Anda di halaman 1dari 19

Minggu ke-47

HULL No. : DBN-025

LAPORAN PROGRES
Kapal Ferry Ro-Ro 300 GT
Lintas Danau Toba

AGUSTUS 2017 - NOVEMBER 2018

INDEX

COVER……………………………………………………………………………………………………………………………………………………………..
PAGE 01

PROGRES KEMAJUAN PEKERJAAN…………………………………………………………………………………………………… PAGE 02

S-CURVE………………………………………………………………………………………………………………………………………………………..
PAGE 09

RESUME PROGRES KEMAJUAN PEKERJAAN……………………………………………………………………………….. PAGE 10

VISUALISASI PEKERJAAN KONSTRUKSI……………………………………………………………………………………….. PAGE 11

DOKUMENTASI……………………………………………………………………………………………………………………………………………..
PAGE 12
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
A. MATERIAL/KOMPONEN PEMBANGUNAN KAPAL

I. LAMBUNG
I.1 Bahan baku
* Material Konstruksi (Pelat dan Profil):
- Geladak Navigasi termasuk cerobong asap
- Geladak Penumpang 1 SHIPSET 17.478 99.916% 17.432 0.031 17.463
- Geladak Kendaraan
- Lambung termasuk skeg & bilge keel
* Material Konstruksi (Pelat dan Profil) Outfitting:
- Tiang Radar
- Tiang Bendera Buritan
- Rampa Haluan & Buritan
- Daun Kemudi
- Sepatu Daun Kemudi 1 SHIPSET 1.471 95.250% 1.359 0.042 1.401
- Pisang-pisang (steel fender)
- Pipa Rantai Jangkar (hawse pipe)
- Skeg Pelindung Tabrakan Buritan
* Material Fitting dan Cutting:
- Electrode 1 SHIPSET 1.243 99.581% 1.227 0.011 1.238
- Oxygen 1 SHIPSET 0.600 99.581% 0.593 0.005 0.598
- Acetylene 1 SHIPSET 0.500 99.581% 0.494 0.004 0.498
- Gauging Carbon 1 SHIPSET 0.180 99.581% 0.178 0.002 0.179
* Pengecatan dan Perlindungan Karat:
- Blasting & Cat Dasar
- Blasting Abrassive Precious Slag Ball (PS Ball) 1 SHIPSET 0.790 95.400% 0.632 0.122 0.754
- Cat Dasar (shop primer) 1 SHIPSET 0.185 100.000% 0.185 0.000 0.185
- Cat (marine coating/painting)
- Cat Anti Karat (AC) 1 SHIPSET 0.253 80.000% 0.202 0.000 0.202
- Cat Anti Fouling (AF) 1 SHIPSET 0.373 80.000% 0.298 0.000 0.298
- Cat Akhir Bottop 1 SHIPSET 0.122 0.098 0.000 0.098
- Cat Akhir (Finish) 1 SHIPSET 0.272 80.000% 0.217 0.000 0.217
- Epoxy 1 SHIPSET 0.154 80.000% 0.124 0.000 0.124
- Tar Epoxy 1 SHIPSET 0.197 80.000% 0.157 0.000 0.157
- Thinner 1 SHIPSET 0.265 80.000% 0.212 0.000 0.212
- Alluminium Anode/ Cathodic Protection 1 LOT 0.138 80.000% 0.110 0.000 0.110
- Sea Chest
- Buritan dan Kemudi
- Lambung
Sub Total Progres I.1 24.221 23.518 0.217 23.735
I.2. Perlengkapan Lambung
* Dapra (Rubber Fender) 14 BH 0.319 51.429% 0.164 0.000 0.164
* Pagar Pengaman (Guard Railing) Tipe 01 1 LOT 0.350 96.000% 0.315 0.021 0.336
- Geladak Penumpang
- Geladak Antara (Akomodasi Penumpang)
* Pagar Pengaman (Guard Railing) Tipe 02 1 LOT 0.404 96.000% 0.380 0.008 0.388
- Geladak Antara, Gld. Kimbul, Gld. Akil
- Geladak Navigasi
- Atap Rumah Gld. Navigasi
* Pegangan Tangan Koridor G.Penumpang & G.Navigasi 1 LOT 0.114 0.000% 0.000 0.000 0.000
* Tangga Akomodasi (Ladder) & Railing
- Tangga Akomodasi Penumpang 10 SET 0.263 100.000% 0.263 0.000 0.263
- Tangga Akses Kamar Mesin 2 SET 0.053 100.000% 0.053 0.000 0.053
* Tangga Tegak (vertical ladder) 1 LOT 0.072 100.000% 0.072 0.000 0.072
- Tangga Akses Atap Rumah G.Navigasi
- Tangga Akses Kompartemen & Dasar Ganda
* Dudukan ILR 4 UNIT 0.071 0.000% 0.000 0.000 0.000
* Ventilasi:
- Ceiling Exhaust Fan & Musroom Kapasitas 82 m3/h 3 SET 0.044 80.000% 0.035 0.000 0.035
- R. CO2 & Gudang Gld. Kendaraan (P/S)
- KM/WC G.Navigasi
- Wall Mounted Exhaust Fan Kapasitas 82 m3/h 6 SET 0.088 80.000% 0.071 0.000 0.071
- KM/WC R. Penumpang Gld. Antara (P/S)
- Semua R. Akomodasi ABK Gld. Navigasi
- Ceiling Exhaust Fan & Musroom Kapasitas 165 m3/h 3 SET 0.101 80.000% 0.081 0.000 0.081
- R.Mesin Kemudi Kompartemen Lambung
- R.Generator & Pemadam Darurat
- R. Pemadam Sprinkler
- Wall Exhaust Fan Kapasitas 165 m3/h R.Mess G.Navigasi 1 SET 0.034 80.000% 0.027 0.000 0.027
- Exhaust Hood Chimney Kapasitas 165 m3/h
- Dapur dan Cafetaria R. Penumpang Gld. Penumpang 1 SET 0.013 80.000% 0.010 0.000 0.010
- Supply fan, ducting dan mushroom kap. 190 m3/hr R.Generator darurat 1 SET 0.013 80.000% 0.010 0.000 0.010
- Ceiling Exhaust Fan, Ducting & Musroom Kapasitas 300 m3/h 2 SET 0.025 80.000% 0.020 0.000 0.020
- KM/WC Laki-laki Gld. Penumpang
- KM/WC Perempuan Gld. Penumpang
- Mechanical fan, ducting punkah louvre & mushroom :
- Supply Fan kap. 16000 m3/hr kamar mesin 1 SET 0.020 80.000% 0.016 0.000 0.016

Page 1
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
- Exhaust Fan kap 14000 m3/hr. Kamar mesin 1 SET 0.019 80.000% 0.015 0.000 0.015
* Atap Tipis (awning) R.Penumpang Terbuka Gld. Navigasi 1 LOT 0.209 70.000% 0.146 0.000 0.146
* Pelat Nama & Tanda-Tanda :
- Nama Kapal & Tanda Sarat di Lambung 1 LOT 0.021 96.000% 0.017 0.003 0.020
- Nama Kapal di Atap R.Geladak Navigasi 1 LOT 0.013 0.000% 0.000 0.000 0.000
- Petunjuk & Tanda-tanda dalam kapal (bahasa Indonesia & Inggris) 1 LOT 0.032 0.000% 0.000 0.000 0.000
* Terpal Pelindung Mesin & Perlengkapan Geladak 1 LOT 0.034 80.000% 0.000 0.027 0.027
- Tutup Terpal Lampu Sorot & Kompas Magnetik
- Tutup Terpal Mesin Windlass, Winch Buritan, & Winch Sekoci
- Tutup Terpal Sekoci Penolong
* Lantai Kerja Kamar Mesin 1 LOT 0.313 80.000% 0.250 0.000 0.250
* AKSES KOMPARTEMEN
- Pintu Palka Orang Kedap Air (watertight access hatch cover) 2 SET 0.063 100.000% 0.063 0.000 0.063
- Lubang Orang (manholes) 42 SET 0.470 100.000% 0.470 0.000 0.470
Sub Total Progres I.2 3.157 2.479 0.059 2.538
I.3. Mesin-mesin dan perlengkapan geladak.
* Jangkar dan Rantai
- Jangkar 2 SET 0.232 90.000% 0.209 0.000 0.209
- Rantai jangkar 14 SEGEL 0.811 90.000% 0.730 0.000 0.730
- Perlengkapan jangkar 2 SET 0.219 90.000% 0.197 0.000 0.197
* Mesin Geladak
- Windlass + warping end 2 UNIT 1.344 92.000% 1.176 0.060 1.236
- Winch rampa haluan + twin drum + warping end 1 UNIT 0.541 92.000% 0.473 0.024 0.497
- Winch rampa buritan + twin drum + warping end 1 UNIT 0.425 92.000% 0.372 0.019 0.391
* Mesin Kemudi
- Mesin Kemudi (steering gear) & Tiller/Joystick tipe non-follow up 1 SET 1.008 87.500% 0.882 0.000 0.882
- Steering Wheel tipe non-follow up R.Kemudi 1 SET 0.190 80.000% 0.152 0.000 0.152
- Emergency Steering Wheel di Kamar Mesin Kemudi 1 SET 0.126 80.000% 0.044 0.057 0.101
- Rudder Angle Indicator Tiap Daun Kemudi 2 SET 0.051 80.000% 0.018 0.023 0.040
- Tongkat Kemudi 2 SET 0.605 80.000% 0.212 0.272 0.484
* Perlengkapan Tambat dan tali temali
- Fairlead 8 SET 0.160 98.000% 0.152 0.005 0.157
- Double Bollard 4 SET 0.101 90.000% 0.091 0.000 0.091
- Tali tarik 1 ROLL 0.063 0.000% 0.000 0.000 0.000
- Tali tambat 4 ROLL 0.154 0.000% 0.000 0.000 0.000
* Dewi-dewi & Winch sekoci penolong tipe Pivot 1 SET 0.123 80.000% 0.000 0.098 0.098
* Perlengkapan Pintu Rampa 2 SET 0.049 0.000% 0.000 0.000 0.000
* Perlengkapan Pengikatan Kendaraan
- Titik Penahan D-Ring 69 set 0.145 100.000% 0.131 0.015 0.145
- Tali Pengikat (web lashing) Truk Sedang 22 set 0.058 0.000% 0.000 0.000 0.000
- Tali Pengikat (web lashing) Truk Besar 18 set 0.057 0.000% 0.000 0.000 0.000
- Kotak Penyimpanan 2 set 0.028 0.000% 0.000 0.000 0.000
* Perlengkapan penyejuk ruangan (Air Conditioner Split Type)
- AC Split 1/2 PK 2 UNIT 0.041 90.000% 0.037 0.000 0.037
- Setiap ruang akomodasi Nakhoda & KKM
- AC Split 3/4 PK 2 UNIT 0.049 90.000% 0.044 0.000 0.044
- Setiap ruang akomodasi ABK
- AC Split 2 PK 16 UNIT 0.452 90.000% 0.406 0.000 0.406
- Ruang Kemudi (2 unit)
- Dapur (1 unit)
- Ruang akomodasi penumpang haluan (5 unit)
- Ruang akomodasi penumpang buritan (6 unit)
- Ruang kontrol kamar mesin (1 unit)
Sub Total Progres I.3 7.033 5.326 0.574 5.899
I.4. Perlengkapan Rumah Geladak
* Insulation dan Interior R. Akomodasi Tertutup :
- Lapisan isolasi Laminasi Rockwool & Aluminium Foil 30 mm 1 SHIPSET 0.841 90.000% 0.756 0.000 0.756
- Langit-langit (ceiling) R. Akomodasi
- Dinding (lining & bulkhead) R. Akomodasi
- Panel B-15 Laminasi (sandwich) Rockwool & Aluminium langit-langit 1 SHIPSET 0.718 70.000% 0.503 0.000 0.503
- Langit-langit (ceiling) R. Akomodasi
- Panel B-15 Laminasi (sandwich) Rockwool & Aluminium Dinding 1 SHIPSET 0.852 70.000% 0.597 0.000 0.597
- Dinding (lining & bulkhead) R. Akomodasi
- Partisi Garida (double partition) R. Akomodasi ABK & Penumpang
- Panel B-15 Laminasi (sandwich) Rockwool & Stainless steel dinding 1 SHIPSET 0.403 70.000% 0.282 0.000 0.282
- Dinding (lining & bulkhead) Dapur
- Panel B-0 Laminasi (sandwich) Rockwool & aluminium partisi 1 SHIPSET 0.336 70.000% 0.235 0.000 0.235
- Partisi (partition) KM/WC
- Lapisan dekoratif langit-langit dan dinding (wall paper)
- Dinding ruang kemudi 1 SHIPSET 0.156 70.000% 0.109 0.000 0.109
- Langit-langit ruang kemudi 1 SHIPSET 0.115 70.000% 0.080 0.000 0.080
- Dinding langit-langit lainnya 1 SHIPSET 0.168 70.000% 0.118 0.000 0.118
- Lantai (Floating Floor) :
- Panel laminasi lantai apung rockwool & galvanized steel 1 SHIPSET 0.916 98.000% 0.898 0.000 0.898
- Lapisan pelindung vynil 1 SHIPSET 0.362 70.000% 0.254 0.000 0.254
- Lapisan pelindung parquet kayu 1 SHIPSET 0.758 70.000% 0.531 0.000 0.531
- Lapisan Pelindung Sika & Keramik Ruang Basah 1 SHIPSET 0.304 98.000% 0.298 0.000 0.298

Page 2
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
* Insulation dan Interior R. Akomodasi Terbuka :
- Lantai Panel Sintetik Kayu G.Antara, G.Penumpang & G.Navigasi 1 SHIPSET 0.834 70.000% 0.584 0.000 0.584
* Insulation dan Interior Kamar Mesin
- Lapisan isolasi Laminasi Rockwool & Aluminium Foil 50 mm : 1 SHIPSET 0.365 80.000% 0.292 0.000 0.292
- Dinding Koridor Tangga Kamar Mesin
- Dinding R.Kontrol Kamar Mesin
- Dinding R.Generator Darurat
- Langit-langit R.Kontrol Kamar Mesin
- Langit-langit R.Generator Darurat
- Lapisan Akustik Laminasi Acoustic Foil & Perforated Steel Plate : 1 SHIPSET 0.447 70.000% 0.313 0.000 0.313
- Dinding R.Kontrol Kamar Mesin
- Dinding R.Generator Darurat
- Langit-langit R.Kontrol Kamar Mesin
- Langit-langit Kamar Mesin
- Langit-langit R.Generator Darurat
* PINTU KEDAP CUACA (WEATHERTIGHT DOOR)
- Pintu Kedap Cuaca 1400 x 600 mm : 8 SET 0.209 98.000% 0.205 0.000 0.205
- Ruang Generator Darurat & R.Sprinkler P/S
- Akses Cuaca Kamar Mesin P/S
- Akses Dalam Kamar Mesin P/S
- Ruang Rantai Jangkar P/S
- Pintu Kedap Cuaca 1600 x 600 mm : 4 SET 0.116 98.000% 0.114 0.000 0.114
- Akses Cuaca Haluan G.Antara P/S
- Akses Cuaca Buritan G.Antara P/S
* PINTU KABIN KEDAP CUACA (WEATHERTIGHT CABIN DOOR)
- Pintu Kabin Kedap Cuaca 1700 x 700 mm Jendela Bulat : 10 SET 0.211 70.000% 0.147 0.000 0.147
- Akses R.Kontrol Kamar Mesin
- Akses Cuaca Haluan G.Antara P/S
- Akses Cuaca Samping G.Penumpang P/S
- Akses Cuaca Buritan G.Penumpang P/S
- Akses Cuaca Samping G.Navigasi
* PINTU KABIN (CABIN DOOR)
- Pintu Kabin 1700 x 700 mm Jendela Bulat : 6 SET 0.126 70.000% 0.088 0.000 0.088
- Akses Dapur G.Penumpang
- Akses Mess G.Penumpang
- Akses Cafetaria G.Penumpang
- Akses R.Penumpang Buritan G.Penumpang P/S
- Akses R.Kemudi G.Navigasi
- Pintu Kabin 1700 x 700 mm : 2 SET 0.042 70.000% 0.029 0.000 0.029
- Akses R.CO2 & Gudang G.Kendaraan P/S
- Pintu Kabin 1700 x 700 mm Kisi-kisi Ventilasi : 2 SET 0.042 70.000% 0.029 0.000 0.029
- Akses Akomodasi Perwira G.Navigasi
- Pintu Kabin KM/WC 1700 x 600 mm : 5 SET 0.105 70.000% 0.074 0.000 0.074
- Akses KM/WC G.Antara P/S
- Akses KM/WC G.Penumpang P/S
- Akses KM/WC G.Navigasi
- Pintu Kabin Partisi 1700 x 700 mm Jendela Bulat : 2 SET 0.042 70.000% 0.029 0.000 0.029
- Akses R.Penumpang Haluan G.Penumpang P/S
- Pintu Kabin 1700 x 700 mm Kisi-kisi Ventilasi : 2 SET 0.042 70.000% 0.029 0.000 0.029
- Akses R.Akomodasi ABK G.Navigasi
- Pintu Partisi KM/WC 1700 x 600 mm : 6 SET 0.126 70.000% 0.088 0.000 0.088
- Akses KM/WC Penumpang G.Penumpang
* JENDELA BULAT (SIDE SCUTTLE)
- Jendela Bulat Dilengkapi Engsel : 4 SET 0.024 100.000% 0.024 0.000 0.024
- KM/WC Penumpang G.Penumpang P/S
* JENDELA KOTAK (SQUARE WINDOW)
- Jendela Kotak 400x600 mm : 6 SET 0.094 100.000% 0.094 0.000 0.094
- Akomodasi ABK G.Navigasi
- Mess G.Navigasi
- Jendela Kotak 700x500 mm KM/WC G.Penumpang P/S 2 SET 0.033 100.000% 0.033 0.000 0.033
- Jendela Kotak 700x1100 mm : 28 SET 0.549 100.000% 0.549 0.000 0.549
- Haluan & Buritan R.Penumpang G.Penumpang
- Samping R.Penumpang G.Penumpang
- Jendela Kotak Navigasi 1000x1000 mm 3 SET 0.055 100.000% 0.055 0.000 0.055
- Jendela Prisma Segiempat Navigasi 1200x1000 mm 12 SET 0.248 100.000% 0.248 0.000 0.248
- Jendela Kotak R.Kontrol Kamar Mesin 900x800 mm 3 SET 0.052 80.000% 0.042 0.000 0.042
- Jendela Gulung (rolling window) cafetaria 1 SET 0.015 70.000% 0.010 0.000 0.010
* Lapisan Kaca Film Jendela Kotak R.Penumpang G.Penumpang 1 LOT 0.034 80.000% 0.027 0.000 0.027
* Furniture
- Kursi Akomodasi :
- Kursi Pilot R.Kemudi 2 set 0.077 70.000% 0.054 0.000 0.054
- Bangku Sofa Berlaci Kapasitas 3 orang R.Kemudi 1 set 0.012 70.000% 0.009 0.000 0.009
- Kursi Kerja untuk meja kerja, peta & meja radio 6 UNIT 0.024 70.000% 0.017 0.000 0.017
- Kursi Kerja Putar Sandaran Tangan R.Kontrol Kamar Mesin 2 UNIT 0.010 70.000% 0.007 0.000 0.007
- Kursi Sofa L Kap.5 org R.Mess ABK 1 SET 0.026 70.000% 0.018 0.000 0.018
- Kursi Panjang Gang Kapasitas 2 org R.Penumpang Terbuka 10 UNIT 0.118 70.000% 0.083 0.000 0.083
- Kursi Panjang Gang Kapasitas 3 org R.Penumpang Terbuka 14 UNIT 0.227 70.000% 0.159 0.000 0.159
- Kursi Panjang Gang Kapasitas 4 org R.Penumpang Terbuka 31 UNIT 0.551 70.000% 0.386 0.000 0.386
- Kursi Sofa Tunggal Ergonomis R.Penumpang Haluan 50 UNIT 0.406 70.000% 0.284 0.000 0.284

Page 3
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
- Kursi Sofa Lingkar Kap.8 org R.Penumpang Buritan 4 UNIT 0.110 70.000% 0.077 0.000 0.077
- Kursi Sofa Lingkar Kap.6 org R.Penumpang Buritan 4 UNIT 0.109 70.000% 0.076 0.000 0.076
- Mebel Akomodasi :
- Meja Kemudi & NAVCOM R.Kemudi 1 set 0.013 70.000% 0.009 0.000 0.009
- Meja Peta & Lemari Penyimpanan SET R.Kemudi 1 set 0.013 70.000% 0.009 0.000 0.009
- Meja Radio & Lemari Penyimpanan SET R.Kemudi 1 set 0.013 70.000% 0.009 0.000 0.009
- Lemari Panel Listrik & Alarm SET R.Kemudi 1 set 0.016 70.000% 0.011 0.000 0.011
- Tempat Tidur Tunggal Berlaci 2 set 0.046 70.000% 0.032 0.000 0.032
- Tempat Tidur Tingkat Berlaci 4 set 0.093 70.000% 0.065 0.000 0.065
- Lemari Gantung Akomodasi ABK Dua Pintu 4 set 0.063 70.000% 0.044 0.000 0.044
- Lemari Televisi SET R.Mess 1 set 0.016 70.000% 0.011 0.000 0.011
- Meja Makan R.Mess 1 set 0.013 70.000% 0.009 0.000 0.009
- Meja Kerja Berlaci Akomodasi ABK 4 set 0.054 70.000% 0.038 0.000 0.038
- Meja Panjang R.Penumpang Terbuka G.Navigasi 8 set 0.108 70.000% 0.075 0.000 0.075
- Meja Sofa R.Penumpang Buritan G.Penumpang 8 set 0.108 70.000% 0.075 0.000 0.075
- Rak Gantung R.Penumpang Buritan G.Penumpang 1 LOT 0.158 70.000% 0.111 0.000 0.111
- Kitchen SET lengkap Dapur ABK 1 set 0.029 70.000% 0.021 0.000 0.021
- Cafetaria SET R.Penumpang Buritan G.Penumpang 1 set 0.053 70.000% 0.037 0.000 0.037
- Bracket Televisi Layar Datar 6 UNIT 0.046 70.000% 0.032 0.000 0.032
- Lemari Jaket Penyelamat 6 set 0.096 70.000% 0.067 0.000 0.067
- Meja Berlaci Panel Mesin & Genset R.Kontrol Kamar Mesin 1 set 0.013 70.000% 0.009 0.000 0.009
- Mebel KM/WC :
- Toilet Duduk Tangki Flush Otomatis Semprotan Pembersih 7 set 0.121 99.000% 0.120 0.000 0.120
- Toilet Jongkok Tangki Flush Otomatis Semprotan Pembersih 2 set 0.024 98.000% 0.024 0.000 0.024
- Urinoir 3 set 0.023 70.000% 0.016 0.000 0.016
- Mini Wash Basin SET KM/WC Dalam 3 set 0.035 98.000% 0.034 0.000 0.034
- Wash Basin KM/WC Penumpang G.Penumpang 4 set 0.076 99.000% 0.075 0.000 0.075
- Rak & Perlengkapan Serang Gudang Gld.Kendaraan 1 LOT 0.114 70.000% 0.080 0.000 0.080
- Perlengkapan Komaliwan 1 LOT 0.080 70.000% 0.056 0.000 0.056
- Perlengkapan Kamar Tidur 1 LOT 0.274 70.000% 0.192 0.000 0.192
Sub Total Progres I.4 13.109 10.196 0.000 10.196

Total Progres I 47.519 41.519 0.850 42.369

II. PERALATAN & PERLENGKAPAN NAVIGASI, KOMUNIKASI,


KESELAMATAN & KEBAKARAN
II.1. NAVIGASI
* Perlengkapan Navigasi
- Peta Pelayaran & Perlengkapannya 1 Shipset 0.088 0.000% 0.000 0.000 0.000
- Bendera & Perlengkapannya 1 Shipset 0.014 0.000% 0.000 0.000 0.000
- Buku-buku Navigasi 1 Shipset 0.008 0.000% 0.000 0.000 0.000
- Gambar-gambar as build drawing di kapal 1 Shipset 0.105 0.000% 0.000 0.000 0.000
- Teropong Jauh (binocular) 2 UNIT 0.005 0.000% 0.000 0.000 0.000
- Benda Tanda Berlabuh Siang Hari 3 UNIT 0.028 0.000% 0.000 0.000 0.000
- Hand Lead 2 UNIT 0.014 0.000% 0.000 0.000 0.000
* Peralatan Navigasi
- Marine Radar X-Band dengan peta elektronik 1 SET 0.560 90.000% 0.392 0.112 0.504
- Magnetic Compass 1 SET 0.173 90.000% 0.121 0.035 0.155
- Bridge Navigational Watch Alert System (BNWAS) 1 SET 0.105 90.000% 0.074 0.021 0.095
- Automatic Identification System (AIS) 1 SET 0.164 90.000% 0.115 0.033 0.148
- Global Positioning System (GPS) dengan Peta Electronik 1 SET 0.152 90.000% 0.106 0.030 0.137
- Global Positioning System (GPS) standar Meja Peta 1 SET 0.025 90.000% 0.018 0.005 0.023
- Pengukur Kecepatan (speed log) 1 SET 0.029 90.000% 0.021 0.006 0.027
- Pengukur Kedalaman (Echo Sounder) 1 SET 0.211 90.000% 0.147 0.042 0.190
- Penghapus Kaca/Marine Wiper Jendela Navigasi 15 SET 0.240 0.000% 0.000 0.000 0.000
- Air Pressure Horn 1 SET 0.005 0.000% 0.000 0.000 0.000
- Digital Anemometer & Wind Direction 1 SET 0.038 0.000% 0.000 0.000 0.000
- Digital Clinometer 1 SET 0.007 0.000% 0.000 0.000 0.000
- Analog Clinometer R.Kemudi & R.Kontrol Kamar Mesin 2 SET 0.013 0.000% 0.000 0.000 0.000
- Barometer 1 SET 0.019 0.000% 0.000 0.000 0.000
- Marine Clock R.Kemudi, R.Nahkoda & R.Kontrol Kamar Mesin 3 SET 0.080 0.000% 0.000 0.000 0.000
Sub Total Progres II.1 2.084 0.994 0.284 1.278
II.2. KOMUNIKASI
* Peralatan komunikasi Ruangan
- Public Adressor 1 Shipset 0.025 90.000% 0.018 0.005 0.023
- Interphone System 1 Shipset 0.021 90.000% 0.015 0.004 0.019
- Engine Telegraph 1 SET 0.078 90.000% 0.055 0.016 0.071
- Sistem Alarm & Indikator 1 Shipset 0.046 90.000% 0.032 0.009 0.042
- Sistem Pemantauan CCTV 1 Shipset 0.219 90.000% 0.153 0.044 0.197
* Peralatan komunikasi Hiburan
- Multimedia Workstation 1 SET 0.042 90.000% 0.029 0.008 0.038
- Radio/CD/DVD Blue Ray SET Player 1 SET 0.034 90.000% 0.024 0.007 0.030
- Audio Amplifier SET 1 SET 0.027 90.000% 0.019 0.005 0.025
- Speaker Coaxial 3 way system 18 UNIT 0.057 90.000% 0.040 0.011 0.051
- Video Amplifier SET 1 SET 0.015 90.000% 0.010 0.003 0.013
- Televisi Layar Datar 32" 6 UNIT 0.076 70.000% 0.053 0.000 0.053
- Televisi Satellite Receiver & Antena 1 SET 0.008 90.000% 0.006 0.002 0.008
* Peralatan Komunikasi Radio Perairan Pedalaman

Page 4
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
- VHF Radio telephone DSC watch receiver 2 SET 0.298 90.000% 0.209 0.060 0.269
- Antenna System
- VHF Antenna 1 SET 0.012 90.000% 0.009 0.002 0.011
- Two Way VHF Radio Telephone Apparatus 2 SET 0.050 90.000% 0.035 0.010 0.045
- Handy Talkie komunikasi internal kapal 5 UNIT 0.044 90.000% 0.031 0.009 0.039
Sub Total Progres II.2 1.054 0.738 0.196 0.933
II.3 PERLENGKAPAN KESELAMATAN
- Sekoci Penyelamat Cepat Kap. 6 org. 1 UNIT 0.448 80.000% 0.313 0.045 0.358
- Tangga Tali Darurat 2 UNIT 0.011 70.000% 0.007 0.000 0.007
- Rakit Penyelamat (inflatable life raft/ILR) 14 UNIT 1.401 70.000% 0.981 0.000 0.981
- Gelang Pelampung (life buoy) :
- Sinyal Asap & Lampu 2 UNIT 0.004 80.000% 0.003 0.000 0.003
- Tali 30m 2 UNIT 0.002 70.000% 0.001 0.000 0.001
- Lampu 2 UNIT 0.001 70.000% 0.001 0.000 0.001
- Biasa 2 UNIT 0.001 70.000% 0.000 0.000 0.000
- Jaket Penyelamat (life jacket) :
- Dewasa dengan Lampu 320 UNIT 0.416 70.000% 0.291 0.000 0.291
- Anak-anak 40 UNIT 0.042 70.000% 0.029 0.000 0.029
- Baju Renang (immersion suit) dengan peralatan selam' 2 UNIT 0.197 70.000% 0.138 0.000 0.138
- Pelempar Tali Otomatis (line throwing apparatus) 2 UNIT 0.029 0.000% 0.000 0.000 0.000
- Red Hand Flare 2 UNIT 0.002 0.000% 0.000 0.000 0.000
- Sinyal Parasut 2 UNIT 0.002 0.000% 0.000 0.000 0.000
- Sinyal Asap Otomatis 2 UNIT 0.002 0.000% 0.000 0.000 0.000
- Perlengkapan P3K 2 UNIT 0.008 0.000% 0.000 0.000 0.000
- Gambar rencana evakuasi cetak warna diatas whiteboard 2 UNIT 0.018 0.000% 0.000 0.000 0.000
- Gambar rencana kendali kebakaran cetak warna diatas whiteboard 2 UNIT 0.018 0.000% 0.000 0.000 0.000
Sub Total Progres II.3 2.601 1.766 0.045 1.811
II.4. PERLENGKAPAN KEBAKARAN
- Perlengkapan Pemadam Hidran :
- Selang Nozzle & Kopling Hidran SET 9 SET 0.062 70.000% 0.043 0.000 0.043
- Kotak Penyimpanan Pintu Kaca 9 SET 0.017 70.000% 0.012 0.000 0.012
- Pemadam Jinjing (portable) :
- Busa (foam) 9 liter 10 UNIT 0.028 70.000% 0.020 0.000 0.020
- Bubuk (powder) 6.8 kg 6 UNIT 0.015 70.000% 0.010 0.000 0.010
- CO2 6.8 kg 1 UNIT 0.007 70.000% 0.005 0.000 0.005
- Pemadam Foam @45 liter Beroda 1 UNIT 0.024 70.000% 0.017 0.000 0.017
- Baju Tahan Api dilengkapi Alat bantu pernapasan 2 UNIT 0.077 70.000% 0.054 0.000 0.054
- Alat Bantu Pernapasan (emergency escape breathing device/EEBD) 4 UNIT 0.169 70.000% 0.118 0.000 0.118
- Water fog apllicator 4 UNIT 0.056 70.000% 0.039 0.000 0.039
- Portable Foam apllicator 2 UNIT 0.049 70.000% 0.034 0.000 0.034
- Perlengkapan Petugas Pemadam SET 2 SET 0.035 70.000% 0.025 0.000 0.025
- Tombol Tekan & Bel Kebakaran (manual call point) 12 SET 0.042 70.000% 0.029 0.000 0.029
Sub Total Progres II.4 0.581 0.407 0.000 0.407

Total Progres II 6.320 3.904 0.524 4.428

III. INSTALASI MESIN


III.1. Mesin Induk & Perlengkapan
* Mesin Induk
- Heavy Duty Marine Diesel Engine & Remote Control 2 SET 12.661 92.000% 11.648 0.000 11.648
- Panel Indikator Mesin & Alarm 4 SET 0.152 80.000% 0.121 0.000 0.121
- Baterai Starter 2 SET 0.084 80.000% 0.067 0.000 0.067
- Kotak Transmisi (gear box) 2 SET 0.850 92.000% 0.782 0.000 0.782
* Propulsi
- Baling-baling 2 SET 1.011 35.000% 0.354 0.000 0.354
- Poros Baling-baling 2 SET 0.800 35.000% 0.280 0.000 0.280
- Tabung Poros Baling-baling 2 SET 0.337 95.000% 0.270 0.051 0.320
- Panel Indikator putaran poros baling-baling 4 UNIT 0.118 35.000% 0.041 0.000 0.041
Sub Total Progres III.1 16.013 13.563 0.051 13.614
III.2. Mesin Bantu & Perlengkapan
* Mesin Bantu Utama
- Marine Diesel Engine & Generator SET 2 SET 5.484 92.000% 5.045 0.000 5.045
- Panel Indikator Mesin & Alarm 2 SET 0.051 92.000% 0.047 0.000 0.047
- Baterai Starter 2 SET 0.059 80.000% 0.047 0.000 0.047
* Mesin Bantu Pendukung
- Marine Diesel Engine & Generator SET Pelabuhan 1 SET 0.597 92.000% 0.522 0.027 0.549
- Marine Diesel Engine & Generator SET Darurat 1 SET 0.632 92.000% 0.553 0.028 0.581
Sub Total Progres III.2 6.823 6.214 0.055 6.270
III.3. Pompa-pompa
* Pompa Kamar Mesin
- Pompa Bilga 1 UNIT 0.074 95.000% 0.070 0.000 0.070
- Pompa Dinas Umum & Pemadam Kebakaran 1 UNIT 0.074 95.000% 0.070 0.000 0.070
- Pompa Pemadam Kebakaran Drencher 1 UNIT 0.257 95.000% 0.244 0.000 0.244
- Pompa Ballas 1 UNIT 0.074 95.000% 0.070 0.000 0.070
- Pompa Sewage 2 UNIT 0.079 95.000% 0.075 0.000 0.075
- Pompa Transfer Bahan Bakar 1 UNIT 0.119 95.000% 0.113 0.000 0.113
- Hidrofor Air Laut & 1 Pompa 1 SET 0.097 95.000% 0.092 0.000 0.092
- Hidrofor Air Tawar & 2 Pompa 1 SET 0.131 95.000% 0.124 0.000 0.124

Page 5
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
- Pemisah Air Minyak 1 SET 0.219 95.000% 0.208 0.000 0.208
- Pompa Minyak Kotor 1 UNIT 0.122 95.000% 0.116 0.000 0.116
- Kompresor Udara & Botol Angin 1 SET 0.040 95.000% 0.038 0.000 0.038
- Pompa Tangan Transfer Bahan Bakar 1 UNIT 0.026 95.000% 0.025 0.000 0.025
- Pompa Tangan Transfer Minyak Lumas 1 UNIT 0.026 95.000% 0.025 0.000 0.025
* Pompa Luar Kamar Mesin
- Pompa Bilga Darurat 1 UNIT 0.067 95.000% 0.064 0.000 0.064
- Pompa Pemadam Kebakaran Darurat 1 UNIT 0.067 95.000% 0.064 0.000 0.064
- Hidrofor Air Tawar Pemadam Sprinkler & 1 Pompa 1 SET 0.097 95.000% 0.085 0.007 0.092
* Tangki-Tangki Harian
- Tangki Sewage 2 UNIT 0.463 99.500% 0.461 0.000 0.461
- Tangki Bahan Bakar Mesin Induk 2 UNIT 0.510 99.500% 0.507 0.000 0.507
- Tangki Bahan Bakar Mesin Bantu 1 UNIT 0.255 99.500% 0.254 0.000 0.254
- Tangki Bahan Bakar Generator Set darurat 1 UNIT 0.031 99.500% 0.031 0.000 0.031
- Tangki Minyak Lumas 1 UNIT 0.031 99.500% 0.031 0.000 0.031
Sub Total Progres III.3 2.859 2.767 0.007 2.774
III.4. Suku Cadang & Inventaris
- Suku Cadang Mesin Induk, Mesin Bantu, Gear, Pompa-pompa 1 LOT 1.580 90.000% 1.422 0.000 1.422
- Inventaris Kamar Mesin 1 LOT 0.463 0.000% 0.000 0.000 0.000
Sub Total Progres III.4 2.043 1.422 0.000 1.422
III.5. Sistem & Pipa
* Sistem Pipa Duga, Isi & Udara 1 LOT 0.177 94.802% 0.168 0.000 0.168
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Air Tawar 1 LOT 0.451 95.000% 0.424 0.004 0.428
- Pipa & Fitting
- Valve & Cocks
- Manifold
- Pancuran Air/Shower di tiap KM/WC
* Sistem Pipa Bahan Bakar 1 LOT 0.202 92.982% 0.188 0.000 0.188
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Minyak Lumas 1 LOT 0.135 92.982% 0.125 0.000 0.125
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Bilga 1 LOT 0.139 95.000% 0.132 0.000 0.132
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Ballas 1 LOT 0.164 95.000% 0.156 0.000 0.156
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Pemadam Kebakaran Hidran & Dinas Umum 1 LOT 0.126 94.219% 0.119 0.000 0.119
- Pipa & Fitting
- Valve & Cocks
- Manifold
- Hidran Pemadam
- International Shore Connection (P/S)
* Sistem Pipa Pemadam Kebakaran Drencher 1 LOT 0.114 86.484% 0.098 0.001 0.098
- Pipa & Fitting
- Valve & Cocks
- Manifold
- Corong Drencher
- Electric Pneumatic Valve kendali jarak jauh R.Kemudi
- Panel & Alarm Zona Drencher R.Kemudi
* Sistem Pipa Pemadam Kebakaran Sprinkler 1 LOT 0.126 93.125% 0.116 0.002 0.118
- Pipa & Fitting
- Valve & Cocks
- Manifold
- Corong Drencher
* Sistem Pipa Pemadam Kebakaran CO2 Kamar Mesin 1 LOT 0.053 88.750% 0.045 0.001 0.047
- Pipa & Fitting
- Valve & Cocks
- Manifold
- Corong CO2
- Tabung CO2 7x@45 kg
* Sistem Detektor Kebakaran
- Detektor Panas 8 titik 1 LOT 0.022 0.000% 0.000 0.000 0.000
- Detektor Asap 40 titik 1 LOT 0.051 0.000% 0.000 0.000 0.000
* Sistem Pipa Pendinginan Mesin Air Laut 1 LOT 0.085 94.350% 0.068 0.012 0.080
- Pipa & Fitting
- Valve & Cocks

Page 6
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)
- Manifold
* Sistem Pipa Saniter Air Laut 1 LOT 0.081 95.000% 0.076 0.001 0.077
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Pengeringan Geladak 1 LOT 0.096 95.000% 0.091 0.000 0.091
- Pipa & Fitting
- Valve & Cocks
- Scupper
* Sistem Pipa Utama Air Laut 1 LOT 0.111 95.000% 0.105 0.000 0.105
- Pipa & Fitting
- Valve & Cocks
- Saringan (strainer)
* Sistem Pipa Pembuangan Air Kotor 1 LOT 0.100 95.000% 0.095 0.000 0.095
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Pembuangan Minyak Kotor 1 LOT 0.055 95.000% 0.044 0.008 0.052
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Gas Buang
- Gas Buang Mesin Induk 2 SET 0.113 88.684% 0.097 0.003 0.100
- Gas Buang Mesin Bantu 2 SET 0.094 95.000% 0.075 0.014 0.089
- Gas Buang Generator Pelabuhan 1 SET 0.043 95.000% 0.038 0.003 0.041
- Gas Buang Generator Darurat 1 SET 0.023 95.000% 0.020 0.002 0.022
* Sistem Pipa Udara Tekan 1 LOT 0.069 83.570% 0.058 0.000 0.058
- Pipa & Fitting
- Valve & Cocks
- Manifold
* Sistem Pipa Hidrolik Mesin Geladak 1 LOT 0.063 0.000% 0.000 0.000 0.000
- Pipa & Fitting
- Valve & Cocks
- Manifold
Sub Total Progres III.5 2.691 2.339 0.051 2.389

Total Progres III 30.429 26.305 0.164 26.469


IV. INSTALASI LISTRIK
IV.1. Baterai
- Baterai ESEP 2 SET 0.023 0.000% 0.000 0.000 0.000
- Regulator/Charger & Rectifier 1 LOT 0.011 0.000% 0.000 0.000 0.000
- Uninterrubtible Power System (UPS) Peralatan Navcom 1 LOT 0.011 0.000% 0.000 0.000 0.000
Sub Total Progres IV.1 0.046 0.000 0.000 0.000
IV.2. Panel Hubung
- Panel Hubung Utama (Main Switchboard) 1 SET 0.527 90.000% 0.474 0.000 0.474
- Panel Hubung Darurat Arus AC (Emergency Switchboard AC) 1 SET 0.160 90.000% 0.144 0.000 0.144
- Panel Hubung Darurat Arus DC (Emergency Switchboard DC) 1 SET 0.063 80.000% 0.051 0.000 0.051
- Panel Hubung Darat (shore connection board) 1 SET 0.027 80.000% 0.022 0.000 0.022
- Panel Distribusi Lampu Penerangan (lighting distribution board) 1 SET 0.013 80.000% 0.010 0.000 0.010
- Panel Lampu Navigasi (junction lighting board) 1 SET 0.013 80.000% 0.010 0.000 0.010
- Panel Alat Navigasi & Komunikasi (junction navcom board) 1 SET 0.013 80.000% 0.010 0.000 0.010
- Panel Pantau (junction monitoring board) 1 SET 0.013 80.000% 0.010 0.000 0.010
- Panel Peralatan Listrik Akomodasi 1 SET 0.013 80.000% 0.010 0.000 0.010
Sub Total Progres IV.2 0.841 0.741 0.000 0.741
IV.3. Kabel Listrik
- Kabel Listrik 1 LOT 1.334 87.000% 1.161 0.000 1.161
- Penyangga Kabel (cable tray) & Fitting 1 LOT 0.316 90.000% 0.284 0.000 0.284
Sub Total Progres IV.3 1.650 1.445 0.000 1.445
IV.4. Lampu
* Lampu Penerangan Jenis LED
- Lampu Interior 1 LOT 0.214 90.000% 0.150 0.043 0.193
- Lampu Eksterior & Lampu Kerja 1 LOT 0.173 90.000% 0.121 0.035 0.156
- Lampu Darurat 1 LOT 0.096 90.000% 0.067 0.019 0.087
* Lampu Navigasi
- Lampu Utama 1 LOT 0.106 90.000% 0.074 0.021 0.095
- Lampu Darurat 1 LOT 0.056 90.000% 0.039 0.011 0.051
Sub Total Progres IV.4 0.645 0.452 0.129 0.581
IV.5. Peralatan Listrik Rumah Tangga (Home Appliances)
- Microwaves Dapur & Cafetaria 2 UNIT 0.015 0.000% 0.000 0.000 0.000
- Lemari Pendingin Dua Pintu 250 Liter Dapur 1 UNIT 0.017 0.000% 0.000 0.000 0.000
- Lemari Pendingin Minuman 200 Liter Cafetaria 1 UNIT 0.015 0.000% 0.000 0.000 0.000
- Water Dispencer 3 UNIT 0.019 0.000% 0.000 0.000 0.000
- Kompor Listrik 4 mata & Oven Dapur 1 UNIT 0.021 0.000% 0.000 0.000 0.000
- Penyedot Debu 2 UNIT 0.021 0.000% 0.000 0.000 0.000
Sub Total Progres IV.5 0.107 0.000 0.000 0.000

Total Progres IV 3.289 2.638 0.129 2.767

Page 7
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI Progress s/d 20 Juli 2018 : 84.504 %
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA

Rencana Total REALISASI PRESTASI TOTAL


BOBOT S/D REALISASI
BOBOT S/D
NO ITEM PEKERJAAN Volume Satuan Bobot PROGRES MINGGU BOBOT KET.
MINGGU INI
PHISIK LALU MINGGU INI
(%) (%) (%) (%)

V. DOKUMENTASI
- Foto Cetak & Album Elektronik Kapal 1 LOT 0.004 0.000% 0.000 0.000 0.000
- Model Kapal 3 UNIT 0.095 0.000% 0.000 0.000 0.000
- Video Udara (drone) & Promosi Kapal 1 LOT 0.011 0.000% 0.000 0.000 0.000
- Video Animasi Petunjuk Keselamatan di Kapal 1 LOT 0.014 0.000% 0.000 0.000 0.000

Total Progres V 0.124 0.000 0.000 0.000

TOTAL BAHAN DAN PERLENGKAPAN 87.681 74.366 1.667 76.033


B JASA PEMBANGUNAN / PEMBUATAN KAPAL

VI JASA GALANGAN PEMBANGUN


VI.1 Persiapan, gambar dan konstruksi
1 Pekerjaan Muold loft, pengemalan, & persiapan building berth 1 LOT 0.176 100.000% 0.176 0.000 0.176
2 Pembuatan desain, gambar kerja & final drawing 1 SET 1.053 72.652% 0.746 0.019 0.765
3 Konstruksi 1 LOT 6.127 99.581% 6.047 0.055 6.102
4 Peluncuran 1 LOT 0.527 0.000% 0.000 0.000 0.000
Sub Total Progres VI.1 7.883 6.969 0.074 7.042
VI.2 Perlengkapan dan interior
1 Perlengkapan lambung dan geladak 1 LOT 0.211 30.352% 0.058 0.006 0.064
2 Interior ruangan-ruangan 1 LOT 0.614 23.251% 0.132 0.011 0.143
3 Pengecatan dan perlindungan karat 1 LOT 0.193 26.697% 0.050 0.001 0.052
Sub Total Progres VI.2 1.018 0.241 0.018 0.258
VI.3 Permesinan dan perlengkapannya
1 Instalasi mesin-mesin geladak 1 LOT 0.088 54.824% 0.034 0.014 0.048
2 Instalasi mesin induk 1 LOT 0.140 78.627% 0.110 0.000 0.110
3 Instalasi mesin bantu 1 LOT 0.053 71.898% 0.036 0.001 0.038
4 Instalasi perlengkapan dalam kamar mesin 1 LOT 0.035 93.826% 0.033 0.000 0.033
5 Instalasi perpipaan 1 LOT 0.474 64.966% 0.264 0.044 0.308
Sub Total Progres VI.3 0.790 0.478 0.059 0.537
VI.4 Listrik dan perlengkapannya
1 Instalasi kabel-kabel listrik & fitting 1 LOT 0.176 75.745% 0.133 0.000 0.133
2 Instalasi panel-panel 1 LOT 0.035 81.704% 0.029 0.000 0.029
Sub Total Progres VI.4 0.211 0.162 0.000 0.162
VI.5 Pemeriksaan dan pengujian
Pemeriksaan dan pengujian konstruksi 1 LOT 0.075 95.806% 0.072 0.000 0.072
Pemeriksaan dan pengujian permesinan 1 LOT 0.091 0.000% 0.000 0.000 0.000
Pemeriksaan dan pengujian kelistrikan 1 LOT 0.032 0.000% 0.000 0.000 0.000
Pemeriksaan dan pengujian pompa & valve 1 LOT 0.025 0.000% 0.000 0.000 0.000
Dock trial dan sea trial 1 LOT 0.105 0.000% 0.000 0.000 0.000
Sub Total Progres VI.5 0.328 0.072 0.000 0.072

Total Progres VI 10.230 7.921 0.151 8.072


VII PIHAK KETIGA
VII.1 Pengawasan dan klasifikasi 1 LOT 1.229 32.438% 0.399 0.000 0.399
VII.2 Pengurusan perijinan 1 LOT 0.263 0.000% 0.000 0.000 0.000
VII.3 Training dan alih teknologi 1 LOT 0.246 0.000% 0.000 0.000 0.000
VII.4 Penyeberangan 1 LOT 0.351 0.000% 0.000 0.000 0.000
Total Progres VII 2.089 0.399 0.000 0.399

TOTAL JASA PEMBANGUNAN KAPAL 12.319 8.320 0.151 8.471

TOTAL 100.000 82.685 1.818 84.504

Menyetujui Mengetahui, Porsea, 20 Juli 2018


PEJABAT PEMBUAT KOMITMEN KONTRAKTOR PEMBANGUN KONSULTAN PENGAWAS
BPTD WILAYAH II PROV. SUMATERA UTARA PT. DOK BAHARI NUSANTARA PT. SWASTIKA PERDANA CONSULTANT

Drs. Rijaya S., M.M. Dimas Munandar, S.T. Moch. Amintadaya, S.T.
Pembina (IV/a) Kepala Proyek Koordinator Pengawas
NIP. 19670621 198803 1 004

Page 8
PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA PERIODE : JULI 2018

BOBOT 2017 2018


No. Iitem Ket.
(%) Agust Sept Okt Nov Des Jan Feb Mar Apr Mei Jun Jul Agust Sept Okt Nov
I LAMBUNG
Rencana 6.062 6.062 1.900 1.900 1.287 1.287 1.287 1.287 0.669 0.669 0.669 0.368 0.368 0.368 0.040
I.1 Bahan baku 24.221
Realisasi 0.000 3.716 5.206 8.432 1.488 1.258 0.678 0.544 0.717 0.159 1.320 0.217
Rencana 0.245 0.245 0.245 0.245 0.199 0.199 0.199 0.199 0.186 0.186 0.186 0.162 0.162 0.162 0.337
I.2 Perlengkapan Lambung 3.157
Realisasi 0.000 0.474 0.000 0.253 0.053 0.266 0.072 0.350 0.175 0.409 0.296 0.191
Rencana 1.635 0.131 0.131 0.636 0.636 0.636 0.636 0.554 0.554 0.554 0.284 0.284 0.284 0.081
I.3 Mesin-mesin dan perlengkapan geladak. 7.033
Realisasi 0.000 0.135 0.774 0.000 0.056 0.064 0.731 0.016 0.000 1.750 1.312 1.061
Rencana 0.428 1.740 1.740 0.266 0.266 0.266 0.266 1.952 1.952 1.952 0.615 0.615 0.615 0.432
I.4 Perlengkapan Rumah Geladak 13.109
Realisasi 0.000 0.000 0.000 0.000 4.583 0.636 2.052 0.000 0.000 2.819 0.106 0.000
II PERALATAN & PERLENGKAPAN NAVIGASI, s/d 20 JULI '18
KOMUNIKASI, KESELAMATAN & KEBAKARAN
Rencana 0.511 0.908 0.169 0.169 0.169 0.157
II.1 NAVIGASI 2.084
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.497 0.000 0.000 0.000 0.497 0.284
Rencana 0.316 0.527 0.070 0.070 0.070
II.2 KOMUNIKASI 1.054
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.278 0.000 0.000 0.000 0.459 0.196
Rencana 0.767 0.934 0.286 0.286 0.286 0.044
II.3 PERLENGKAPAN KESELAMATAN 2.601
Realisasi 0.000 0.000 1.958 0.000 0.000 0.000 0.000 0.000 0.000 1.821 0.000 0.045
Rencana 0.174 0.290 0.039 0.039 0.039
II.4 PERLENGKAPAN KEBAKARAN 0.581
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.407 0.000
III INSTALASI MESIN
Rencana 7.553 1.133 1.526 1.526 1.526 0.916 0.916 0.916
III.1 Mesin Induk & Perlengkapan 16.013
Realisasi 0.000 0.000 0.000 4.811 3.199 0.000 0.000 0.000 3.780 1.419 0.354 0.051
Rencana 1.678 0.369 0.853 0.853 0.853 0.853 0.455 0.455 0.455
III.2 Mesin Bantu & Perlengkapan 6.823
Realisasi 0.000 0.000 0.000 0.000 0.979 0.000 0.000 0.000 0.000 0.000 3.278 0.055
Rencana 0.700 0.803 0.757 0.200 0.200 0.200
III.3 Pompa-pompa 2.859
Realisasi 0.000 0.000 0.000 1.032 0.473 0.000 0.439 0.000 0.514 0.157 0.153 0.007
Rencana 0.316 0.276 0.276 0.276 0.276 0.053 0.053 0.053 0.463
III.4 Suku Cadang & Inventaris 2.043
Realisasi 0.000 0.000 1.106 0.000 0.000 0.000 0.000 0.000 0.316 0.000 0.000 0.000
Rencana 0.789 0.101 0.101 0.101 0.101 0.387 0.387 0.387 0.113 0.113 0.113
III.5 Sistem & Pipa 2.691
Realisasi 0.000 0.000 0.000 0.000 0.000 0.396 0.009 0.001 0.000 0.020 0.000 1.963
IV INSTALASI LISTRIK
Rencana 0.007 0.006 0.006 0.006 0.006 0.006 0.006
IV.1 Baterai 0.046
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Rencana 0.225 0.027 0.143 0.143 0.143 0.053 0.053 0.053
IV.2 Panel Hubung 0.841
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.120 0.000 0.429 0.069 0.123 0.000
Rencana 0.527 0.286 0.286 0.286 0.044 0.044 0.044 0.133
IV.3 Kabel Listrik 1.650
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.934 0.000 0.000 0.449 0.062 0.000
Rencana 0.194 0.065 0.065 0.065 0.065 0.065 0.065 0.065
IV.4 Lampu 0.645
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.136 0.000 0.000 0.000 0.000 0.445
Rencana 0.107
IV.5 Peralatan Listrik Rumah Tangga (Home Appliances) 0.107
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
V DOKUMENTASI Rencana 0.124
0.124
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
VI JASA GALANGAN PEMBANGUN
Rencana 0.964 0.964 0.723 0.723 0.230 0.230 0.230 0.230 0.993 0.993 0.993 0.204 0.204 0.204
VI.1 Persiapan, gambar dan konstruksi 7.883
Realisasi 0.000 0.464 1.319 0.652 1.206 1.293 0.743 0.423 0.646 0.223 0.000 0.074
Rencana 0.021 0.011 0.011 0.057 0.057 0.057 0.057 0.149 0.149 0.149 0.094 0.094 0.094 0.019
VI.2 Perlengkapan dan interior 1.018
Realisasi 0.000 0.002 0.001 0.041 0.009 0.002 0.000 0.000 0.000 0.104 0.028 0.071
Rencana 0.095 0.039 0.039 0.039 0.039 0.111 0.111 0.111 0.058 0.058 0.058 0.032
VI.3 Permesinan dan perlengkapannya 0.790
Realisasi 0.000 0.000 0.000 0.000 0.000 0.008 0.066 0.059 0.009 0.274 0.061 0.060
Rencana 0.021 0.035 0.035 0.035 0.021 0.021 0.021 0.021
VI.4 Listrik dan perlengkapannya 0.211
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.096 0.066 0.000
Rencana 0.023 0.051 0.036 0.036 0.036 0.028 0.028 0.028 0.062
VI.5 Pemeriksaan dan pengujian 0.328
Realisasi 0.000 0.002 0.013 0.008 0.011 0.011 0.003 0.007 0.007 0.009 0.000 0.000
VII JASA PIHAK KE TIGA
Rencana 0.154 0.154 0.031 0.031 0.031 0.031 0.031 0.031 0.123 0.123 0.123 0.082 0.082 0.082 0.123
VII.1 Pengawasan dan klasifikasi 1.229
Realisasi 0.000 0.006 0.000 0.045 0.062 0.063 0.019 0.040 0.041 0.052 0.000 0.000
Rencana 0.033 0.033 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.024 0.024 0.024 0.024 0.024
VII.2 Pengurusan perijinan 0.263
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Rencana 0.246
VII.3 Training dan alih teknologi 0.246
Realisasi 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Rencana -0.056 0.351
VII.4 Penyeberangan 0.351
Realisasi 0.000 0.000 0.071 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Jumlah 100.000
Rencana Per Bulan : 0.000 7.457 19.788 4.790 8.862 2.854 2.854 2.854 6.701 8.559 8.559 11.231 4.210 4.210 4.210 2.862
Akumulasi Rencana Progress Bulanan : 0.000 7.457 27.246 32.036 40.898 43.752 46.607 49.461 56.162 64.720 73.279 84.510 88.719 92.929 97.138 100.000
T-I T - II T - III T - IV T-V T - VI
Realisasi Per Bulan : 0.000 4.799 10.447 15.274 12.118 3.998 6.776 1.439 6.635 9.828 8.524 4.665
Akumulasi Progres Aktual Bulanan : 0.000 4.799 15.246 30.521 42.638 46.636 53.413 54.852 61.487 71.315 79.839 84.504
T-I T - II T - III T - IV
Deviasi Bulan Berjalan : 0.000 -2.658 -11.999 -1.515 1.740 2.884 6.806 5.391 5.325 6.595 6.560 -0.006

Menyetujui, Mengetahui, Porsea, 20 Juli 2018


PEJABAT PEMBUAT KOMITMEN KONTRAKTOR PEMBANGUN KONSULTAN PENGAWAS
BPTD WILAYAH II PROV. SUMATERA UTARA PT. DOK BAHARI NUSANTARA PT. SWASTIKA PERDANA CONSULTANT

Drs. Rijaya S., M.M. Dimas Munandar, S.T. Moch. Amintadaya, S.T.
Pembina (IV/a) Kepala Proyek Koordinator Pengawas
NIP. 19670621 198803 1 004

Page 9
RESUME PROGRESS KEMAJUAN PEKERJAAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL PENYEBERANGAN PENUMPANG Ro-Ro 300 GT
LINTAS DANAU TOBA

No Proyek : DBN-025
DIREKTORAT JENDERAL PERHUBUNGAN DARAT KEMENTERIAN PERHUBUNGAN RI
BALAI PENGELOLA TRANSPORTASI DARAT WILAYAH II PROVINSI SUMATERA UTARA
Galangan : PT. DOK BAHARI NUSANTARA
MINGGU KE : 47

REALISASI PRESTASI TOTAL (%)


RENCANA
s/d s/d DEVIASI
No. Iitem Bobot (%) s/d BULAN KENAIKAN KETERANGAN
MINGGU MINGGU (%)
INI (%) MINGGU INI
LALU INI

I LAMBUNG 47.519 42.339 41.519 0.850 42.369 0.030 MEMENUHI

PERALATAN & PERLENGKAPAN NAVIGASI,


II 6.320 4.428 3.904 0.524 4.428 0.000 MEMENUHI
KOMUNIKASI, KESELAMATAN & KEBAKARAN

III INSTALASI MESIN 30.429 25.355 26.305 0.164 26.469 1.114 MEMENUHI

IV INSTALASI LISTRIK 3.289 2.478 2.638 0.129 2.767 0.289 MEMENUHI

V DOKUMENTASI 0.124 0.000 0.000 0.000 0.000 0.000 MEMENUHI

VI JASA GALANGAN PEMBANGUN 10.230 8.881 7.921 0.151 8.072 -0.809 TIDAK MEMENUHI

VII JASA PIHAK KE TIGA 2.089 1.029 0.399 0.000 0.399 -0.630 TIDAK MEMENUHI

TOTAL 100.000 84.510 82.685 1.818 84.504 -0.006

Page 10
VISUALISASI PEKERJAAN
KONSTRUKSI
VISUALISASI PEKERJAAN KONSTRUKSI
PEMBANGUNAN KAPAL PENYEBERANGAN PENUMPANG RO-RO 300 GT
LINTAS DANAU TOBA (DBN-025)
s/d 20 JULI 2018
PROSES FABRIKASI
Total Progres Proyek = 84.504 %
SELESAI FABRIKASI, PROSES ASSEMBLY

SELESAI ASSEMBLY, PROSES ERECTION

SELESAI/CLOSED
VISUALISASI
Blasting car deck kapal Ferrry DBN-025 on site di Ruang penumpang kapal Ferrry DBN-025 on site di
building berth kawasan Danau Toba building berth kawasan Danau Toba

Blasting car deck kapal Ferrry DBN-025 on site di Blasting car deck kapal Ferrry DBN-025 on site di
building berth kawasan Danau Toba building berth kawasan Danau Toba

Primer painting car deck kapal Ferrry DBN-025 on site di Primer painting car deck kapal Ferrry DBN-025 on site di
building berth kawasan Danau Toba building berth kawasan Danau Toba
Primer painting car deck kapal Ferrry DBN-025 on site di Primer painting car deck kapal Ferrry DBN-025 on site di
building berth kawasan Danau Toba building berth kawasan Danau Toba

Brusting Navigation deck kapal Ferrry DBN-025 on site Primer pinting Navigation deck kapal Ferrry DBN-025 on
di building berth kawasan Danau Toba site di building berth kawasan Danau Toba

Inspeksi Stern Tube dan skerm kapal Ferrry DBN-025 di Inspeksi Stern Tube dan skerm kapal Ferrry DBN-025 di
building berth kawasan Danau Toba building berth kawasan Danau Toba
Pemasangan kulit Skerm kapal Ferrry DBN-025 di Pemasangan IMO number kapal Ferrry DBN-025 di
building berth kawasan Danau Toba building berth kawasan Danau Toba

Assembly Ramdoor kapal Ferrry DBN-025 di building Assembly Ramdoor kapal Ferrry DBN-025 di building
berth kawasan Danau Toba berth kawasan Danau Toba

Tongkat kemudi kapal Ferrry DBN-025 onsite di building Rescue boat kapal Ferrry DBN-025 onsite di building
berth kawasan Danau Toba berth kawasan Danau Toba
Dewi-dewi kapal Ferrry DBN-025 onsite di building berth Dewi-dewi kapal Ferrry DBN-025 onsite di building berth
kawasan Danau Toba kawasan Danau Toba

Peralatan navigasi dan komunikasi kapal Ferrry DBN- Peralatan navigasi dan komunikasi kapal Ferrry DBN-
025 onsite di building berth kawasan Danau Toba 025 onsite di building berth kawasan Danau Toba

Peralatan navigasi dan komunikasi kapal Ferrry DBN- Peralatan navigasi dan komunikasi kapal Ferrry DBN-
025 onsite di building berth kawasan Danau Toba 025 onsite di building berth kawasan Danau Toba
Peralatan navigasi dan komunikasi kapal Ferrry DBN- Peralatan navigasi dan komunikasi kapal Ferrry DBN-
025 onsite di building berth kawasan Danau Toba 025 onsite di building berth kawasan Danau Toba

Overall visual pembangunan kapal Ferrry DBN-025 di Overall visual pembangunan kapal Ferrry DBN-025 di
building berth kawasan Danau Toba building berth kawasan Danau Toba

Overall visual pembangunan kapal Ferrry DBN-025 di Overall visual pembangunan kapal Ferrry DBN-025 di
building berth kawasan Danau Toba building berth kawasan Danau Toba

Anda mungkin juga menyukai