METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
1/13

JUDUL : METODE KERJA PEKERJAAN PAGAR


OWNER : PT. WIKA INDUSTRI & KONSTRUKSI
KONTRAKTOR : PT. WIKA REKAYASA KONSTRUKSI
NAMA PROYEK : PABRIK FABRIKASI BAJA PT.WIKA INDUSTRI
& KONSTRUKSI MAJALENGKA
LOCATION : MAJALENGKA

0 27/08/2019 For Review SV IM AH

Made By Reviewed By Approved By Reviewed by Approved by

REV. DATE Description


Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
2/13

DAFTAR ISI

1. Pendahuluan ................................................................................................................................. 3
2. Perencanaan Layout .................................................................................................................... 3
3. Alat .................................................................................................................................................. 3
4. Pekerjaan Pagar ........................................................................................................................... 3
Lampiran 1 – Perencanaan Layout ................................................................................................... 8
Lampiran 2 – Prosedur Keamanan.................................................................................................... 9
Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
3/13

1. Pendahuluan
Metode ini mencakup prosedur pembuatan pagar pada Proyek Pabrik Fabrikasi
Baja PT. Wika Industri & Konstruksi.

2. Perencanaan Layout
Perencanaan layout untuk pembuatan pagar terdapat pada Lampiran 1.

3. Alat
a. Theodolit
b. Unting-unting (manual)
c. Water Pass
d. Tali
e. Alat angkat panel precast / Tripod
f. Takel
g. Truck Mixer
h. Molen

4. Pekerjaan Pagar
a. Joint Survey koordinat as pagar precast panel beton antara PT. WIKA
Rekayasa Konstruksi dengan PT. WIKA Industri & Konstruksi.
b. Pekerjaan galian tanah untuk pondasi pagar panel beton precast sesuai
dengan rencana (Bottom sloof sesuai dengan design grading, yaitu minimal
0,5 dan 1,25).
Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
4/13
Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
5/13

c. Pemasangan sand layer dengan ketebalan 5 cm


d. Pemasangan aanstamping dengan lebar 1 m.

e. Pemasangan pondasi batu kali dengan komposisi campuran mortar 1:4.


f. Pekerjaan sloof beton
Pekerjaan sloof beton berfungsi untuk menjepit kolom pagar oleh karena itu
sloof dilaksanakan setelah kolom pagar berdiri/ terpasang, pekerjaan sloof
dilaksanakan dengan uraian metode kerja seperti berikut:
1. Melakukan pembesian untuk sloof beton dengan ukuran sesuai gambar
rencana, pada saat pemasangan besi harus diperhatikan bahwa besi
tulangan harus benar-benar menjepit kolom.
2. Setelah pembesian dan bekisting terpasang serta telah disetujui oleh
Pengawas Lapangan, selanjutnya adalah melaksanakan pengecoran
Sloof menggunakan Beton fc 25 atau sesuai spesifikasi teknis. Sebelum
dilakukan pengecoran sloof maka akan dilaksanakan pemeriksaan akhir
pekerjaan dan pembersihan lokasi pengecoran.
3. Pengecoran dilaksanakan menggunakan ready mix namun apabila tidak
memungkinkan, pengecoran dilaksanakan secara site mix menggunakan
beton molen mixer.
4. Campuran beton yang sudah homogen dituangkan ke dalam bekisting.
5. Setelah beton dituangkan kedalam bekisting, beton tersebut akan
dipadatkan menggunakan alat bernama concrete vibrator agar udara
yang masih ada didalam adukan keluar, pemadatan dilakukan sesuai
dengan spesifikasi teknis.

g. Pemasangan Kolom Panel Beton Precast


1. Kolom pagar dipasang pada lubang pondasi batu kali yang sudah
tersedia.
Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
6/13

2. Kolom diangkat dengan menggunakan tripod, kemudian dimasukkan


kedalam lubang yang telah disediakan.
3. Cek kelurusan horizontal dan vertikal kolom agar posisi kolom presisi
terhadap kolom lainnya.
4. Setelah kolom selesai terpasang/berdiri lurus, maka lubang ditutup
dengan memasang batu kali sesuai dengan gambar.

h. Pemasangan Panel Beton Precast


1. Pemasangan panel precast dengan mengangkat panel precast dan
memasukannya ke dalam lubang dudukan precast yang ada di kolom
precast, jika pagar precast yang di pasang tinggi bisa memakai alat bantu
takel atau crane kecil saja.
Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
7/13

2. Pemasangan pagar panel beton diangkat dengan menggunakan tripod,


kemudian dimasukkan kedalam celah yang telah tersedia pada kolom.
Pekerjaan pemasangan panel beton dilaksanakan sesuai gambar kerja.
Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
8/13

Lampiran 1 – Perencanaan Layout


Document Number

METODE KERJA PEKERJAAN PAGAR


Rev. : 0
WRK-MK-BDG-STR-FNC-001 Page Number
9/13

Lampiran 2 – Prosedur Keamanan


PT. WIJAYA KARYA
Document Number

HAZARD IDENTIFICATION AND RISK ANALYSIS


WRK-MK-BDG-STR-FNC-001

RESIKO RESIKO
URAIAN SEBELUM SETELAH
NO POTENSI BAHAYA TINDAKAN PENCEGAHAN
PEKERJAAN MITIGASI MITIGASI
L S RR L S RR
1 Lifting/Rigging Lecutan sling 3 3 9 Menjaga jarak dengan alat 3 2 6
Tertimpa 2 4 8 Menjaga jarak dengan alat 2 3 6
Terjepit 2 1 2 Memakai sarung tangan, dan sepatu safety 2 1 2
Terkena benda tajam 2 1 2 Memakai sarung tangan, dan sepatu safety 2 1 2
2 Erection Terjepit 2 1 1 Memakai sarung tangan, dan sepatu safety 2 1 2
Tertimpa 2 4 8 Jaga jarak aman saat pemasangan, dan pastikan 2 2 4
pekerja menggunakan alat pelindung diri (helm,
sepatu safety, rompi, sarung tangan, full body
METODE KERJA PEKERJAAN PAGAR

hardness)
Terkena benda tajam 2 1 2 Memakai sarung tangan, dan sepatu safety 2 1 2
Shouring protection 2 4 8 Jaga jarak aman saat pemasangan, dan pastikan 2 2 4
roboh pekerja menggunakan alat pelindung diri (helm,
sepatu safety, rompi, sarung tangan, full body
hardness)
3 Demolition Terjepit 2 1 2 Memakai sarung tangan, dan sepatu safety 2 1 2
Tertimpa 2 4 8 Jaga jarak aman saat pemasangan, dan pastikan 2 2 4
10/13
Rev. : 0

pekerja menggunakan alat pelindung diri (helm,


Page Number

sepatu safety, rompi, sarung tangan, full body


hardness)
Terkena benda tajam 2 1 2 Memakai sarung tangan, dan sepatu safety 2 1 2
PT. WIJAYA KARYA
Document Number

HAZARD IDENTIFICATION AND RISK ANALYSIS


WRK-MK-BDG-STR-FNC-001

RESIKO RESIKO
URAIAN
NO POTENSI BAHAYA SEBELUM TINDAKAN PENCEGAHAN SETELAH
PEKERJAAN
L S RR L S RR
Shouring protection 2 4 8 Jaga jarak aman saat pemasangan, dan pastikan 2 2 4
roboh pekerja menggunakan alat pelindung diri (helm,
sepatu safety, rompi, sarung tangan, full body
hardness)
4 Excavation Longsor /keruntuhan 2 4 8 Excavation perlayer kedalaman 2 2 4
tanah
Muka air tanah tinggi 2 2 4 Digunakan dewatering system 2 1 2
Pekerjaan terjatuh ke 2 2 4 Memasang rambu-rambu peringatan 2 1 2
lubang galian
METODE KERJA PEKERJAAN PAGAR

Pagar runtuh 2 2 4 Lakukan perkuatan dengan semi perancah 2 1 2


Terluka akibat alat 2 3 6 Jaga jarak aman saat pemasangan, dan pastikan 2 2 4
manual pekerja menggunakan alat pelindung diri (helm,
sepatu safety, rompi, sarung tangan, full body
hardness)
Gangguan pernafasan 3 1 3 Memakai masker untuk perlindungan pernafasan 3 1 3
akibat debu material
5 Dumping Area pekerjaan sempit 2 2 4 2 1 1
11/13

Material terjatuh 2 1 2 2 1 2
Rev. : 0

6 Transport Lalu lintas padat 3 1 3 Perlunya rambu lalu lintas, dan pengarah lalu lintas 3 1 3
Page Number

pada saat proyek berlangsung


Kecelakaan lalu lintas 2 2 4 Pengaturan lalu lintas dan mengendara sesuai aturan 2 1 2
yang berlaku
PT. WIJAYA KARYA
Document Number

HAZARD IDENTIFICATION AND RISK ANALYSIS


WRK-MK-BDG-STR-FNC-001

RESIKO RESIKO
URAIAN
NO POTENSI BAHAYA SEBELUM TINDAKAN PENCEGAHAN SETELAH
PEKERJAAN
L S RR L S RR
Jalan akses sempit 3 2 6 Rekayasa lalu lintas 3 1 3
Jalan licin 2 1 2 Menghindari pekerjaan saat hujan 2 1 2
7 Dumping material Material tercecer/ 2 1 2 Memuat material sesuai kapasitas bucket 2 1 2
terjatuh
Pekerjaan tertimbun 2 4 8 Jaga jarak aman dengan pada saat penimbunan 2 2 4
material tanah
8 Pemadatan Tanah licin 2 1 2 Menghindari pekerjaan saat hujan 2 1 2
Terluka akibat alat 2 3 6 Jaga jarak aman saat pemasangan, dan pastikan 2 2 4
pemadat pekerja menggunakan alat pelindung diri (helm,
METODE KERJA PEKERJAAN PAGAR

sepatu safety, rompi, sarung tangan, full body


hardness)
9 Pengiriman beton Tertabrak truk mixer 2 1 2 Berdiri jauh dari truk mixer 2 1 2
Tertimbun beton cair 2 1 2 Berdiri pada jarak 1 m dari talang dan di bag belakang 2 1 2
talang
Ban truk tergelincir 2 1 2 Truk mixer bergerak sesuai instruksi rigger 2 1 2
Truk mixer terguling 2 2 4 Truk mixer hanya beroperasi di jalan dengan 2 1 2
perkerasan
10 Pemotongan besi Terkena lontaran 2 1 2 Berdiri di tempat yg aman dari lontaran potongan besi 2 1 2
12/13
Rev. : 0

potongan besi saat


Page Number

dipotong dgn bar cutter


Tangan terjepit besi 2 1 2 Pengangkatan besi sesuai dengan berat yg dapat 2 1 2
diangkat manual dan gunakan sarung tangan standar
PT. WIJAYA KARYA
Document Number

HAZARD IDENTIFICATION AND RISK ANALYSIS


WRK-MK-BDG-STR-FNC-001

RESIKO RESIKO
URAIAN
NO POTENSI BAHAYA SEBELUM TINDAKAN PENCEGAHAN SETELAH
PEKERJAAN
L S RR L S RR
Jari putus akibat bar 2 1 2 Gunakan safety cover bar cutter 2 1 1
cutter
Kaki kejatuhan potongan 2 1 2 Gunakan safety shoes 2 1 2
besi
Tersengat listrik 2 1 2 Pastikan kabel ground terpasang dgn baik, gunakan 2 1 2
sepatu dan sarung tangan safety
11 Pembengkokan Terhempas oleh besi 2 1 2 Berdiri di tempat yang aman, jauhi arah putar bar 2 1 2
besi bender
Terkena lontaran dlm 2 1 2 Berdiri di tempat yg aman dari lontaran potongan besi 2 1 2
METODE KERJA PEKERJAAN PAGAR

bar bender
Tersengat listrik 2 1 2 Pastikan kabel ground terpasang dgn baik, gunakan 2 1 2
sepatu dan sarung tangan safety
Tangan terjepit besi 2 1 2 Bengkokkan besi sesuai kapasitas alat 2 1 2
12 Pemasangan besi Kaki tertancap potongan 2 1 2 Gunakan safety shoes 2 1 2
besi
Kaki tersandung besi 2 1 2 Perhatikan jalan akses saat melintas 2 1 2
13 Pabrikasi panel Terpukul oleh palu 2 1 2 Pemasangan bekisting harus dilakukan orang yg ahli 2 1 2
13/13

bekisting
Rev. : 0

Tertancap paku 2 1 2 Bersihkan area kerja dari material tdk berguna seblm 2 1 2
Page Number

mulai
Tangan tergores material 2 1 2 Menggunakan sarung tangan 2 1 2
kayu
PT. WIJAYA KARYA
Document Number

HAZARD IDENTIFICATION AND RISK ANALYSIS


WRK-MK-BDG-STR-FNC-001

RESIKO RESIKO
URAIAN
NO POTENSI BAHAYA SEBELUM TINDAKAN PENCEGAHAN SETELAH
PEKERJAAN
L S RR L S RR
Tangan terluka akibat 2 1 2 Menggunakan sarung tangan 2 1 2
pemotongan material
14 Pemasangan Tertimpa panel bekisting 2 4 8 Jaga jarak aman dengan pada saat pemasangan, dan 2 3 6
panel bekisting pastikan pekerja menggunakan alat pelindung diri
(helm, sepatu safety, rompi, sarung tangan, full body
Terjepit panel bekisting 2 2 4 Hati-hati melakukan penetrasi panel dan komunikasi 2 1 2
yang baik antar pekerja
15 Pengecoran beton Tertabrak truk mixer 2 1 2 Berdiri jauh dari truk mixer 2 1 2
Tertimbun beton cair 2 2 4 Berdiri pd jarak 1 m dari talang dan di bag belakang talang 2 1 2
METODE KERJA PEKERJAAN PAGAR

Tertimpa concrete pump 2 1 2 Berdiri jauh dari boom dan di arah yang menjauhi 2 1 2
gerakan boom
16 Pembongkaran Tertimpa panel bekisting 2 4 8 Jaga jarak aman dengan pada saat pemasangan, dan 2 3 6
panel bekisting pastikan pekerja menggunakan alat pelindung diri
(helm, sepatu safety, rompi, sarung tangan, full body
Terjepit panel bekisting 2 2 4 Hati-hati melakukan penetrasi panel dan komunikasi 2 1 2
yang baik antar pekerja
Terjatuh ketika sedang 2 4 8 Penggunaan full body hardness ketika bekerja di 2 3 6
pembongkaran ketinggian
14/13
Rev. : 0

Terpukul palu saat 2 1 2 Pembongkaran bekisting harus dilakukan orang yg ahli 2 1 2


Page Number

membuka sambungan
Terjepit panel bekisting 2 1 2 Hati-hati melakukan pembongkaran panel dan 2 1 2
komunikasi yang baik antar pekerja