REKAPITULASI RAB KONTRAKAN PORIS TANGERANG

PEKERJAAN : PEMBANGUN KONTRAKAN PORIS

HARGA
NO URAIAN KEGIATAN VOLUME SATUAN JUMLAH %
SATUAN

A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1 IS Rp 500,000 Rp 500,000 25%
2 Pemasangan Bouwplank 50.3 M2 Rp 20,000 Rp 1,006,000 50%
3 Direksi Keet 1 IS Rp 500,000 Rp 500,000 25%
SUB TOTAL Rp 2,006,000 1%
B PEKERJAAN TANAH
1 Galian Tanah Pondasi 0.6:0.3:50.3 50.3 M3 Rp 50,000 Rp 2,515,000 83%
2 Septic Tank 2x1x2 1 m3 Rp 500,000 Rp 500,000 17%
SUB TOTAL Rp 3,015,000 2%
C PEKERJAAN BATU KALI & BETON BERTULANG, 1 : 2:;
1 Pondasi Batu Kali 1:4 50.3 M2 Rp 300,000 Rp 15,090,000 20%
2 Sloof 15/20 50.3 M2 Rp 400,000 Rp 20,120,000 27%
3 Kolom 10/15 50.3 M2 Rp 200,000 Rp 10,060,000 13%
4 Kolom Expose 50.3 M2 Rp 200,000 Rp 10,060,000 13%
5 Ring Balok 50.3 M2 Rp 200,000 Rp 10,060,000 13%
6 Ring Balok Sofi2 10/15 50.3 M2 Rp 200,000 Rp 10,060,000 13%
Besi Ulir 10/8
Besi ring 8/6
SUB TOTAL Rp 75,450,000 42%
D PEKERJAAN PASANGAN
1 Pasangan Dinding habel 161 M2 Rp 150,000 Rp 24,150,000 64%
2 Plesteran Halus, 1:4, t=1.5 cm 150 M2 Rp 60,000 Rp 9,000,000 24%
3 kabel istalasi listrik 37.4 M Rp 100,000 Rp 3,740,000 10%
4 stop klontak 8.4 pcs Rp 100,000 Rp 840,000 2%
SUB TOTAL Rp 37,730,000 21%
E PEKERJAAN SANITASI
1 Pemasangan Kloset Jongkok 2 pcs Rp 200,000 Rp 400,000 6%
2 Pemasangan Bak Mandi 2 pcs Rp 500,000 Rp 1,000,000 14%
3 Pemasangan Kramik Lantai 20x20 cm 5 M2 Rp 140,000 Rp 700,000 10%
4 Pemasangan Keramik Dinding 20x20 cm 6 M2 Rp 200,000 Rp 1,200,000 17%
5 Pemasangan Instalasi Air Bersih 1 IS Rp 1,500,000 Rp 1,500,000 21%
6 Pemasangan Keran Air 4 IS Rp 100,000 Rp 400,000 6%
8 Pemasangan Instalasi Air Kotor 2 IS Rp 1,000,000 Rp 2,000,000 28%
SUB TOTAL Rp 7,200,000 4%
F PEKERJAN DAPUR
Pemasangan Kramik Meja Dapur 60x60 cm 3 M2 Rp 140,000 Rp 420,000 30%
Pemasangan Kitchen Zing 2 PCS Rp 500,000 Rp 1,000,000 70%
Avour 2 IS Rp 50,000 Rp 100,000 7%
SUB TOTAL Rp 1,420,000 1%
E PEKERJAAN KUSEN KAYU
1 Kusen Pintu 4 pcs Rp 700,000 Rp 2,800,000 33%
2 Kusen Jendela 1 Lubang 2 pcs Rp 500,000 Rp 1,000,000 12%
3 Kusen KM/WC, PVC Lengkap 2 pcs Rp 500,000 Rp 1,000,000 12%
4 Daun Pintu Panel 4 pcs Rp 700,000 Rp 2,800,000 33%
5 Daun Jendela+Kaca 5 mm 2 pcs Rp 500,000 Rp 1,000,000 12%
SUB TOTAL Rp 8,600,000 5%
F PEKERJAAN ATAP
1 Rangka Atap Baja Ringan 0.7 80 pcs Rp 120,000 Rp 9,600,000 48%
2 Asbes 21 pcs Rp 150,000 Rp 3,150,000 16%
4 Plafond Gipsum+Holow 21 pcs Rp 150,000 Rp 3,150,000 16%
5 List Plafond 54 m Rp 50,000 Rp 2,700,000 14%
6 cor beton depan 8.4 m2 Rp 150,000 Rp 1,260,000.00 6%
SUB TOTAL Rp 19,860,000.00 11%
G PEKERJAAN LANTAI
2 Floor lantai Adukan 1:3:5 50.3 M2 Rp 50,000 Rp 2,515,000 28%
3 Pemasangn Lantai Keramik 40x40 37.4 M2 Rp 140,000 Rp 5,236,000 59%
5 Pemasangan Keramik Teras 40x40 8.4 M2 Rp 140,000 Rp 1,176,000 13%
SUB TOTAL Rp 8,927,000 5%

H PEKERJAAN FINISHING
1 Cat Dinding nippon 90 M2 Rp 50,000 Rp 4,500,000 3%
2 Aquaproof 60 M2 Rp 60,000 Rp 3,600,000 2%
SUB TOTAL Rp 8,100,000 5%
I PEKERJAAN LAIN NYA
1 Pemasangan AC 2 PCS Rp 3,000,000 Rp 6,000,000 79%
2 Hexos 2 PCS Rp 400,000 Rp 800,000 11%
3 Pembersihan lokasi 1 IS Rp 800,000 Rp 800,000 11%

SUB TOTAL Rp 7,600,000 4%

Jumlah total Rp 179,908,000 100%


Dibulatkan Rp 180,000,000
Terbilang Seratus Delapan Puluh Ribu Rupiah