Planning (MRP)
2
PENDAHULUAN
Input dan Output MRP
Material
Product Inventory
Requirements
Structure Master
Planning
File File
3
PENDAHULUAN
Input MRP
Master production schedule (MPS) /Jadwal Produksi
Induk
Product structure file (bill of materials)
Inventory master file
4
2. Master Production Schedule
5
Master Production Schedule
6
3.Struktur Produk
7
Indented Bill of Material
LEVEL ITEM Quantity
0---- Clipboard 1
-1--- Clip Assembly 1
--2-- Top Clip 1
---3- Sheet Metal 8
--2-- Bottom Clip 1
---3- Sheet Metal 8
--2-- Pivot 1
---3- Iron Rod 3
--2-- Spring 1
---3- Spring Steel 10
-1--- Rivet 2
-1--- Board 1
--2-- Press Board 1
--2-- Finish 2
8
4. Inventory Master File
9
Physical Inventory Usage/Sales
On hand 100 YTD usage/sales 1,100
Location W142 MTD usage/sales 75
On order 50 YTD receipts 1,200
Allocated 75 MTD receipts 0
Cycle 3 Last receipt 8/25
Difference -2 Last issue 10/5
Codes
Cost acct. 00754
Routing 00326
Engr 07142
10
Inventory Accuracy
Bagaimana caranya?
11
Untuk mencapai akurasi Catatan
12
5.MRP Procedure
Amp-booster
12 Speaker 12 Speaker
MRP Logic Time Phased Product
Structure
Must have D and E
Start production of D completed here so
production can begin on
B
1 week
2 weeks to
D produce
B
2 weeks
E
A
2 weeks 1 week
E
2 weeks 1 week
G C
3 weeks
F
1 week
D
| | | | | | | |
1 2 3 4 5 6 7 8
Time in weeks
6. Matriks MRP
16
Matriks MRP
LLC
low-level-code; level paling rendah suatu item
ditemukan dalam struktur produk
Item
nama atau nomor yang mengidentifikasakan
item terjadwal
Lot size
Ukuran lot
LT (lead time)
Waktu sejak order dipesan sampai order
diterima
17
Matriks MRP
PD (past-due)
orders behind schedule
Gross requirements
Permintaan akan item pada perioda tertentu
Scheduled receipts
Jumlah dalam on order & receipt date
Order yang telah dirilis menjadi scheduled
receipt
18
Matriks MRP
Projected on hand
inventory pada akhir perioda
Net requirements
jumlah bersih yang diperlukan
Planned order receipts
net requirements yang diubah menjadi ukuran
lot
Planned order releases
planned order receipts yang dioffset dengan
lead time
19
7.MRP Example
20
The Alpha Beta Company
A B
LT=3 LT=2
21
MRP Matrices For A & B
Item: A LLC: 0 Period
Lot size: 1 LT: 3 PD 1 2 3 4 5 6 7 8
Gross requirements 100
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10 10 0
Net requirements 90
Planned order receipts 90
Planned order releases 90
22
MRP Matrices For C & D
23
Alpha Beta Planned Order Report
24
Planned Order Report
Item #2740 Date 9-25-98
On hand 100 Lead Time 2 weeks
On order 200 Lot size 200
Allocated 50 Safety Stock 50
50
9-26 AL 4416 25 25
9-30 AL 4174 25 0
10-01 GR 6470 50 -50
10-08 SR 7542 200 150 Expedite SR 10-1
10-10 CO 4471 75 75
10-15 GR 6471 50 25
10-23 GR 6471 25 0
10-27 GR 6473 50 -50 Release PO 10-13
Key: AL = allocated CO = customer order
PO = purchase order WO = work order
SR = scheduled receipt GR = gross requirements
25
MRP Action Report
26
8.Teknik Lot-Sizing
27
Teknik Lot-Sizing
28
Teknik Lot-Sizing
PD 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
On Hand 35 0
POR
29
Teknik Lot-Sizing
EOQ
Menggunakan model EOQ
Rata-rata demand per minggu= 27 unit, maka EOQ:
2 dS 2 27 200 74
Q0
h 2
PD 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
On Hand 35 0 44 4 4 68 28 72 72 42 61
POR 74 74 74 74
30
Teknik Lot-Sizing
Pendekatan Minimum Cost Per Period
Periode Trial Cumulative Cost per
dikombinasi Lot Size Cost Period
2 30 200 $200.00
2,3 70 280 $140.00 Min
2,3,4 70 280 $93.33
2,3,4,5 80 340 $85.00
2,3,4,5,6 120 660 $132.00
6 40 200 $200.00
6,7 70 260 $130.00 Min
6,7,8 70 260 $86.67
6,7,8,9 100 440 $110.00
PD 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
On Hand 35 0 50 10 10 0 30 0 0 55
POR 80 70 85
31
Teknik Lot-Sizing
PD 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
On Hand 35 0 50 10 10 0 60 30 30 0
POR 80 100 55
3 minggu 3 minggu
32
Teknik Lot-Sizing
Pendekatan Least Unit Cost
Periode Trial Cumulative Cost per
dikombinasi Lot Size Cost Unit
2 30 200 $6.67
2,3 70 280 $4.00
2,3,4 70 280 Tidak berubah
2,3,4,5 80 340 $4.25
4,5 10 200 $20.00
4,5,6 50 280 $5.60
4,5,6,7 80 400 $5.00
4,5,6,7,8 80 400 Tidak berubah
4,5,6,7,8,9 110 640 $5.82
8,9 30 200 $6.67
8,9,10 85 310 $3.65
PD 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
On Hand 35 0 40 0 0 70 30 0 0 55 0
POR 70 80 85
33
Teknik Lot-Sizing
Perbandingan Teknik
34
9.Ketidakpastian
Ketidakpastian juga
muncul dalam sistem
Sumber Ketidakpastian
MRP Jenis Demand Supply
Sumber ketidak- Timing Saat kebutuhan bergeser Order tidak diterima pada
pastian dapat dilihat di waktunya
samping
Quantity Kebutuhan lebih atau Order diterima lebih atau
Untuk mengatasi
dikenal safety lead kurang dari rencana kurang dari rencana
time dan safety
stock
35
Ketidakpastian
Up-dating Sistem MRP
Adanya ketidakpastian mengakibatkan terjadinya
perubahan-perubahan
Diperlukan up-dating pada sistem sehingga diperoleh
informasi terkini dan membuat pengendalian efektif
Dikenal dua cara up-dating:
Regenerative System: up-dating dilakukan secara
batch, misalkan mingguan atau bulanan, dll
Net Change System: up-dating dilakukan setiap
ada transaksi
36
10. Manufacturing Resource
Planning (MRP II)
Variasi meliputi
Service Requirements Planning (SRP)
Business Requirements Planning (BRP)
Distribution Requirements Planning (DRP)
37
Manufacturing Resource Planning (MRP II)
38
Manufacturing Resource Planning (MRP II)
Business
Plan
Marketing Financial
Plan Plan
Production
Plan
No
Feasible?
Yes more
39
Master production
schedule
Capacity requirements
planning
No
Feasible?
Yes
Purchase Work
orders orders
Shop floor
Inventory
control
Manufacture
40
11. Sistem Perencanaan dan
Pengendalian Lanjut
Enterprise Resource Planning (ERP)
Pengembangan MRP II dalam kaitan client/server
architecture
Manufacturing Execution Systems (MES)
Menghubungkan antara business planning & mgmt
control systems
Customer-Oriented Manufacturing Management
Systems (COMMS)
Menyatukan kegiatan produksi dan pemasok
untuk kepentingan konsumen
Perencanaan multi-plant, multi-language &
multi-currency
41
12. Kelemahan MRP
42
Kelemahan MRP
43
13. Prospek MRP/MRP II
44
Latihan
Jika diketahui sebuah produk A
dengan struktur seperti di samping,
dengan kebutuhan masing-masing 1
unit kecuali untuk Z1 dibutuhkan 2
unit untuk menghasilkan 1 unit Z.
Lead time untuk merakit A 1 minggu,
untuk mendatangkan X, dan
membuat Y dan Z: 2 minggu;
mendatangkan Y1, Y2, Z1: 2 minggu.
Dengan JIP: masing-masing 25, 35,
dan 30 unit untuk minggu 4, 5, dan 6
dan tersedia on hand stock untuk A,
X, Y, dan Z masing-masing 15, 10, 10,
dan 10 unit serta Y1, Y2, dan Z1
masing-masing 5, 5 dan 10 unit buat
ringkasan POR untuk pembelian
material, komponen maupun
perakitan sub komponen dan produk
45
-ris2014- 3. Aggregate Planning 46