3 QSHE/TQM/AE/P/011
JUKLAK
PROYEK PEMBANGUNAN TERMINAL PETIKEMAS KALIBARU UTARA TAHAP 1
PELABUHAN TANJUNG PRIOK
Perubahan : 1. Pemancangan cluster bambu awalnya memakai Excavator Method, diganti dengan metode Ponton Template
2. Awalnya direncanakan penyelesaian Breakwater Type E terlebih dahulu kemudian dilakukan disposal material dredging , diganti
dengan memakai silt curtain terlebih dahulu baru melakukan disposal material dredging
3. Foto realisasi pelaksanaan
Disetujui oleh :
UNIT PM GM KDVO
PERSETUJUAN oleh
1. PROJECT DESCRIPTION
2. QUALITY PLAN
3. SAFETY PLAN
4. ENVIRONMENTAL PLAN
6. FINANCIAL PLANNING
7. MANAJEMEN RESIKO
DEVELOPMENT OF NORTH KALIBARU
CONTAINER TERMINAL PHASE I
PORT OF TANJUNG PRIOK
PROJECT MANAGEMENT ORGANIZATION
IPC
CLIENT
RHI DHV
SUPERVISOR
PT. PP
Main Contractor
PRECAST
E. BREAKWATER (5.750,8 M)
- Type : Rock Breakwater
- Soil Improvement : Cluster & Mattrass Bamboo
- Core Layer : Rock 50-70 kg ( 1.728.570 M3)
- Cover Layer : Rock 150 s/d 400 kg (454.043 M3)
- Armor : A-Jack System (79.593 Unit)
BREAKWATER
DREDGING WORK CT 1
PANGKALAN
PASIR
ADHIGUNA JETTY
AKSES BRIDGE
DKB
PRECAST YARD
PACIFIC PAINT
PRECAST YARD
VOLUME DOMINANT AWAL
No Item Satuan Jumlah
1 Bambu Batang 5,609,835
2 Batu m³ 2,182,613
834
c. Tiang pancang 500 mm Titik
4 Beton m³ 480,634
7 PVD m’ 19,162,680
2 Batu M3 2.837.396
7 PVD m’ 19,162,680
PROJECT LOCATION
Indonesia
Jakarta
PROJECT LAYOUT
SATELIT OVERVIEW
Pembangunan Terminal Peti Kemas Kalibaru Utara Tahap I Pelabuhan Tanjung Priok, merupakan pelabuhan New Priok
oleh PT. Pelabuhan Indonesia II (Persero) / IPC salah satu implementasi dari proyek strategis jangka panjang pembangunan
sektor transportasi Indonesia yang tertuang dalam Masterplan Percepatan dan Perluasan Pembangunan Ekonomi
Indonesia (MP3EI)
PROJECT LAYOUT
3D PERSPEKTIF VERSION
New Priok tahap pertama akan dibangun di atas lahan seluas ±392 ha dengan penambahan
kapasitas sebesar 4,5 juta TEUs peti kemas. New Priok tahap I juga dirancang dengan draft
hingga -22 meter at Low Water Spring (mLWS) sehingga kapal terbesar di dunia dapat bersandar
di New Priok
DEVELOPMENT OF NORTH KALIBARU
CONTAINER TERMINAL PHASE I
PORT OF TANJUNG PRIOK
QUALITY POLICY
1. Peduli keinginan dan kepuasan pelanggan
2. Peningkatan Kualitas yang berkesinambungan
3. Pendekatan Rekayasa Teknik maupun Bisnis
4. Pemanfaatan Teknologi Mutakhir
5. Profesionalisme SDM yang berwawasan Global
• Company Policy
• Quality Target
• Quality Plan
• ITP Revision • ITP
• Work Instruction Revision Plan
and/or Increasing
• Socialization • Certification
• Calibration
Improve Train • Mock Up/Show Unit
• Work Permit
• Sampling
Review Action • Documentation
• Quality Assessment
• Corrective & Preventive
• Quality Analysis
Monitoring
• Inspection
• Check List
FLOW
Company Policy CORRECTIVE & PREVENTIVE
ACTION
Quality Target
MANAGEMENT REVIEW
ITP
MEASURING
CUSTOMER CUSTOMER
AND
PROCUREMENT HAND-OVER
REQUIREMENTS SATISFACTION
CONSTRUCTION SERVICE
ANALYSIS DATA
MONITORING SATISFACTION MEASUREMENT AUDIT
CIVIL QUALITY TARGET
PILLING WORK
- Straight Pilling
- No Cracking Pile
PRECAST CASTING
- Nonporous
- No segregation
- Straight angle
- Smooth surface
REINFORCEMENT
- Bonded / Firmly connected
- Dimension accordance with drawing
FORMWORK
PREPARATION
- Uniform coverage
- Dimension accordance with
drawing
INSPECTION & TEST PLAN
PARTICIPATION BY:
ITEM OF INSPECTION & TEST ACCEPTANCE CRITERIA FREQUENCY RECORD INSPECTION LEVEL ENG/O
SUB CONT
WN
INSPECTION & TEST PLAN
RESPONSIBILITY
Method of Frequen
No Test Item References Level of acceptance SUPP- Remark
test ce PP HSK
LIER
A. FORMWORK
1 Dimension of Formwork Review Design/Shop Length, Height and Width 100% M R R
Drawing
2 Check Cleanliness on Formwork Visual Design/Shop Formwork surface clean and 100% M R R
Drawing dry/uniform coverage
B. PREPARATION
1 Compliance rebar with 1. Tension ASTM A 370 FyBjTP 24 ≥ 240 MPa New M W W
specification supplier
2. Bending FyBjTP 40 ≥ 40 MPa approval
3 Rebar surface cleaning Visual Specification - Free from mud, dirt, grease, 100% M W W
loose mills, scale, etc
2 Check the interval of subsequent Visual PBI 1971, Pouring concrete should be finish 100% M W W
pouring concrete to avoid cold joint Specification at mold before setting time ± 3
hours
- Curing compound
2 Chipping surface of concrete to be Visual Punchlist - Clean and expose rebar of 100% M (W) (W) Appendix 5
repaired concrete to be re-pouring
3 Appearance of surface after form Visual Punchlist No honey comb, no crack 100% M W W Appendix 5
removal
4 Mortar finishing Visual Punchlist Level, chamber, crack, mortar 100% M W W Appendix 5
proportion
5 Dimensional inspection for Visual Design/Shop Restricted formwork area 100% M H H Appendix 5
complete casting drawing
NON-CONFORMANCE PRODUCT CONTROL
CONTRACTOR OWNER/
is Non-fulfilment of
a Requirement ENGINEER
Discovery Nonconformance
Disposition
DISPOSITION
AND Propose for Use-as-is, Repair,
DECISION
Rework, Reject
ACTION
Implementation of Approved
Disposition
NO
HOLD HOLD
TAG TAG
NOT TO BE No. NC :
Drawing No. :
REMOVED Item Description :
WITHOUT Qty :
AUTHORIZATION
Reason for hold :
OF QCO
TIDAK UNTUK
DICABUT
TANPA WEWENANG Date :
Sign :
DARI QCO
Name of QCO :
Non-Conformance
Report (NCR) LOG
NON-CONFORMANCE PRODUCT CONTROL
PREVENTIVE/CORECTIVE ACTION REQUEST
Preventive Action
Action taken to eliminate the cause of a potential nonconformity or
other potential undesirable situation
NCR PCAR
APENDIX – PHOTO, NCR log, and PCAR log
PCAR log
MATERIAL APPROVAL PROCEDURE
START
PP SELEKSI VENDOR :
1. BROSUR
2. SPESIFIKASI
3. SAMPLE
GENERAL NO
MANAGER
VERIFIKASI
YES
7 HARI SEBELUM
PENGAJUANMATERIAL
RENCANA
KE PT. (PERSERO)
PENDATANGAN
PELINDO II
MATERIAL
EVALUASI DARI NO
3 HARI PT. (PERSERO)
PELINDO II
YES
PENGIRIMAN MATERIAL
KE LAPANGAN
FINISH
METHOD STATEMENT SUBMISSION
SHE Patrol
Dilakukan setiap hari
jam 08.30 – 10,00 dan 13.00 –
14.00 WIB
SHE INSPECTION 09.00 – 10.00 GM, PM, CM, SHEO, QCO, GSP,
( BULANAN ) KOORD. PERALATAN, CHIEF SE-
CURITY, PM SUBKON & MANDOR
NOTE : MANAGER SUBKON DAN MANDOR WAJIB IKUT SHE TALK, SHE INSPECTION & SHE MEETING P2K3L MINIMAL 1 KALI DALAM SEBULAN
NILAI ASSESSMENT 2014
94,00%
92,00% 87,68%
90,00% 87,96%
88,00% 85,14% 86,28%
84,80% 85,85%
86,00%
84,00%
82,00%
80,00%
JAN
FEB
SAFETY
ENVIRONMENTAL & HOUSEKEEPING
GREEN CONTRACTOR
2
3
1
2
AKSES JALAN DEPAN BEDENG PEKERJA BECEK AKSES JALAN DEPAN BEDENG PEKERJA SUDAH
DIFLOOR
SUBKON / MANDOR : PT. PP (PERSERO) Tbk SUBKON / MANDOR : PT. PP (PERSERO) Tbk
STOP KONTAK MESIN POMPA AIR TIDAK TERTUTUP STOP KONTAK DIGANTI DAN TERTUTUP
SUBKON / MANDOR : PT. PP (PERSERO) Tbk SUBKON / MANDOR : PT. PP (PERSERO) Tbk
WEBSLING UNTUK PENGANGKATAN BALOK PRECAST SLING DIGANTI DENGA N SLING BAJA
RUSAK DAN TIDAK LAYAK PAKAI
SUBKON / MANDOR : PT. PP (PERSERO) Tbk SUBKON / MANDOR : PT. PP (PERSERO) Tbk
KAPASITAS KERANJANG ORANG HANYA UNTUK 2 PEKERJA NAIK DI ATAS BUCKET SAAT TRANSFER
ORANG DIISI 4 ORANG BUCKET DARI JETY KE PONTON SERVICE
P. JAWAB PEKERJAAN : INDRA JODI / BUDIANTO P. JAWAB PEKERJAAN : INDRA JODI / BUDIANTO
KABEL LISTRIK DIGANTUNG DIRANGKA BESI AREA DIPASANG PROTEKSI SPIRAL DAN CONDUIT / PIPA
FABRIKASI TANPA MENGGUNAKAN PROTEKSI PARALON
SUBKON / MANDOR : PT. PP (PERSERO) Tbk SUBKON / MANDOR : PT. PP (PERSERO) Tbk
PENGANGKATAN PLAT LANTAI DAN BALOK PRECAST DIPASANG TAGLINE UNTUK SETIAP PENGANGKATAN
TIDAK MENGGUNAKAN ALAT BANTU TALI MATERIAL BALOK PRECAST MAUPUN PLAT LANTAI
P. JAWAB PEKERJAAN : INDRA JODI / HADI P P. JAWAB PEKERJAAN : INDRA JODI /HADI P
PENGELASAN TANPA SARUNG TANGAN LAS, BODY MENGGUNAKAN ALAT PELINDUNG DIRI YANG DI
PROTE CT DAN TIDAK TERSEDIA TABUNG APAR WAJIBKAN
P. JAWAB PEKERJAAN : INDRA JODI / HADI P P. JAWAB PEKERJAAN : INDRA JODI / HADI P
KABEL LISTRIK DILETAKAN / DITEMPATKAN DIBAWAH KABEL LISTRIK DILETAKAN / DITEMPATKAN DIBAWAH
SUBKON / MANDOR : PT. PP (PERSERO) Tbk SUBKON / MANDOR : PT. PP (PERSERO) Tbk
SLING KANVAS UNTUK PENGANGKATAN BAMBU SLING KANVASDIGANTI DENGAN YANG BARU
RUSAK DAN TIDAK LAYAK PAKAI
SUBKON / MANDOR : PT. PP (PERSERO) Tbk SUBKON / MANDOR : PT. PP (PERSERO) Tbk
PERATURAN
SAFETY, HEALTH & ENVIRONMENT (S.H.E.)
1. WAJIB PAKAI ALAT PELINDUNG DIRI
2. WAJIB MENJAGA KEBERSIHAN
3. WAJIB IKUT SHE TALK
4. TIDAK MEROKOK PADA SAAT BEKERJA
5. TIDAK BUANG SAMPAH SEMBARANGAN
6. TIDAK PAKAI CELANA PENDEK SAAT BEKERJA
CATATAN : - ID CARD INI HARUS SELALU DIBAWA.
- ID CARD INI TIDAK BOLEH HILANG, BILA
HILANG AKAN DI DENDA Rp. 25.000,-
PROYEK
TERMINAL PETIKEMAS KALIBARU
DEVELOPMENT OF NORTH KALIBARU
CONTAINER TERMINAL PHASE I
PORT OF TANJUNG PRIOK
ENVIRONMENTAL PLAN
Pembuatan Schedule Pemantauan dan Pengukuran :
Membuat Perencanaan - Kebisingan - Uji emisi gas buang
Manajemen Lingkungan - Getaran - Kwalitas udara / ambien
- Pencahayaan - Air limbah
1 Kebisingan
2 Getaran
3 Pencahayaan
Pemantauan dan Pengukuran 4 Emisi Gas Buang
Mencegah terjadinya ganguan kesehatan 5 Pengujian Udara Ambien
(Pengukuran kwalitas udara)
bagi pekerja dan 6 Air limbah
PENERANGAN
• Konstruksi Panel kuat dan isi sesuai kapasitas.
• Lokasi Panel direncanakan.
Pelaksana HK membuat rencana kerja • Lokasi lampu direncanakan dan cukup terang.
Mengarahkan pekerja Housekeeping • Sambungan kabel di Isolasi dengan kuat.
• Kabel digantung rapi.
Pekerjaan pemancangan menggunakan Concrete Spun Pile (CSP) dengan diameter 1000mm
untuk pekerjaan pemancangan dermaga 1A dan dermaga 1B, sedangan digunakan CSP berdiamater
800mm untuk pekerjaan pemancangan container yard.
Pemancangan di area dermaga 1A dan dermaga 1B digunakan casing baja sebagai alat bantu
pemancangan.
METHOD STATEMENT
PILING DERMAGA 1A
2 SEQUENCE OF WORK
Arah pemancangan
METHOD STATEMENT
INSTALL UPPER STRUCTURE PHASE 1A
Pekerjaan install upper structure terdiri dari pekerjaan beton, pekerjaan baja dan
aksesoris yang diperlukan. Pekerjaan beton terdiri dari pekerjaan precast dan insitu.
METHOD STATEMENT
INSTALL UPPER STRUCTURE PHASE 1A
400 M
Cap. 6pcs/day
Cap. 5pcs/day
Cap. 45 pcs
Cap. 5pcs/day
Cap. 6pcs/day
Cap. 6pcs/day Cap. 5pcs/day
Cap. 45 pcs
Cap. 45 pcs
Cap. 20 pcs
PILING WORK – SEQUENCE OF WORK
Handling CSP from Stockyard or Handling CSP to Piling Rig Pile Positioning
Ship to Transport Barge
Equipment : Equipment : Equipment :
Crawler Crane 80 ton, Barge 100 ft, Piling Rig, CrawlerCrane 80 ton. Piling Rig, GPS Support, Theodolite.
Tug Boat 2x500 HP.
PILING WORK – SEQUENCE OF WORK
Equipment : Equipment :
Piling Rig.
PILING WORK – CONCRETE SPUN PILE (CSP)
OCEANIC
Panjang 25 m’
Panjang 27 m’
PILING WORK - CSP TRANSPORT TO SITE
PILING WORK – PREBORING
PILING WORK – PREBORING
PILING WORK – PILE DRIVING PROCESS
PILING WORK – PILE DRIVING PROCESS
PILING WORK – PILE DRIVING PROCESS
PILING WORK
PILING WORK
CONTAINER TERMINAL 1 – LOADING TEST
TC 2
50T TC 3
TC 4
150T TC 6
TC 5
50T
TC 7
TC 1
80T 80T
25T
25T
75T
80T
25T 150T
50T
75T 25T
Precast Beam Installation Pile Cap Concrete Casting Precast Slab Installation
Insitu Concrete Rebar Installation Insitu Slab Concrete Casting Deck Slab Finishing
SITE PROJECT
Pacific paint is in the area of
2,5 ha with 1 bacthing plant Temporary access will
and 2 service cranes 80 ton DKB WORKSHOP support land
to support fabrication transportation
process.
Transportation of precast
PACIFIC PAINT WORKSHOP by long bed truck
PRECAST FABRICATION AREA
PRECAST FABRICATION AREA – DKB
PRECAST FABRICATION AREA – PACIFIC PAINT
UPPER STRUCTURE – PRECAST FABRICATION
PRECAST FABRICATION
UPPER STRUCTURE - PRECAST FABRICATION
Precast Beam
UPPER STRUCTURE - PRECAST FABRICATION
Precast Pilecap
UPPER STRUCTURE - PRECAST FABRICATION
1 SEQUENCE OF WORK
Fleet alat 1
Fleet alat 3 Start 3 Start 2 Start 1
TIPE C TIPE A
Fleet alat 2
TIPE E
TIPE B
TIPE E
TIPE E
TIPE D
a) Pekerjaan breakwater 1B dimulai dari dua titik start point. Untuk start point 1 diikuti
2 fleet alat. Dan start point 2 menggunakan 1 alat.
b) Pekerjaan breakwater disposal menggunakan 1 fleet alat dengan start point 3
METHOD STATEMENT
BREAKWATER TEMPORARY DISPOSAL
1 SEQUENCE OF WORK
1. PEMANCANGAN CLUSTER BAMBU
START POINT Pemancangan cluster bambu menggunakan excavator PC
200 yang telah dimodifikasi ditambahkan boom untuk
keperluan pemancangan. Dengan kapasitas produksi alat
200 titik per hari
Pancang Bambu
METODE PANCANG BAMBU
TEMPLATE
PONTON PONTON
KETERANGAN :
CRANE Diameter Pipa 40 cm
Jumlah pipa guide 100 unit
Jarak pipa guide 1 m
PONTON Ukuran template 11 m x 11 m
TAMPAK ATAS
METODE PANCANG BAMBU
HAMMER
Pipa 36 cm
Bambu Cluster
Pipa 40 cm
DAFTAR ALAT :
1. PONTON
2. CRANE 35 TON
3. TEMPLATE BAJA
HAMMER 4. PIPA GUIDE
5. HAMMER
6. SPUD PILE
Pipa 36 cm
KETERANGAN :
Bambu Cluster
Diameter Pipa 40 cm
Jumlah pipa guide 100 unit
Jarak pipa guide 1 m
DETAIL Ukuran template 11 m x 11 m
METODE PANCANG BAMBU
DAFTAR ALAT :
1. PONTON
2. CRANE 35 TON
3. TEMPLATE BAJA
4. PIPA GUIDE
5. HAMMER
6. SPUD PILE
KETERANGAN :
Diameter Pipa 40 cm
Jumlah pipa guide 100 unit
Jarak pipa guide 1 m
Ukuran template 11 m x 11 m
POTONGAN
METODE PANCANG BAMBU
DAFTAR ALAT :
1. PONTON
2. CRANE 35 TON
3. TEMPLATE BAJA
4. PIPA GUIDE
5. HAMMER
6. SPUD PILE
KETERANGAN :
TAMPAK SAMPING Diameter Pipa 40 cm
Jumlah pipa guide 100 unit
Jarak pipa guide 1 m
Ukuran template 11 m x 11 m
PERSIAPAN PEMANCANGAN BAMBU CLUSTER
Ponton Template
Ponton Template
VOLUME :
Material guide pile : 40 btg
SSP sudah di pancang : 1 btg
METHOD STATEMENT
BREAKWATER
Detail gambar matras bambu
Matras bambu terdiri atas tujuh lapis. Masing-
masing lapisnya disatukan dengan
menggunakan tali ijuk/tali kapal.
Satu segmen matras bambu berukuran 8m x
50m, dengan space bambu 20cm ke arah
melintang dan 1m ke arah melintang.
a) Pemasangan matras bambu dengan cara mengapungkan matras bambu di elevasi yang sudah
ditentukan.
b) Menyambung tiap segmen (50mx8m) dengan sling baja sampai terhubung ±5 segmen matras
c) Menenggelamkan matras pertama (awal) dengan bantuan balok beton dengan alat crane 100 ton
d) Penenggelaman berikutnya dengan menggunaan batu dengan bantuan excavator longarm
METHOD STATEMENT
BREAKWATER TEMPORARY DISPOSAL
DETAIL MATRAS BAMBU
Sling Baja
Matras Bambu
A-Jack yang digunakan adalh A-Jack 2,5 ton yang akan di instal dengan bantuan alat
crane. Digunakan A-jack untuk lapisan paling atas dari breakwater type A, B,C dan E.
BREAKWATER TIPE D
Breakwater tipe E merupakan breakwater yang letaknya berada di bawah dermaga 1B, pelaksanaan
pekerjaan breakwater ini dilakukan setelah dredging di bawah dermaga 1B selesai.
Material yang digunakan dalam pekerjaan breakwater ini adala :
1. Batu
2. Geotextile
Pekerjaan breakwater type D berada di bawah dermaga 1B, sehingga pekerjaan dilakukan
setelah pekerjaan pemancangan hampir selesai. Pekerjaan ini menggunakan alat
unloading batu berupa conveyor dan clamshell.
FLOW CART PENGADAAN MATERIAL BATU BREAKWATER
START
TRANSPORTASI KE
STOCK YARD
SELESAI
Jarak antara lokasi Quary batu dan
LOKASI QUARRY BATU
pelabuhan Tanjung Priok ± 45 mil
Bojonegara
Tanjung
Priok
METODE HANDLING BATU
Quarry
Batu
Pekerjaan penambangan batu
Tongkang
Stock Yard
Penumpukan
Batu
13 hours
FLEET 3
FLEET 3 48 hours
FLEET 2(13 + 2)
LOADING 48 hours SITE
FLEET 4
FLEET 4 FLEET 1
10 hours
Square Drill
Rectanguler
Stanggered
(Zig-zag)
METODE PELEDAKAN
Pekerjaan peledakan dimulai dengan pekerjaan pengisian bahan peledak, pekerjaan pengisian
bahan peledak ada dua cara yaitu :
- Langsung tanpa pelindung plastik. Dilakukan apabila lubang ledak kondisi kering tidak ada
hujan (kemarau)
- Dengan pelindung plastik. Dilakukan apabila lubang ledak basah saat musim hujan.
Pengisian langsung
Pengisian dengan pelindung
METODE PELEDAKAN
RANGKAIAN PELEDAKAN
Setelah bahan peledak diisi pada lubang bor maka langkah selanjutnya adalah
menghubungkan tiap-tiap lubang yang berisi bahan peledak tersebut dengan rangkaian
listrik yang terhubung pada blasting machine.
Ada tiga rangkaian dasar yang umum digunakan yaitu :
1. Seri
2. Pararel
3. Seri Pararel
Umumnya hubungan pararel lebih menguntungkan karena memperkecil kemungkinan
terjadinya ”missfire” akibat aliran listrik yang kurang mencukupi (Nilai hambatan kecil).
Hubungan Seri-Pararel digunakan untuk jumlah lubang peledakan yang lebih banyak untuk
sekali peledakan.
Menjaga keamanan pekerja maupun area peledakan dapat dilakukan dengan cara :
1. Membuat gudang penyimpanan bahan peledak
2. Melakukan training untuk para pekerja
3. Pekerjaan dibantu dari tim peledak yang sudah ahli di bidangnya
Quary Batu
Andhesite Class H (Berat = 64 < W < 100 Kg) Andhesite Class G (Berat = 80 < W < 125 Kg)
Limestone Class B
(Berat = 1200 < W < 1875 Kg) Limestone Class A
(Berat = 2000 < W < 3125 Kg)
DOKUMENTASI STOCK QUARY :
Blasting
2500 6500
1000
10
00
1550
2000
800
NO ITEM OF WORKS UNIT QUANTITY SPECIFICATION
1 Bamboo Cluster Unit 329,328 dia. 5 – 10 cm
Bamboo cluster piling use crane that has been modified with boom for piling. Productivity estimated is about 200 point per day per fleet.
Bamboo mattress installation conducted by floating this mattress at predetermined elevation. Connecting each segment (50mx8m) with steel
sling until connected ± 5 segments mattress. Submerging first mattress with the assistance of concrete block by a crane 100 ton. Following
sinking use rock with assistance by excavator long-arm. Once the bamboo mattress sinking, overall rock able to installed on top by using
excavators. For tidiness, then an excavator made finishing as the figure.
BREAKWATER WORK – SEQUENCE OF WORK
Mattress and Cluster Bamboo Mattress and Cluster Bamboo Driving Cluster Bamboo
Installation Transportation
Equipment : Equipment : Equipment :
Service Boat. Barge 80 ft, Crawler Crane 80 ton.
BREAKWATER WORK – SEQUENCE OF WORK
Sinking Mattress Bamboo Placing Core Rock followed with Placing A-Jack
Armour Rock
Equipment : Equipment : Equipment :
Barge 180 ft, Excavator PC-200 Barge 180 ft, Excavator PC-200 Crawler Crane 80 ton, Peel Bucket
STD, PC-300 STD , PC-300 Long STD, PC-300 STD, PC-300 Long Orange 2-4 m³, Excavator PC-200
Arm. Arm. STD.
BREAKWATER WORK – BAMBOO STOCK YARD
BREAKWATER WORK - MATTRESS BAMBOO
BREAKWATER WORK – BAMBOO CLUSTER INSTALLATION
BREAKWATER WORK – BAMBOO CLUSTER INSTALLATION
BREAKWATER WORK – BAMBOO MATTRESS INSTALLATION
ROCK QUARRY – TANJUNG AWURAN BOJONEGARA
ROCK QUARRY – CICANDI BOJONEGARA
ROCK QUARRY – GANDASARI BOJONEGARA
ARMOUR AND ROCK PRODUCTION
BREAKWATER WORK – ROCK INSTALLATION
BREAKWATER WORK – ROCK INSTALLATION
12,8 m
FABRICATION OF A-JACK
FABRICATION OF A-JACK
ARMOUR AND ROCK PRODUCTION
BREAKWATER WORK – ARMOUR INSTALLATION
BREAKWATER WORK
BREAKWATER WORK
BREAKWATER WORK
METHOD STATEMENT
DREDGING DERMAGA 1A
Kapasitas 1.470 kW
METHOD STATEMENT
RECLAMATION Sisa material dredging
dibuang sejauh 16 mil dari
lokasi proyek
Dredging material
Dredging material CSD 16.159.890 m3 Dredging material
TSHD 4.033.622 m3 Grab dredger 4.081.902 m3
PEMBUANGAN MATERIAL DREDGING
CY 1B TSHD
Pengambilan Pasir
SERANG
Tj. PRIOK
RECLAMATION RECLAMATION
(DredgIng material) (DredgIng material & Sand)
Remarks :
Dredging Jetty : 4,188,375.85 m3
Dredging Basin : 16,797,600.04 m3
Dredging Channel : 4,194,618.84 m3
DREDGING & RECLAMATION
-18 mLWS
-15 mLWS
-20 mLWS
-16 mLWS
-2 mLWS
-3 mLWS
-4 mLWS
-16 mLWS
-20 mLWS
Remarks :
Dredging Jetty 1A : 1,230,657.40 m3
Dredging Jetty 1B : 762,961.15 m3
SILT CURTAIN to protect dredging material
Contract method : Dumping dredging material after breakwater disposal A was finished
Innovation : Dumping material using silt curtain
DREDGING USING GRAB DREDGER
Split Barge
Capacity : 1000 m³
DREDGING USING GRAB DREDGER
Split Barge
Capacity : 1000 m³
DREDGING USING GRAB DREDGER
Split Barge
Capacity : 1000 m³
Split Barge
Capacity : 1000 m³
DREDGING USING TSHD
Split Barge
Capacity : 1000
Trailer m³ Hopper Dredger “HAM 310”
Suction
Productivity : 300.000 m³/week
Hopper Capacity : 13.000 m3
DREDGING USING TSHD
PVD
708.000
709.000
709.500
710.000
710.500
711.000
711.500
712.000
712.500
713.000
CUTTER SECTION DREDGER
6 3 2
T AHAP -1B
CONTA INER
5 4 1
T AHAP -1A
CONTA INER
RECLAMATION WORK
Split Barge
Capacity : 1000 m³
RECLAMATION WORK
Metode Pemancangan :
Pekerjaan pemancangan
dimulai dari sisi container
yard 1A menuju sisi daratan.
Pekerjaan pemancangan
menggunakan alat crane dan
ponton .
Pemancangan dibagi dalam
beberapa zona sesuai denga
alinyement nya.
METODE JEMBATAN
17800
500 500 3500 3500 500 800 500 3500 3500 500 500
89 S1 D19~200
88 S4 D19~200
300
5 B3 D13
250 550
100 550
800
650
500
830 120
3 B2 D13 ~ B6 D13
900 3200 3200 3200 3200 3200 900 950
15 B7 D13
17800
CSP Ø 500 mm
2 Concrete work M2 Fc 45
6,177
3 Road Pavement M3 11,055 Aspal AC-WC, t : 5 cm
4 Sheet Pile M3 9,674 Concrete sheet pile (1000x300, L=14 m)
ACCESS ROAD
SEQUENCE OF WORK
Pier Head Form Work Installation
Piling Method :
Piling work begins from side
near the container yard 1A
heading to land side. This
piling work use crane and
pontoon as equipments. Piling
area divided into several zone
corresponding to its
alignment.
ACCESS ROAD