INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 1
A IFR 01/08/2023
Construction Project
Prepared Approved
Rev Status Issue Date Reason for Issue Manager Manager
CONTRACTOR Approval MEDCO Approval
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 2
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 3
Daftar Isi
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 4
1 Pendahuluan 4
2 Lingkup Pekerjaan 4
2.1 Definisi 5
3 Referensi 6
3.1 Project Planning and Scheduling 6
3.2 Progress Measuring 15
3.3 Project Cost Control 16
3.4 Project Reporting and Forecasting 17
4 Financial and Cost Control, Reporting and Cash Flow Forecast 26
4.1 Financial and cost control procedures 26
4.2 Cost Baseline 26
4.3 Monthly cost report 27
4.4 Monthly Progress Report 28
4.5 Financial and cost control procedures 28
5 INVOICING 28
5.1 Original invoice 28
5.2 Draft copies of invoices (Performa invoice) 29
5.3 Value added tax (VAT) 29
5.4 First Invoice 29
5.5 Evaluation and verification 29
5.6 Final Lien 30
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 5
1 Pendahuluan
Dokumen ini merupakan spesifikasi standar yang berlaku untuk Proyek CORRIDOR
PROJECTS CONSTRUCTION & INSTALLATION BLANKET, dan dikendalikan oleh
Project Manager. Dokumen tidak boleh diubah atau direvisi tanpa ditinjau dan
disetujui oleh Instansi Teknis yang ditunjuk untuk spesifikasi standar ini. Revisi dan
tambahan pada spesifikasi standar ini harus disetujui oleh Project Manager Proyek
CORRIDOR PROJECTS CONSTRUCTION & INSTALLATION BLANKET. Setiap
penyimpangan dari spesifikasi standar ini dan pemeliharaannya harus mengikuti
dokumen 02.1-4. Appendix A1.4 - Report, Documentation and Project Control.
2 Lingkup Pekerjaan
Sistem kontrol proyek Kontraktor dikembangkan dan ditetapkan untuk memastikan
perkiraan yang akurat, perencanaan, penjadwalan, penganggaran, pemantauan,
pengendalian dan pelaporan pelaksanaan pekerjaan berdasarkan Kontrak.
Dokumen ini membahas elemen kunci berikut dan didasarkan pada:
• Work Breakdown Structure (WBS) dan Cost of Account
• Schedule Development dan Control Plan; harus mencakup semua bidang
penting dari schedule development and control.
• Progress Measurement system untuk mengukur dan melaporkan kemajuan fisik
untuk semua aktivitas dan hasil Layanan yang dapat diidentifikasi
• The basic cost control; harus merupakan perkiraan biaya terperinci yang
mencakup seluruh cakupan layanan, didukung oleh perincian lengkap dan tarif
satuan.
• Dasar Manajemen Perubahan Sistem dan bagaimana perubahan akan
diidentifikasi, dilacak, dikendalikan dan dipantau
• Progress Reporting, Analysis and forecasting yang akan diterbitkan dalam
Persyaratan Pelaporan Mingguan dan Bulanan Proyek
• Invoicing and Payment Procedure; mengatur mekanisme penagihan selama
pelaksanaan pekerjaan.
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 6
2.1 Definisi
Term Definition
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 7
3 Referensi
Prosedur dan catatan panduan lain yang memiliki hubungan, dan digunakan
bersama dengan Rencana Pengendalian Proyek meliputi:
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 8
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A Page 9
WBS harus dikembangkan untuk semua fase proyek. Untuk fase proyek saat ini,
Struktur Perincian Pekerjaan harus dirinci sampai tingkat yang sesuai. Untuk fase
proyek mendatang, Work Breakdown Structure memiliki persyaratan minimum untuk
setiap fase proyek untuk tujuan perencanaan, seperti yang dijelaskan dalam
Lampiran C dan D. Idealnya, tingkat WBS untuk perencanaan dan biaya harus
diselaraskan dengan tingkat Perincian Aktivitas Standar.
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 10
Perincian Aktivitas Standar akan menjadi bagian dari masker SAP WBS. Contoh
format ditunjukkan pada tabel di bawah ini:
Character 1 to 3 (CTR) diisi dengan nomor kontrak proyek, tunggal. Semua proyek
dimulai dengan “CTR” pada Level 0, yang secara jelas membedakan struktur rincian
proyek dari struktur rincian proyek lainnya. "CTR" tidak boleh digunakan kecuali
untuk WBS level tertinggi untuk proyek.
Character 5 to 7 (XXX) are used to identify the year in which the project starts.
Character 9 to 12 (NNNN) are used to identify the project name; the project name
acronym is used here.
Character 14 and 15 (YY) on level 1 are used to identify the project phase, and it
can also be used to differentiate whether a project cost is treated as expense or as
capital (DN, AP and SL are treated as expense; DF and EX are treated as capital):
Character 17 and 18 (ZZ) on level 2 are used to identify the project’s Sub-Project
or Process Unit/Area (PU).
Character 20 and 21 (PP) on level 3 are used to identify the project’s Components.
Character 23 and 24 (QQ) on level 4 are used to identify the project’s Standard
Activity Breakdown. Character 23 and 24 (QA) on level 5 are used to identify the
project’s Sub-Activity. These last two characters on level 5 will be a combination of
number and alphabet, whereas the “Q” will be replaced by a number, and the “A” will
be a sequential of alphabet (starting from A, B, C, and so on, sequentially for each
different sub-activity).
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 11
A graphical display of these WBS mask structure, both for onshore and offshore,
are attached in appendix E of this procedure
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 12
• Deskripsi aktivitas unik dan spesifik yang mendefinisikan tugas dengan jelas
• Penggunaan logika yang dipertahankan sebagai kebalikan dari progres override
• Persen selesai berdasarkan jam kerja yang diperoleh dan bukan durasi aktivitas
• Semua aktivitas diberi kode WBS yang sesuai
• Sumber daya dimuat per perkiraan (semua aktivitas yang membutuhkan upaya)
• Setiap kegiatan harus memiliki durasi yang wajar dengan tingkat kerincian
jadwal, terukur dan berbasis estimasi
• Penyisihan untuk liburan yang diamati di lokasi teknik dan Lokasi
• Minimalkan jumlah kalender berbeda yang digunakan
• Tidak ada negatif float paths di Baseline Schedule
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 13
Setelah Persetujuan Jadwal Dasar dan setiap tiga (3) bulan setelahnya,
Perusahaan dapat, atas kebijakan Perusahaan sendiri, melakukan audit jadwal
yang memastikan kepatuhan terhadap Exhibit F. Kontraktor harus menanggapi
temuan audit dengan cermat dan memperbaiki ketidaksesuaian atau tindakan
korektif diidentifikasi dalam waktu empat belas (14) Hari.
Level 4 and 5 Data - Contractor's detailed Level 4 and 5 schedule data can be
defined as the supporting documents to the schedule (i.e. Progress
measurement system, procurement status report, drawing registers/logs, any tool
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 14
or document that provides status of deliverables and supports the Level 3 schedule
in duration and status).
Controlling the schedule also means monitoring progress against the time scale,
hence it can be done by comparing actual progress achieved against the
planned progress which is usually delineated by a planned progress 'S'-curve.
This 'S'-curve can be derived from the Project Master Schedule by plotting
percentage complete (by man-hour or by cost basis) over the elapsed time for the
project. Once the actual physical progress for a certain period is calculated, it can
be plotted on the planned progress 'S'• curve. Contractor also will calculate the
forecasted progress for the next period until end of project and plot this in the S -
Curve.
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 15
The overall physical progress of the total project is calculated from the average
status of all defined project activities. In doing this, each activity has to be
weighted for its share of the total project. The 'weight factor' is determined by the
allocated cost used to accomplish the task. By multiplying the 'weighted value'
and the progress percentage of the activity, 'Earned Value' of the task which is
the activity's contribution to the overall progress, can be determined. Progress
percentage of activity is calculated with referring to rules of credit which is agreed
by Company for the project.
Contractor shall provide the progress measurement calculation in native file format
no later than 2 working days after the cut-off date for weekly and 5 working days
after the cut-off date for monthly update.
All the engineering documents and drawings associated with each schedule
activity will be monitored and reviewed on daily basis by the Document Controller.
The man-hour estimate, manpower assignment and productivity tracking become
project control major areas.
Rules of credit and how to measure Engineering Progress are described in
Document No. ID-G-BU-YYO-PRO-GN-00-XXXX (Contractor Progress
Measurement Requirement).
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 16
All the requisitions and purchase orders associated with each schedule activity
will be monitored and reviewed by Buyer and Expediter. In the same manner,
Expediter will control and monitor the status of engineered equipment and
materials against the planned target schedule.
Rules of credit and how to measure Procurement Progress are described in
Document No. ID-G-BU-YYO-PRO-GN-00-XXXX (Contractor Progress
Measurement Requirement).
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 17
Weighting allocation for all the deliverables I activities at all levels will be based on
the Work Breakdown Structure (WBS), shown and described in Document No. ID•
G-BU-00000-00000-XXXX
Project Cost are consist of Cost of total spent of Man Hours, Cost of
Equipment and Permanent Material, Cost of Sub-Contractor work (can
illustrated by spent of man hours), Cost of Construction equipment, and others
cost project supporting facilities such as cost of non-technical aspect for
security of the project, etc.
The control of the project cost in related to the Man-hour consumption for the
project execution, are follows:
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 18
o Direct Hire Field Labor Man hour cost, including Craft I Labor,
Helper, Foreman, etc.
Cost of Account
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 19
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 20
o Procurement
o Construction and Sub construction
o Project Control
o QA/QC
6. Any critical items
7. Areas of concern (i.e. nature of problem, work activities affected, potential
impact if not corrected, mitigating action being taken and recommended action,
estimated time to bring affected activities back on schedule)
8. Manpower Histograms (Plan and actual)
9. Status of subcontracting
10. Status of procurement (Procurement Master Schedule)
11. Quality control - QA/QC (status of defects and non-conformances)
12. Engineering Deliverable List Status.
13. Temporary Facility Progress.
14. Construction Progress.
15. The weekly report shall be discussed at the weekly progress meetings between
Company and Contractor.
16. For further weekly reporting requirements refer to Specification No. ID• G-BU-
YYO-PO-GN-00-0013- "Contractor Project Progress Reporting
Requirements".
17. Photograph.
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 21
the Month) for Company review and comment. Contractor shall edit the
report or incorporate comments therein as may be required by
Company and issue the report immediately thereafter. The monthly
report shall include, but not be limited to, the following items and may
improve during the project execution upon Company request.
C. Contract Schedules
1) Bar charts of all schedule levels status, updated as at the cut-off
shown by means of a data date. Schedules should show as a
minimum the activity description, forecast early start, forecast
early finish, remaining duration and total float in the column
area and the activity early bar, baseline bar and float bar in the
bar area.
2) Criticality Reports.
3) Activity Listings.
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 22
Progress
1) Progress tables for Level 1, Level 2 and Level 3 activities
showing planned and actual progress percentages for the
reporting period and cumulative.
2) Progress S-curves (overall, phase, discipline, subcontract and
work product) showing target, actual and forecast progress.
3) Narrative on significant variances to the planned progress and a
report on any areas of concern affecting the progress (including
poor productivity).
4) Narrative mitigation plan on the significant variance.
5) Progress and Status of the Contract Administration items per
Appendix 1 - Contract Administration table of this Exhibit F.
E. Manpower I Capacity
1) Changes in Contractor's Contract organization.
2) A labor productivity report, by engineering discipline or
construction craft, showing budget man-hours, earned man-hours,
actual man• hours, schedule performance index (SPI), cost
performance index (CPI) and forecast man-hours.
3) Summary table of the project manpower by each Site and
discipline.
4) Manning histograms planned vs. actual and earned by phase,
discipline and subcontract
5) The Manpower Projection Plan in the form set out in Appendix 3.
6) A comparison between the total number of personnel actually
engaged on the Work and the number planned for the reporting
period. This comparison shall be presented in a tabular format
that highlights specific discrepancies by Site at discipline and
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 23
F. Procurement
The reports will be in tabulated form and will cover all equipment and
materials with planned, forecast and actual dates for:
1) Requisition/Purchase Order number
2) Equipment/Material description & compliance with PMFL
3) COPI approval points in accordance with the contract
requirements (vendor lists, awards etc.)
4) Issue of bids
5) Receipt of bids
6) Bid Analysis
7) Issue request for approval to COPI (if required)
8) Issue of orders and/or amendments/changes
9) Supplier drawing reviews
10) Spare parts recommended lists
11) Inspection and expediting activity
12) Shipping status
13) Required on-site date
14) PO closeout date
15) Local Content Achievement report actual against local content
commitment in the contract)
16) Master lists status report (if any)
Separate monthly reports will be prepared for Expediting,
Inspection and Logistics, as required.
In addition, a separate exception report will be prepared on a
monthly basis with the lists of activities which have not been
CORRIDOR PROJECTS CONSTRUCTION &
INSTALLATION BLANKET
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 24
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 25
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 26
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 27
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 28
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 29
phased budget that shall be used as a basis to measure, monitor, and control cost
performance of the Project.
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 30
6 INVOICING
Reference to General Terms & Conditions, Clause 7 and Exhibit E of this Contract
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 31
Doc. No :
PLANNING & PROGRESS MEASUREMENT PROCEDURE ……………………….
Rev. A P a g e 32
equipment, materials or services to it, and fulfilled all of its rental, tax, duty and other
fiscal obligations with respect to the Work.
Following submittal of said Final Lien Waiver, Contractor may submit its final
invoice to Company. Said final invoice shall be for all payments due to
Contractor for the Work under this Contract and all Change Order
Authorizations thereunto. The final invoice shall contain the following statement
on the front page of the invoice signed by Contractor's Project Manager:
"This invoice covers the entire remaining compensation due to Contractor for
the Work under Contract No. CS-16703664 including, but not limited to, all
remaining compensation for direct and indirect costs for engineering,
material and equipment, plant, tools, consumables, supplies, supervision,
utilities, inspection, Subcontractors and Suppliers, labor, general overheads,
bonuses, profit, travel and expenses, computer usage, reproduction, any and
all other incidental costs, changes in schedule, delays resulting directly or
indirectly from Changes to the Work, and acts or omissions of Company during
the Contract Term up to Final Acceptance of all of the Work."