PT.

TRADECORP INDONESIA
PROSES LOADING, UNLOADING UNIT MODHOUSE & INSTALATION UNIT

MODHOUSE
AREA INSTALASI UNIT MODHOUSE
DOKUMEN & APD

1. PERMIT IZIN AREA KERJA

2. HELMET

3. SEPATU SAFETY

4. BODY HARNEST

5. SARUNG TANGGAN
PERALATAN YANG DIGUNAKAN UNTUK LOADING UNIT MODHOUSE

1 FORKLIFT 3 TON SAMPAI DENGAN 4 TON

2 HOOK

3 TAMBANG SLING / RANTAI

4 CROSBY SHAKLES

BALOK KAYU UKURAN 10X10 DENGAN PANJANG 1 METER


5 ASUMSI UNTUK PEMAKAIAN 8 PCS
PROSES LOADING UNIT MODHOUSE
1. SIAPKAN KORDINASI PERMIT & PROSES BARRICADE LINE UNTUK
PROSES AREA YANG AKAN DILAKUKAN UNTUK BEKERJA

2. UNTUK PROSES PERTAMA LAKUKAN PROSES PEMASANGAN HOOK


DENGAN CROSBY SHAKLES PADA TAMBANG SLING

3. UNTUK PROSES KEDUA LAKUKAN PEMASANGAN HOOK PADA POSISI


BOTTOM CONTAINER MODHOUSE

4. PROSES KETIGA KELUARKAN UNIT SECARA PERLAHAN DAN


DILAKUKAN SUPPORT DENGAN MENGUNAKAN BALOK KAYU UNTUK
MENSUPPORT UNIT AGAR STABIL
PROSES UNLOADING UNIT MODHOUSE
PERALATAN UNTUK PROSES INSTALASI UNIT

Try it yourself with these two simple “planets”:

1 MOBIL TRUCK CRANE

2 SLING BAJA /RANTAI

3 CROSBY SHACKLES / HOCK

UNTUK PROSESNYA SLING BAJA/ RANTAI DIMASUKAN KE DALAM


4 LUBANG CORNER CASTING DAN DI LOCK DENGAN CROSBY
SHACKLES / HOCK DAN PASTIKAN SUDAH TERKUNCI DENGAN AMAN
LALU DIARAHKAN KE POSISI YANG AKAN DI INSTAL
PROSES VIDEO INSTALASI MODHOUSE