I. DATA PROYEK
V
GEDUNG TAMAN KANAK-
100,00% 57,03% 1,96% 58,98%
KANAK
PEKERJAAN STRUKTUR 56,35% 51,11% 1,96% 53,07%
b. TENAGA KERJA :
PT. Musca Pekerjaan struktur (30 orang)
PT. Sindang Pekerjaan Mekanikal Elektrikal (4 Orang)
PT. Amma Praja Mataram Pekerjaan Arsitektur/ACP ( 4 orang)
PT. Karya Sakti Sejahtera Pekerjaan Baja (7 orang)
Pelaksana Finishing (75 Orang)
Pelaksana Finishing Landscape (15 Orang)
c. MATERIAL :
Besi ulir: D10, D13, (onsite)
Material Wiremesh (onsite)
Material Pipa PVC Dia 4” (onsite).
On Site Uditch Drainase (onsite).
Kayu (onsite).
Triplek (onsite).
Pasir (onsite).
Paku (onsite).
Semen (onsite).
Bata merah (onsite)
Batu kali (onsite)
GRC cetak (onsite )
Sanitair (onsite)
Paving Blok
Homogeneous Tile (onsite)
7. WAKTU PELAKSANAAN
a. Waktu Kontrak : 649 Hari Kalender
b. Waktu Terpakai : 518 Hari Kalender
c. Sisa Waktu Kontrak : 131 Hari Kalender
VIII. ALOKASI DANA
LOAN ADB No. 3793 – INO
IX. PEMBAYARAN UANG MUKA/SERTIFIKASI BULANAN
a. PMSC Yodya Karya (Persero) KSO
No Uraian Nilai Pembayaran Keterangan
X. MASALAH DILAPANGAN
Hasil Uji Kuat tekan Sampel Benda Uji Beton menggunakan dana Provsum
PMSC untuk cross check rutinitas control kendali mutu diperoleh nilai kuat
tekan dibawah syarat Design, telah ditindak lanjuti dengan uji sampel Inti
core yang juga tidak memenuhi syarat kuat tekan Design.