PERHITUNGAN JARAK

PERENCANAAN PERKERASAN JALAN 2023 | 1


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN JALAN

Titik Pada Peta (Skala 1:1000)

Titik X (m) Y (m)

A 19400 28700
1 15200 23100
2 13700 19500
B 15100 15200
1’ 10650 12300
C 8600 9500
Perhitungan Jarak

DA-1 = √(𝑿𝟐 − 𝑿𝟏)𝟐 + (𝒀𝟐 − 𝒀𝟏)𝟐`

= √(𝟏𝟓𝟐𝟎𝟎 − 𝟏𝟗𝟒𝟎𝟎)𝟐 + (𝟐𝟑𝟏𝟎𝟎 − 𝟐𝟖𝟕𝟎𝟎)𝟐

= 7000 m

D1-2 = √(𝑿𝟐 − 𝑿𝟏)𝟐 + (𝒀𝟐 − 𝒀𝟏)𝟐

= √(𝟏𝟑𝟕𝟎𝟎 − 𝟏𝟓𝟐𝟎𝟎)𝟐 + (𝟏𝟗𝟓𝟎𝟎 − 𝟐𝟑𝟏𝟎𝟎)𝟐

= 3900 m

D2-B = √(𝑿𝟐 − 𝑿𝟏)𝟐 + (𝒀𝟐 − 𝒀𝟏)𝟐

= √(𝟏𝟓𝟏𝟎𝟎 − 𝟏𝟑𝟕𝟎𝟎)𝟐 + (𝟏𝟓𝟐𝟎𝟎 − 𝟏𝟗𝟓𝟎𝟎)𝟐

= 4522,16 m

DB-1’ = √(𝑿𝟐 − 𝑿𝟏)𝟐 + (𝒀𝟐 − 𝒀𝟏)𝟐

= √(𝟏𝟎𝟔𝟓𝟎 − 𝟏𝟓𝟏𝟎𝟎)𝟐 + (𝟏𝟐𝟑𝟎𝟎 − 𝟏𝟓𝟐𝟎𝟎)𝟐

= 5311,54 m

PERENCANAAN PERKERASAN JALAN 2023 | 2


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

D1’-C = √(𝑿𝟐 − 𝑿𝟏)𝟐 + (𝒀𝟐 − 𝒀𝟏)𝟐

= √(𝟖𝟔𝟎𝟎 − 𝟏𝟎𝟔𝟓𝟎)𝟐 + (𝟗𝟓𝟎𝟎 − 𝟏𝟐𝟑𝟎𝟎)𝟐

= 3470,23 m

PERENCANAAN PERKERASAN JALAN 2023 | 3


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN SUDUT AZIMUT

&

SUDUT LUAR

PERENCANAAN PERKERASAN JALAN 2023 | 4


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN SUDUT AZIMUT & SUDUT LUAR

 Perhitungan Sudut Azimut

A – 1 = arc tan {15200–19400} = 36,86°


23100–2870

1-2 = arc tan { 13700–1520 } = 22,61°


19500–2310

2 - B = arc tan {15100–13700} = 18,03°


15200–1950

B – 1’ = arc tan {10650–15100} = 56,90°


12300–1520

1’ - C = arc tan {8600–10650} = 36,20°


9500–12300

 Sudut Luar

Δ1 = A - 1 - 1 – 2 = 36,86° - 22,61° = 14,25°

Δ2 = 1 - 2 - 2 – B = 22,61° - 14,25° = 8,36°

Δ3 = 2 - B - B - 1’ = 14,25° - 56,90° = 42,65°

Δ4 = B – 1’ – 1’ – C = 56,90° - 36,20° = 20,7°

PERENCANAAN PERKERASAN JALAN 2023 | 5


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN ALINYEMEN

HORIZONTAL

PERENCANAAN PERKERASAN JALAN 2023 | 6


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN ALINYEMEN HORIZONTAL

1. Titik 1 ( Lengkung Full Circle)


 Klasifikasi Jalan : Kolektor Primer (jalan antar kota)
 Jalur : 2 x 3,25 m
 Kecepatan Rencana (VR) : 70 km/jam
 Sudut Luar (Δ1) : Titik 1 = 14,25°
 emaks : 10% = 0,1 (Antar kota)
 syarat : e ≤ 6,0%

Perhitungan

Direncanakan Alinyemen Full Circle

 fm = −0,00065 𝑥 𝑉R + 0,192

= −0,00065 𝑥 70 + 0,192

= 0,1465

PERENCANAAN PERKERASAN JALAN 2023 | 7


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

V R2
 RMin =
127 x (eMax +fm)

702
=
127 x (0,1+0,147)

= 156,20 m

PERENCANAAN PERKERASAN JALAN 2023 | 8


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Tabel 2.1 Panjang lengkung peralihan (Ls) minimum dan super elevasi (e), yang dibutuhkan
untuk jalan antar kota.

Penyelesaian :
e <6%
e = 0,055% ; Rc = 477 Ls = 60m
1
 Tc = Rc x tan Δ1
2

= 477 x tan 1 𝑥 14,25


2

= 59,31 m
1
 Ec = Tc x tan Δ1
4

= 59,31 x tan 1 𝑥 14,25


4

= 3,69 m

Δ1 X π x Rc
 Lc =
180°
14,25 x 3,14 x 477
= = 118,57 𝑚
180

PERENCANAAN PERKERASAN JALAN 2023 | 9


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Grafik 2.2 Diagram koefisien Gesekan Memanjang Jalan (fp)

Fp = 0,314

VR2
 Jh = 0,694 𝑥 𝑉R + 0,004 𝑥
fp

702
= 0,694 𝑥 70 + 0,004 𝑥
0,314

= 111,00 m

Syarat untuk persamaan rumus E , Jh (111,00m) < Lc (118,57m)

90° x Jh
 E = 𝑅𝑐 𝑥 { 1 − 𝐶𝑜𝑠 ( )}
π x Rc

90° x 111,00
= 477 𝑥 {1 − 𝐶𝑜𝑠 ( )}
3,14 x 477

= 3,22 m

PERENCANAAN PERKERASAN JALAN 2023 | 10


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

2. Titik 2 (Lengkung Spiral – Circle – Spiral)


 Klasifikasi Jalan : Kolektor Primer (jalan antar kota)
 Jalur : 2 x 3,25 m
 Kecepatan Rencana (VR) : 70 km/jam
 Sudut Luar (Δ1) : Titik 2 = 8,36°
 emaks : 10% = 0,1 (Antar kota)
 syarat : e ≤ 6,0%

Perhitungan

Direncanakan Alinyemen Lengkung Spiral – Circle – Spiral

 fm = −0,00065 𝑥 𝑉R + 0,192

= −0,00065 𝑥 70 + 0,192

= 0,1465

PERENCANAAN PERKERASAN JALAN 2023 | 11


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

V R2
 RMin =
127 x (eMax +fm)

702
=
127 x (0,1+0,147)

= 156,20 m

PERENCANAAN PERKERASAN JALAN 2023 | 12


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Tabel 2.1 Panjang lengkung peralihan (Ls) minimum dan super elevasi (e), yang dibutuhkan
untuk jalan antar kota.

Penyelesaian :
e <5%
e = 0,055 = 0,6% ; Rc = 477 Ls = 60 m
 90 x Ls
Ꝋs =
π x Rc
90 x 60
=
3,14 x 477

= 3,60°
 Δc = Δ – 2 x Ꝋs

= 8,36 – 2 x 3,60°

= 1,16°

 Δc X π x Rc
Lc =
180°

1,16 X 3,14 x 477


= = 9,65 𝑚
180°

PERENCANAAN PERKERASAN JALAN 2023 | 13


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

 Lt = Lc + 2 x Ls

= 9,65+ 2 x 60

= 129,65 m

2
 P = Ls — 𝑅𝑐 𝑥 [1 − 𝐶𝑜𝑠 (Ꝋ 𝑠)]
6 x Rc
602
= — 477 𝑥 [1 − 𝐶𝑜𝑠 (3,6)]
6 x 477

= 0,316 m
Ls3
 k = 𝐿𝑠 − — 𝑅𝑐 𝑥 𝑆𝑖𝑛 (Ꝋ 𝑠)
40 x Rc2
603
= 60 − — 477 𝑥 𝑆𝑖𝑛 (3,6)
40 x 4772

= 30,04 m
1
 Ts = (Rc + P) x Tan ( Δ2 ) + k
2

= (477 + 0,316) x Tan (1 x 8,36 ) + 30,04


2

= 64,92 m

Es = Cos (1Δ ) – Rc
Rc+P

477 ,316
= 1 - 477
Cos ( X 8,36)
2

= 1,58 m

PERENCANAAN PERKERASAN JALAN 2023 | 14


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Grafik 2.2 Diagram koefisien Gesekan Memanjang Jalan (fp)

 Fp = 0,314
VR2
 Jh = 0,694 𝑥 𝑉R + 0,004 𝑥
fp

702
= 0,694 𝑥 70 + 0,004 𝑥
0,314

= 111,00 m

Syarat untuk persamaan rumus E , Jh (111,00 m) < Lt (129,65 m)

90° x Jh
 E = 𝑅𝑐 𝑥 { 1 − 𝐶𝑜𝑠 ( )}
π x Rc

90° x 111,00
= 477 𝑥 {1 − 𝐶𝑜𝑠 ( })
3,14 x 477

= 3,22 𝑚

PERENCANAAN PERKERASAN JALAN 2023 | 15


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

3. Titik 3 (Full Circle)


 Klasifikasi Jalan : Kolektor Primer (jalan antar kota)
 Jalur : 2 x 3,25 m
 Kecepatan Rencana (VR) : 70 km/jam
 Sudut Luar (Δ1) : Titik 3 = 42,65°
 emaks : 10% = 0,1 (Antar kota)
 syarat : e ≤ 6,0%

Perhitungan

Direncanakan Alinyemen Full Circle

 fm = −0,00065 𝑥 𝑉R + 0,192

= −0,00065 𝑥 70 + 0,192

= 0,1465

PERENCANAAN PERKERASAN JALAN 2023 | 16


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

V R2
 RMin =
127 x (eMax +fm)

702
=
127 x (0,1+0,147)

= 156,20 m

Tabel 2.1 Panjang lengkung peralihan (Ls) minimum dan super elevasi (e), yang dibutuhkan
untuk jalan antar kota.

PERENCANAAN PERKERASAN JALAN 2023 | 17


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Penyelesaian :
e <5%
e = 0,055 = 0,6% ; Rc = 477 Ls = 60m
1
 Tc = Rc x tan Δ3
2

= 477 x tan 1 𝑥 42,65


2

= 186,21 m
1
 Ec = Tc x tan Δ3
4

= 186,21 x tan 1 𝑥 42,65


4

= 35,05 m

Δc X π x Rc
 Lc =
180°

42,65 x 3,14 x 477


= = 354,89 𝑚
180

PERENCANAAN PERKERASAN JALAN 2023 | 18


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Grafik 3.3 Diagram koefisien Gesekan Memanjang Jalan (fp)

 Fp = 0,314
VR2
 Jh = 0,694 𝑥 𝑉R + 0,004 𝑥
fp

702
= 0,694 𝑥 70 + 0,004 𝑥
0,314

= 111,00 m

Syarat untuk persamaan rumus E , Jh (111,00m) < Lt (354,89m)

90° x Jh
 E = 𝑅𝑐 𝑥 { 1 − 𝐶𝑜𝑠 ( )}
π x Rc

90° x 111,00
= 477 𝑥 {1 − 𝐶𝑜𝑠 ( })
3,14 x 477

= 3,22 𝑚

PERENCANAAN PERKERASAN JALAN 2023 | 19


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

4. Titik 4 ( Lengkung Full Circle)


 Klasifikasi Jalan : Kolektor Primer (jalan antar kota)
 Jalur : 2 x 3,25 m
 Kecepatan Rencana (VR) : 70 km/jam
 Sudut Luar (Δ1) : Titik 1 = 20,7°
 emaks : 10% = 0,1 (Antar kota)
 syarat : e ≤ 6,0%

Perhitungan

Direncanakan Alinyemen Full Circle

 fm = −0,00065 𝑥 𝑉R + 0,192

= −0,00065 𝑥 70 + 0,192

= 0,1465

PERENCANAAN PERKERASAN JALAN 2023 | 20


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

V R2
 RMin =
127 x (eMax +fm)

702
=
127 x (0,1+0,147)

= 156,20 m

PERENCANAAN PERKERASAN JALAN 2023 | 21


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Tabel 2.1 Panjang lengkung peralihan (Ls) minimum dan super elevasi (e), yang dibutuhkan
untuk jalan antar kota.

Penyelesaian :
e <6%
e = 0,055 = 0,6% ; Rc = 477 Ls = 60m
1
 Tc = Rc x tan Δ4
2

= 477 x tan 1 𝑥 20,7


2

= 86,16 m
1
 Ec = Tc x tan Δ4
4

= 86,16 x tan 1 𝑥 20,7


4

= 7,78 m

Δ4 X π x Rc
 Lc =
180°
20,7 x 3,14 x 477
= = 172,24 𝑚
180

PERENCANAAN PERKERASAN JALAN 2023 | 22


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Grafik 2.2 Diagram koefisien Gesekan Memanjang Jalan (fp)

Fp = 0,314

VR2
 Jh = 0,694 𝑥 𝑉R + 0,004 𝑥
fp

702
= 0,694 𝑥 70 + 0,004 𝑥
0,314

= 111,00 m

Syarat untuk persamaan rumus E , Jh (111,00m) < Lc (172,24m)

90° x Jh
 E = 𝑅𝑐 𝑥 { 1 − 𝐶𝑜𝑠 ( )}
π x Rc

90° x 111,00
= 477 𝑥 {1 − 𝐶𝑜𝑠 ( })
3,14 x 477

= 3,22 m

PERENCANAAN PERKERASAN JALAN 2023 | 23


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PELEBARAN
PERKERASAN PADA TIKUNGAN

PERENCANAAN PERKERASAN JALAN 2023 | 24


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PELEBARAN PERKERASAN PADA TIKUNGAN


RC = 477 m

 Vr : 70 kmÚjam

 R : 477 m
 Lebar Perkerasan Perjalur : 3,25 m
 Jumlah Jalur (N) : 2 Lajur
 Lebar Perkerasan Jalur Lurus (Bn) : 6,5 m
 Lebar Kendaraan Rencana (µ) : 2,6 m
 Jarak Gandar Kendaraan (L) : 7,6 m
 Tonjolan Depan Kendaraan (A) : 2,1 m

Penyelesaian :

Vr
 Z = 0,105 𝑥
√R
70
= 0,105 𝑥 = 0,336 m
√477
 U = µ + R - √𝑅2 − 𝐿2
= 2,6 + 477 - √4772 − 72
= 2,65 m
 Fa = √𝑅2 + 𝐴 (2𝐿 + 𝐴) – R
=√4772 + 2,1 (7,6 + 2,1) – 477
= 0,021 m
 Wc = N (µ + C) + (N – 1) x Fa + Z
= 2 ( 2,6 +1) + (2 – 1) x 0,021 + 0,336
= 7,557 m
 W = wc – Bn
= 7,557 – 6,5
= 1,057 m

Diambil nilai w sebesar 1,00 m

PERENCANAAN PERKERASAN JALAN 2023 | 25


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN

GALIAN & TIMBUNAN

PERENCANAAN PERKERASAN JALAN 2023 | 26


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
PERHITUNGAN GALIAN DAN TIMBUNAN

Contoh Perhitungan Galian dan Timbunan

Keterangan:
1. Garis Hijau: Kontur Asli
2. Garis Merah : Galian
3. Garis Kuning : Timbunan

GALIAN
1 66 3 1 198
2 66 3 0,5 99

TIMBUNAN
1 28 3 1 84
2 10 1 1 10

Penyelesaian:

F. Lepas = 1
F. Padat = 1

Volume Galian Tanah Lepas = Volume Galian x F.Lepas


= 297 x 1
= 297 m³
Volume Timbunan Tanah
Lepas = Volume Timbunan x F.Lepas
F. Padat
= 94
x 1
1
= 94 m³
Selisih Volume Tanah = V. Galian - V.Timbunan
= 297 - 94
= 203 m³

PERENCANAAN PERKERASAN JALAN 2023 | 27


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN ALINYEMEN
VERTIKAL

PERENCANAAN PERKERASAN JALAN 2023 | 28


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
PERENCANAAN ALINYEMEN VERTIKAL
Lengkung Vertikal 1 Cekung

g0 =0%
g1 = 9,00–6,00 𝑥100% = 4,54%
66

A = {g1 – g0 = {4,54 – 0} = 4,54%

Syarat Kenyamanan

Jarak Pandang Henti


Vr = 70 km/jam
Interpolasi :
H1 = 75
H2 = 120
B1 = 80 – 70 = 10
B2 = 80 – 60 = 20
X = H1 – B1/ B2 x (H1 – H2)
X = 75 – 10/ 20 x (75 – 120)
X = 97,5 m

PERENCANAAN PERKERASAN JALAN 2023 | 29


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
Jh = 97,5 m
A.jh
2 4,54.97,52
Jh < Lv, Lv = = = 108,95 m (diterima)
100(√2.h1+(√2.h2 )) 100(√2.1,05+(√2.0,15 ))^2
2
100(√2.h1+(√2.h2 ) )
Jh > Lv, Lv = 2𝑥𝐽ℎ −
A
100(√2.1,05+√2.0,15 )^2
= 2𝑥97,5 − = 107 m (Tidak diterima)
4,54

Keluwesan Bentuk
Lv = 0,6 x VR
= 0,6 x 70
= 42 m
Syarat Drainase
Lv = 40 x A
= 40 x 4,54
= 181,6 m
Diambil Lv = 181,6 m

A x Lv
EV =
800
4,54 x 181,6
=
800

= 1,03 m
Elevasi dan Stasioning
PVI = STA + 117
Elv. +9
PLV = STA = STA PVI – (1 𝑥 𝑉𝑟)
2

= + 117 – (1 𝑥 70)
2

= +82
Elevasi = Elevasi PVI + g0. (1 𝑥 𝑉𝑟)
2

= +9 + 0% (1 𝑥 70)
2

= +9
S : STA = STA PV1 = +117

PERENCANAAN PERKERASAN JALAN 2023 | 30


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
Elevasi = Elevasi PV1 + EV
= +9 + 1,03
= +10,03
PTV : STA = STA PV1 + (1 𝑥 𝑉𝑟)
2

= 82 + (1 𝑥 70)
2

= +117
Elevasi = Elevasi PV1 + g (1 𝑥 𝑉𝑟)
2

= +9 + 4,54% (1 𝑥 70)
2

= +10,58

Lengkung Vertikal 2 Cembung

g1 = 9,00–6,00 𝑥100% = 4,54%


66

g2 = 0%
A = {g1 – g0} = {4,54 – 0} = 4,54%
Syarat Kenyamanan

Vr = 70 km/jam

PERENCANAAN PERKERASAN JALAN 2023 | 31


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
Interpolasi :
H1 = 75
H2 = 120
B1 = 80 – 70 = 10
B2 = 80 – 60 = 20
X = H1 – B1/ B2 x (H1 – H2)
X = 75 – 10/ 20 x (75 – 120)
X = 97,5 m
Jh = 97,5 m
2 4,54.97,52
Jh < Lv, Lv = A.jh = = 108,95 m (diterima)
100(√2.h1+(√2.h2 )) 100(√2.1,05+(√2.0,15 ))^2
2
100(√2.h1+(√2.h2 ) )
Jh > Lv, Lv = 2𝑥𝐽ℎ −
A
100(√2.1,05+√2.0,15 )^2
= 2𝑥97,5 − = 107 m (Tidak diterima)
4,54

Keluwesan Bentuk
Lv = 0,6 x VR
= 0,6 x 70
= 42 m
Syarat Drainase
Lv = 40 x A
= 40 x 4,54
= 181,6 m
Diambil Lv = 181,6 m
A x Lv
EV =
800
4,54 x 181,6
=
800

= 1,03 m
Elevasi dan Stasioning
PVI = STA + 143
Elv. +9
PLV = STA = STA PVI – (1 𝑥 𝑉𝑟)
2

PERENCANAAN PERKERASAN JALAN 2023 | 32


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
= + 143 – (1 𝑥 70)
2

= +108
Elevasi = Elevasi PVI + g1. (1 𝑥 𝑉𝑟)
2

= +9 + 4,54% (1 𝑥 70)
2

= +10,58
S : STA = STA PV1 = +108
Elevasi = Elevasi PV1 + EV
= +9 + 1,03
= +10,03
PTV : STA = STA PV1 + (1 𝑥 𝑉𝑟)
2

= 108 + (1 𝑥 70)
2

= +143
Elevasi = Elevasi PV1 + g0 (1 𝑥 𝑉𝑟)
2

= +9 + 0% (1 𝑥 70)
2

= +9

PERENCANAAN PERKERASAN JALAN 2023 | 33


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN DATA

LALU LINTAS

PERENCANAAN PERKERASAN JALAN 2023 | 34


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
PERHITUNGAN DATA LALU LINTAS

 Data Lalu Lintas


a. Jalan di buka tahun 2024
Umur rancana : (5 tahun)
b. Perkembangan lalu lintas selama umur rencana 2% lebih dari masa kontruksi
c. Data arus kendaraan tahun (kendaraan / hari / 2 jalur)
Jenis Kendaraan Tahun 2017 Tahun 2020
Kendaraan ringan 2 ton (1+1) 2584 2655
Bus 8 ton (3+5) 334 362
Truk 2 as 9 ton (3+6) 285 301
Truk 2 as 12 ton (4+8) 211 242
Truk 3 as 21 ton (5+8,8) 108 124

Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2) 102 115

Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6)) 63 98


Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)) 31 46

a. Perkembangan Lalu lintas pada masa kontruksi sebagai berikut :


 Mobil Penumpang 2 ton (1+1)
2655 )1/3 -1)x100% = 0,90%
= ((
2584

 Bus 8 ton (3+5)


362 1/3
= (( ) -1)x100% = 2,71%
334

 Truk 2 as 9 ton (3+6)


= (( )1/3 -1)x100%
301 = 1,83%
285

 Truk 2 as 12 ton (4+8)


= (( )1/3 -1)x100%
242 = 4,67%
211

 Truk 3 as 21 ton (5+8,8)


= (( )1/3 -1)x100%
124 = 4,71%
108

 Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2)


115 1/3
= (( ))
102
-1)x100% = 4,07%

PERENCANAAN PERKERASAN JALAN 2023 | 35


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
 Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6))
= ((98))1/3 -1)x100% = 15,86%
63

 Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)


46
= (( ))1/3
31
-1)x100% = 14,05%
b. LHR dengan n = 3 tahun (2020-2017):
 Mobil Penumpang 2 ton (1+1)
= 2655(1+0,90%) 3 = 2727,33 kendaraan
 Bus 8 ton (3+5)
= 362(1+2,71%) 3 = 392,23 kendaraan
 Truk 2 as 9 ton (3+6)
3
= 301(1+1,83%) = 317,82 kendaraan
 Truk 2 as 12 ton (4+8)
= 242(1+4,67%) 3 = 277,51 kendaraan
 Truk 3 as 21 ton (5+8,8)
= 124(1+4,71%) 3 = 142,35 kendaraan
 Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2)
3
= 115(1+4,07%) = 129,62 kendaraan
 Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6))
3
= 98(1+15,86%) = 152,41 kendaraan
 Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)
3
= 46(1+14,05%) = 68,24 kendaraan
c. LHR pada tahun ke 5 dengan i = 2% lebih dari masa kontruksi (𝐿𝐻𝑅2029):
 Mobil Penumpang 2 ton (1+1)
= 2727,33 (1+2,9%) 5 = 3146,40 kendaraan
 Bus 8 ton (3+5)
= 392,23 (1+4,71%) 5= 493,72 kendaraan
 Truk 2 as 9 ton (3+6)
5
= 317,82 (1+3,83%) = 383,53 kendaraan

PERENCANAAN PERKERASAN JALAN 2023 | 36


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
 Truk 2 as 12 ton (4+8)
= 277,51 (1+6,67%) 5= 383,26 kendaraan
 Truk 3 as 21 ton (5+8,8)
= 142,35 (1+6,71%) 5= 196,96 kendaraan
 Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2)
= 129,62 (1+6,07%) 5= 174,03 kendaraan
 Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6))
= 152,41 (1+17,86%) 5= 346,61 kendaraan
 Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)
= 68,24 (1+16,05%) 5= 143,64 kendaraan

PERENCANAAN PERKERASAN JALAN 2023 | 37


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
a. Angka Ekivalen ( E ) = Tabel
 Mobil Penumpang 2 ton (1+1)
= 0,0002 + 0,0002 = 0,0004
 Bus 8 ton (3+5)
= 0,0183 + 0,1410 = 0,1593
 Truk 2 as 9 ton (3+6)

= 0,0183 + 0,2923 = 0,3106

 Truk 2 as 12 ton (4+8)

= 0,0577 + 0,923 = 0,35

 Truk 3 as 21 ton (5+8,8)

= 0,1410 + 0,8476 = 0,9886

 Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2)


= 0,1410 + 0,2175 . 0,2175 + 0,2175 . 0,2175 = 0,2356
 Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6))
= 0,0577 + 0,9238 + 0,2923 + 0,2923 = 1,5661
 Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)
= 0,1410 + 0,8476 + 0,2923 + 0,2923 = 1,5732

PERENCANAAN PERKERASAN JALAN 2023 | 38


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
b. Perhitungan Lintas ekivalen permulaan (LEP) = C x LHR x E (5 tahun)
 Mobil Penumpang 2 ton (1+1)
= 0,5 x 2727,33 x 0,0004 = 0,54
 Bus 8 ton (3+5)
= 0,5 x 392,23 x 0,1593 = 31,24
 Truk 2 as 9 ton (3+6)
= 0,5 x 317,82 x 0,3106 = 49,35
 Truk 2 as 12 ton (4+8)
= 0,5 x 277,51 x 0,35 = 48,56
 Truk 3 as 21 ton (5+8,8)
= 0,5 x 142,35 x 0,9886 = 70,36
 Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2)
= 0,5 x 129,62 x 0,2356 = 15,26
 Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6))
= 0,5 x 152,41 x 1,5661 = 119,34
 Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)
= 0,5 x 68,24 x 1,5732 = 53,67
TOTAL = 388,32

c. Perhitungan Lintas ekivalen permulaan (LEP) = C x LHR x E (5 tahun)


 Mobil Penumpang 2 ton (1+1)
= 0,5 x 3146,40 x 0,0004 = 0,62
 Bus 8 ton (3+5)
= 0,5 x 493,72 x 0,1593 = 39,32
 Truk 2 as 9 ton (3+6)
= 0,5 x 383,53 x 0,3106 = 59,56
 Truk 2 as 12 ton (4+8)
= 0,5 x 383,26 x 0,35 = 67,07
 Truk 3 as 21 ton (5+8,8)
= 0,5 x 196,96 x 0,9886 = 97,35

PERENCANAAN PERKERASAN JALAN 2023 | 39


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
 Truk tempel/semi trailer truck, 5 as 31 ton (5+61/2. 61/2+ 61/2. 61/2)
= 0,5 x 174,03 x 0,2356 = 20,50
 Truk gandeng/trailer truck, 2 as + 2 as 24 ton (4+8+(6+6))
= 0,5 x 346,61 x 1,5661 = 271,41
 Truk gandeng/trailer truck, 3 as + 2 as 33 ton (5+8,8+(6+6)
= 0,5 x 143,64 x 1,5732 = 112,98
TOTAL = 668,81

Perhitungan Lintas Ekivalen tengah

LET = ½ (LEP + LEA)

LET = ½(388,32 + 668,81)

= 538,56

LER = LET X Fp, dimana Fp = UR


10

LER = LET x UR
10

= 538,56 x 5
10

= 269,28

PERENCANAAN PERKERASAN JALAN 2023 | 40


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN CBR

PERENCANAAN PERKERASAN JALAN 2023 | 41


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
PERHITUNGAN CBR
Harga CBR :
10 8 8 9 12 11 11 9

Perhitungan secara Analitis


Jumlah titik pengamatan adalah 8 , maka R = 2,96 (tabel)
CBR max – CBR min
CBR Segmen = CBR rata-rata - ( )
R
78 12–8
= ( )- ( )
8 2,96

= 8,4%

Nilai Jumlah Nilai CBR yang Persen (%) nilai CBR yang
CBR sama atau lebih besar sama atau lebih besar
8 8 8/8x100% = 100%
9 6 6/8x100% = 75%
10 5 5/8x100% = 62,5%
11 3 3/8x100% = 37,5%
12 2 2/8x100% = 25%

PERENCANAAN PERKERASAN JALAN 2023 | 42


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Dari Grafik diperoleh nilai CBR adalah

Maka :

Nilai CBR (analitis) = 8,4%

Nilai CBR (Grafis) = 7,3%

Dengan rata-rata = 7,85%

Dengan nilai CBR 7,85% didapat DDT = 5,4%

PERENCANAAN PERKERASAN JALAN 2023 | 43


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN LAPISAN

PERKERASAN

PERENCANAAN PERKERASAN JALAN 2023 | 44


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
PERHITUNGAN LAPISAN PERKERASAN

Menghitung nilai R (Factor Regional)

Kendaraan Berat = ZKendaraan Berat 𝑥100%


ZKendaraan

362+301+242+124+115+98+4
=
2655 + ZKendaraan Berat
𝑥100%

1288
= 𝑥100%
2655 + 1288

= 1288 𝑥100%
3943

= 32,66% > 30%

Curah hujan = 950 mm/tahun

Kelandaian I (6%)

Dari table diatas nilai FR = 2 – 2,5

Dipakai = 2,5

Menentukan nilai Ipo(indeks Permukaan Awal)

Nilai Ipo ditentukan dari bahan perkerasan yang digunakan, dimana bahan perkerasan yang
digunakan adalah laston. Karena merupakan jalan baru, sehingga nilai Ipo > 3,9 – 3,5

PERENCANAAN PERKERASAN JALAN 2023 | 45


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Menetukan nilai Ipt (indeks Permukaan Akhir)

Klasifikasi jalan = Kolektor Primer (jalan antar kota)

Nilai LER5 = 269,28 x 2,5 = 673,2 Nilai Ipt5 = 2,0 (Rentang 2,0 – 2,5)

PERENCANAAN PERKERASAN JALAN 2023 | 46


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
Nomogram 4 untuk IP = > 3,9 – 3,5 , LER5 = 269,28

Dari Grafik diatas nilai ITP = 8,4 dan ITP = 10

PERENCANAAN PERKERASAN JALAN 2023 | 47


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

Koefisien kekuatan Relatif

Surface Coarse = Laston (MS 744) 𝑎1= 0,40

Base Coarse = Laston (MS 590) 𝑎2= 0,28

Sub Base Coarse = Sirtu Kelas B 𝑎3= 0,12

Menentukan Tebal Perkerasan

UR = 5 tahun

ITP7= a1.D1 + a2.D2 + a3.D3 Susunan Perkerasan 5 tahun

8,4 = 0,40D1 + 0,28 . 10 + 0,12 . 10 Laston (MS 744) = 10 cm

8,4 = 0,40D1 + 4 Laston (MS 590) = 10 cm

D1 = 10 Sirtu Klas B = 10 cm

PERENCANAAN PERKERASAN JALAN 2023 | 48


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 49


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

ANALISA SARINGAN

PERENCANAAN PERKERASAN JALAN 2023 | 50


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
ANALISAN SARINGAN

a. Fraksi Agregat Sub Base Coarse


Presentase Berat Agregat yang Lolos Ayakan
No Agregat
2'' 1'' 3/4 No. 4 No. 10 No. 40 No. 200
1 I 100 98 91 83,2 53 29 16,9
2 II 100 95 67 33,8 21,1 12,1 3,4
3 III 100 97 86,8 39 25,4 7,9 2,9

No Ayakan 2'' 1'' 3/4 No. 4 No. 10 No. 40 No. 200


Gradasi 80 Maks 15 Maks

Saringan Presentase Berat Agregat yang Lolos Ayakan


Proporsi
Gradasi 2'' 1'' 3/4 No. 4 No. 10 No. 40 No. 200
Fraksi I 13,8 13,8 13,524 12,30684 10,23929 5,426824 1,573779 0,265969
Fraksi II 86 86 81,7 54,739 18,50178 3,903876 0,472369 0,016061
Fraksi III 0 0 0 0 0 0 0 0
Campuran 99,8 95,224 67,04584 28,74107 9,3307 2,046148 0,282029

PERENCANAAN PERKERASAN JALAN 2023 | 51


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 52


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 53


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
b. Fraksi Agregat Base Coarse

Presentase Berat Agregat yang Lolos Ayakan


No Agregat
2'' 1'' 3/8 No. 4 No. 10 No. 40 No. 200
1 I 100 67 41 30,5 17,5 11 3,1
2 II 100 49,5 32,5 20,1 11,2 5 2,5
3 III 100 70 36,9 19,9 10,7 6,2 3,8

No Ayakan 2'' 1'' 3/4 No. 4 No. 10 No. 40 No. 200


Gradasi 60-100 40-60 25-50 15-30 Aug-15

Saraingan
Presentase Berat Agregat yang Lolos Ayakan
Gradasi Proporsi
2'' 1'' 0,75 No. 4 No. 10 No. 40 No. 200
Fraksi I 21,24 21,24 14,230 5,834628 1,77956 0,31142 0,03425 0,00106
Fraksi II 78,76 78,76 38,986 12,67051 2,54677 0,28523 0,01426 0,00035
Fraksi III 0 0 0 0 0 0 0 0
Campuran 100 53,217 18,50514 4,32633 0,59666 0,04851 0,00141

PERENCANAAN PERKERASAN JALAN 2023 | 54


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 55


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 56


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
c. Fraksi Agregat Surface Coarse

Presentase Berat Agregat yang Lolos Ayakan


No Agregat
3/4 3/8 No. 4 No. 8 No. 30 No. 50 No. 200
1 I 100 75,5 67,5 35 23 6 3
2 II 95 88 63,5 42,5 25,5 14,5 1,5
3 III 98,7 90,5 82 68 44 25 9

No Ayakan 2'' 1'' 3/4 No. 4 No. 10 No. 40 No. 200


Gradasi 95-100 57-79 38-60 27-47 15-28 Aug-20 Aug-22
`
Saraingan Propors
Presentase Berat Agregat yang Lolos Ayakan
Gradasi i
2'' 1'' 0,75 No. 4 No. 10 No. 40 No. 200
Fraksi I 2,42 2,42 1,8271 1,233292 0,43165 0,09928 0,00595 0,00017
Fraksi II 97,58 92,701 81,5768 51,80131 22,0155 5,61396 0,81402 0,01221
Fraksi III 72 71,064 64,3129 52,73659 35,8608 15,7787 3,94469 0,35502
Campuran 166,18 147,716 105,7712 58,3081 21,4920 4,76467 0,36741

PERENCANAAN PERKERASAN JALAN 2023 | 57


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 58


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | 59


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERHITUNGAN
KEBUTUHAN BAHAN

PERENCANAAN PERKERASAN JALAN 2023 | 60


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
PERHITUNGAN KEBUTUHAN BAHAN

a. Panjang jalan : 2850 m


b. Agregat Sub Base : 2,42 ton/ 𝑚3
c. Agregat Base Coarse : 2,60 ton/ 𝑚3
d. Agregat Surface and Filler : 2,61 ton/𝑚3

 Agregat Sub Base


Tebal Lapisan : 10 cm
Kebutuhan bahan sepanjang jalan : 2850 x 0,1 m x (2 x 3,25 m) x 2,42 ton/𝑚3
: 4483,05 ton
 Agregat Base Coarse
Tebal Lapisan : 10 cm
Kebutuhan bahan sepanjang jalan : 2850 x 0,1 m x (2 x 3,25 m) x 2,60 ton/𝑚3
: 4816,5 ton
 Agregat Surface UR 7 Tahun
Tebal Lapisan : 10 cm
Kebutuhan bahan sepanjang jalan : 2850 x 0,1 m x (2 x 3,25 m) x 2,61 ton/𝑚3
: 4835,02 ton
 Kadar Aspal : 7,5 % x (4835,02) ton
: 362,62 ton

PERENCANAAN PERKERASAN JALAN 2023 | 61


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

KESIMPULAN
&
SARAN

PERENCANAAN PERKERASAN JALAN 2023 | 62


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
KESIMPULAN

1. Jalan yang direncanakan merupakan jalan Kolektor Primer (jalan antar kota) Dengan lebar 2
x 3,25m, dan dengan kecepatan rencana 70 km/jam.
a. Pada PI 1 di rencanakan jenis tikungan full circle dengan jari-jari lengkung 477m , sudut
luar PI 1 sebesar 14,25°
b. Pada PI 2 di rencanakan jenis tikungan spiral-circle-spiral dengan jari- jari lengkung 477m
, sudut luar PI 2 sebesar 8,36°
c. Pada PI 3 di rencanakan jenis tikungan full circle dengan jari-jari lengkung 409m , sudut
luar PI 3 sebesar 42,65°
d. Pada PI 4 di rencanakan jenis tikungan full circle dengan jari-jari lengkung 409m , sudut
luar PI 4 sebesar 20,7°
2. Pada alinyemen vertical jalan ini terdapat 2PVI. Untuk mendapatkan keseimbangan antara
galian dan timbunan
3. Perkerasan jalan ini menggunakan jenis perkerasan lentur berdasarkan volume LHR yang ada
dengan :
a. Jenis Bahan yang dipakai adalah :
 Surface Coarse : Laston MS 744
 Base Coarse : Laston MS 590
 Sub Base Coarse : Sirtu Kelas B
b. Dengan perhitungan didapat dimensi tebal dari masing-masing lapisan
 Surface Coarse : 10 cm
 Base Coarse : 10 cm
 Sub Base Coarse : 10 cm

PERENCANAAN PERKERASAN JALAN 2023 | 63


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
SARAN

1. Perencanaan geometrik jalan sebaiknya dilakukan berdasarkan data hasil survey langsung di
lapangan agar diperoleh perencanaan yang optimal.
2. Perencanaan perkerasan jalan sebaiknya menggunakan data selengkap mungkin baik data
lalu lintas maupun data lainnya agar pembangunan dapat berjalan dengan optimal.
3. Bagi tenaga kerja harus mendapatkan asuransi kecelakaan diri dan jaminan keselamatan dan
Kesehatan kerja mengingat pelaksanaan proyek adalah pekerjaan dengan resiko kecelakaan
yang tinggi.

PERENCANAAN PERKERASAN JALAN 2023 | 64


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

TUGAS BESAR
PERENCANAAN PERKERASAN JALAN

Disusun Oleh:

AZRIAL ILHAMA YUSTIEALDO (201910340311082)


IQBAL WAHYU RHOMADHANI (201910340311208)

JURUSAN TEKNIK SIPIL


FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH MALANG
2023

PERENCANAAN PERKERASAN JALAN 2023 | i


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
LEMBAR PENGESAHAN

TUGAS BESAR

PERENCANAAN PERKERASAN JALAN

Disusun oleh :

AZRIAL ILHAMA YUSTIEALDO (201910340311082)

IQBAL WAHYU RHOMADHANI (201910340311208)

Tugas Besar ini disusun sebagai salah satu syarat untuk mengikuti program Praktek Kerja
Nyata di Fakultas Teknik Jurusan Sipil Universitas Muhammadiyah Malang.

Laporan ini disetujui pada,

Hari :

Tanggal :

Tempat :

Mengetahui,

Dosen Pembimbing

Ir. Andi Syaiful Amal, MT.

PERENCANAAN PERKERASAN JALAN 2023 | ii


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
SOAL

PERENCANAAN PERKERASAN JALAN 2023 | iii


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | iv


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | v


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | vi


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
LEMBAR ASISTENSI

PERENCANAAN PERKERASAN JALAN 2023 | vii


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

PERENCANAAN PERKERASAN JALAN 2023 | viii


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208
KATA PENGANTAR
Dengan memanjatkan puji syukur kehadirat Allah Yang Maha Kuasa yang telah
melimpahkan rahmat dan hidayah-Nya, sehingga kami dapat menyelesaikan Laporan Tugas
Besar Perkerasan Jalan Raya ini dengan baik.

Tugas akhir ini disusun sebagai syarat untuk mengikuti program Praktek Kerja Nyata di
Fakultas Teknik Jurusan Sipil pada Universitas Muhammadiyah Malang.

Pada kesempatan ini penyusun menyampaikan terimakasih kepada :

1. Bapak Ir. Andi Syaiful Amal, MT. selaku dosen pembimbing.


2. Bapak Ir. Alik Ansyori Alamsyah, MT. selaku dosen pengampu mata kuliah
Perencanaan Perkerasan Jalan.
3. Rekan-rekan mahasiswa yang telah banyak membantu hingga terselesaikannya
laporan tugas besar ini.

Akhirnya penyusun berharap semoga laporan ini dapat berguna bagi penyusun pada
khususnya dan pembaca pada umumnya. Penyusun berharap akan adanya kritik, saran dan
masukan yang bersifat membangun demi kesempurnaan laporan praktikum ini ini.

Malang,

AZRIAL ILHAMA Y IQBAL WAHYU R


(201910340311082) (201910340311208)

PERENCANAAN PERKERASAN JALAN 2023 | ix


AZRIAL ILHAMA Y 201910340311082
IQBAL WAHYU R 201910340311208

DAFTAR ISI

LEMBAR PENGESAHAN.................................................................................. ii

SOAL ................................................................................................................... iii

LEMBAR ASISTENSI ........................................................................................ vii

KATA PENGANTAR ......................................................................................... ix

DAFTAR ISI ........................................................................................................ xii

PERHITUNGAN GEOMETRIK JALAN .......................................................... 4

A. Perhitungan Jarak ................................................................................... 1


B. Perhitungan Sudut Azimut & Sudut Luar .............................................. 4
C. Perhitungan Alinyemen Horizontal......................................................... 6
D. Perencanaan Pelebaran Perkerasan Pada Tikungan ............................. 24
E. Perhitungan Galian & Timbunan ........................................................... 26
F. Perencanaan Alinyemen Vertikal ............................................................ 28

PERHITUNGAN TEBAL PERKERASAN JALAN .......................................... 34

A. Perhitungan Data Lalu Lintas ................................................................. 34


B. Perhitungan CBR..................................................................................... 41
C. Perhitungan Lapisan Perkerasan ............................................................ 44
D. Analisa Saringgan .................................................................................... 50
E. Perhitungan Kebutuhan Bahan............................................................... 60

KESIMPULAN & SARAN ................................................................................. 62