ID Task WBS Task Name Duration Start Finish

14 Apr '19 21 Apr '19 28 Apr '19 05 May '19


Mode S S M T W T F S S M T W T F S S M
1 1 Tender 1 day Mon 22/04/19 Mon 22/04/19
2 2 Kontrak 2 days Tue 23/04/19 Wed 24/04/19
7 3 Persiapan Galangan 3 days Wed 24/04/19 Fri 26/04/19
12 4 Tahap Desain 7 days Mon 29/04/19 Tue 07/05/19
30 5 Fabrikasi 7 days Wed 08/05/19 Thu 16/05/19
40 6 Sub-Assemby 3 days Fri 17/05/19 Tue 21/05/19
43 7 Assemby 4 days Tue 21/05/19 Fri 24/05/19
46 8 Keel Laying 1 day Fri 24/05/19 Fri 24/05/19
47 9 Erection 2 days Mon 27/05/19 Tue 28/05/19
51 10 Launching 1 day Wed 29/05/19 Wed 29/05/19
52 11 Out-Fitting dan Finishing 7 days Thu 30/05/19 Fri 07/06/19

57 12 Test 5 days Mon 10/06/19 Fri 14/06/19


78 13 Persetujuan Kelas dan 2 days Mon 17/06/19 Tue 18/06/19
Sertifikasi
79 14 Delivery 1 day Wed 19/06/19 Wed 19/06/19
80
81
82 Nama Kelompok :
83 Lingga Choiruman F
(04311640000025)
84 Dwi Maharani
(04311640000068)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 22/04/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task WBS Task Name Duration Start Finish
14 Apr '19 21 Apr '19 28 Apr '19 05 May '19
Mode S S M T W T F S S M T W T F S S M
85 Reynaldi Surya Pratama
(04311640000074)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 22/04/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
05 May '19 12 May '19 19 May '19 26 May '19 02 Jun '19 09 Jun '19 16 Jun '19
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 22/04/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
05 May '19 12 May '19 19 May '19 26 May '19 02 Jun '19 09 Jun '19 16 Jun '19
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 22/04/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4

Anda mungkin juga menyukai