DAN MRR
5 elemen dasar Proses Pemesinan

1. Kecepatan Potong

2. Kecepatan makan
Gerak potong

Gerak makan
3. Kedalaman Potong

4. Waktu Potong

5. Kecepatan penghasilan geram


MRR atau RMR
5 elemen dasar Proses Pemesinan

1. Kecepatan Potong

2. Kecepatan makan
Gerak potong

Gerak makan
3. Kedalaman Potong

4. Waktu Potong
Parameter pemotongan
Atau

Kondisi pemotongan
Terdiri dari 5. MRR atau RMR
f, d, Vc
Latihan

baja karbon : L 130 mm, Dia. 30 mm

30 mm
130 mm

Sampel uji Jominy

Berapa waktu yang dibutuhkan


untuk membuat sampel uji Jominy
Operasion Plan
no operation sket tool Waktu Keterangan
potong
1 Chucking Chuck pengama
tan

2 Facing Facing Tool Rumus

3 Roughing Roughing rumus


Tool

4 Finishing n Finishing Rumus n


Champering Tool pengama
handTool tan
5 Cut off Cut off Tool rumus

6 Facing the other Facing Tool rumus


side
5 elemen dasar
 Kec Potong ( Cutting Speed ) :
Vc = (π D n) / 1000 ( m/menit
 Kecepatan makan (Feeding Speed)
: Vf = f . n ( mm/menit)
 Kedalaman Potong ( Depth of Cut )
: a ( mm )
 Waktu Potong ( Cutting Speed ) :
tc = L / Vf ( menit )
 Kec Penghasilan Geram ( Rate of
metal removal) (RMR )/ Metal
Removal rate (MRR )= Z ( cm3 /
menit )
V = π . D . N / 1000 ( m/menit )

V = π . D . N / 1000.60 ( m/detik )
1. Sebuah bahan baja karbon dengan diameter 30 mm dan panjang 250 mm akan diraut menjadi diameter 28 mm
dengan proses turning pada mesin bubut. Poros utama ( spindle) berputar pada 600 rpm proses produktif . Kecepatan
gerak pahat adalah 0,75 mm / putaran. Kedalaman potong proses pengkasaran 1 mm.
Hitung : a. Kecepatan potong pada proses turning
b. Waktu potong
V = π . D . N / 1000 ( m/menit )

Tc = Lt (mm) (mm) / vf (mm /menit)


= (L + a + o) / f. n (mm/put) x put /menit )

Tc = (L + a + o) (mm) / vf (mm /menit) = Lt (mm) / f. n (mm/put) x put /menit )


= ( 250 + 2 + 5) mm / f.n (mm/put) x put /menit )
= 257 (mm) / 0,75 (mm /put) . 600 (put / menit) = 257 / 450 menit = 0,57 menit = 34,2 detik
Kondisi Pemotongan (Cutting
Conditions)
f : Feeding
f : mm/rev

Vc : Cutting speed

Vc : m / min

d : depth of cut
d : mm
MRR
MRR = v.f.d Cutting conditions

tc = Volume / MRR
Pc Fc v
Pc U = Pu = =
Pg = RMR vto w
E

MRR
Cutting conditions
Note: - Primary cutting due to speed (v)
- Lateral motion of tool is feed (f)
- Tool penetration is depth of cut ( d )
The three together form the material removal rate (MRR):
MRR = v . f . d
with units of (in/min)(in/rev)(in) = in3/min/rev (or vol / min-rev)

Types of cuts:
Roughing : feeds of 0.015 – 0.05 in/rev depths of 0.1 – 0.75 in
Finishing : feeds of 0.005 – 0.015 in/rev depths of 0.03 – 0.075 in
Introduction

Cutting motion
Gerak potong

Gerak makan Cutting condition :


• Cutting speed, Vc, m/sec
• Feed f , mm/rev
• Depth of cutd, mm
Contoh Soal
1. Pada operasional turning bahan baja tahan karat (stainless steel) berdimensi Panjang 400 mm, diameter 25 mm
dengan kekerasan = 200 HB, kecepatan potong = 200 m / menit, Pemakanan (feed) = 0,25 mm / putaran, dan
kedalaman potong (depth of cut) = 7,5 mm.
a. Berapa daya yang akan digunakan mesin bubut dalam melakukan operasi ini jika efisiensi mekanisnya = 90%.
Gunakan Tabel / diagram untuk mendapatkan nilai energi spesifik ( U atau Pu atau Ps ) yang sesuai.
b. Berapa waktu potong shg benda kerja tersebut berdiameter 10 mm.

Solution:
1. Lihat tabel untuk mencari nilai specific cutting energy , U = 2.8 N-m/mm3 = 2.8 J/mm3
2. Hitung nilai Laju pembuangan geram ( MRR atau RMR)
RMR = vfd = (200 m/min)(103 mm/m)(0.25 mm)(7.5 mm) = 375,000 mm3/min = 6250 mm3/s
3. Cari daya yg digunakan :
Pc = (6250 mm3/s)(2.8 J/mm3) = 17,500 J/s = 17,500 W = 17.5 kW
Pc Fc v Pc
U = Pu = = Pg =
RMR vto w E