Manajemen
Proyek IT
Critical Path Method
(Metode Jalur Kritis)
07
Teknologi Informatika TIF047 Mutaqin Akbar, S.Kom., M.T.
Informasi
DAFTAR ISI
PEMBAHASAN ................................................................................................................... 3
Critical Path Method .......................................................................................................... 3
Menghitung Critical Path ................................................................................................... 3
Menggunakan Critical Path untuk Membuat Trade-Off pada Penjadwalan ...................... 4
Menggunakan Critical Path untuk Memperpendek Jadwal ProyekError! Bookmark not
defined.
LATIHAN ............................................................................................................................ 8
DAFTAR PUSTAKA .......................................................................................................... 9
Untuk menemukan jalur kritis untuk suatu proyek, Anda harus terlebih dahulu
mengembangkan diagram jaringan yang baik, yang pada gilirannya memerlukan daftar
kegiatan yang baik berdasarkan WBS. Setelah membuat diagram jaringan, Anda juga
Contoh Soal
Diketahui table aktifitas beserta predesesor dan durasinya sebagai berikut :
Aktifitas Predesesor Durasi
A - 3
B A,C 4
C A 3
D C 2
E B,D 2
Maka yang pertama perlu kita adalah membuat network diagramnya. Didalam
network diagram diketahui terdapat node (simpul) aktifitas yang terdiri dari beberapa
komponen seperti berikut :
Slack