAAN GRC 253,810,000.00

X PEKERJAAN PENGECATAN 824,354,200.00

XI PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 25,269,015,800.00
.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

E PEKERJAAN LANTAI LIMA

I PEKERJAAN BETON

a Kolom Beton
- Kolom beton type KL.1 223.20 m3 8,250,000.00 1,841,400,000.00
- Kolom beton type KL.2 63.00 m3 8,000,000.00 504,000,000.00
- Kolom beton type KL.3 6.00 m3 7,600,000.00 45,600,000.00
- Kolom beton type KL.4 14.40 m3 7,250,000.00 104,400,000.00
- Kolom beton type KP 7.43 m3 6,250,000.00 46,406,250.00
b Balok Beton
- Balok, type BL.1 655.38 m3 8,500,000.00 5,570,687,500.00
- Balok, type BL.2 77.15 m3 8,000,000.00 617,200,000.00
- Balok, type BL.3 55.76 m3 7,650,000.00 426,564,000.00
- Balok, type BL.4 0.95 m3 7,250,000.00 6,851,250.00
c Plat Lantai Beton
- Floor deck, 0,75mm 6,072.00 m2 225,000.00 1,366,200,000.00
- Wiremesh MØ8, 150x150 ( 2 lapis ) 6,072.00 m2 290,000.00 1,760,880,000.00
- Cor beton lantai, t=15cm 910.80 m3 1,525,000.00 1,388,970,000.00
d Tangga Beton
- Cor beton tangga 79.20 m3 5,500,000.00 435,600,000.00

Jumlah 14,114,759,000.00
II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 5,806.08 m2 185,000.00 1,074,124,800.00


- Plesteran dinding 11,612.16 m2 85,000.00 987,033,600.00
- Acian dinding 11,612.16 m2 45,000.00 522,547,200.00
- Dinding Partisi Exposed Kaca 8mm 2,835.00 m3 450,000.00 1,275,750,000.00

Jumlah 3,859,455,600.00
III PEKERJAAN PLAFOND
- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 6,072.00 m2 185,000.00 1,123,320,000.00

Jumlah 1,123,320,000.00
IV PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.1 (kelas) 36.00 unit 7,495,000.00 269,820,000.00


- Kusen pintu, type PT.2 (janitor) 4.00 unit 1,250,000.00 5,000,000.00
- Kusen pintu, type PT.3 (shaft) 8.00 unit 750,000.00 6,000,000.00
- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00
- Kusen pintu PVC (toilet) 32.00 unit 950,000.00 30,400,000.00
- Kusen jendela, type JD.1 (kelas) 72.00 unit 9,160,000.00 659,520,000.00
- Kusen jendela, type JD.2 (kelas) 24.00 unit 474,000.00 11,376,000.00
- Kusen jendela, type JD.3 (tangga) 6.00 unit 13,350,000.00 80,100,000.00
- Kusen jendela, type JD.4 (koridor & r.duduk) 8.00 unit 4,980,000.00 39,840,000.00
- Kusen bovenlight, type BV.1 (toilet) 8.00 unit 4,700,000.00 37,600,000.00
Jumlah 1,150,656,000.00
V PEKERJAAN PELAPIS LANTAI DAN DINDING

a Lantai
- Lantai R.kelas, granit tile 60x60 1,728.00 m2 450,000.00 777,600,000.00
- Lantai Teras, granit tile 60x60 1,336.00 m2 450,000.00 601,200,000.00
- Lantai toilet, keramik 40x40 270.00 m2 300,000.00 81,000,000.00
- Lantai tangga, granit tile 60x60 308.58 m2 450,000.00 138,861,000.00

b Dinding
- Dinding lift, granit tile 60x60 64.80 m2 540,000.00 34,992,000.00
- Dinding toilet, keramik 25x40 156.60 m2 225,000.00 35,235,000.00
- Plint dinding, granit tile 10x60 1,172.00 m1 75,000.00 87,900,000.00

Jumlah 1,756,788,000.00

VI PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 559.00 ttk 250,000.00 139,750,000.00


- Instalasi titik stop kontak 12.00 ttk 250,000.00 3,000,000.00
- Instalasi titik saklar 62.00 ttk 250,000.00 15,500,000.00
- Instalasi AC 184.00 ttk 475,000.00 87,400,000.00
- Lampu downlight 203.00 bh 215,000.00 43,645,000.00
- Lampu TL inbow 2x40 watt 350.00 bh 550,000.00 192,500,000.00
Lampu baret outbow 6.00 bh 750,000.00 4,500,000.00
- Stop kontak 12.00 bh 75,000.00 900,000.00
- Saklar Tunggal 10.00 bh 75,000.00 750,000.00
- Saklar ganda 52.00 bh 85,000.00 4,420,000.00
- Panel box 4.00 bh 5,000,000.00 20,000,000.00
- MCB 76.00 bh 450,000.00 34,200,000.00
- AC split wall 184.00 unit 5,000,000.00 920,000,000.00

Jumlah 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR

- Instalasi air bersih 668.80 m1 35,000.00 23,408,000.00


- Instalasi air kotor 88.80 m1 125,000.00 11,100,000.00
- Instalasi air buangan 144.00 m1 125,000.00 18,000,000.00
- Instalasi air hujan 380.00 m1 47,000.00 17,860,000.00
- Closet duduk 32.00 bh 1,250,000.00 40,000,000.00
- Urinoir 16.00 bh 2,550,000.00 40,800,000.00
- Washtafel 24.00 bh 1,850,000.00 44,400,000.00
- Jet washer 32.00 bh 275,000.00 8,800,000.00
- Kran tangan 36.00 bh 275,000.00 9,900,000.00
- Cermin 24.00 m2 225,000.00 5,400,000.00
- Floor drain 36.00 bh 225,000.00 8,100,000.00

Jumlah 227,768,000.00

VIII PEKERJAAN RAILLING

- Railing tangga stainlessteel 40x40 & 40x60 225.60 m1 1,150,000.00 259,440,000.00


- Railing selasar & koridor, stainlessteel 40x40 & 40x60 266.00 m1 850,000.00 226,100,000.00

Jumlah 485,540,000.00
IX PEKERJAAN GRC

- Listplank GRC 298.60 m1 850,000.00 253,810,000.00

Jumlah 253,810,000.00

X PEKERJAAN PENGECATAN

- Cat dinding 11,612.16 m2 45,000.00 522,547,200.00


- Cat plafond 6,072.00 m2 47,000.00 285,384,000.00
- Cat listplank GRC 298.60 m1 55,000.00 16,423,000.00

Jumlah 824,354,200.00

XI PEKERJAAN LAIN-LAIN

- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00


- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

E PEKERJAAN LANTAI LIMA


I PEKERJAAN BETON 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 3,859,455,600.00

III PEKERJAAN PLAFOND 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA 1,150,656,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING 1,756,788,000.00

VI PEKERJAAN ELEKTRIKAL 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR 227,768,000.00

VIII PEKERJAAN RAILLING 485,540,000.00

IX PEKERJAAN GRC 253,810,000.00

X PEKERJAAN PENGECATAN 824,354,200.00

XI PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 25,269,015,800.00
.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

F PEKERJAAN LANTAI ENAM

I PEKERJAAN BETON

a Kolom Beton
- Kolom beton type KL.1 223.20 m3 8,250,000.00 1,841,400,000.00
- Kolom beton type KL.2 63.00 m3 8,000,000.00 504,000,000.00
- Kolom beton type KL.3 6.00 m3 7,600,000.00 45,600,000.00
- Kolom beton type KL.4 14.40 m3 7,250,000.00 104,400,000.00
- Kolom beton type KP 7.43 m3 6,250,000.00 46,406,250.00
b Balok Beton
- Balok, type BL.1 655.38 m3 8,500,000.00 5,570,687,500.00
- Balok, type BL.2 77.15 m3 8,000,000.00 617,200,000.00
- Balok, type BL.3 55.76 m3 7,650,000.00 426,564,000.00
- Balok, type BL.4 0.95 m3 7,250,000.00 6,851,250.00
c Plat Lantai Beton
- Floor deck, 0,75mm 6,072.00 m2 225,000.00 1,366,200,000.00
- Wiremesh MØ8, 150x150 ( 2 lapis ) 6,072.00 m2 290,000.00 1,760,880,000.00
- Cor beton lantai, t=15cm 910.80 m3 1,525,000.00 1,388,970,000.00
d Tangga Beton
- Cor beton tangga 79.20 m3 5,500,000.00 435,600,000.00

Jumlah 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 5,806.08 m2 185,000.00 1,074,124,800.00


- Plesteran dinding 11,612.16 m2 85,000.00 987,033,600.00
- Acian dinding 11,612.16 m2 45,000.00 522,547,200.00
- Dinding Partisi Exposed Kaca 8mm 2,835.00 m3 450,000.00 1,275,750,000.00

Jumlah 3,859,455,600.00

III PEKERJAAN PLAFOND

- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 6,072.00 m2 185,000.00 1,123,320,000.00

Jumlah 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.1 (kelas) 36.00 unit 7,495,000.00 269,820,000.00


- Kusen pintu, type PT.2 (janitor) 4.00 unit 1,250,000.00 5,000,000.00
- Kusen pintu, type PT.3 (shaft) 8.00 unit 750,000.00 6,000,000.00
- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00
- Kusen pintu PVC (toilet) 32.00 unit 950,000.00 30,400,000.00
- Kusen jendela, type JD.1 (kelas) 72.00 unit 9,160,000.00 659,520,000.00
- Kusen jendela, type JD.2 (kelas) 24.00 unit 474,000.00 11,376,000.00
- Kusen jendela, type JD.3 (tangga) 6.00 unit 13,350,000.00 80,100,000.00
- Kusen jendela, type JD.4 (koridor & r.duduk) 8.00 unit 4,980,000.00 39,840,000.00
- Kusen bovenlight, type BV.1 (toilet) 8.00 unit 4,700,000.00 37,600,000.00
Jumlah 1,150,656,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING

a Lantai
- Lantai R.kelas, granit tile 60x60 1,728.00 m2 450,000.00 777,600,000.00
- Lantai Teras, granit tile 60x60 1,336.00 m2 450,000.00 601,200,000.00
- Lantai toilet, keramik 40x40 270.00 m2 300,000.00 81,000,000.00
- Lantai tangga, granit tile 60x60 231.44 m2 450,000.00 104,145,750.00

b Dinding
- Dinding lift, granit tile 60x60 32.40 m2 540,000.00 17,496,000.00
- Dinding toilet, keramik 25x40 156.60 m2 225,000.00 35,235,000.00
- Plint dinding, granit tile 10x60 1,172.00 m1 75,000.00 87,900,000.00

Jumlah 1,704,576,750.00

VI PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 559.00 ttk 250,000.00 139,750,000.00


- Instalasi titik stop kontak 12.00 ttk 250,000.00 3,000,000.00
- Instalasi titik saklar 62.00 ttk 250,000.00 15,500,000.00
- Instalasi AC 184.00 ttk 475,000.00 87,400,000.00
- Lampu downlight 203.00 bh 215,000.00 43,645,000.00
- Lampu TL inbow 2x40 watt 350.00 bh 550,000.00 192,500,000.00
Lampu baret outbow 6.00 bh 750,000.00 4,500,000.00
- Stop kontak 12.00 bh 75,000.00 900,000.00
- Saklar Tunggal 10.00 bh 75,000.00 750,000.00
- Saklar ganda 52.00 bh 85,000.00 4,420,000.00
- Panel box 4.00 bh 5,000,000.00 20,000,000.00
- MCB 76.00 bh 450,000.00 34,200,000.00
- AC split wall 184.00 unit 5,000,000.00 920,000,000.00

Jumlah 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR

- Instalasi air bersih 668.80 m1 35,000.00 23,408,000.00


- Instalasi air kotor 88.80 m1 125,000.00 11,100,000.00
- Instalasi air buangan 144.00 m1 125,000.00 18,000,000.00
- Instalasi air hujan 380.00 m1 47,000.00 17,860,000.00
- Closet duduk 32.00 bh 1,250,000.00 40,000,000.00
- Urinoir 16.00 bh 2,550,000.00 40,800,000.00
- Washtafel 24.00 bh 1,850,000.00 44,400,000.00
- Jet washer 32.00 bh 275,000.00 8,800,000.00
- Kran tangan 36.00 bh 275,000.00 9,900,000.00
- Cermin 24.00 m2 225,000.00 5,400,000.00
- Floor drain 36.00 bh 225,000.00 8,100,000.00

Jumlah 227,768,000.00

VIII PEKERJAAN RAILLING

- Railing tangga stainlessteel 40x40 & 40x60 225.60 m1 1,150,000.00 259,440,000.00


- Railing selasar & koridor, stainlessteel 40x40 & 40x60 266.00 m1 850,000.00 226,100,000.00

Jumlah 485,540,000.00

IX PEKERJAAN GRC

- Listplank GRC 298.60 m1 850,000.00 253,810,000.00


Jumlah 253,810,000.00

X PEKERJAAN PENGECATAN

- Cat dinding 11,612.16 m2 45,000.00 522,547,200.00


- Cat plafond 6,072.00 m2 47,000.00 285,384,000.00
- Cat listplank GRC 298.60 m1 55,000.00 16,423,000.00

Jumlah 824,354,200.00

XI PEKERJAAN LAIN-LAIN

- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00


- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

F PEKERJAAN LANTAI ENAM

I PEKERJAAN BETON 14,114,759,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 3,859,455,600.00

III PEKERJAAN PLAFOND 1,123,320,000.00

IV PEKERJAAN KUSEN, PINTU DAN JENDELA 1,150,656,000.00

V PEKERJAAN PELAPIS LANTAI DAN DINDING 1,704,576,750.00

VI PEKERJAAN ELEKTRIKAL 1,466,565,000.00

VII PEKERJAAN INSTALASI DAN SANITAIR 227,768,000.00

VIII PEKERJAAN RAILLING 485,540,000.00

IX PEKERJAAN GRC 253,810,000.00

X PEKERJAAN PENGECATAN 824,354,200.00

XI PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 25,216,804,550.00
.
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

No URAIAN VOLUME HARGA SAT JUMLAH

G PEKERJAAN ATAP

I PEKERJAAN BETON

a Kolom Beton
- Kolom beton type KL.2 5.76 m3 8,000,000.00 46,080,000.00
- Kolom beton type KL.3 4.80 m3 7,650,000.00 36,720,000.00
- Kolom beton type KL.5 1.44 m3 7,000,000.00 10,080,000.00
b Balok Beton
- Balok, type BL.3 36.08 m3 8,000,000.00 288,640,000.00
- Balok, type BL.4 132.84 m3 7,250,000.00 963,090,000.00
c Plat Lantai Beton
- Floor deck, 0,75mm 3,123.00 m2 225,000.00 702,675,000.00
- Wiremesh MØ8, 150x150 ( 1 lapis ) 3,123.00 m2 290,000.00 905,670,000.00
- Cor beton lantai, t=12cm 374.76 m3 1,525,000.00 571,509,000.00
d Plat Lantai Beton Atap Lift
- Floor deck, 0,75mm 288.00 m2 5,500,000.00 1,584,000,000.00
- Wiremesh MØ8, 150x150 ( 1 lapis ) 288.00 m2 125,000.00 36,000,000.00
- Cor beton lantai, t=12cm 34.56 m3 1,525,000.00 52,704,000.00

Jumlah 5,197,168,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN

- Pas. dinding hebel 10cm 876.20 m2 185,000.00 162,097,000.00


- Plesteran dinding 1,752.40 m2 85,000.00 148,954,000.00
- Acian dinding 1,752.40 m2 45,000.00 78,858,000.00

Jumlah 389,909,000.00

III PEKERJAAN DROP OFF

- Rangka atap baja ringan 4,219.20 m2 175,000.00 738,360,000.00


- Atap genteng metalroof 4,219.20 m2 165,000.00 696,168,000.00
- Genteng nok metalroof 330.00 m1 125,000.00 41,250,000.00
- Talang 106.00 m1 245,000.00 25,970,000.00

Jumlah 1,501,748,000.00

IV PEKERJAAN PLAFOND

- Plafond gygsum 9mm rangka hollow 20x40 & 40x40 253.00 m2 185,000.00 46,805,000.00

Jumlah 46,805,000.00

V PEKERJAAN KUSEN, PINTU DAN JENDELA

- Kusen pintu, type PT.4 (AHU & panel) 2.00 unit 5,500,000.00 11,000,000.00

Jumlah 11,000,000.00

VI PEKERJAAN ELEKTRIKAL

- Instalasi titik lampu 24.00 ttk 250,000.00 6,000,000.00


- Instalasi titik stop kontak 8.00 ttk 250,000.00 2,000,000.00
- Instalasi titik saklar 8.00 ttk 250,000.00 2,000,000.00
- Lampu downlight 8.00 bh 215,000.00 1,720,000.00
- Lampu pijar 20 watt 16.00 bh 550,000.00 8,800,000.00
- Stop kontak 8.00 bh 75,000.00 600,000.00
- Saklar Tunggal 2.00 bh 75,000.00 150,000.00
- Saklar ganda 6.00 bh 85,000.00 510,000.00

Jumlah 21,780,000.00

VII PEKERJAAN RAILLING

- Railing lobby lift stainlessteel 40x40 & 40x60 24.00 m1 1,150,000.00 27,600,000.00

Jumlah 27,600,000.00

VIII PEKERJAAN PENGECATAN

- Cat dinding 1,752.40 m2 45,000.00 78,858,000.00


- Cat plafond 253.00 m2 47,000.00 11,891,000.00

Jumlah 90,749,000.00

IX PEKERJAAN LAIN-LAIN

- Pembersihan akhir 1.00 ls 3,500,000.00 3,500,000.00


- Buang puing 1.00 ls 2,500,000.00 2,500,000.00

Jumlah 6,000,000.00

RENCANA ANGGARAN BIAYA


Jenis Pekerjaan : Pembangunan STIKES
Lokasi Proyek : Singkawang - Kalimantan Barat
Periode : November 2018

REKAPITULASI

No URAIAN JUMLAH

G PEKERJAAN ATAP

I PEKERJAAN BETON 5,197,168,000.00

II PEKERJAAN PASANGAN DINDING, PLESTERAN DAN ACIAN 389,909,000.00

III PEKERJAAN DROP OFF 1,501,748,000.00

IV PEKERJAAN PLAFOND 46,805,000.00

V PEKERJAAN KUSEN, PINTU DAN JENDELA 11,000,000.00

VI PEKERJAAN ELEKTRIKAL 21,780,000.00

VII PEKERJAAN RAILLING 27,600,000.00

VIII PEKERJAAN PENGECATAN 90,749,000.00

IX PEKERJAAN LAIN-LAIN 6,000,000.00

Jumlah 7,292,759,000.00
.