TUGAS 2

PERENCANAAN GEOMETRI JALAN

DEFRI SETIAWAN SAEHANA


F 111 20 003
KELAS A

FAKULTAS TEKNIK
JURUSAN TEKNIK SIPIL (S-1)
UNIVERSITAS TADULAKO
Palu – Sulawesi Tengah
2021
TUGAS :

Carilah contoh-contoh soal berikut :

1. Tikungan full circle


2. Tikungan spiral-spiral
3. Tikungan spiral-circle-spiral

JAWABAN :

1. Tikungan full circle


Diketahui data-data sebagai berikut :
 á1 =124º34’
 á2 = 25º15’
 Δ = 99º19’
 Rdata = 2,5 cm
 Rlap = 750 m
 Rmin = 700 m
Penyelesaian :
a. Data perencanaan :
 Rype jalan = jalan arteri
 Sudut á1 = 124º34’
 Sudut á2 = 25º15’
 Jari-jari lapangan = 750 m
 Kecepatan rencana = 70 Km/jam
b. Perhitungan perencanaan
 Lebar badan jalan =8m
 Jika Vr = 70 km/jam
 Maka Rmin = 700 m
 e max = 10%
 sudut Δ = 99º19’
 Karena Rlap>Rmin ,maaka digunakan full circle
 Tc = R * Tg ½ Δ
= 750 * Tg ½ 99º19’
= 883,06
 Ec = Tc * Tg ¼ Δ
= 883,06* Tg ¼ 99º19’
= 408,57

 Lc =

= 1299,39 m
 Tlb = 2 * R * sin ¼ Δ
= 2 * 750 * sin ¼ 99º19’
=1143,29 m
2. Tikungan spiral-spiral
Diketahui data-data sebagai berikut :
 á1 = 47º14’
 á2 = 132º11’11”
 Δ = 84º57’11”
 Rdata = 1 cm
 Rlap = 300 m
 Rmin = 700 m
Penyelesaian :
a. Data perencanaan :
 Rype jalan = jalan arteri
 Sudut á1 = 47º14’
 Sudut á2 = 132º11’11”
 Jari-jari lapangan = 300 m
 Kecepatan rencana = 70 Km/jam
b. Perhitungan perencanaan
 Lebar badan jalan =8m
 Jika Vr = 70 km/jam
 Maka Rmin = 700 m
 e max = 10%
 sudut Δ = 84º57’11”
 Karena Rlap << Rmin ,maaka digunakan SS
 Jika Vr = 70 km/jam, dan R = 300 m
 Maka e = 7,7 %
 Ls = 60
 Dari table konstruksi jalan raya , Ls = 60, dan R = 300 m diperoleh
 θs = 5,7296
 P = 0,4998
 K = 29,9900
 Xs = 59,9400
 Ys = 1,9986
 Δs = 2 * θs

= 2 * 5,7296

= 11,4592

 Lt = Xs -

= 59,9900 -

= 49,97734

 St =

= 20,019
 Ts = (R +P) Tg ½ Δ +k
= (300 + 0,4998) Tg ½ 84º57’11” + 29,9900
= 305,12

 Es = –R

= - 300

= 107,42
 L = 2 * Ls
= 2 * 60
= 120
 Kontrol :
 2 * Ls < 2 * Ts
 120 < 610,24…………………. Aman !!!
3. Tikungan spiral-spiral
Diketahui data-data sebagai berikut :
 á1 = 24º18’47”
 á2 = 106º16’18”
 Δ = 81º57’31”
 Rdata = 1,5 cm
 Rlap = 450 m
 Rmin = 700 m
Penyelesaian :
c. Data perencanaan :
 Rype jalan = jalan arteri
 Sudut á1 = 24º18’47”
 Sudut á2 = 106º16’18”
 Jari-jari lapangan = 450 m
 Kecepatan rencana = 70 Km/jam
d. Perhitungan perencanaan
 Lebar badan jalan =8m
 Jika Vr = 70 km/jam
 Maka Rmin = 700 m
 e max = 10%
 sudut Δ = 81º57’31”
 Karena Rlap<Rmin ,maaka digunakan SCS
 Jika Vr = 70 km/jam, dan R = 450 m
 Maka e = 5,7 %
 Ls = 50
 Dari table konstruksi jalan raya , Ls = 50, dan R = 450 m diperoleh
 θs = 3,1831
 P = 0,2315
 K = 24,9974
 Xs = 49,9846
 Ys = 0,9957
 Lt = Xs -

= 49,9846-

= 32,0805

 St =

= 17,93
 Ts = (R +P) Tg ½ Δ +k
= (450 + 0,2315) Tg ½ 81º57’31” + 24,9974
= 416,092

 Es = –R

= - 450

= 146,37
 Δc = Δ – 2 * θs
= 81º57’31” – 2 * 3,1831
= 75,5920
 Tc = R * Tg ½ Δc
= 450 * Tg ½ 75,5920
= 349,005

 Lc =

= 593,39
 L = Lc + 2 * Ls
= 593,39 + 2 * 50
= 693,39
 Ec = Tc * Tg ¼ Δc
= 349,005 * Tg ¼ 75,5920
= 119,47
 Kontrol :
 Lc < 20 m
 593,39 < 20 m…………………. Aman !!!
L < 2 * Ls
693,39 < 832,184